SlideShare a Scribd company logo
1 of 73
Download to read offline
FLUIDS & CEMENTING
3rd year bachelor’s degree students
Prepared by: Dr. Ali SeyfeddineGUENAOUI
2022-2023
University of Kasdi Merbah Ouargla
Faculty of Hydrocarbons, Reneweble Energies, Earth and Univers Sciences
Department of Production of Hydrocarbons
Summary
Introduction
Why cementing ?
Before cementing (well preparation)
Cementing equipment
Laboratory tests
Primary cementing
Two stages cementing
Introduction
• The drilling operation makes it possible to connect
the layer containing oil or gas to the surface to allow
the exploitation of these sources, but the difficulties
of the ground make it necessary to drill the wells in
successive sections. Each phase is carried out in two
operations:
• A drilling operation,
• A casing and cementing operation to isolate the
formations crossed.
Why cementing the well?
Primary cementing is the introduction of cementitious material
into the annulus between casing and open hole to:
• Provide zonal isolation,
• Support axial load of casing stfloat collar and other stfloat
collars to be run later,
• Provide casing protection,
• Support the borehole,
Secondary/or Remedial jobs:
• Squeeze cementing,
• Cement plug.
The principle of cementing
Cementing operations can be divided into two broad categories:
• Primary cementing
• Remedial cementing.
Cementing is the process of mixing a slurry of cement and water
and pumping it down through casing to critical points in the
annulus around the casing or in the open hole below the casing
stfloat collar.The two principal functions of the cementing
process are to restrict fluid movement between the formations
and to bond and support the casing.
BEFORE CEMENTING
Condition of the well
In order to prepare a cementing, it is necessary to have as much information as
possible about the condition of the well and the drilling history. In particular:
• The lithological section,
• Deviation measurements,
• The geometry of the hole,
• The static well temperature and a good estimate of the circulation temperature,
• The characteristics and type of mud,
• Fracture gradient,
• Pore size and pressure,
Condition of the well
Based on this information and the difficulties encountered during drilling, it will be
possible to schedule:
• The control of the hole before casing,
• The descent and the casing of the column,
• Cementing.
Well preparation
This phase consists of cleaning the walls of the hole to
ensure good cement adhesion and water tightness.
This is done as follows:
• Ensure that the hole has a sufficient diameter,
• Ream all friction points,
• Preliminary circulation (for 1 or 2 cycles) with the
drilling pumps until the cuttings are completely
evacuated (one to two hours),
• during this circulation, move the column to scrape
the cake with the scrapers,
Well preparation
It should be noted that circulation is also done to
check the efficiency of the float collar and shoe valves
and to ensure that nothing is blocking the inside of
the tubes. It is also done to:
• Check the stability of the well (no losses, no gains),
• Eliminate gas plugs,
• Reduce the bottom temperature and stabilize it,
• Homogenize the mud.
The casing column
• The lengths are added together in such a
way that during the descent, the depth of
the shoe can be known at any time by the
number of the last tube inserted.
Distance between the shoe and the float
collar
• The float collar is always inserted
two to three tubes above the shoe so
that the interior volume of the
column between the shoe and the
float collar serves as a reserve for the
slag polluted by the last scraping of
the upper plug.
Centralizers
• The centering of a column is a determining factor in obtaining a good cementing,
the centering devices must be placed :
• In line with the zones to be cemented,
• In line with the doglegs,
• In areas where there is a risk of sticking or loss.
The drilling rig
• The preparation of the drilling rig consists of removing some tubular materials,
setting up the pipe handling equipment and checking the components whose
correct functioning conditions the success of the operation.
CEMENTING
EQUIPMENT
Bottom hole equipment
Float Shoe or Guide Shoe
• The cement shoe is screwed to the first length of casing
to be run and acts as a guide.
• Inside is a ported check valve to prevent a back flow of
cement during the cementing operation.
• It can be drilled out with the bit so the next section of
hole can be drilled.
Float Shoe or Guide Shoe
• Prevents back flow of cement
• Can be drilled out with the bit
• It is attached to the bottom casing joint,
• It serves as a guide for the casing as it is being run
into the wellbore and acts as a one way valve.
Float Collar
• Float collars are set about 20 feet
back from the shoe and allow the
cement to be displaced through
into the annulus by a simple plug
launch system.
• This is set about two-three joints
above the casing shoe, and act as a
one way valve.
• When it is used, the cement plugs
land on top of it.
Cementing Basket, Centralizer
• Cementing Basket, to minimize losses in weak zones.
• Centralizer, to center casing in bore hole to promote even distribution of cement
around casing. Centralizers are placed around the outside of the casing in sections
of the hole were this is most likely to occur.They allow the casing sheath to be
equal in thickness all the way around the hole to prevent fluid migrating up the
low side of the hole
Scratchers
• to scratch off the mud cake to
improve cement bond,The
scratchers are attached to
scrape away the wall cake to
allow a good bond to the wall of
the well.
Wiper Plugs
• The launch plugs are held in place until all the cement has
been pumped.The lower pin is pulled allowing the
bottom plug to be launched inside the casing.Then the
cementer switches over to pumping mud.
• The bottom plug lands out on the float collars and
releases the check valve to allow the cement to pass
through into the annulus.The top plug with the drilling
mud behind it is then pumped.When it lands out on the
bottom plug all the cement will have been displaced into
the annulus.
Wiper Plugs
• They both fit inside the cement head. After the cement has be pumped they are
released to ensure the cement is displaced Into the annulus.
• The purpose of the launch plugs is to separate the cement from the mud during
displacement of the cement.
• Wiping the casing clean,
• Surface indication of placement.
Cement Head
• Cement heads are fitted to the last length of
casing to allow the cement to be pumped into
the casing and displaced to the annulus with
spacers or cement plugs.
Cement Head
Surface equipment
Video
(56)WATCH: Overall Cementing Process -YouTube
LABORATORYTESTS
Salinity checking
Salinity of mixing water needs to be less than 1000 mg/l
Quantab method, we wait until the orange line becomes black, then we read, result 2.4 which
means 325 mg/l
Rheology at surface conditions
• 5 min in the surface conditioning
• Viscosity fann35YP w viscosity
Plastic viscosity (VP)
• Plastic viscosity in centipoise (cP) and (pascale per second) is calculated by the
Fann viscometer by the following formula:
• VP = L600 - L300
• Where, L300: Fann reading 300
Yield value
• The yield value (expressed in Pa or lb/100ft2) is given by the following relationship:
YP= L300 -VP = (VA -VP).2
The yield value is the initial resistance that must be overcome for the fluid to flow.
It is a measure of the attractive force; these forces are the result of the negative
and positive charges placed on the surface.The yield point therefore measures
these forces under flow conditions.
Rheology at BH conditions
• A Conditiometer is used to simulate BH conditions
• In creaseTemperature + Pressure at a specified time
• Than theViscosity andYV are measured usingViscometer Fann35
• YP of cement is always bigger than spacerYP which bigger than theYP of mud
• Cement G (API) is usually used in Algeria
Video
Get to Know the Model 35Viscometer -YouTube
Thickening time
• A consistometer is used to Increase Pressure
• IncreaseTemperature
• BC is measured
• Burden consistency (pumpability) (needs to be less than 80 BC)
Video
5Thickening performance test -YouTube
Free fluid
• After finishing cement job a free fluid will be escaped to the top
• Fluid loss additives is optional
• ESCA ultra sonic cement analyzing (pressure of cement) compressive strength
• SGSA static gel strength analysisTransit time from liquid to gel less than 30 min
Video
(56) 3 Fluid loss control test of cement slurry -YouTube
ESCA ultra sonic cement analyzing
• A pressure is applied on cement to measure the compressive strength
• To be able to start the drilling of the new phase the CS needs to be more than 500
psi
• Transit time from liquid to gel less which needs to be less than 30 min
SGSA static gel strength analysis
PRIMARY CEMENTING
Primary Cementing
• Here we can see in the left-hand
drawing, the bottom plug landed in the
float collar which is an integral part of
the shoe in this case.When the
diaphragm splits due to the pump
pressure at the top of the bottom plug
the cement shown in green is forced
through and up the annulus. In the right
hand drawing we can see the top plug
has landed out on the bottom plug.
This plug is solid rubber so the
cementer can see a pressure build up
and knows that the cement has been
displaced.
Conductor Pipe
Purpose
• Prevent cavities under the unit
Standard sizes and depths :
• 30-in. - 20 -in. - 16 -in. Screwed
or welded
• 10 - 100 m
Cementing Procedure:
• Plugs not used,
• Large excess required,
• Thru-drill pipe cementing
common,
• BOP’s not usually connected,
• Common Cements;
Accelerated Neat
Conductor Pipe
Thru-Drill Pipe Cementing;
• Key Points:
• Cement Contamination,
• Channeling,
• Displacement,
• Pump Until Slurry is at surface.
Conductor Pipe
Outside Cementing;
Purpose:
• Bring collar Cement to Surface.
MacaroniTBG used:
• Max depth 250 - 300 ft,
• High friction Pressures,
• Non-standard Connections
Surface Casing
Purpose:
• To protect groundwater
• Isolate unconsolidated formations or lossy areas.
• Support the following casings
• Allow well control (BOP)
Typical sizes and depths :
• 20-in. - 9 5/8-in. screwed
• 30 m - 1000 m (or more)
Surface Casing
Cementing Procedure:
• Excess of 100%,
• Recommended thru-drill pipe method to save:
• Cement,
• Rig time.
Common Cements:
• Lead light slurry with high yields,
• Neat tail slurries with good compressive strength,
• Reduce WOC to a minimum with accelerators.
Video
(56) Primary cementing procedure | PetroShine -YouTube
Intermediate Casing
Purpose
• Separating incompatible areas
• Losses
• Saline horizons
• High pressure
• Reactive clays
Typical sizes and depths:
• 13 3/8-in., 10 ¾-in., 9 5/8-in.
• 1,000 to 3,000 m
Intermediate Casing
Cementing Procedure:
• Cemented to surface or to
previous casing shoe,
• Possibly a two stage jobs,
• Plugs, casing equipment and
casing accessories are usual,
• Good cementing practices are
required,
• Large cement volumes.
Common Cements:
• Typically filler slurries followed
by high compressive tail,
• Specialized (light, heavy, salt -
saturated, etc.)
Production Casing
Purpose
• Isolate the production area from
others
• Protecting production equipment
• Subsurface artificial lift
• Multiple completion
• Safety barrier
• Protection against defective
intermediate casing
• Mesh for sand control
Standard sizes:
• 4 ½-in., 5-in., 7-in., & 9 5/8-in.
Liner cementing
• Run on liner hangers with Drill pipe
• Cemented toTop Of Liner (TOL)
• Drill pipe and liner wiper plug combination used
• Generally small volumes
• Fewer pipes
• Deep well
• Smaller annular space
• Specific equipment
• Less cemented column
Video
(56) Primary Cementing Job (animation) -YouTube
TWO STAGES
CEMENTING
Two Stages Cementing
Reasons to do:
• Separation and isolation of zones,
• Reduces hydrostatic,
• Can leave zone in the annulus
uncemented (cement atTD and
surface),
• Loss zone.
Two Stages Cementing
Video
(56) ?How do you cement #two_stage -YouTube

More Related Content

What's hot

4 drilling problems and prevent
4 drilling problems and prevent4 drilling problems and prevent
4 drilling problems and preventShabaz Ahmad
 
1. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 11. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 1Elsayed Amer
 
Casing design
Casing designCasing design
Casing designSYED NAWAZ
 
Drilling fluid
Drilling fluidDrilling fluid
Drilling fluidSARWAR SALAM
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluidsAAPG SU SC
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Aijaz Ali Mooro
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1Elsayed Amer
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operationsElsayed Amer
 
Wellhead
WellheadWellhead
Wellheadamrhaggag
 
Wenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreMohamed Abdelshafy Abozeima
 
Drilling Mud Laboratory
Drilling Mud LaboratoryDrilling Mud Laboratory
Drilling Mud LaboratoryJames Craig
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdfTinaMarey
 

What's hot (20)

Stuck pipe manual
Stuck pipe manualStuck pipe manual
Stuck pipe manual
 
4 drilling problems and prevent
4 drilling problems and prevent4 drilling problems and prevent
4 drilling problems and prevent
 
1. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 11. sequance of well drilling and completion part 1
1. sequance of well drilling and completion part 1
 
Casing design
Casing designCasing design
Casing design
 
Drilling bits
Drilling bitsDrilling bits
Drilling bits
 
Drilling fluid
Drilling fluidDrilling fluid
Drilling fluid
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4Fundamentals of Petroleum Engineering Module 4
Fundamentals of Petroleum Engineering Module 4
 
Completion equipment packer part #1
Completion equipment packer part #1Completion equipment packer part #1
Completion equipment packer part #1
 
3. sequances of drilling operations
3. sequances of drilling operations3. sequances of drilling operations
3. sequances of drilling operations
 
Wellhead
WellheadWellhead
Wellhead
 
Wenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product CatalogueWenzel Downhole Tools Product Catalogue
Wenzel Downhole Tools Product Catalogue
 
Casing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger systemCasing Accessories , completion tools, liner hanger system
Casing Accessories , completion tools, liner hanger system
 
Bits
BitsBits
Bits
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and more
 
Wellhead basics
Wellhead basicsWellhead basics
Wellhead basics
 
Drilling Mud Laboratory
Drilling Mud LaboratoryDrilling Mud Laboratory
Drilling Mud Laboratory
 
Drilling Problems.pdf
Drilling Problems.pdfDrilling Problems.pdf
Drilling Problems.pdf
 
Drilling fluid
Drilling fluidDrilling fluid
Drilling fluid
 
Cementation
CementationCementation
Cementation
 

Similar to FLUIDS & CEMENTING: BACHELOR'S DEGREE COURSE

self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Secondary cementing
Secondary cementingSecondary cementing
Secondary cementingkareem Hassan
 
Pressure Draw Down Test
Pressure Draw Down TestPressure Draw Down Test
Pressure Draw Down TestMubarik Rao
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionShyam Anandjiwala
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete Salman H. Sindhoo
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnelsHimanshu Batra
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixturesTarun kumar
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxodiliagilby
 
Standard test on fresh concrete
Standard test on fresh concreteStandard test on fresh concrete
Standard test on fresh concreteAbhishek Shah
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalAMIT PAYAL
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniquesvelMurugan260
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process proceduresDrilling Manual
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONShivananda Roy
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdfPradeepPokhrel5
 

Similar to FLUIDS & CEMENTING: BACHELOR'S DEGREE COURSE (20)

self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Secondary cementing
Secondary cementingSecondary cementing
Secondary cementing
 
Pressure Draw Down Test
Pressure Draw Down TestPressure Draw Down Test
Pressure Draw Down Test
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
WELL COMPLETIONS.pptx
WELL COMPLETIONS.pptxWELL COMPLETIONS.pptx
WELL COMPLETIONS.pptx
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
 
Standard test on fresh concrete
Standard test on fresh concreteStandard test on fresh concrete
Standard test on fresh concrete
 
benkle(DS)...pptx
benkle(DS)...pptxbenkle(DS)...pptx
benkle(DS)...pptx
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Ppt on test certificate-Amit Payal
Ppt on test certificate-Amit PayalPpt on test certificate-Amit Payal
Ppt on test certificate-Amit Payal
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
Well completion techniques
Well completion techniquesWell completion techniques
Well completion techniques
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process procedures
 
DEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATIONDEWATERING METHODS IN EXCAVATION
DEWATERING METHODS IN EXCAVATION
 
publication_1580218342.pdf
publication_1580218342.pdfpublication_1580218342.pdf
publication_1580218342.pdf
 

Recently uploaded

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)Dr. Mazin Mohamed alkathiri
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxAvyJaneVismanos
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 

Recently uploaded (20)

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Final demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptxFinal demo Grade 9 for demo Plan dessert.pptx
Final demo Grade 9 for demo Plan dessert.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 

FLUIDS & CEMENTING: BACHELOR'S DEGREE COURSE

  • 1. FLUIDS & CEMENTING 3rd year bachelor’s degree students Prepared by: Dr. Ali SeyfeddineGUENAOUI 2022-2023 University of Kasdi Merbah Ouargla Faculty of Hydrocarbons, Reneweble Energies, Earth and Univers Sciences Department of Production of Hydrocarbons
  • 2. Summary Introduction Why cementing ? Before cementing (well preparation) Cementing equipment Laboratory tests Primary cementing Two stages cementing
  • 3. Introduction • The drilling operation makes it possible to connect the layer containing oil or gas to the surface to allow the exploitation of these sources, but the difficulties of the ground make it necessary to drill the wells in successive sections. Each phase is carried out in two operations: • A drilling operation, • A casing and cementing operation to isolate the formations crossed.
  • 4. Why cementing the well? Primary cementing is the introduction of cementitious material into the annulus between casing and open hole to: • Provide zonal isolation, • Support axial load of casing stfloat collar and other stfloat collars to be run later, • Provide casing protection, • Support the borehole, Secondary/or Remedial jobs: • Squeeze cementing, • Cement plug.
  • 5. The principle of cementing Cementing operations can be divided into two broad categories: • Primary cementing • Remedial cementing. Cementing is the process of mixing a slurry of cement and water and pumping it down through casing to critical points in the annulus around the casing or in the open hole below the casing stfloat collar.The two principal functions of the cementing process are to restrict fluid movement between the formations and to bond and support the casing.
  • 7. Condition of the well In order to prepare a cementing, it is necessary to have as much information as possible about the condition of the well and the drilling history. In particular: • The lithological section, • Deviation measurements, • The geometry of the hole, • The static well temperature and a good estimate of the circulation temperature, • The characteristics and type of mud, • Fracture gradient, • Pore size and pressure,
  • 8. Condition of the well Based on this information and the difficulties encountered during drilling, it will be possible to schedule: • The control of the hole before casing, • The descent and the casing of the column, • Cementing.
  • 9. Well preparation This phase consists of cleaning the walls of the hole to ensure good cement adhesion and water tightness. This is done as follows: • Ensure that the hole has a sufficient diameter, • Ream all friction points, • Preliminary circulation (for 1 or 2 cycles) with the drilling pumps until the cuttings are completely evacuated (one to two hours), • during this circulation, move the column to scrape the cake with the scrapers,
  • 10. Well preparation It should be noted that circulation is also done to check the efficiency of the float collar and shoe valves and to ensure that nothing is blocking the inside of the tubes. It is also done to: • Check the stability of the well (no losses, no gains), • Eliminate gas plugs, • Reduce the bottom temperature and stabilize it, • Homogenize the mud.
  • 11. The casing column • The lengths are added together in such a way that during the descent, the depth of the shoe can be known at any time by the number of the last tube inserted.
  • 12. Distance between the shoe and the float collar • The float collar is always inserted two to three tubes above the shoe so that the interior volume of the column between the shoe and the float collar serves as a reserve for the slag polluted by the last scraping of the upper plug.
  • 13. Centralizers • The centering of a column is a determining factor in obtaining a good cementing, the centering devices must be placed : • In line with the zones to be cemented, • In line with the doglegs, • In areas where there is a risk of sticking or loss.
  • 14. The drilling rig • The preparation of the drilling rig consists of removing some tubular materials, setting up the pipe handling equipment and checking the components whose correct functioning conditions the success of the operation.
  • 17. Float Shoe or Guide Shoe • The cement shoe is screwed to the first length of casing to be run and acts as a guide. • Inside is a ported check valve to prevent a back flow of cement during the cementing operation. • It can be drilled out with the bit so the next section of hole can be drilled.
  • 18. Float Shoe or Guide Shoe • Prevents back flow of cement • Can be drilled out with the bit • It is attached to the bottom casing joint, • It serves as a guide for the casing as it is being run into the wellbore and acts as a one way valve.
  • 19. Float Collar • Float collars are set about 20 feet back from the shoe and allow the cement to be displaced through into the annulus by a simple plug launch system. • This is set about two-three joints above the casing shoe, and act as a one way valve. • When it is used, the cement plugs land on top of it.
  • 20. Cementing Basket, Centralizer • Cementing Basket, to minimize losses in weak zones. • Centralizer, to center casing in bore hole to promote even distribution of cement around casing. Centralizers are placed around the outside of the casing in sections of the hole were this is most likely to occur.They allow the casing sheath to be equal in thickness all the way around the hole to prevent fluid migrating up the low side of the hole
  • 21. Scratchers • to scratch off the mud cake to improve cement bond,The scratchers are attached to scrape away the wall cake to allow a good bond to the wall of the well.
  • 22. Wiper Plugs • The launch plugs are held in place until all the cement has been pumped.The lower pin is pulled allowing the bottom plug to be launched inside the casing.Then the cementer switches over to pumping mud. • The bottom plug lands out on the float collars and releases the check valve to allow the cement to pass through into the annulus.The top plug with the drilling mud behind it is then pumped.When it lands out on the bottom plug all the cement will have been displaced into the annulus.
  • 23. Wiper Plugs • They both fit inside the cement head. After the cement has be pumped they are released to ensure the cement is displaced Into the annulus. • The purpose of the launch plugs is to separate the cement from the mud during displacement of the cement. • Wiping the casing clean, • Surface indication of placement.
  • 24. Cement Head • Cement heads are fitted to the last length of casing to allow the cement to be pumped into the casing and displaced to the annulus with spacers or cement plugs.
  • 29. Salinity checking Salinity of mixing water needs to be less than 1000 mg/l Quantab method, we wait until the orange line becomes black, then we read, result 2.4 which means 325 mg/l
  • 30. Rheology at surface conditions • 5 min in the surface conditioning • Viscosity fann35YP w viscosity
  • 31. Plastic viscosity (VP) • Plastic viscosity in centipoise (cP) and (pascale per second) is calculated by the Fann viscometer by the following formula: • VP = L600 - L300 • Where, L300: Fann reading 300
  • 32. Yield value • The yield value (expressed in Pa or lb/100ft2) is given by the following relationship: YP= L300 -VP = (VA -VP).2 The yield value is the initial resistance that must be overcome for the fluid to flow. It is a measure of the attractive force; these forces are the result of the negative and positive charges placed on the surface.The yield point therefore measures these forces under flow conditions.
  • 33. Rheology at BH conditions • A Conditiometer is used to simulate BH conditions • In creaseTemperature + Pressure at a specified time • Than theViscosity andYV are measured usingViscometer Fann35 • YP of cement is always bigger than spacerYP which bigger than theYP of mud • Cement G (API) is usually used in Algeria
  • 34. Video Get to Know the Model 35Viscometer -YouTube
  • 35. Thickening time • A consistometer is used to Increase Pressure • IncreaseTemperature • BC is measured • Burden consistency (pumpability) (needs to be less than 80 BC)
  • 37. Free fluid • After finishing cement job a free fluid will be escaped to the top • Fluid loss additives is optional • ESCA ultra sonic cement analyzing (pressure of cement) compressive strength • SGSA static gel strength analysisTransit time from liquid to gel less than 30 min
  • 38. Video (56) 3 Fluid loss control test of cement slurry -YouTube
  • 39. ESCA ultra sonic cement analyzing • A pressure is applied on cement to measure the compressive strength • To be able to start the drilling of the new phase the CS needs to be more than 500 psi • Transit time from liquid to gel less which needs to be less than 30 min SGSA static gel strength analysis
  • 41. Primary Cementing • Here we can see in the left-hand drawing, the bottom plug landed in the float collar which is an integral part of the shoe in this case.When the diaphragm splits due to the pump pressure at the top of the bottom plug the cement shown in green is forced through and up the annulus. In the right hand drawing we can see the top plug has landed out on the bottom plug. This plug is solid rubber so the cementer can see a pressure build up and knows that the cement has been displaced.
  • 42. Conductor Pipe Purpose • Prevent cavities under the unit Standard sizes and depths : • 30-in. - 20 -in. - 16 -in. Screwed or welded • 10 - 100 m Cementing Procedure: • Plugs not used, • Large excess required, • Thru-drill pipe cementing common, • BOP’s not usually connected, • Common Cements; Accelerated Neat
  • 43. Conductor Pipe Thru-Drill Pipe Cementing; • Key Points: • Cement Contamination, • Channeling, • Displacement, • Pump Until Slurry is at surface.
  • 44. Conductor Pipe Outside Cementing; Purpose: • Bring collar Cement to Surface. MacaroniTBG used: • Max depth 250 - 300 ft, • High friction Pressures, • Non-standard Connections
  • 45. Surface Casing Purpose: • To protect groundwater • Isolate unconsolidated formations or lossy areas. • Support the following casings • Allow well control (BOP) Typical sizes and depths : • 20-in. - 9 5/8-in. screwed • 30 m - 1000 m (or more)
  • 46. Surface Casing Cementing Procedure: • Excess of 100%, • Recommended thru-drill pipe method to save: • Cement, • Rig time. Common Cements: • Lead light slurry with high yields, • Neat tail slurries with good compressive strength, • Reduce WOC to a minimum with accelerators.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51. Video (56) Primary cementing procedure | PetroShine -YouTube
  • 52. Intermediate Casing Purpose • Separating incompatible areas • Losses • Saline horizons • High pressure • Reactive clays Typical sizes and depths: • 13 3/8-in., 10 Âľ-in., 9 5/8-in. • 1,000 to 3,000 m
  • 53. Intermediate Casing Cementing Procedure: • Cemented to surface or to previous casing shoe, • Possibly a two stage jobs, • Plugs, casing equipment and casing accessories are usual, • Good cementing practices are required, • Large cement volumes. Common Cements: • Typically filler slurries followed by high compressive tail, • Specialized (light, heavy, salt - saturated, etc.)
  • 54. Production Casing Purpose • Isolate the production area from others • Protecting production equipment • Subsurface artificial lift • Multiple completion • Safety barrier • Protection against defective intermediate casing • Mesh for sand control Standard sizes: • 4 ½-in., 5-in., 7-in., & 9 5/8-in.
  • 55. Liner cementing • Run on liner hangers with Drill pipe • Cemented toTop Of Liner (TOL) • Drill pipe and liner wiper plug combination used • Generally small volumes • Fewer pipes • Deep well • Smaller annular space • Specific equipment • Less cemented column
  • 56.
  • 57.
  • 58.
  • 59.
  • 60.
  • 61. Video (56) Primary Cementing Job (animation) -YouTube
  • 63. Two Stages Cementing Reasons to do: • Separation and isolation of zones, • Reduces hydrostatic, • Can leave zone in the annulus uncemented (cement atTD and surface), • Loss zone.
  • 65.
  • 66.
  • 67.
  • 68.
  • 69.
  • 70.
  • 71.
  • 72.
  • 73. Video (56) ?How do you cement #two_stage -YouTube