COTM 5104: CONSTRUCTION MANAGEMENT
Chapter 1
Introduction
GETANEH GEZAHEGNE
March 2014
School of Civil and Environmental Engineering
ContentsContents
Introduction
1. Construction Industry
2. Domestic Construction Industry
3. Fundamentals of Management
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 2
1. Construction Industry1. Construction Industry
1.1. General
 Construction: is a process of constructing something by
man for one purpose or another. It may be a road, bridge,
dam, dwelling place, an airport, commercial building,
etc.
 Construction types:
 Residential buildings;
 Institutional and commercial buildings;
 Specialized industrial construction; and
 Infrastructure and heavy construction.
 Construction Industry (CI)) is an industry which is
involved in the planning, execution and evaluation of
all types of civil works.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 3
1. Construction Industry1. Construction Industry
1.1. General
 Project: is some form of human activity that has a
beginning, a productive phase and an end, creating
something that did not exist before.
 Construction Project: is an investment of scarce
resources with a definite objective, time horizon and
geographical boundary.
 Construction projects are mostly constructed on the
ground and exposed fully to the local environment.
 A construction project has different scale and
complexities. It ranges from improvements to large
investments. But, every project is:
 An investment of resources, and
 A cause of irreversible change.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 4
1. Construction Industry1. Construction Industry
1.1. General
 Common characteristics of construction projects:
 It has a specific starting and finishing time.
 It has usually geographical and sometimes
organizational boundary.
 It has clearly defined set of objectives.
 It entails the investment of scarce resources in the
expectation of future benefits.
 It may be planned, financed and implemented as a unit.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 5
1. Construction Industry1. Construction Industry
1.2. Study of Construction
 Study of Construction mainly covers two themes:
1. Construction Technology: Relates to methods and
techniques used to place the physical materials and
elements of construction at the Job site.
2. Construction Management: Addresses how available
resources will be applied.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 6
Money Manpower
Materials Machines
1. Construction Industry1. Construction Industry
1.2. Study of Construction
 Many great construction projects
mark significant milestones in
human history:
1. Great Pyramids;
2. Brooklyn Bridge;
3. Panama Canal; and
4. Euro/channel tunnel.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 7
1. Construction Industry1. Construction Industry
1.3. Construction Industry Category
 Construction Industry can be categorized into three major
sectors:
i.i. Transport and Communication SectorTransport and Communication Sector - Road, Railway,
Airway, and Telecommunication related physical works;
ii.ii. Water and Energy WorksWater and Energy Works – Hydropower development,
transmission lines, wind power, irrigation projects; and
iii.iii. Buildings and Other Physical InfrastructuresBuildings and Other Physical Infrastructures.
 CI is among the leading industry in producing
employment and contribute to the over all national
development.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 8
1. Construction Industry1. Construction Industry
1.3. Construction Industry Category
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 9
Transportation Infrastructure
Urban development
Energy supply
Water supply
The ConstructionThe Construction
IndustryIndustry
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry:
 Requires big capital investment thus is highly affected by
the economy of the nation.
 Consumes much of the national budget in developing
countries like Ethiopia.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 10
World Total 3.41 Trillion $
Asia 1,113 Billion $
Europe 1,017 Billion $
North America 885 Billion $
Latin America 241 Billion $
Middle East 101 Billion $
Africa 56 Billion $
1. US $819 B (8.2%)
2. Japan $618 B (13.9%)
3. Germany $253 B (11.4%)
4. China $181 B (17.0%)
5. UK $109 B (7.7%)
Ethiopia $ 402 M(59.8%)
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry:
A. Nature of production:A. Nature of production: mainly on site.
 Changing supply-chain relationship and production site.
 Exposed to inclement weather condition.
 Seasonal disruption.
 Health and safety concerns.
B. Nature of productB. Nature of product
 Large, heavy, durable, expensive, heterogeneous, and
immobile.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 11
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry:
C. Demand for the productC. Demand for the product
 Demand is usually driven by ‘other’ goods and services;
not controlled by industry,
 In the majority of cases, clients define requirements
before the industry provides it,
 Time lags between demand and supply is long.
D. The WorkforceD. The Workforce
 The industry is, by its very nature, an overwhelmingly
domestic and labor-intensive industry despite the
advancement in modern technologies.
 Construction is a team output and requires motivated and
skilled workers.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 12
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:
 Fragmented industry;
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 13
Need Design Bid Build
Client ClientA/E Contractor
Fragmented project participants
Sequential process
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:
 Long production cycle;
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 14
1. Construction Industry1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:
 Large uncertainty;
 Transient organization nature;
 Unpredictable work load; and
 Subject to environmental impact.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 15
1. Construction Industry1. Construction Industry
1.5. Roles of Construction Industry
 Construction Industry is the most important enabler for
social, economic and political development of countries.
 It provides the basis upon which other sectors can grow
by constructing the physical facilities required for the
production and distribution of goods and services.
 Specifically this fact is true for least developing countries
like Ethiopia because projects are:
 Inter-sectoral;
 Source of employment; and
 Demands huge capital budget.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 16
1.6. Construction Project Lifecycle
 The project life cycle of a construction project may be viewed as a
process through which a project is implemented from cradle to
grave.
1. Construction Industry1. Construction Industry
17
Definition of project
objectives and scope
Conceptual plan or
preliminary design
Plans and specifications
Completion of
construction
Acceptance of facility
Fulfillment
of useful life
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G.
1. Construction Industry1. Construction Industry
1.7. Stakeholders of Construction sector
 Stakeholders of Construction sector:
 Construction Industry involves many people, organization, agencies,
ministries, designers, contractors, project managers, equipment
suppliers, material suppliers, testing Laboratories, etc.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 18
ContractorContractor
ArchitectArchitect
EngineerEngineer
SuppliersSuppliers
SubsSubs
VendorsVendors
PublicPublic
OwnerOwner
1. Construction Industry1. Construction Industry
1.7. Stakeholders of Construction sector
 Contractual stakeholders:
 Employer/Client,
 Consultant/Engineer, and
 Contractor.
 Non-contractual stakeholders:
 Public agencies: Statutory Agencies (EEPCo, AAWSA,
Fire Authority), Public authorities and Municipalities
(land and building permit),
 Suppliers, and
 End users etc.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 19
1. Construction Industry1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.1 Employer/client
 Employer/Client is the initiator and owner of the project (it
can be public or private client).
 The client is the most important party who is active from
inception to completion and event to post-occupancy
maintenance.
 Duties of the client encompass the following:
 Availability and cost of land,
 Location & accessibility
 Required Infrastructure
 Legal constraints
 Current & future development
 Soil characteristics of land
 Site preparation (right of way)
 Permits
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 20
1. Construction Industry1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.2 Consultant
 The main role of the consultant is to interpret the client’s
project requirement into a specific design and possibly the
supervision.
 The consultants’ team shall:
 Ascertain, interpret and formulate the client’s requirement into an
understandable project.
 Design the project to much requirements and constraints (imposed by
statutory obligations, technical feasibility, environmental factors, site
conditions, cost, etc)
 Assess client’s cost limit to decide on materials & the like.
 Prepare contract documents.
 Supervise the project and constantly inform the client on the progress
 Approve payments
 Resolve contractual disputes
 Issue provisional and final acceptance certification
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 21
1. Construction Industry1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.3 Contractor
 These are groups established mainly as commercial
companies, that contract to construct development projects.
 Responsibility of contractors:
 Carry out a full site investigation prior to submission of tender,
 Submit tender,
 Plan, Program, Control the construction process.
 Notify the consultant about delays, discrepancies,
 Effect all payments to his employees, suppliers, subcontractors,
 Rectify all defects on completion of works, etc
 Provide post occupancy repair and maintenance if required.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 22
1. Construction Industry1. Construction Industry
1.8. Resources for Construction Industry
 The following resources are vital that make up an integral
components for construction industry:
 Human Resources (Labor or Workmen);
 Financial Resources ( Fund);
 Information Resources;
 Physical Resources ( Materials, Equipment and Other
Assets); and
 Services and Management.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 23
2. Domestic Construction Industry2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 Previous monarchies had contributed to the development of
construction in Ethiopia.
 Historic chronicles of the 17th
and 18th
centuries showed
that there were a number of small roads, palaces and
river improvement works.
 Among the Emperors Atse Fasil, Atse Tewodros and Atse
Menilik were noted for their major contributions.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 24
2. Domestic Construction Industry2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 Modern construction however had started during the reign
of Emperor Menilik II (The road from Addis Ababa toAddis Ababa to
AsmaraAsmara).
 Italy during its invasion (1936-19411936-1941) had also contributed
to the development of the construction industry. It had
constructed about 6000km6000km of roads.
 After Italian invasion, the first Ministry called “MinistryMinistry
of Communication and Public Worksof Communication and Public Works’’ was established
during the Imperial regime.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 25
2. Domestic Construction Industry2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 The construction development can be reviewed into six
distinct periods based on the historical paradigm shifts
in the construction industry in Ethiopia:
i. Pre 1968: Foreign Companies dominated construction
Industry.
ii. 1968-1982: Emergence of Small scale Domestic construction
companies,
iii. 1982-1987: Parastatal companies dominated Construction
Industry,
iv. 1987-1991: Fragmentation between Design services &
Construction works,
v. 1991-2001: Parastatal Domination legally abolished, and re-
emergence of private construction companies,
vi. 2001- to date: Integration and Capacity Building.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 26
2. Domestic Construction Industry2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 Current status of the construction industry is
distinguished by:
 Lack of clear developmental objectives for the industry;
 Inadequate co-ordination of planning between the industry and
infrastructure programs in the various sectors of the economy;
 Heavy dependence on foreign resources such as materials,
equipment and expertise, which continue to be supplied to a
major extent by foreign consultants and contractors;
 Transport bottlenecks to the distribution of construction
materials and equipment;
 Inadequate relevant local construction regulations and
standards;
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 27
2. Domestic Construction Industry2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 Current status of the construction industry is
distinguished by:
 Control of the construction sector by small-to-medium sized
firms and parastatal construction enterprises operating at low
levels of capacity and with inadequate working capital;
 Inadequate and ineffective organizations representing the
interests of contractors, consultants and engineers;
 Inadequate numbers of suitably qualified and experienced
personnel, at all levels: engineers, technicians, mechanics,
operators and foremen etc.;
 Inadequate consideration given to the use of local resources
(including community participation in labor-based works);
 Little consideration given to the concept or cost of maintenance
as a component of investment costs.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 28
2. Domestic Construction Industry2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 The general state of the domestic construction industry
in Ethiopia is characterized by the following five major
deficiencies:
 An inadequate capital base;
 Old and limited numbers of equipment;
 Low levels of equipment availability and utilization;
 Deficiencies in technical, managerial, financial and
entrepreneurial skills; and
 Insufficient and ineffective use of labor-based construction
and maintenance technology.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 29
2. Domestic Construction Industry2. Domestic Construction Industry
2.3. Challenges of Domestic Construction Industry
 Some of the major challenges faced in the Ethiopian
construction industry are:
 Lack of equipment and material;
 Obstacles posed by government regulations;
 Scarcity of finance;
 Big projects off-limits to domestic firms;
 Inefficient custom and clearance;
 Lack of skilled labor; and
 Construction project delays:- Delays are endemic to
construction projects in Ethiopia.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 30
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 The Road Sector Development Plan (RSDP) has been
implemented over a period of thirteen years and in three
separate phases, as follows:
 RSDP I – Period from July 1997 to June 2002 (5 year plan);
 RSDP II – Period July 2002 to June 2007 (5 year plan); and
 RSDP III – Period July 2007 to June 2010 (3 year plan).
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 31
Phases of the Program Financial (in Million
ETB)
% Physical ( in km) %
Budget Disb. Plan Acco.
RSDP I (Five Years ) 9812.9 7284.57284.5 74 8908 87098709 98
RSDP II (Five Years) 15985.8 18112.818112.8 113 8486 1200612006 142
RSDP III (Three Years) 34643.9 34957.834957.8 101 20686 1925019250 93
Total RSDP (Thirteen
Years ) 60442.6 60355.160355.1 100 38080 3996539965 105
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 RSDP IV is prepared as part of Governments’ overall
Growth and Transformation Plan.
 Implementation of RSDP IV is major strategic pillar of the
Growth and Transformation Plan.
 RSDP IV consists of:
 Rehabilitation of 728Km of trunk roads;
 Upgrading of 5,023Km of trunk and link roads;
 Construction of 4,331Km of new link roads;
 Heavy maintenance of 4,700Km of paved and gravel roads;
and
 Routine maintenance of 84,649Km of road network.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 32
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 The program also consists of the following regional and
Wereda road components through Universal Road Access
Program, URAP.
 Construction of 11,212Km of new rural roads through
the RRAs; and
 Construction of 71,523Km of Wereda roads through the
Wereda road offices.
 Cost Estimate:
 The total cost of implementing RSDP IV is estimated to
be ETB 125,276.7 million.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 33
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
 Ethiopian Railway Corporation, ERC is presently
managing a 5,000Km proposed National Railway Network
study and the Addis Ababa Light Rail Transit (AALRT)
Project.
A. Addis Ababa Light Rail transit Project (AA LRT):
 The 1st Phase of the LRT project comprises an East-West
line from Ayat to Torhailoch (17.35Km) and a North-
South line from Menelik II Sq. to Kality (16.90 Km).
 The Total Length of Phase I will be 34.25Km.
 Cost: USD 3 milion per Kilometre.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 34
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
A. Addis Ababa Light Rail transit Project (AA LRT):
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 35
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
B. Federal Railway Projects
 Ethiopia has launched the construction of a 5,000Km
railway complex which aims to link the capital, Addis
Ababa, to various regions of the country.
 According to the GTP 2,000Km of the total will be
constructed in the next five years.
 The first phase of construction will be the construction of
five railway tracks, which will create job opportunities for
over 300,000 citizens nationwide, and will cost the nation
an estimated 6 billion Birr (US$336 million) annually.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 36
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
B. Federal Railway Projects
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 37
Project
Phase
Route Via Distance
(Km)
Phase I Route 1 Addis Ababa (Sebeta)_Mojo_Awash_Dire Dewa_ Djibouti 656
Part of Route 3 Addis Ababa(Sebeta)_Ejaji_Seka_Bedele 366
Part of Route 6 Weldia_Mile_Djibouti_Railway 256
Part of Route 5 Awash_Kombolcha_Mekele 556.2
Phase II Route 4 Ejaji_Nekemt_Asossa_Kurmuk 460
Route 2 Mojo_Shashemene_Konso_Woyito_ Konso_ Moyale 905
Route 7 Wereta_Azezo_Metema 244
Part of Route 5 Mekele_Shire 201.2
Part of Route 6 Fnoteselam_Bahirdar_Wereta_Weldia 461
Route 8 Adama_Indeto_Gasera 248
Extension Extension to Sudan Via Boma (not part of the project) 115
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
B. Federal Railway Projects
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 38
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
 Ethiopia has a vast hydropower potential, which is
estimated to be about 45,000 MW.
 Even though Ethiopia considers itself the Powerhouse of
Africa, so far very little percentage (less than 5%) of the
vast potential has been harnessed.
 In 2009 less than 10% of Ethiopians had access to
electricity and the country was plagued by power outages.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 39
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 40
Name Installed
Capacity
Commissi
oning
Basin Contractor Financing Cost
Fincha 134 MW 1973 Fincha (Blue Nile)
Gilgel Gibe I 180 MW 2004 Omo river Salini (bid) World Bank $331m
Tekeze 300 MW 2009 Tekeze (Atbara) Sinohydro
Corporation (bid)
Chinese $365m
Beles 460 MW 2010 Lake Tana (Blue
Nile)
Salini (no bid) Ethiopian
government
Gilgel Gibe II 420 MW 2010 Omo River (no dam,
fed by GG I)
Salini (no bid) Italy and EIB Euro 370m
Gilgel Gibe III 1870 MW 2012-13 Omo river Salini (no bid) Italy Euro 1.55bn
Fincha Amerti
Nesse (FAN)
100 MW 2013 Fincha (Blue nile) China (CGGC) Exim Bank of
China
$276m
Halele
Worabese
440 MW 2014 Omo river Sinohydro
Corporation
FairFund? Euro 470m
Gilgel Gibe IV 2000 MW 2014 Tributary of the Omo
River
Sinohydro
Corporation
Chinese $1.9bn
Chemoga Yeda 278 MW 2013 tributary of the Blue
Nile, near Debre
Markos
Sinohydro
Corporation
Chinese $555m
Genale Dawa
III
256 MW Awarded
in 2009
between Oromo and
Somali state
Chineese (CGGC) Chinese $408m
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
Possible interconnection with neighboring countries
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 41
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
 EEPCo has decided to use wind power for the several
advantages that it posses:
 Being renewable;
 Being reliable and affordable;
 Being complementary to hydropower plants: rainy season
– low wind; dry season – high wind potential; and
 combining wind and hydro adds value to the hydro plant,
i.e. longer operation time, also at the end of dry season
(water saving through wind).
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 42
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 43
S. No. Name of the project Electric power
generation capacity in
MW
Year of
completion
11 Ashengoda Wind Power ProjectAshengoda Wind Power Project 120120 ((€210 million )€210 million ) 20122012
22 Adama Wind Power ProjectAdama Wind Power Project 51 (51 ($117 million)$117 million) 20112011
3 Adama II Wind Power Project 51 2013
4 Assela Wind Power Project 100 2013
5 Ayisha Wind Power Project 300 2012
66 Debre Birhan Wind Power ProjectDebre Birhan Wind Power Project 400400 20132013
7 Messobo Wind Power Project 42 2012
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
Four major search areas for wind power
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 44
2. Domestic Construction Industry2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.5 Irrigation Projects
2.4.6 Housing development projects
2.4.7 University Capacity Building Projects, UCBP
2.4.8 Sugar Factory Projects
2.4.9 Fertilizer Factory Projects
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 45
3. Fundamentals of Management3. Fundamentals of Management
3.1. Management: Definition
 A means of achieving political, economic, and social
objectives.
 A means of integrating resources (materials, finance,
human resources, information, etc.,) in order to achieve
organizational objectives efficiently and effectively.
 A means of getting things done through people in order
to achieve objectives.
 A process of establishing vision, mission, values,
objectives, goals, and strategies and communicating
these, and guiding and empowering others to accomplish
them.
 A process of planning, organizing, directing and
controlling of organizational activities in order to achieve
objectives.AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 46
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
 Management is a set of goal-directed,
interrelated and interdependent activities, aimed
at accomplishing organizational goals in an
efficient and effective manner.
 Generally, management functions encompass:
planning, organizing, leading and controlling.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 47
3. Fundamentals of Management3. Fundamentals of Management
Management Function inputs and outputs
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 48
Management sets direction
ResourcResourc
eses•HumanHuman
•FinancialFinancial
•Raw MaterialsRaw Materials
•TechnologicalTechnological
•InformationInformation
Inputs
PerformancePerformance
•Attain goalsAttain goals
•ProductsProducts
•ServicesServices
•EfficiencyEfficiency
•EffectivenessEffectiveness
Outputs
Planning
Controlling Organizing
Leading
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
 Planning: devising a systematic approach for attaining
the goals of the organization.
 Organizing: determining how activities and resources are
grouped and the composition of work groups and the way
in which work and activities are to be coordinated.
 Leading: guiding, leading and overseeing of employees
to achieve organizational goals.
 Controlling: establishing performance standards and
comparing results and expectations to make appropriate
changes.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 49
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 50
PlanningPlanningPlanningPlanning OrganizingOrganizingOrganizingOrganizing
LeadingLeadingLeadingLeadingControllingControllingControllingControlling
ManagementManagement
FunctionsFunctions
ManagementManagement
FunctionsFunctions
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.1 Planning
 Management starts with planning. Without a plan
organizations will never succeed. If they do, it will have
been by luck or chance and is not repeatable. Plan, will
help us in:
 What to accomplish (goals);
 When to accomplish the goals;
 What resources to use;
 Who should accomplish what;
 Where to accomplish; and
 What methods to use.
 Assess all possible scenarios including the best and worst
and what actions to take.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 51
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.2 Organizing
 Organizing refers to the process of designing jobs and
departments and determining authority relationships in
organizations.
 Organizing:
 Permits people to work together in order to achieve goals;
 Helps to achieve synergy;
 Avoid duplication of resources;
 Establish authority ; and
 And facilitate communication.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 52
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.2 Organizing
 Some issues in organizing include:
 Specialization (division of labor);
 Grouping jobs into departments and structuring
(functional, product, customer, geographic, matrix);
 Determining authority relationships (span of control,
chain of command);
 Delegation of authority; and
 Centralization and decentralization.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 53
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.3 Leading
 Influencing, inspiring and empowering employees to
work towards the leaders vision.
 Leading involves:
 Building successful groups and teams in organizations;
 Motivating people;
 Communication; and
 Developing organizational change.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 54
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
 The process of measuring performance, comparing it
with the objectives, and making any necessary
adjustments.
 The purpose of control include:
 Adapting to changes;
 Minimizing consequences of errors;
 Helping the organization cope with complexities; and
 Improving efficiency.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 55
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
A. Control Purpose
 The control function, in turn, has four basic purposes.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 56
3. Fundamentals of Management3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
B. Control Process
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 57
3. Fundamentals of Management3. Fundamentals of Management
3.3. Levels of Management
Manager: Definition
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 58
 The people looking beyond
themselves and exercising
formal authority over the
activities and performance of
other people in pursuit of
organizational goals.
 Someone whose primary
responsibility is to carry out the
management process.
 Someone who plans and makes
decisions, organizes, leads, and
controls human, financial,
physical, and information
resources.
3. Fundamentals of Management3. Fundamentals of Management
3.3. Levels of Management
A. Top Managers
 The relatively small group of executives who manage the
organization’s overall goals, strategy, and operating
policies.
B. Middle Managers
 Largest group of managers in organizations who are
primarily responsible for implementing the policies and
plans of top managers. They supervise and coordinate the
activities of lower-level managers.
C. First-Line Managers
 Managers who supervise and coordinate the activities of
operating employees.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 59
3. Fundamentals of Management3. Fundamentals of Management
3.3. Levels of Management
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 60
M
arketing
A
dm
inistration
O
ther
H
um
an
resources
O
perations
Finance
Middle managers
Areas of Management
Levels of Management
First-line managers
Top managers
3. Fundamentals of Management3. Fundamentals of Management
3.3. Levels of Management
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 61
Lower Level
Middle Level
Top Level
Make decision about the
overall direction and
performance of the
organization
Translate the over all direction
and performance into specific
objectives and plans
Implement directions
and plans through
production and delivery
of services
3. Fundamentals of Management3. Fundamentals of Management
3.4. Managerial skills
 Conceptual skills: the capacity to think in the abstract
and to see the organization as a complete unit and to
integrate and give direction to its diverse activities so that
objectives are achieved.
 Interpersonal skills: the ability to communicate with,
understand and motivate both individuals and groups.
 Technical skills: skills necessary to accomplish or
understand the specific kind of work being done in an
organization.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 62
3. Fundamentals of Management3. Fundamentals of Management
3.4. Managerial skills
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 63
Management Skills
Interpersonal Skills
Communication , conflict resolution, leading
Conceptual Skills
Intellectual ability to process information and make accurate
decision about the work, group, and the job
Technical Skills
Knowledge and ability to accomplish the specialized activities of the
work group
Top Level Middle Level Lower Level
3. Fundamentals of Management3. Fundamentals of Management
3.5. Construction Management
 The management of construction is an enterprise that
involves many people with diverse interests, talents and
backgrounds. The owner, design professional and
contractor comprise the primary triad of parties,
 However, others such as subcontractors, material
suppliers, bankers, insurance and bonding companies,
attorneys and public agency officials, are vital elements
of the project team whose interrelated roles must be
coordinated to assure a successful project.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 64
3. Fundamentals of Management3. Fundamentals of Management
3.5. Construction Management
 The function of project management for construction
include:
 Specification of project objectives and plans including
delineation of scope, budgeting, scheduling, setting
performance requirements, and selecting project participants.
 Maximization of efficient resource utilization through
procurement of labor, materials and equipment according to
the prescribed schedule and plan.
 Implementation of various operations through proper
coordination and control of planning, design, estimating,
contracting and construction in the entire process.
 Development of effective communications and mechanisms
for resolving conflicts among the various participants.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 65
3. Fundamentals of Management3. Fundamentals of Management
3.6. Organization Management
A. Organization
 A consciously coordinated social unit, composed of two
or more people influencing each other that functions on a
relatively continuous basis to achieve a common goal or
set of goals.
 It is a structured process in which people interact and
influence each other in order to achieve objectives.
B. Components of Origination
 People,
 Influence ,
 Goals or Purpose,
 Structure, and
 Technology.AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 66
3. Fundamentals of Management3. Fundamentals of Management
3.6. Organization Management
C. Organization Environment
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 67
ORGANIZATION
Near or Operating
Environment
Customers
Clients
Competitors
Suppliers
Partners
Macro or Far Environment
Technological
Factors
Social
Factors
Political
Factors
Economic
Factors
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organizational Structure
 Organizational structures can fall into either
mechanistic or organic forms.
 Mechanistic organizations are rather rigid in that they
comprise distinctly delineated jobs, clearly defined
hierarchical structure and are driven primarily by top-
down command and control. Mechanistic organizations
are tall structures, consisting of hierarchies with several
layers of management levels.
 Organic structures are is relatively flexible. They are
structurally decentralized, empowering employees at all
levels of the organization to take personal responsibility
for the processes and activities in which they are
engaged.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 68
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organizational Structure
 Organizational design is creating an appropriate
organizational structure that will enable the organization
to accomplish its goals.
 The organization can choose from among functional,
divisional or matrix designs, whichever is appropriate.
 It is the process of arranging, allocating work authority
and resources to achieve organization goals.
 It involves:
 Identifying tasks to be performed;
 Allocating the tasks among members; and
 Integrating efforts to achieve its objectives.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 69
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organizational Structure
Key Concepts
 Span of Management Control: The number of
subordinates reporting directly to a given manger;
 Chain of Command: The plan that specifies who reports
to whom in an organization, such reporting lines are
prominent features of organization chart;
 Coordination: The integration of the activities of the
separates parts of an organization to accomplish
organizational goals; and
 Downsizing: A version of organizational restructuring
which results in decreasing the size of the organization
and often results in a flatter organizational structure.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 70
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organization Structure
3.7.1. Functional Organization
 In a functional organization, tasks or jobs of similar
nature are grouped together and structured as a unit.
Each unit is staffed by functional specialists.
 Structuring the organization along the functional lines
facilitates good coordination and makes supervision of
the unit easy for managers as they only need to be
familiar with a narrow set of skills.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 71
General ManagerGeneral Manager
Marketing MgrMarketing Mgr.. Production Mgr.Production Mgr. Finance Mgr. HRM Mgr.HRM Mgr.
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organization Structure
3.7.2. Divisional Organization
 Divisional structures are grouped according to workflow
and structures are made up of independent strategic
organizational units.
 The workflow can be broken into product lines,
geographic regions, etc.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 72
GM (Head Quarter)GM (Head Quarter)
(A.A)(A.A)
DGM (Awasa)DGM (Awasa) DGM (Mekelle)DGM (Mekelle) DGM (Bahir DarDGM (Bahir Dar)DGM (Jimma)DGM (Jimma)
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organization Structure
3.7.3. Matrix Organization
 In matrix organization, individuals are made responsible
both to their line manager and the project manager
involved.
 The matrix concept facilitates working on concurrent
projects by creating a dual chain of command, the
project (program, systems, or product) manager and the
functional manager.
 Matrix structures utilize functional and divisional chains
of command simultaneously in the same part of the
organization, commonly for one-of-a-kind projects.
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 73
3. Fundamentals of Management3. Fundamentals of Management
3.7. Organization Structure
3.7.3. Matrix Organization
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 74
FinanceFinance
GrpGrp
MarketingMarketing
GrpGrp
MaterialsMaterials
GrpGrp
HRHR
GrpGrp
HRHR
GrpGrp
ProductionProduction
GrpGrp
FinanceFinance
GrpGrp
MaterialsMaterials
GrpGrp
ProductionProduction
GrpGrp
MarketingMarketing
GrpGrpProject AProject A
ManagerManager
Project BProject B
ManagerManager
ProductionProduction FinanceFinance MarketingMarketing
MaterialMaterial
&&
ProcurementProcurement
HumanHuman
ResourceResource
Head QuarterHead Quarter
THANK YOU!
AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 75

More Related Content

What's hot

Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in ConstructionSamsonFemiAdesope
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1KohSungJie
 
Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction companyRevati Bargale
 
Construction Management Introduction ppt
Construction Management  Introduction pptConstruction Management  Introduction ppt
Construction Management Introduction pptRajeshPV12
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanAnis Rahman Khokan
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptssuserb4074f
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
basics of civil engineering
basics of civil engineeringbasics of civil engineering
basics of civil engineeringChirag Bhanagale
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPTKEVINMISTRY8
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project managementAravind Samala
 
building construction,ppt
building construction,pptbuilding construction,ppt
building construction,pptPawankumarm65
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Job layout of cinstruction site
Job layout of cinstruction siteJob layout of cinstruction site
Job layout of cinstruction siteraj balar
 

What's hot (20)

Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Building Construction 1: Project 1
Building Construction 1: Project 1Building Construction 1: Project 1
Building Construction 1: Project 1
 
Manpower planning for a construction company
Manpower planning for a construction companyManpower planning for a construction company
Manpower planning for a construction company
 
Researches in engineering project management
Researches in engineering project managementResearches in engineering project management
Researches in engineering project management
 
Construction Management Introduction ppt
Construction Management  Introduction pptConstruction Management  Introduction ppt
Construction Management Introduction ppt
 
Construction industry
Construction industryConstruction industry
Construction industry
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
basics of civil engineering
basics of civil engineeringbasics of civil engineering
basics of civil engineering
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Planning of materials in Construction Project management
Planning of materials in Construction Project managementPlanning of materials in Construction Project management
Planning of materials in Construction Project management
 
Concrete works
Concrete worksConcrete works
Concrete works
 
building construction,ppt
building construction,pptbuilding construction,ppt
building construction,ppt
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
List Of Post Graduate Thesis in engineering project management
List Of Post Graduate Thesis in engineering project managementList Of Post Graduate Thesis in engineering project management
List Of Post Graduate Thesis in engineering project management
 
Job layout of cinstruction site
Job layout of cinstruction siteJob layout of cinstruction site
Job layout of cinstruction site
 

Similar to 1. introduction cm 2014

Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET Journal
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdfFaruq42
 
Challenges Faced in Indian Construction Sector
Challenges Faced in Indian Construction SectorChallenges Faced in Indian Construction Sector
Challenges Faced in Indian Construction Sectorijtsrd
 
Mechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in IndiaMechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in IndiaJIT KUMAR GUPTA
 
Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...IJAEMSJORNAL
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 
IRJET- Risk Management in BOT PNG Toll Plaza
IRJET- Risk Management in BOT PNG Toll PlazaIRJET- Risk Management in BOT PNG Toll Plaza
IRJET- Risk Management in BOT PNG Toll PlazaIRJET Journal
 
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksakCOTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak2cd
 
Chapter 1 introduction of construction engineering
Chapter 1 introduction of construction engineeringChapter 1 introduction of construction engineering
Chapter 1 introduction of construction engineeringSuhaimi Alsegamati
 

Similar to 1. introduction cm 2014 (20)

CHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdfCHAPTER-1 INTRODUCTION.pdf
CHAPTER-1 INTRODUCTION.pdf
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Essay Construction
Essay ConstructionEssay Construction
Essay Construction
 
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
IRJET- Project Economic Appraisal Techniques in Construction Industry - A Com...
 
20320140503023
2032014050302320320140503023
20320140503023
 
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdfARC 425 - LECTURE RESOURCE 1  - Const Mgt.pdf
ARC 425 - LECTURE RESOURCE 1 - Const Mgt.pdf
 
Challenges Faced in Indian Construction Sector
Challenges Faced in Indian Construction SectorChallenges Faced in Indian Construction Sector
Challenges Faced in Indian Construction Sector
 
Mechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in IndiaMechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in India
 
Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...Sustainability Indicators in Building Projects in Khartoum State during Const...
Sustainability Indicators in Building Projects in Khartoum State during Const...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdf
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 
IRJET- Risk Management in BOT PNG Toll Plaza
IRJET- Risk Management in BOT PNG Toll PlazaIRJET- Risk Management in BOT PNG Toll Plaza
IRJET- Risk Management in BOT PNG Toll Plaza
 
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksakCOTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak
COTM (1).ppt gwremejjjedhdwfwqoijfkskjlksak
 
Chapter 1 introduction of construction engineering
Chapter 1 introduction of construction engineeringChapter 1 introduction of construction engineering
Chapter 1 introduction of construction engineering
 

Recently uploaded

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

1. introduction cm 2014

  • 1. COTM 5104: CONSTRUCTION MANAGEMENT Chapter 1 Introduction GETANEH GEZAHEGNE March 2014 School of Civil and Environmental Engineering
  • 2. ContentsContents Introduction 1. Construction Industry 2. Domestic Construction Industry 3. Fundamentals of Management AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 2
  • 3. 1. Construction Industry1. Construction Industry 1.1. General  Construction: is a process of constructing something by man for one purpose or another. It may be a road, bridge, dam, dwelling place, an airport, commercial building, etc.  Construction types:  Residential buildings;  Institutional and commercial buildings;  Specialized industrial construction; and  Infrastructure and heavy construction.  Construction Industry (CI)) is an industry which is involved in the planning, execution and evaluation of all types of civil works. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 3
  • 4. 1. Construction Industry1. Construction Industry 1.1. General  Project: is some form of human activity that has a beginning, a productive phase and an end, creating something that did not exist before.  Construction Project: is an investment of scarce resources with a definite objective, time horizon and geographical boundary.  Construction projects are mostly constructed on the ground and exposed fully to the local environment.  A construction project has different scale and complexities. It ranges from improvements to large investments. But, every project is:  An investment of resources, and  A cause of irreversible change. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 4
  • 5. 1. Construction Industry1. Construction Industry 1.1. General  Common characteristics of construction projects:  It has a specific starting and finishing time.  It has usually geographical and sometimes organizational boundary.  It has clearly defined set of objectives.  It entails the investment of scarce resources in the expectation of future benefits.  It may be planned, financed and implemented as a unit. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 5
  • 6. 1. Construction Industry1. Construction Industry 1.2. Study of Construction  Study of Construction mainly covers two themes: 1. Construction Technology: Relates to methods and techniques used to place the physical materials and elements of construction at the Job site. 2. Construction Management: Addresses how available resources will be applied. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 6 Money Manpower Materials Machines
  • 7. 1. Construction Industry1. Construction Industry 1.2. Study of Construction  Many great construction projects mark significant milestones in human history: 1. Great Pyramids; 2. Brooklyn Bridge; 3. Panama Canal; and 4. Euro/channel tunnel. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 7
  • 8. 1. Construction Industry1. Construction Industry 1.3. Construction Industry Category  Construction Industry can be categorized into three major sectors: i.i. Transport and Communication SectorTransport and Communication Sector - Road, Railway, Airway, and Telecommunication related physical works; ii.ii. Water and Energy WorksWater and Energy Works – Hydropower development, transmission lines, wind power, irrigation projects; and iii.iii. Buildings and Other Physical InfrastructuresBuildings and Other Physical Infrastructures.  CI is among the leading industry in producing employment and contribute to the over all national development. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 8
  • 9. 1. Construction Industry1. Construction Industry 1.3. Construction Industry Category AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 9 Transportation Infrastructure Urban development Energy supply Water supply The ConstructionThe Construction IndustryIndustry
  • 10. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry:  Requires big capital investment thus is highly affected by the economy of the nation.  Consumes much of the national budget in developing countries like Ethiopia. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 10 World Total 3.41 Trillion $ Asia 1,113 Billion $ Europe 1,017 Billion $ North America 885 Billion $ Latin America 241 Billion $ Middle East 101 Billion $ Africa 56 Billion $ 1. US $819 B (8.2%) 2. Japan $618 B (13.9%) 3. Germany $253 B (11.4%) 4. China $181 B (17.0%) 5. UK $109 B (7.7%) Ethiopia $ 402 M(59.8%)
  • 11. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry: A. Nature of production:A. Nature of production: mainly on site.  Changing supply-chain relationship and production site.  Exposed to inclement weather condition.  Seasonal disruption.  Health and safety concerns. B. Nature of productB. Nature of product  Large, heavy, durable, expensive, heterogeneous, and immobile. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 11
  • 12. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.1 Nature of Construction Industry:1.4.1 Nature of Construction Industry: C. Demand for the productC. Demand for the product  Demand is usually driven by ‘other’ goods and services; not controlled by industry,  In the majority of cases, clients define requirements before the industry provides it,  Time lags between demand and supply is long. D. The WorkforceD. The Workforce  The industry is, by its very nature, an overwhelmingly domestic and labor-intensive industry despite the advancement in modern technologies.  Construction is a team output and requires motivated and skilled workers. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 12
  • 13. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:  Fragmented industry; AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 13 Need Design Bid Build Client ClientA/E Contractor Fragmented project participants Sequential process
  • 14. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:  Long production cycle; AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 14
  • 15. 1. Construction Industry1. Construction Industry 1.4. Construction Industry Attributes 1.4.2 Uniqueness of Construction Industry:1.4.2 Uniqueness of Construction Industry:  Large uncertainty;  Transient organization nature;  Unpredictable work load; and  Subject to environmental impact. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 15
  • 16. 1. Construction Industry1. Construction Industry 1.5. Roles of Construction Industry  Construction Industry is the most important enabler for social, economic and political development of countries.  It provides the basis upon which other sectors can grow by constructing the physical facilities required for the production and distribution of goods and services.  Specifically this fact is true for least developing countries like Ethiopia because projects are:  Inter-sectoral;  Source of employment; and  Demands huge capital budget. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 16
  • 17. 1.6. Construction Project Lifecycle  The project life cycle of a construction project may be viewed as a process through which a project is implemented from cradle to grave. 1. Construction Industry1. Construction Industry 17 Definition of project objectives and scope Conceptual plan or preliminary design Plans and specifications Completion of construction Acceptance of facility Fulfillment of useful life AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G.
  • 18. 1. Construction Industry1. Construction Industry 1.7. Stakeholders of Construction sector  Stakeholders of Construction sector:  Construction Industry involves many people, organization, agencies, ministries, designers, contractors, project managers, equipment suppliers, material suppliers, testing Laboratories, etc. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 18 ContractorContractor ArchitectArchitect EngineerEngineer SuppliersSuppliers SubsSubs VendorsVendors PublicPublic OwnerOwner
  • 19. 1. Construction Industry1. Construction Industry 1.7. Stakeholders of Construction sector  Contractual stakeholders:  Employer/Client,  Consultant/Engineer, and  Contractor.  Non-contractual stakeholders:  Public agencies: Statutory Agencies (EEPCo, AAWSA, Fire Authority), Public authorities and Municipalities (land and building permit),  Suppliers, and  End users etc. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 19
  • 20. 1. Construction Industry1. Construction Industry 1.7. Stakeholders of Construction Sector 1.7.1 Employer/client  Employer/Client is the initiator and owner of the project (it can be public or private client).  The client is the most important party who is active from inception to completion and event to post-occupancy maintenance.  Duties of the client encompass the following:  Availability and cost of land,  Location & accessibility  Required Infrastructure  Legal constraints  Current & future development  Soil characteristics of land  Site preparation (right of way)  Permits AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 20
  • 21. 1. Construction Industry1. Construction Industry 1.7. Stakeholders of Construction Sector 1.7.2 Consultant  The main role of the consultant is to interpret the client’s project requirement into a specific design and possibly the supervision.  The consultants’ team shall:  Ascertain, interpret and formulate the client’s requirement into an understandable project.  Design the project to much requirements and constraints (imposed by statutory obligations, technical feasibility, environmental factors, site conditions, cost, etc)  Assess client’s cost limit to decide on materials & the like.  Prepare contract documents.  Supervise the project and constantly inform the client on the progress  Approve payments  Resolve contractual disputes  Issue provisional and final acceptance certification AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 21
  • 22. 1. Construction Industry1. Construction Industry 1.7. Stakeholders of Construction Sector 1.7.3 Contractor  These are groups established mainly as commercial companies, that contract to construct development projects.  Responsibility of contractors:  Carry out a full site investigation prior to submission of tender,  Submit tender,  Plan, Program, Control the construction process.  Notify the consultant about delays, discrepancies,  Effect all payments to his employees, suppliers, subcontractors,  Rectify all defects on completion of works, etc  Provide post occupancy repair and maintenance if required. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 22
  • 23. 1. Construction Industry1. Construction Industry 1.8. Resources for Construction Industry  The following resources are vital that make up an integral components for construction industry:  Human Resources (Labor or Workmen);  Financial Resources ( Fund);  Information Resources;  Physical Resources ( Materials, Equipment and Other Assets); and  Services and Management. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 23
  • 24. 2. Domestic Construction Industry2. Domestic Construction Industry 2.1. Domestic Construction Industry: Historical Aspect  Previous monarchies had contributed to the development of construction in Ethiopia.  Historic chronicles of the 17th and 18th centuries showed that there were a number of small roads, palaces and river improvement works.  Among the Emperors Atse Fasil, Atse Tewodros and Atse Menilik were noted for their major contributions. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 24
  • 25. 2. Domestic Construction Industry2. Domestic Construction Industry 2.1. Domestic Construction Industry: Historical Aspect  Modern construction however had started during the reign of Emperor Menilik II (The road from Addis Ababa toAddis Ababa to AsmaraAsmara).  Italy during its invasion (1936-19411936-1941) had also contributed to the development of the construction industry. It had constructed about 6000km6000km of roads.  After Italian invasion, the first Ministry called “MinistryMinistry of Communication and Public Worksof Communication and Public Works’’ was established during the Imperial regime. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 25
  • 26. 2. Domestic Construction Industry2. Domestic Construction Industry 2.1. Domestic Construction Industry: Historical Aspect  The construction development can be reviewed into six distinct periods based on the historical paradigm shifts in the construction industry in Ethiopia: i. Pre 1968: Foreign Companies dominated construction Industry. ii. 1968-1982: Emergence of Small scale Domestic construction companies, iii. 1982-1987: Parastatal companies dominated Construction Industry, iv. 1987-1991: Fragmentation between Design services & Construction works, v. 1991-2001: Parastatal Domination legally abolished, and re- emergence of private construction companies, vi. 2001- to date: Integration and Capacity Building. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 26
  • 27. 2. Domestic Construction Industry2. Domestic Construction Industry 2.2. Current Status of Local Construction Industry  Current status of the construction industry is distinguished by:  Lack of clear developmental objectives for the industry;  Inadequate co-ordination of planning between the industry and infrastructure programs in the various sectors of the economy;  Heavy dependence on foreign resources such as materials, equipment and expertise, which continue to be supplied to a major extent by foreign consultants and contractors;  Transport bottlenecks to the distribution of construction materials and equipment;  Inadequate relevant local construction regulations and standards; AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 27
  • 28. 2. Domestic Construction Industry2. Domestic Construction Industry 2.2. Current Status of Local Construction Industry  Current status of the construction industry is distinguished by:  Control of the construction sector by small-to-medium sized firms and parastatal construction enterprises operating at low levels of capacity and with inadequate working capital;  Inadequate and ineffective organizations representing the interests of contractors, consultants and engineers;  Inadequate numbers of suitably qualified and experienced personnel, at all levels: engineers, technicians, mechanics, operators and foremen etc.;  Inadequate consideration given to the use of local resources (including community participation in labor-based works);  Little consideration given to the concept or cost of maintenance as a component of investment costs. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 28
  • 29. 2. Domestic Construction Industry2. Domestic Construction Industry 2.2. Current Status of Local Construction Industry  The general state of the domestic construction industry in Ethiopia is characterized by the following five major deficiencies:  An inadequate capital base;  Old and limited numbers of equipment;  Low levels of equipment availability and utilization;  Deficiencies in technical, managerial, financial and entrepreneurial skills; and  Insufficient and ineffective use of labor-based construction and maintenance technology. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 29
  • 30. 2. Domestic Construction Industry2. Domestic Construction Industry 2.3. Challenges of Domestic Construction Industry  Some of the major challenges faced in the Ethiopian construction industry are:  Lack of equipment and material;  Obstacles posed by government regulations;  Scarcity of finance;  Big projects off-limits to domestic firms;  Inefficient custom and clearance;  Lack of skilled labor; and  Construction project delays:- Delays are endemic to construction projects in Ethiopia. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 30
  • 31. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.1 Road Construction  The Road Sector Development Plan (RSDP) has been implemented over a period of thirteen years and in three separate phases, as follows:  RSDP I – Period from July 1997 to June 2002 (5 year plan);  RSDP II – Period July 2002 to June 2007 (5 year plan); and  RSDP III – Period July 2007 to June 2010 (3 year plan). AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 31 Phases of the Program Financial (in Million ETB) % Physical ( in km) % Budget Disb. Plan Acco. RSDP I (Five Years ) 9812.9 7284.57284.5 74 8908 87098709 98 RSDP II (Five Years) 15985.8 18112.818112.8 113 8486 1200612006 142 RSDP III (Three Years) 34643.9 34957.834957.8 101 20686 1925019250 93 Total RSDP (Thirteen Years ) 60442.6 60355.160355.1 100 38080 3996539965 105
  • 32. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.1 Road Construction  RSDP IV is prepared as part of Governments’ overall Growth and Transformation Plan.  Implementation of RSDP IV is major strategic pillar of the Growth and Transformation Plan.  RSDP IV consists of:  Rehabilitation of 728Km of trunk roads;  Upgrading of 5,023Km of trunk and link roads;  Construction of 4,331Km of new link roads;  Heavy maintenance of 4,700Km of paved and gravel roads; and  Routine maintenance of 84,649Km of road network. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 32
  • 33. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.1 Road Construction  The program also consists of the following regional and Wereda road components through Universal Road Access Program, URAP.  Construction of 11,212Km of new rural roads through the RRAs; and  Construction of 71,523Km of Wereda roads through the Wereda road offices.  Cost Estimate:  The total cost of implementing RSDP IV is estimated to be ETB 125,276.7 million. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 33
  • 34. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.2 Railway Construction  Ethiopian Railway Corporation, ERC is presently managing a 5,000Km proposed National Railway Network study and the Addis Ababa Light Rail Transit (AALRT) Project. A. Addis Ababa Light Rail transit Project (AA LRT):  The 1st Phase of the LRT project comprises an East-West line from Ayat to Torhailoch (17.35Km) and a North- South line from Menelik II Sq. to Kality (16.90 Km).  The Total Length of Phase I will be 34.25Km.  Cost: USD 3 milion per Kilometre. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 34
  • 35. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.2 Railway Construction A. Addis Ababa Light Rail transit Project (AA LRT): AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 35
  • 36. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.2 Railway Construction B. Federal Railway Projects  Ethiopia has launched the construction of a 5,000Km railway complex which aims to link the capital, Addis Ababa, to various regions of the country.  According to the GTP 2,000Km of the total will be constructed in the next five years.  The first phase of construction will be the construction of five railway tracks, which will create job opportunities for over 300,000 citizens nationwide, and will cost the nation an estimated 6 billion Birr (US$336 million) annually. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 36
  • 37. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.2 Railway Construction B. Federal Railway Projects AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 37 Project Phase Route Via Distance (Km) Phase I Route 1 Addis Ababa (Sebeta)_Mojo_Awash_Dire Dewa_ Djibouti 656 Part of Route 3 Addis Ababa(Sebeta)_Ejaji_Seka_Bedele 366 Part of Route 6 Weldia_Mile_Djibouti_Railway 256 Part of Route 5 Awash_Kombolcha_Mekele 556.2 Phase II Route 4 Ejaji_Nekemt_Asossa_Kurmuk 460 Route 2 Mojo_Shashemene_Konso_Woyito_ Konso_ Moyale 905 Route 7 Wereta_Azezo_Metema 244 Part of Route 5 Mekele_Shire 201.2 Part of Route 6 Fnoteselam_Bahirdar_Wereta_Weldia 461 Route 8 Adama_Indeto_Gasera 248 Extension Extension to Sudan Via Boma (not part of the project) 115
  • 38. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.2 Railway Construction B. Federal Railway Projects AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 38
  • 39. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.3 Hydropower Development  Ethiopia has a vast hydropower potential, which is estimated to be about 45,000 MW.  Even though Ethiopia considers itself the Powerhouse of Africa, so far very little percentage (less than 5%) of the vast potential has been harnessed.  In 2009 less than 10% of Ethiopians had access to electricity and the country was plagued by power outages. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 39
  • 40. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.3 Hydropower Development AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 40 Name Installed Capacity Commissi oning Basin Contractor Financing Cost Fincha 134 MW 1973 Fincha (Blue Nile) Gilgel Gibe I 180 MW 2004 Omo river Salini (bid) World Bank $331m Tekeze 300 MW 2009 Tekeze (Atbara) Sinohydro Corporation (bid) Chinese $365m Beles 460 MW 2010 Lake Tana (Blue Nile) Salini (no bid) Ethiopian government Gilgel Gibe II 420 MW 2010 Omo River (no dam, fed by GG I) Salini (no bid) Italy and EIB Euro 370m Gilgel Gibe III 1870 MW 2012-13 Omo river Salini (no bid) Italy Euro 1.55bn Fincha Amerti Nesse (FAN) 100 MW 2013 Fincha (Blue nile) China (CGGC) Exim Bank of China $276m Halele Worabese 440 MW 2014 Omo river Sinohydro Corporation FairFund? Euro 470m Gilgel Gibe IV 2000 MW 2014 Tributary of the Omo River Sinohydro Corporation Chinese $1.9bn Chemoga Yeda 278 MW 2013 tributary of the Blue Nile, near Debre Markos Sinohydro Corporation Chinese $555m Genale Dawa III 256 MW Awarded in 2009 between Oromo and Somali state Chineese (CGGC) Chinese $408m
  • 41. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.3 Hydropower Development Possible interconnection with neighboring countries AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 41
  • 42. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.4 Wind Power Development  EEPCo has decided to use wind power for the several advantages that it posses:  Being renewable;  Being reliable and affordable;  Being complementary to hydropower plants: rainy season – low wind; dry season – high wind potential; and  combining wind and hydro adds value to the hydro plant, i.e. longer operation time, also at the end of dry season (water saving through wind). AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 42
  • 43. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.4 Wind Power Development AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 43 S. No. Name of the project Electric power generation capacity in MW Year of completion 11 Ashengoda Wind Power ProjectAshengoda Wind Power Project 120120 ((€210 million )€210 million ) 20122012 22 Adama Wind Power ProjectAdama Wind Power Project 51 (51 ($117 million)$117 million) 20112011 3 Adama II Wind Power Project 51 2013 4 Assela Wind Power Project 100 2013 5 Ayisha Wind Power Project 300 2012 66 Debre Birhan Wind Power ProjectDebre Birhan Wind Power Project 400400 20132013 7 Messobo Wind Power Project 42 2012
  • 44. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.4 Wind Power Development Four major search areas for wind power AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 44
  • 45. 2. Domestic Construction Industry2. Domestic Construction Industry 2.4. Recent Trends and Future Prospects 2.4.5 Irrigation Projects 2.4.6 Housing development projects 2.4.7 University Capacity Building Projects, UCBP 2.4.8 Sugar Factory Projects 2.4.9 Fertilizer Factory Projects AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 45
  • 46. 3. Fundamentals of Management3. Fundamentals of Management 3.1. Management: Definition  A means of achieving political, economic, and social objectives.  A means of integrating resources (materials, finance, human resources, information, etc.,) in order to achieve organizational objectives efficiently and effectively.  A means of getting things done through people in order to achieve objectives.  A process of establishing vision, mission, values, objectives, goals, and strategies and communicating these, and guiding and empowering others to accomplish them.  A process of planning, organizing, directing and controlling of organizational activities in order to achieve objectives.AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 46
  • 47. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions  Management is a set of goal-directed, interrelated and interdependent activities, aimed at accomplishing organizational goals in an efficient and effective manner.  Generally, management functions encompass: planning, organizing, leading and controlling. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 47
  • 48. 3. Fundamentals of Management3. Fundamentals of Management Management Function inputs and outputs AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 48 Management sets direction ResourcResourc eses•HumanHuman •FinancialFinancial •Raw MaterialsRaw Materials •TechnologicalTechnological •InformationInformation Inputs PerformancePerformance •Attain goalsAttain goals •ProductsProducts •ServicesServices •EfficiencyEfficiency •EffectivenessEffectiveness Outputs Planning Controlling Organizing Leading
  • 49. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions  Planning: devising a systematic approach for attaining the goals of the organization.  Organizing: determining how activities and resources are grouped and the composition of work groups and the way in which work and activities are to be coordinated.  Leading: guiding, leading and overseeing of employees to achieve organizational goals.  Controlling: establishing performance standards and comparing results and expectations to make appropriate changes. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 49
  • 50. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 50 PlanningPlanningPlanningPlanning OrganizingOrganizingOrganizingOrganizing LeadingLeadingLeadingLeadingControllingControllingControllingControlling ManagementManagement FunctionsFunctions ManagementManagement FunctionsFunctions
  • 51. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.1 Planning  Management starts with planning. Without a plan organizations will never succeed. If they do, it will have been by luck or chance and is not repeatable. Plan, will help us in:  What to accomplish (goals);  When to accomplish the goals;  What resources to use;  Who should accomplish what;  Where to accomplish; and  What methods to use.  Assess all possible scenarios including the best and worst and what actions to take. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 51
  • 52. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.2 Organizing  Organizing refers to the process of designing jobs and departments and determining authority relationships in organizations.  Organizing:  Permits people to work together in order to achieve goals;  Helps to achieve synergy;  Avoid duplication of resources;  Establish authority ; and  And facilitate communication. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 52
  • 53. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.2 Organizing  Some issues in organizing include:  Specialization (division of labor);  Grouping jobs into departments and structuring (functional, product, customer, geographic, matrix);  Determining authority relationships (span of control, chain of command);  Delegation of authority; and  Centralization and decentralization. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 53
  • 54. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.3 Leading  Influencing, inspiring and empowering employees to work towards the leaders vision.  Leading involves:  Building successful groups and teams in organizations;  Motivating people;  Communication; and  Developing organizational change. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 54
  • 55. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.4 Controlling  The process of measuring performance, comparing it with the objectives, and making any necessary adjustments.  The purpose of control include:  Adapting to changes;  Minimizing consequences of errors;  Helping the organization cope with complexities; and  Improving efficiency. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 55
  • 56. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.4 Controlling A. Control Purpose  The control function, in turn, has four basic purposes. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 56
  • 57. 3. Fundamentals of Management3. Fundamentals of Management 3.2. Management Functions 3.2.4 Controlling B. Control Process AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 57
  • 58. 3. Fundamentals of Management3. Fundamentals of Management 3.3. Levels of Management Manager: Definition AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 58  The people looking beyond themselves and exercising formal authority over the activities and performance of other people in pursuit of organizational goals.  Someone whose primary responsibility is to carry out the management process.  Someone who plans and makes decisions, organizes, leads, and controls human, financial, physical, and information resources.
  • 59. 3. Fundamentals of Management3. Fundamentals of Management 3.3. Levels of Management A. Top Managers  The relatively small group of executives who manage the organization’s overall goals, strategy, and operating policies. B. Middle Managers  Largest group of managers in organizations who are primarily responsible for implementing the policies and plans of top managers. They supervise and coordinate the activities of lower-level managers. C. First-Line Managers  Managers who supervise and coordinate the activities of operating employees. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 59
  • 60. 3. Fundamentals of Management3. Fundamentals of Management 3.3. Levels of Management AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 60 M arketing A dm inistration O ther H um an resources O perations Finance Middle managers Areas of Management Levels of Management First-line managers Top managers
  • 61. 3. Fundamentals of Management3. Fundamentals of Management 3.3. Levels of Management AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 61 Lower Level Middle Level Top Level Make decision about the overall direction and performance of the organization Translate the over all direction and performance into specific objectives and plans Implement directions and plans through production and delivery of services
  • 62. 3. Fundamentals of Management3. Fundamentals of Management 3.4. Managerial skills  Conceptual skills: the capacity to think in the abstract and to see the organization as a complete unit and to integrate and give direction to its diverse activities so that objectives are achieved.  Interpersonal skills: the ability to communicate with, understand and motivate both individuals and groups.  Technical skills: skills necessary to accomplish or understand the specific kind of work being done in an organization. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 62
  • 63. 3. Fundamentals of Management3. Fundamentals of Management 3.4. Managerial skills AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 63 Management Skills Interpersonal Skills Communication , conflict resolution, leading Conceptual Skills Intellectual ability to process information and make accurate decision about the work, group, and the job Technical Skills Knowledge and ability to accomplish the specialized activities of the work group Top Level Middle Level Lower Level
  • 64. 3. Fundamentals of Management3. Fundamentals of Management 3.5. Construction Management  The management of construction is an enterprise that involves many people with diverse interests, talents and backgrounds. The owner, design professional and contractor comprise the primary triad of parties,  However, others such as subcontractors, material suppliers, bankers, insurance and bonding companies, attorneys and public agency officials, are vital elements of the project team whose interrelated roles must be coordinated to assure a successful project. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 64
  • 65. 3. Fundamentals of Management3. Fundamentals of Management 3.5. Construction Management  The function of project management for construction include:  Specification of project objectives and plans including delineation of scope, budgeting, scheduling, setting performance requirements, and selecting project participants.  Maximization of efficient resource utilization through procurement of labor, materials and equipment according to the prescribed schedule and plan.  Implementation of various operations through proper coordination and control of planning, design, estimating, contracting and construction in the entire process.  Development of effective communications and mechanisms for resolving conflicts among the various participants. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 65
  • 66. 3. Fundamentals of Management3. Fundamentals of Management 3.6. Organization Management A. Organization  A consciously coordinated social unit, composed of two or more people influencing each other that functions on a relatively continuous basis to achieve a common goal or set of goals.  It is a structured process in which people interact and influence each other in order to achieve objectives. B. Components of Origination  People,  Influence ,  Goals or Purpose,  Structure, and  Technology.AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 66
  • 67. 3. Fundamentals of Management3. Fundamentals of Management 3.6. Organization Management C. Organization Environment AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 67 ORGANIZATION Near or Operating Environment Customers Clients Competitors Suppliers Partners Macro or Far Environment Technological Factors Social Factors Political Factors Economic Factors
  • 68. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organizational Structure  Organizational structures can fall into either mechanistic or organic forms.  Mechanistic organizations are rather rigid in that they comprise distinctly delineated jobs, clearly defined hierarchical structure and are driven primarily by top- down command and control. Mechanistic organizations are tall structures, consisting of hierarchies with several layers of management levels.  Organic structures are is relatively flexible. They are structurally decentralized, empowering employees at all levels of the organization to take personal responsibility for the processes and activities in which they are engaged. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 68
  • 69. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organizational Structure  Organizational design is creating an appropriate organizational structure that will enable the organization to accomplish its goals.  The organization can choose from among functional, divisional or matrix designs, whichever is appropriate.  It is the process of arranging, allocating work authority and resources to achieve organization goals.  It involves:  Identifying tasks to be performed;  Allocating the tasks among members; and  Integrating efforts to achieve its objectives. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 69
  • 70. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organizational Structure Key Concepts  Span of Management Control: The number of subordinates reporting directly to a given manger;  Chain of Command: The plan that specifies who reports to whom in an organization, such reporting lines are prominent features of organization chart;  Coordination: The integration of the activities of the separates parts of an organization to accomplish organizational goals; and  Downsizing: A version of organizational restructuring which results in decreasing the size of the organization and often results in a flatter organizational structure. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 70
  • 71. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organization Structure 3.7.1. Functional Organization  In a functional organization, tasks or jobs of similar nature are grouped together and structured as a unit. Each unit is staffed by functional specialists.  Structuring the organization along the functional lines facilitates good coordination and makes supervision of the unit easy for managers as they only need to be familiar with a narrow set of skills. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 71 General ManagerGeneral Manager Marketing MgrMarketing Mgr.. Production Mgr.Production Mgr. Finance Mgr. HRM Mgr.HRM Mgr.
  • 72. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organization Structure 3.7.2. Divisional Organization  Divisional structures are grouped according to workflow and structures are made up of independent strategic organizational units.  The workflow can be broken into product lines, geographic regions, etc. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 72 GM (Head Quarter)GM (Head Quarter) (A.A)(A.A) DGM (Awasa)DGM (Awasa) DGM (Mekelle)DGM (Mekelle) DGM (Bahir DarDGM (Bahir Dar)DGM (Jimma)DGM (Jimma)
  • 73. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organization Structure 3.7.3. Matrix Organization  In matrix organization, individuals are made responsible both to their line manager and the project manager involved.  The matrix concept facilitates working on concurrent projects by creating a dual chain of command, the project (program, systems, or product) manager and the functional manager.  Matrix structures utilize functional and divisional chains of command simultaneously in the same part of the organization, commonly for one-of-a-kind projects. AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 73
  • 74. 3. Fundamentals of Management3. Fundamentals of Management 3.7. Organization Structure 3.7.3. Matrix Organization AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 74 FinanceFinance GrpGrp MarketingMarketing GrpGrp MaterialsMaterials GrpGrp HRHR GrpGrp HRHR GrpGrp ProductionProduction GrpGrp FinanceFinance GrpGrp MaterialsMaterials GrpGrp ProductionProduction GrpGrp MarketingMarketing GrpGrpProject AProject A ManagerManager Project BProject B ManagerManager ProductionProduction FinanceFinance MarketingMarketing MaterialMaterial && ProcurementProcurement HumanHuman ResourceResource Head QuarterHead Quarter
  • 75. THANK YOU! AAU, AAiT, Construction Management, Lecture Notes, March 2014, Getaneh G. 75