SlideShare a Scribd company logo
Cementing Relationships
ABB improves production process at Podilsky Cement plant
Reprint from World Cement, March 2012
“We were delighted to renew the
partnership with ABB for the installation
of integrated electrical, control and
automation systems for our new
production line. From the first steps of
the detailed project design through to
the intensive commissioning phase, ABB
provided professional and dedicated
support. It was a pleasure to work with
ABB and we look forward to future
collaborations.”
Nigel Reape, Podilsky Cement’s
Production Director
Introduction
JSC Podilsky Cement, part of the Irish building
materials group CRH, is located in Kamyanets-Podilsky,
approximately 420 km southwest of Ukraine’s capital Kiev.
The site was originally commissioned in the 1970s. ABB’s
success story with CRH’s Podilsky Cement started seven
years ago, in 2005, when ABB signed a contract for the
supply of an automation package for a new vertical coal
mill to be installed at the plant. During the execution phase
of this project an engineer from Podilsky Cement and
an engineer from ABB in Ukraine joined the ABB project
team in Switzerland’s main technology centre for electrical,
control and instrumentation systems to jointly elaborate the
design and the control application. The commissioning of
this project was successfully completed in spring 2007. In
2008, a similar setup was applied for the new coal feeder
of kiln line no. 5. Podilsky and ABB established a strong
relationship during the execution stages of these two
projects.
Line no. 7 project
In June 2009, ABB signed a contract for the supply of
systems, solutions and products for the new Podilsky
Cement production line no. 7 project. Among the various
ABB systems, products and services included in the
overall project scope of supply were medium-voltage (MV)
switchgears, intelligent low-voltage (LV) motor control
centres (MNSiS MCC), LV variable-speed drives (VSD), a
Cementing
Relationships
Cementing
Relationships
Alex Kaufmann, ABB Switzerland Ltd,
discusses the new cement
production line no.7 project at
Podilsky Cement.
Podilsky cement plant overview.
Cover Story
Reprint from World Cement, March 2012
plant-wide process control system, MES, instrumentation,
gas analysers, engineering services, technical site services,
as well as on- and off-shore training. Also part of ABB’s
overall solution is the design, procurement, support
and coordination of third-party equipment, including
uninterruptable power supplies (UPS) and additional
instrumentation.
The production line no. 7 project was successfully
commissioned in August 2011. With its production capacity
of 7500 tpd, Podilsky Cement now operates the biggest
cement production line in Ukraine. The project also
constitutes the largest single investment in the Ukrainian
cement industry since independence was achieved in
1991. This was one of the reasons why the new line was
officially inaugurated by the president of Ukraine in October
2011. The new line is important for CRH, with significant
improvements in operational efficiency, product quality and
environmental performance. The old cement plant used
the wet process for clinker production and ball mills for
cement grinding. The modern equipment produces cement
more efficiently, with kilns such as the Polysius-supplied dry
process clinker production line and the FLSmidth-supplied
vertical mill for cement grinding.
Modern instrumentation, such as cross-belt analysers,
provide better control of the processes involved in
making cement and thereby improve product quality. The
new cement production line is fitted with high-efficiency
filtration equipment at all emission points, helping to
significantly reduce particulate and CO2 emissions. The
project is the world’s first Track 2 ‘joint implementation’
project registered with the UNFCCC (United Framework
Convention on Climate Change).
Before Podilsky Cement decided to modernise its
installations and build the new cement production line,
the plant consisted of six cement production lines using a
wet production process and achieving a total production
of 3 million tpa of cement. After the start-up of the new
line, the existing wet production process lines will be
mothballed, since the new dry production process line
alone achieves almost the same capacity as the old lines
together. “The initial performance of the new plant shows
fuel consumption to be less than 50% of the wet process.
Power consumption to make clinker shows a reduction
of over 15%, and the optimisation of the new line will
improve performance further,” says CRH Europe Material’s
Technical Director Eamon Geraghty.
At the beginning of the execution phase of the project,
two engineers from Podilsky Cement joined the ABB core
project team, consisting of engineering experts from ABB
Ukraine and ABB Switzerland. They started the detailed
engineering and the software application programming in
Switzerland before moving back to Ukraine to complete
this part of the engineering. The factory acceptance test
(FAT) of the control system application was executed in
ABB Ukraine’s facilities in Kharkov. The involvement of
Podilsky engineers during the engineering and subsequent
commissioning ensures that they have detailed knowledge
about the ABB systems and solutions installed at the
site, resulting in professional operation, maintenance and
troubleshooting of the plant.
Integrated solutions for process control
ABB supplied the 800xA control system, which extends
the reach of traditional automation systems beyond control
of the process to achieve the productivity gains necessary
to succeed in today’s business markets. This function is
accessible from a single user interface that is configured
to present information and provide interaction in a context
appropriate to all user disciplines, e.g. every electrical loop
diagram is directly linked to its corresponding object in
the control system, independent of whether it is a simple
instrument or a complex MV motor. With this integrated
information, plant operators can make qualified decisions
quickly and based on relevant and reliable data.
“Due to the clear structure of the ABB control system
and the well-arranged process graphics and faceplates,
Kiln line no. 7 at Podilsky Cement.
New central control room (CCR).
our operators easily and efficiently learnt to operate our
new plant. They can reach all the necessary information
to take their decisions with only a few mouse clicks. The
easy navigation with dynamic hyperlinks between objects
is one of the many features that help operators to find the
root cause of abnormal situations.
For us, the new ABB control
system is a perfect combination of
most modern design and ultimate
functionality,” says Podilsky’s
Control System Manager
Aleksey Lavrenyuk.
Extended automation objects
created within the engineering
environment provide a
foundation for the efficient
development, deployment, reuse
and continuous improvement of
production and safety applications,
with great predictability.
ABB’s System 800xA Minerals
Library is especially developed for
the cement industry and suitable
for greenfield projects and control
system upgrades. It is a suite of
object-oriented software control
modules that make it possible to
design process control and power
applications in an efficient and
fully-parameterised fashion. Successfully operating at more
than 300 cement and mineral processing sites worldwide,
the technology increases the standardisation, functionality
and quality of process control software over the complete
life cycle of the production facility.
ABB also installed its Knowledge Manager system at
Podilsky Cement, which offers industry-specific process
data management solutions for cement production and
minerals processing. Goal-oriented decisions can be made
by accessing the information needed at the right time,
place and format. The system provides analytical insights
to identify deviations in the process and best practices to
keep the production on target.
Providing solutions suited to the cement industry,
the Knowledge Manager system supports Podilsky Cement
with monitoring manufacturing performance indicators,
process operations and energy reporting, as well as
downtime management.
Integration of subsystems
As can be seen in Table 1, many subsystems were
delivered by a variety of suppliers. The seamless
integration of these systems into the control system is
proof of the flexibility of the 800xA control system. “ABB
delivered a full turnkey package and was technically
competent with all delivery dates achieved. Their
understanding of the cement process was evident in their
development of the consumer circuits and
MCC designs. Commissioning of the application
software was smooth with no major omissions or errors,”
states CRH’s Technical Electrical Advisor Pat Fullen.
During the commissioning of the new line, ABB also
integrated the existing coal mill application into the new
plant control system. Due to the detailed preparation of
this task, the modification could be completed during an
ordinary scheduled shutdown of the coal mill, avoiding any
additional downtime.
Configuration of the control system.
The preheater tower.
LV distribution system, emergency power
system, UPS system
All LV distribution panels are of modular MNS type and
have front-side operated withdrawable feeders, whereas the
incomer circuit breakers are motor controlled. The intelligent
motor control centre (MNSiS) is fully integrated into ABB’s
800xA control system. Through a complex but efficient fibre
optic network, all intelligent motor starter detail information is
accessible from any of the nine electrical rooms and from any
of the plant’s three control rooms. The availability of essential
information in the whole plant enables the central control
room (CCR) operators and the electrical maintenance staff
to make the most efficient decisions in the shortest possible
time.
For the safety of the equipment and for the emergency
operation during power network shutdowns, the various
emergency consumers are fed by a diesel generator unit.
These consumers are connected to different motor control
centre groups, which contain an incomer circuit breaker for
the distribution transformer, as well as an incomer circuit
breaker for the emergency power. Both incomers are
feeding the same LV busbar and are therefore interlocked in
order to use only either one of the two power supplies.
UPS systems with an output of 220 V are installed in
the CCR building and in the various substations to maintain
power for servers, the central control system, remote I/O
panels, instrumentation and the essential lighting.
Acceleration programmes
Due to overall project requirements during the execution
phase of the line no. 7 project, Podilsky Cement asked
ABB to plan and implement two acceleration programmes
in order to significantly shorten the delivery time of the
equipment included in ABB’s scope of supply.
“On two separate occasions ABB was able to meet our
requests for acceleration of their engineering and delivery
programmes,” says Podilsky Cement’s Production Director
Nigel Reape.
After a detailed investigation, ABB presented the
revised schedule, resulting in a reduced engineering and
manufacturing time of approximately three months. This
reduction of the delivery time could be reached due to the
company’s ability to access its global expert resources in
engineering ad hoc, as well as by increasing the resources
working on the manufacturing side of the project. Despite
the challenging schedule, the project team reached all
the new milestones and delivered all the equipment and
engineering documents on time while keeping ABB’s high
quality standards. Reape continued: “This flexibility in
meeting tight deadlines coupled with the ability to provide
truly professional installation and commissioning engineers
were critical in achieving our project deadlines. It was a
pleasure to work with ABB on this project and we look
forward to future collaborations.”
Excellent cooperation during the
complete project
Building on the existing relationship from previous successful
common projects, the cooperation between Podilsky
Cement, CRH and ABB resulted in an efficient and smooth
project execution.
Reape concludes: “After the successful collaboration
between Podilsky Cement and ABB on our coal mill
installation project in 2006, Podilsky Cement was delighted
to renew our partnership with ABB for the installation
of our new cement production line. From the first steps
of the detailed project design through to the intensive
commissioning phase, the ABB project team provided
professional and dedicated support to Podilsky Cement.
Through open and honest communications our two teams
developed a close working relationship, which was a key
element in the successful completion of the project.”
Table 1. Control system details
Process controllers 9
Integration of Profibus
interfaces
138 (55 from ABB scope of
supply)
Integration of Modbus
interfaces
141 (33 from ABB scope of
supply)
Field inputs/outputs (digital) 3616
Field inputs/outputs
(analog)
1072
Intelligent MCC starter 358
PID control loops 32
Third party PLC* interfaces 7
Third party OPC**
interfaces
4
Aspect servers 3
Connectivity servers 2
Domain servers 2
Knowledge Manager (KM) 1
Data collector node (DCN) 1
Engineering station 1
Operators station 5 in CCR***, 1 in LCR****
for clay, 1 in limestone LCR
approximately 3.5 km from plant
800xA version SV5.0 SP2, Rev.C, Minerals Lib
5.1/2
Major OEM interfaces Polysius, FLSmidth, Beumer,
Schenck Process, Hasler,
FLSmidth Pfister, Bedeschi,
Auma, Saacke
Intelligent MCCs with ABB latest MNSiS technology providing
reliable motor protection and control, communicating with the
800xA system throughout the complete plant, including the
nine substations through ModBus@TCPIP protocol
*PLC - Programmable logic controller
**OPC - Object linking and embedding (OLE) for process
control
***CCR - Central control room
****LCR - Local control room
©Copyright2012ABB.Allrightsreserved.3BHS396312ZABE01(03.12250Köpfli&Partner)
Main Technology Center for
electrical, control and instrumentation systems
ABB Switzerland Ltd
Segelhofstrasse 9P
CH-5405 Baden 5 Dättwil
Switzerland
Phone: +41 58 586 84 44
Fax: +41 58 586 73 33
E-mail: minerals@ch.abb.com
Local Operation Center
ABB Ltd
20-A Gagarina Pr.
Kharkiv 61001 Ukraine
Phone: +380 57 714 97 90
Fax: +380 57 714 97 91
E-mail: automation.group@ua.abb.com
ABB’s Minerals business unit, with headquarters in USA
(Houston, Texas), is represented in the following countries:
Argentina, Australia, Brazil, Canada, Chile, China, Egypt,
Estonia, Germany, Greece, India, Indonesia, Kazakhstan,
Latvia, Lithuania, Malaysia, Mexico, North America, Norway,
Oman, Peru, Poland, Saudi Arabia, Serbia, South Africa,
Spain, Sweden, Switzerland, Thailand and Vietnam.
For contact details, please visit our website:
www.abb.com/cement
www.abb.ua
Contact us

More Related Content

What's hot

Nagy_CV_Docx
Nagy_CV_DocxNagy_CV_Docx
Sharma Resume
Sharma ResumeSharma Resume
Sharma Resume
Aman Sharma
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
Raheem Arif
 
OES PPT
OES PPTOES PPT
OES PPT
Onkar Nath
 
CASE STUDY: Two Harbors Municipal Power Plant
CASE STUDY: Two Harbors Municipal Power PlantCASE STUDY: Two Harbors Municipal Power Plant
CASE STUDY: Two Harbors Municipal Power Plant
Aditi Paul
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_new
vasanth morais
 
Leadec conveyor integration 2019
Leadec conveyor integration 2019Leadec conveyor integration 2019
Leadec conveyor integration 2019
Daniel Webb
 
Clo2 system l stn 001
Clo2 system l stn 001  Clo2 system l stn 001
Clo2 system l stn 001
Ahmad Moharram
 
COBRA PRESENTATION
COBRA  PRESENTATIONCOBRA  PRESENTATION
COBRA PRESENTATION
suman Chatterjee_234
 
Mohamed Behiry CV
Mohamed Behiry CVMohamed Behiry CV
Mohamed Behiry CV
mohamed behiry
 
Juliet Joseph
Juliet JosephJuliet Joseph
Juliet Joseph
Juliet Joseph
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
Abdul Alim Dewan
 
Projects Annex
Projects AnnexProjects Annex
Projects Annex
Bardhyl Leka
 

What's hot (13)

Nagy_CV_Docx
Nagy_CV_DocxNagy_CV_Docx
Nagy_CV_Docx
 
Sharma Resume
Sharma ResumeSharma Resume
Sharma Resume
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
OES PPT
OES PPTOES PPT
OES PPT
 
CASE STUDY: Two Harbors Municipal Power Plant
CASE STUDY: Two Harbors Municipal Power PlantCASE STUDY: Two Harbors Municipal Power Plant
CASE STUDY: Two Harbors Municipal Power Plant
 
Vasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_newVasanth_Electrical Engineer_CV_new
Vasanth_Electrical Engineer_CV_new
 
Leadec conveyor integration 2019
Leadec conveyor integration 2019Leadec conveyor integration 2019
Leadec conveyor integration 2019
 
Clo2 system l stn 001
Clo2 system l stn 001  Clo2 system l stn 001
Clo2 system l stn 001
 
COBRA PRESENTATION
COBRA  PRESENTATIONCOBRA  PRESENTATION
COBRA PRESENTATION
 
Mohamed Behiry CV
Mohamed Behiry CVMohamed Behiry CV
Mohamed Behiry CV
 
Juliet Joseph
Juliet JosephJuliet Joseph
Juliet Joseph
 
Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017Resume -Abdul Alim Dewan -2017
Resume -Abdul Alim Dewan -2017
 
Projects Annex
Projects AnnexProjects Annex
Projects Annex
 

Viewers also liked

Cement production line
Cement production lineCement production line
Cement production line
Evita Lee
 
India : Cement Sector Report_August 2013
India : Cement Sector Report_August 2013India : Cement Sector Report_August 2013
India : Cement Sector Report_August 2013
India Brand Equity Foundation
 
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
Sushant Siddhey
 
Portland cement mfg. process for finance, subsidy & project related support...
Portland cement mfg. process   for finance, subsidy & project related support...Portland cement mfg. process   for finance, subsidy & project related support...
Portland cement mfg. process for finance, subsidy & project related support...
Radha Krishna Sahoo
 
Building materials
Building materialsBuilding materials
Building materials
heart trust nta
 
Cementation
CementationCementation
Cementation
Dictor Omien
 
Cement manufacturing process
Cement manufacturing process Cement manufacturing process
Cement manufacturing process
Rohan Sharma
 
Cement industry
Cement industryCement industry
Cement industry
Sumitha Thiru
 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing process
Havalarif
 
Cement Plant Process and Instruments Used
Cement Plant Process and Instruments UsedCement Plant Process and Instruments Used
Cement Plant Process and Instruments Used
Ravi Roy
 
Cement Production Process
Cement Production ProcessCement Production Process
Cement Production Process
Deepesh Mishra
 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing process
Shreenath Bohra
 

Viewers also liked (12)

Cement production line
Cement production lineCement production line
Cement production line
 
India : Cement Sector Report_August 2013
India : Cement Sector Report_August 2013India : Cement Sector Report_August 2013
India : Cement Sector Report_August 2013
 
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
Industrial training report Satna Cement Works (Birla Corp Ltd), Satna, Madhya...
 
Portland cement mfg. process for finance, subsidy & project related support...
Portland cement mfg. process   for finance, subsidy & project related support...Portland cement mfg. process   for finance, subsidy & project related support...
Portland cement mfg. process for finance, subsidy & project related support...
 
Building materials
Building materialsBuilding materials
Building materials
 
Cementation
CementationCementation
Cementation
 
Cement manufacturing process
Cement manufacturing process Cement manufacturing process
Cement manufacturing process
 
Cement industry
Cement industryCement industry
Cement industry
 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing process
 
Cement Plant Process and Instruments Used
Cement Plant Process and Instruments UsedCement Plant Process and Instruments Used
Cement Plant Process and Instruments Used
 
Cement Production Process
Cement Production ProcessCement Production Process
Cement Production Process
 
Cement manufacturing process
Cement manufacturing processCement manufacturing process
Cement manufacturing process
 

Similar to ABB_Podilsky_Reprint_WorldCement_lowres

WC_August06_article_Hatien2
WC_August06_article_Hatien2WC_August06_article_Hatien2
WC_August06_article_Hatien2
Anh Nguyen
 
RESUME_PRAKASH
RESUME_PRAKASHRESUME_PRAKASH
RESUME_PRAKASH
prakash goyal
 
Az Zour EPP08
Az Zour EPP08Az Zour EPP08
Az Zour EPP08
sheffik abdulaziz
 
Resume-Vispute_Prashant
Resume-Vispute_PrashantResume-Vispute_Prashant
Resume-Vispute_Prashant
Prashant VISPUTE
 
CV_Sandeep Anugade
CV_Sandeep AnugadeCV_Sandeep Anugade
CV_Sandeep Anugade
Sandeep Anugade
 
Saint-Petersburg Dam
Saint-Petersburg DamSaint-Petersburg Dam
Saint-Petersburg Dam
Marat Mamleev
 
Phoenix Control Systems
Phoenix Control SystemsPhoenix Control Systems
Phoenix Control Systems
Richard Taylor
 
Liquid foilling machine project
Liquid foilling machine projectLiquid foilling machine project
Liquid foilling machine project
UDYAASEKHARJ
 
ABB Contact - 2/13 India : Oil and Gas issue
ABB Contact - 2/13 India : Oil and Gas issueABB Contact - 2/13 India : Oil and Gas issue
ABB Contact - 2/13 India : Oil and Gas issue
ABBCONTACT
 
ABB Contact 1/13 Egypt- Grid Reliability
ABB Contact 1/13 Egypt- Grid ReliabilityABB Contact 1/13 Egypt- Grid Reliability
ABB Contact 1/13 Egypt- Grid Reliability
ABBCONTACT
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
Pablo Miguel Jurado
 
AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefs
AGE Technologies
 
C. Bright Singh
C. Bright SinghC. Bright Singh
C. Bright Singh
Bright Singh Chellathurai
 
IRJET- Automatic Bottle Filling and Capping System using PLC
IRJET- Automatic Bottle Filling and Capping System using PLCIRJET- Automatic Bottle Filling and Capping System using PLC
IRJET- Automatic Bottle Filling and Capping System using PLC
IRJET Journal
 
A new age of industrial productionThe Internet of Things, Se.docx
A new age of industrial productionThe Internet of Things, Se.docxA new age of industrial productionThe Internet of Things, Se.docx
A new age of industrial productionThe Internet of Things, Se.docx
ransayo
 
INTEGRADDE Concept: AMEF 2018
INTEGRADDE Concept: AMEF 2018INTEGRADDE Concept: AMEF 2018
INTEGRADDE Concept: AMEF 2018
Félix Vidal
 
Customer magazine insider october 2012 final
Customer magazine insider october 2012 finalCustomer magazine insider october 2012 final
Customer magazine insider october 2012 final
Luis Angel Cabrera Hidalgo
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
hugo_mx
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
hugo_mx
 
Sujit Das
Sujit DasSujit Das
Sujit Das
Sujit Das
 

Similar to ABB_Podilsky_Reprint_WorldCement_lowres (20)

WC_August06_article_Hatien2
WC_August06_article_Hatien2WC_August06_article_Hatien2
WC_August06_article_Hatien2
 
RESUME_PRAKASH
RESUME_PRAKASHRESUME_PRAKASH
RESUME_PRAKASH
 
Az Zour EPP08
Az Zour EPP08Az Zour EPP08
Az Zour EPP08
 
Resume-Vispute_Prashant
Resume-Vispute_PrashantResume-Vispute_Prashant
Resume-Vispute_Prashant
 
CV_Sandeep Anugade
CV_Sandeep AnugadeCV_Sandeep Anugade
CV_Sandeep Anugade
 
Saint-Petersburg Dam
Saint-Petersburg DamSaint-Petersburg Dam
Saint-Petersburg Dam
 
Phoenix Control Systems
Phoenix Control SystemsPhoenix Control Systems
Phoenix Control Systems
 
Liquid foilling machine project
Liquid foilling machine projectLiquid foilling machine project
Liquid foilling machine project
 
ABB Contact - 2/13 India : Oil and Gas issue
ABB Contact - 2/13 India : Oil and Gas issueABB Contact - 2/13 India : Oil and Gas issue
ABB Contact - 2/13 India : Oil and Gas issue
 
ABB Contact 1/13 Egypt- Grid Reliability
ABB Contact 1/13 Egypt- Grid ReliabilityABB Contact 1/13 Egypt- Grid Reliability
ABB Contact 1/13 Egypt- Grid Reliability
 
33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)33 kV towerline roadcrossing design modification - Final (English)
33 kV towerline roadcrossing design modification - Final (English)
 
AGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefsAGE TECHNOLOGIES_2014 project briefs
AGE TECHNOLOGIES_2014 project briefs
 
C. Bright Singh
C. Bright SinghC. Bright Singh
C. Bright Singh
 
IRJET- Automatic Bottle Filling and Capping System using PLC
IRJET- Automatic Bottle Filling and Capping System using PLCIRJET- Automatic Bottle Filling and Capping System using PLC
IRJET- Automatic Bottle Filling and Capping System using PLC
 
A new age of industrial productionThe Internet of Things, Se.docx
A new age of industrial productionThe Internet of Things, Se.docxA new age of industrial productionThe Internet of Things, Se.docx
A new age of industrial productionThe Internet of Things, Se.docx
 
INTEGRADDE Concept: AMEF 2018
INTEGRADDE Concept: AMEF 2018INTEGRADDE Concept: AMEF 2018
INTEGRADDE Concept: AMEF 2018
 
Customer magazine insider october 2012 final
Customer magazine insider october 2012 finalCustomer magazine insider october 2012 final
Customer magazine insider october 2012 final
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
I tron automation's experience
I tron automation's experienceI tron automation's experience
I tron automation's experience
 
Sujit Das
Sujit DasSujit Das
Sujit Das
 

ABB_Podilsky_Reprint_WorldCement_lowres

  • 1. Cementing Relationships ABB improves production process at Podilsky Cement plant Reprint from World Cement, March 2012 “We were delighted to renew the partnership with ABB for the installation of integrated electrical, control and automation systems for our new production line. From the first steps of the detailed project design through to the intensive commissioning phase, ABB provided professional and dedicated support. It was a pleasure to work with ABB and we look forward to future collaborations.” Nigel Reape, Podilsky Cement’s Production Director
  • 2. Introduction JSC Podilsky Cement, part of the Irish building materials group CRH, is located in Kamyanets-Podilsky, approximately 420 km southwest of Ukraine’s capital Kiev. The site was originally commissioned in the 1970s. ABB’s success story with CRH’s Podilsky Cement started seven years ago, in 2005, when ABB signed a contract for the supply of an automation package for a new vertical coal mill to be installed at the plant. During the execution phase of this project an engineer from Podilsky Cement and an engineer from ABB in Ukraine joined the ABB project team in Switzerland’s main technology centre for electrical, control and instrumentation systems to jointly elaborate the design and the control application. The commissioning of this project was successfully completed in spring 2007. In 2008, a similar setup was applied for the new coal feeder of kiln line no. 5. Podilsky and ABB established a strong relationship during the execution stages of these two projects. Line no. 7 project In June 2009, ABB signed a contract for the supply of systems, solutions and products for the new Podilsky Cement production line no. 7 project. Among the various ABB systems, products and services included in the overall project scope of supply were medium-voltage (MV) switchgears, intelligent low-voltage (LV) motor control centres (MNSiS MCC), LV variable-speed drives (VSD), a Cementing Relationships Cementing Relationships Alex Kaufmann, ABB Switzerland Ltd, discusses the new cement production line no.7 project at Podilsky Cement. Podilsky cement plant overview. Cover Story Reprint from World Cement, March 2012
  • 3. plant-wide process control system, MES, instrumentation, gas analysers, engineering services, technical site services, as well as on- and off-shore training. Also part of ABB’s overall solution is the design, procurement, support and coordination of third-party equipment, including uninterruptable power supplies (UPS) and additional instrumentation. The production line no. 7 project was successfully commissioned in August 2011. With its production capacity of 7500 tpd, Podilsky Cement now operates the biggest cement production line in Ukraine. The project also constitutes the largest single investment in the Ukrainian cement industry since independence was achieved in 1991. This was one of the reasons why the new line was officially inaugurated by the president of Ukraine in October 2011. The new line is important for CRH, with significant improvements in operational efficiency, product quality and environmental performance. The old cement plant used the wet process for clinker production and ball mills for cement grinding. The modern equipment produces cement more efficiently, with kilns such as the Polysius-supplied dry process clinker production line and the FLSmidth-supplied vertical mill for cement grinding. Modern instrumentation, such as cross-belt analysers, provide better control of the processes involved in making cement and thereby improve product quality. The new cement production line is fitted with high-efficiency filtration equipment at all emission points, helping to significantly reduce particulate and CO2 emissions. The project is the world’s first Track 2 ‘joint implementation’ project registered with the UNFCCC (United Framework Convention on Climate Change). Before Podilsky Cement decided to modernise its installations and build the new cement production line, the plant consisted of six cement production lines using a wet production process and achieving a total production of 3 million tpa of cement. After the start-up of the new line, the existing wet production process lines will be mothballed, since the new dry production process line alone achieves almost the same capacity as the old lines together. “The initial performance of the new plant shows fuel consumption to be less than 50% of the wet process. Power consumption to make clinker shows a reduction of over 15%, and the optimisation of the new line will improve performance further,” says CRH Europe Material’s Technical Director Eamon Geraghty. At the beginning of the execution phase of the project, two engineers from Podilsky Cement joined the ABB core project team, consisting of engineering experts from ABB Ukraine and ABB Switzerland. They started the detailed engineering and the software application programming in Switzerland before moving back to Ukraine to complete this part of the engineering. The factory acceptance test (FAT) of the control system application was executed in ABB Ukraine’s facilities in Kharkov. The involvement of Podilsky engineers during the engineering and subsequent commissioning ensures that they have detailed knowledge about the ABB systems and solutions installed at the site, resulting in professional operation, maintenance and troubleshooting of the plant. Integrated solutions for process control ABB supplied the 800xA control system, which extends the reach of traditional automation systems beyond control of the process to achieve the productivity gains necessary to succeed in today’s business markets. This function is accessible from a single user interface that is configured to present information and provide interaction in a context appropriate to all user disciplines, e.g. every electrical loop diagram is directly linked to its corresponding object in the control system, independent of whether it is a simple instrument or a complex MV motor. With this integrated information, plant operators can make qualified decisions quickly and based on relevant and reliable data. “Due to the clear structure of the ABB control system and the well-arranged process graphics and faceplates, Kiln line no. 7 at Podilsky Cement. New central control room (CCR).
  • 4. our operators easily and efficiently learnt to operate our new plant. They can reach all the necessary information to take their decisions with only a few mouse clicks. The easy navigation with dynamic hyperlinks between objects is one of the many features that help operators to find the root cause of abnormal situations. For us, the new ABB control system is a perfect combination of most modern design and ultimate functionality,” says Podilsky’s Control System Manager Aleksey Lavrenyuk. Extended automation objects created within the engineering environment provide a foundation for the efficient development, deployment, reuse and continuous improvement of production and safety applications, with great predictability. ABB’s System 800xA Minerals Library is especially developed for the cement industry and suitable for greenfield projects and control system upgrades. It is a suite of object-oriented software control modules that make it possible to design process control and power applications in an efficient and fully-parameterised fashion. Successfully operating at more than 300 cement and mineral processing sites worldwide, the technology increases the standardisation, functionality and quality of process control software over the complete life cycle of the production facility. ABB also installed its Knowledge Manager system at Podilsky Cement, which offers industry-specific process data management solutions for cement production and minerals processing. Goal-oriented decisions can be made by accessing the information needed at the right time, place and format. The system provides analytical insights to identify deviations in the process and best practices to keep the production on target. Providing solutions suited to the cement industry, the Knowledge Manager system supports Podilsky Cement with monitoring manufacturing performance indicators, process operations and energy reporting, as well as downtime management. Integration of subsystems As can be seen in Table 1, many subsystems were delivered by a variety of suppliers. The seamless integration of these systems into the control system is proof of the flexibility of the 800xA control system. “ABB delivered a full turnkey package and was technically competent with all delivery dates achieved. Their understanding of the cement process was evident in their development of the consumer circuits and MCC designs. Commissioning of the application software was smooth with no major omissions or errors,” states CRH’s Technical Electrical Advisor Pat Fullen. During the commissioning of the new line, ABB also integrated the existing coal mill application into the new plant control system. Due to the detailed preparation of this task, the modification could be completed during an ordinary scheduled shutdown of the coal mill, avoiding any additional downtime. Configuration of the control system. The preheater tower.
  • 5. LV distribution system, emergency power system, UPS system All LV distribution panels are of modular MNS type and have front-side operated withdrawable feeders, whereas the incomer circuit breakers are motor controlled. The intelligent motor control centre (MNSiS) is fully integrated into ABB’s 800xA control system. Through a complex but efficient fibre optic network, all intelligent motor starter detail information is accessible from any of the nine electrical rooms and from any of the plant’s three control rooms. The availability of essential information in the whole plant enables the central control room (CCR) operators and the electrical maintenance staff to make the most efficient decisions in the shortest possible time. For the safety of the equipment and for the emergency operation during power network shutdowns, the various emergency consumers are fed by a diesel generator unit. These consumers are connected to different motor control centre groups, which contain an incomer circuit breaker for the distribution transformer, as well as an incomer circuit breaker for the emergency power. Both incomers are feeding the same LV busbar and are therefore interlocked in order to use only either one of the two power supplies. UPS systems with an output of 220 V are installed in the CCR building and in the various substations to maintain power for servers, the central control system, remote I/O panels, instrumentation and the essential lighting. Acceleration programmes Due to overall project requirements during the execution phase of the line no. 7 project, Podilsky Cement asked ABB to plan and implement two acceleration programmes in order to significantly shorten the delivery time of the equipment included in ABB’s scope of supply. “On two separate occasions ABB was able to meet our requests for acceleration of their engineering and delivery programmes,” says Podilsky Cement’s Production Director Nigel Reape. After a detailed investigation, ABB presented the revised schedule, resulting in a reduced engineering and manufacturing time of approximately three months. This reduction of the delivery time could be reached due to the company’s ability to access its global expert resources in engineering ad hoc, as well as by increasing the resources working on the manufacturing side of the project. Despite the challenging schedule, the project team reached all the new milestones and delivered all the equipment and engineering documents on time while keeping ABB’s high quality standards. Reape continued: “This flexibility in meeting tight deadlines coupled with the ability to provide truly professional installation and commissioning engineers were critical in achieving our project deadlines. It was a pleasure to work with ABB on this project and we look forward to future collaborations.” Excellent cooperation during the complete project Building on the existing relationship from previous successful common projects, the cooperation between Podilsky Cement, CRH and ABB resulted in an efficient and smooth project execution. Reape concludes: “After the successful collaboration between Podilsky Cement and ABB on our coal mill installation project in 2006, Podilsky Cement was delighted to renew our partnership with ABB for the installation of our new cement production line. From the first steps of the detailed project design through to the intensive commissioning phase, the ABB project team provided professional and dedicated support to Podilsky Cement. Through open and honest communications our two teams developed a close working relationship, which was a key element in the successful completion of the project.” Table 1. Control system details Process controllers 9 Integration of Profibus interfaces 138 (55 from ABB scope of supply) Integration of Modbus interfaces 141 (33 from ABB scope of supply) Field inputs/outputs (digital) 3616 Field inputs/outputs (analog) 1072 Intelligent MCC starter 358 PID control loops 32 Third party PLC* interfaces 7 Third party OPC** interfaces 4 Aspect servers 3 Connectivity servers 2 Domain servers 2 Knowledge Manager (KM) 1 Data collector node (DCN) 1 Engineering station 1 Operators station 5 in CCR***, 1 in LCR**** for clay, 1 in limestone LCR approximately 3.5 km from plant 800xA version SV5.0 SP2, Rev.C, Minerals Lib 5.1/2 Major OEM interfaces Polysius, FLSmidth, Beumer, Schenck Process, Hasler, FLSmidth Pfister, Bedeschi, Auma, Saacke Intelligent MCCs with ABB latest MNSiS technology providing reliable motor protection and control, communicating with the 800xA system throughout the complete plant, including the nine substations through ModBus@TCPIP protocol *PLC - Programmable logic controller **OPC - Object linking and embedding (OLE) for process control ***CCR - Central control room ****LCR - Local control room
  • 6. ©Copyright2012ABB.Allrightsreserved.3BHS396312ZABE01(03.12250Köpfli&Partner) Main Technology Center for electrical, control and instrumentation systems ABB Switzerland Ltd Segelhofstrasse 9P CH-5405 Baden 5 Dättwil Switzerland Phone: +41 58 586 84 44 Fax: +41 58 586 73 33 E-mail: minerals@ch.abb.com Local Operation Center ABB Ltd 20-A Gagarina Pr. Kharkiv 61001 Ukraine Phone: +380 57 714 97 90 Fax: +380 57 714 97 91 E-mail: automation.group@ua.abb.com ABB’s Minerals business unit, with headquarters in USA (Houston, Texas), is represented in the following countries: Argentina, Australia, Brazil, Canada, Chile, China, Egypt, Estonia, Germany, Greece, India, Indonesia, Kazakhstan, Latvia, Lithuania, Malaysia, Mexico, North America, Norway, Oman, Peru, Poland, Saudi Arabia, Serbia, South Africa, Spain, Sweden, Switzerland, Thailand and Vietnam. For contact details, please visit our website: www.abb.com/cement www.abb.ua Contact us