SlideShare a Scribd company logo
Certified Associate Project Management
CAPM® Exam Prep – Week 2
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Project Managers
 use Process Groups to coordinate the effective flow of a project
from its start to its close using ITTOs & Knowledge Areas.
 in collaboration with the project team are ALWAYS responsible for
planning & developing a successful Project Management Process
 actively manages each of these interactions to meet the Sponsor,
Customer & Stakeholder requirements
Project Management Processes
Chapter 3
PROCESS
 “is a set of interrelated actions & activities performed to create a specific product, service or
result.”
 Project Management has 49 processes
PROCESS GROUPS
 organize the process functions by their Actions
 are the project activities broken down into 5 steps
KNOWLEDGE AREAS
 organizes the process functions by their Subject Matter
 are the process elements broken down into 10 areas
 ARE NOT LINEAR !!!
ITTOs
 “each process is linked & characterized by its INPUTS, TOOLS, TECHNIQUES & OUTPUTS.”
 Inputs – information used in the project ex. EEF, OPAs, Charter, etc
 Outputs – documents, deliverables, decisions
 Tools &Techniques – used to do the work ex. Meetings, Expert, Audits
Project Management Processes
Chapter 3
PHASES
 “a set of processes that are ITERATED several times to achieve the required
outcome.”
 each Phase of the project goes thru all of the 5 Process Groups
Sequential Relationship
 Phases of the project that happen one after another
 Teams work together on each phase
Overlapping Relationship
 Phases of the project deliver results independently
 Teams work on different parts of the project
 Complicated to manage due to increased risk & rework
Project Management Processes
Chapter 3
Project Management Process Groups
 Initiating
 Planning
 Executing
 Monitoring & Controlling
 Closing
Project Management Processes
Chapter 3
Project Management Processes
Chapter 3
Project Management Process Groups
INITIATING Process Group
 Develop the Project Charter
 Project Manager is Authorized
 Business Case
 High level planning – Rough Order of Magnitude estimating
 Initial financial resources are committed
 Scope is conceptualize – Progressive Elaboration
 Identify Stakeholders
 Stakeholder Register - List of Internal & External influences
 Identify their expectations
Project Management Processes
Chapter 3
PLANNING Process Group
“… 24 processes used in the strategy to develop a course of action or path to
successfully complete the project or phase. A well managed plan saves
resources, time & money and gets the Stakeholder’s buy-in & engagement.”
Iterative – each planning process may use the results of the previous process that
may affect or change the plan
 Project Management Plan
 Is an Output that guides the Execution & Control of the project
 Project Documents
 Are Outputs detailing each of the Knowledge Areas
Project Management Processes
Chapter 3
EXECUTING Process Group
“… 10 processes performed to complete the project work defined
in the Project Management Plan to meet the project objectives.”
 PM coordinates People & Resources to Do the work
 Communicates with Stakeholders to manage their expectations
 Proactive analysis of baselines, changes in resource availability,
productivity, expected durations, budgets, etc
 Change requests approvals resulting in Project Doc updates
 Deliverables
 Changes Requests
Project Management Processes
Chapter 3
MONITORING & CONTROLLING Process Group
“… 12 processes required to track & review the progress & performance
of the project. ”
 Key benefit is that project performance is measured & analyzed at
regular intervals to identify variances from the project management plan
 Identifies any areas in which changes to the plan are required
 Recommending corrective or preventive action in anticipating problems
 Approved Change Requests
Project Management Processes
Chapter 3
CLOSING Process Group
“… 1 process performed to formally complete the project or contract
obligations.”
 Obtain acceptance by the Customer or Sponsor to formally Close
 Conduct post-project review
 Document Lessons Learned & update OPAs
 Archive project docs as historical data
 Close out procurement activities to terminate agreements
 Perform team members’ assessments & release project resources
 Close Project
 Celebrate Your Success!!!
Project Management Processes
Chapter 3
Process Groups
organizes functions by Action
 Initiating (2) - Start
 Planning (24) - Plan
 Executing (10) - Do
 Monitoring & Controlling (12) – Check & Act
 Closing (1) - End
Project Management Processes
Chapter 3
KNOWLEDGE AREAS
 Organizes functions by Subject Matter
 “…a complete set of activities that make up a
project area of specialization”
 “…provide a detailed description of the ITTOs”
 10 areas further decomposed into 49 processes
 Integrated among the 5 Process Groups
 Is NOT Linear
Project Management Processes
Chapter 3
49
Integration Management
Chapter 4
“Is the Project Manager’s core responsibilities”
“…. is a group of processes required to ensure that the
various elements of the project are properly coordinated.”
Process Process Group Key Deliverables
4.1 Develop Project Charter Initiating Project Charter
4.2 Develop Project Management Plan Planning Project Management Plan
4.3 Direct and Manage Executing Project Deliverables
4.4 Manage Project Knowledge Executing Document Lessons Learned
4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests
4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests
4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
Project Integration Management
Chapter 4
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Key Points
 A project charter formally authorizes the project
 Gives the objectives and business case
 Identifies & authorizes Project Manager use of organizational resources for project use
 Generic enough not to change often
 Written by a Manager higher in authority than Project Manager
 Includes name, description, deliverables
 A project does not start unless it has a Project charter
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
INPUTS
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
TOOLS
 Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page
when making a project decision
Project Integration Management
Chapter 4
Develop Project Charter
Process 1
Project Integration Management
Chapter 4
Develop Project Management Plan (PMP)
Process 2
Key Points
 Key benefit: creates the central document that defines all of the project work
 How the project will be executed, monitored & controlled
 Subsidiary plans are integrated into ONE comprehensive PMP
 The PMP is developed by the Project Manager with inputs from the team, stakeholders & management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Kick-off meeting happens after the planning phase and before the project execution. It is typically used
to communicate responsibilities of key stakeholders.
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Develop Project Management Plan
Process 2
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Key Points
 Key benefit of this process is to provide overall management of the project work
 To lead & perform work as defined in the PMP
 Create deliverables to meet planned project work
 Manage team members & provide them with training
 Obtain, manage & use resources ex. Materials, Equipment, Facilities
 Establish & manage communications internal & external channels
 Manage Stakeholders, Sellers, Risks, Change Requests
Project Integration Management
Chapter 4
Direct & Manage Project Work
Process 3
Project Integration Management
Chapter 4
Manage Project Knowledge
Process 4
Key Points
 Use prior organizational knowledge to produce or improve project outcomes
 Knowledge created by the project used to support operations and future projects
 Use existing knowledge and create new knowledge
 Contribute to organizational lessons learned
Project Integration Management
Chapter 4
Manage Project Work
Process 4
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Key benefit: allows stakeholders to understand current state of the project, any steps taken
and budget, schedule & scope forecasts
 Tracks, reviews & reports actual progress & performance against the PMP objectives
 Is conducted from project inception through completion
 Control includes corrective & preventative actions
 Identify & analyze existing and new risks
 Work Authorization System - PM’s system to ensure work is performed at the right time & in
the right sequence (found in the EEF – PMIS)
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Key Points
 Change Requests
 are submitted when issues are found while project work is being performed
 is a formal (written) proposal to modify any document, baseline, deliverable
 Change Log – all WRITTEN requests approved or not
 PM has authority to make changes IF constraints are not effected
 Types of Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
Project Integration Management
Chapter 4
Monitor & Control Project Work
Process 5
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Key Points
 Key benefit: allows documented changes to be considered in an integrated manner to the
overall project while reducing risks to other areas of the project
 Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc
 Is conducted from project inception through completion
 Is the ultimate responsibility of the Project Manager to carefully & continuously manage
changes
 Changes can be requested by any stakeholder involved in the project
 Every “documented” change must be approved or rejected by a “responsible person”
 Or by the CCB – Change Control Board
Project Integration Management
Chapter 4
Perform Integrated Change Control
Process 6
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Key Points
 Provides lessons learned, formal ending of the project work & release of the organization’s
resources to pursue new endeavors
 Finalizes all activities across all PM Process Groups
 PM measures the scope baseline against the PMP
 Complete & close all contracts, procurement agreements, financials,
 Archive OPA historical records, reports, etc
 For projects terminated before completion, PM engages all stakeholders to investigate &
document reasons why
Project Integration Management
Chapter 4
Close Project or Phase
Process 7
Project Integration Management
Chapter 4
Key Points
 A project charter formally authorizes the project
 Statement of Work (SOW) - from external customer describing project deliverables
 Business Case - from internal whether the project’s Cost-Benefit makes sense
 Expert Judgment – gaining advice from experts in other dept, outside consultants, industry
groups
 Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the
same page when making a project decision
 Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
Project Integration Management
Chapter 4
Key Points
 The PMP is developed by the Project Manager with inputs from the team, stakeholders &
management
 Project baseline refers to the original version of the PMP
 Once the PMP is baselined, it may only be changed by raising a change request
 Progressive Elaboration is the process of taking a project from concept to detailed design
 Monitor & Control is conducted from project inception through completion
 Control includes corrective & preventative Actions aka Changes
 Corrective Action – taken when actual deviations from the performance baseline
 Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting
 Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
 Changes can be made by Crashing or Fast Tracking
Project Integration Management
Chapter 4 - Summary
Project Management Processes
Chapter 4
Group Exercise – The Shuffle Game

More Related Content

What's hot

13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
DavidMcLachlan1
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
DavidMcLachlan1
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
Andersson Lujan Ojeda
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
DavidMcLachlan1
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
Jeffrey Cheah
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
Andrew Mikityuk
 
Project integration management
Project integration managementProject integration management
Project integration management
Ehsan Ullah
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
DavidMcLachlan1
 
Planning process group
Planning process groupPlanning process group
Planning process group
Mudassir Iqbal
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
DavidMcLachlan1
 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)
Jeffrey Cheah
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
pankajsh10
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
Ali Forouzesh PMP,PfMP,OPM3cc
 
PMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management FrameworkPMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management Framework
Mohamed Loey
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
DavidMcLachlan1
 

What's hot (19)

13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 
13.1 Identify Stakeholders
13.1 Identify Stakeholders13.1 Identify Stakeholders
13.1 Identify Stakeholders
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)Project Management Body of Knowledge (Time)
Project Management Body of Knowledge (Time)
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
PMP Preparation 2 - Processes
PMP Preparation 2 - ProcessesPMP Preparation 2 - Processes
PMP Preparation 2 - Processes
 
Project integration management
Project integration managementProject integration management
Project integration management
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
Planning process group
Planning process groupPlanning process group
Planning process group
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)Project Management Body of Knowledge (Introduction)
Project Management Body of Knowledge (Introduction)
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Project scope management 1
Project scope management 1Project scope management 1
Project scope management 1
 
PMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management FrameworkPMP Lecture 2: Project Management Framework
PMP Lecture 2: Project Management Framework
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 

Similar to CAPM Muzette Charles Chapter3-4

CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
Muzette Charles, PMP
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
Ahmed Alageed
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Fida Karim 🇵🇰
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
Paramjit Arora
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration Masterclass
Jeffrey Cheah
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
hatemk
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
AhmedKayed6
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
AhmedKayed6
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
Murali Venkatesh
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
Joshua Render
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
Nawzad Bilal
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOswebuploader
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
Dhamo daran
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
Gaurav Sukhija
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
KareemBullard1
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
robsonnasc
 

Similar to CAPM Muzette Charles Chapter3-4 (20)

CAPM week 1 chapter 3
CAPM week 1 chapter 3CAPM week 1 chapter 3
CAPM week 1 chapter 3
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...Lecture 07: Project Management Fundamentals Project Organization and Integr...
Lecture 07: Project Management Fundamentals Project Organization and Integr...
 
Project management essentials 3 day training program
Project management essentials   3 day training programProject management essentials   3 day training program
Project management essentials 3 day training program
 
Integration Masterclass
Integration MasterclassIntegration Masterclass
Integration Masterclass
 
The Art Of Project Management
The Art Of Project ManagementThe Art Of Project Management
The Art Of Project Management
 
Day 2-1 PMP.pptx
Day 2-1 PMP.pptxDay 2-1 PMP.pptx
Day 2-1 PMP.pptx
 
Day 2 PMP.pptx
Day 2 PMP.pptxDay 2 PMP.pptx
Day 2 PMP.pptx
 
Prestiva PMP process approach
Prestiva PMP process approachPrestiva PMP process approach
Prestiva PMP process approach
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
ProjectManagementforNGOs
ProjectManagementforNGOsProjectManagementforNGOs
ProjectManagementforNGOs
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Pmp
PmpPmp
Pmp
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
PMP Study Guide
PMP Study GuidePMP Study Guide
PMP Study Guide
 
Pmi - Project Management Professional (Pmp) Certification Study Guide
Pmi - Project Management Professional (Pmp)   Certification Study GuidePmi - Project Management Professional (Pmp)   Certification Study Guide
Pmi - Project Management Professional (Pmp) Certification Study Guide
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
Muzette Charles, PMP
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
Muzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
Muzette Charles, PMP
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
Muzette Charles, PMP
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
Muzette Charles, PMP
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
Muzette Charles, PMP
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
Muzette Charles, PMP
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
Muzette Charles, PMP
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
Muzette Charles, PMP
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 

Recently uploaded

Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 

Recently uploaded (20)

Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 

CAPM Muzette Charles Chapter3-4

  • 1. Certified Associate Project Management CAPM® Exam Prep – Week 2 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Project Managers  use Process Groups to coordinate the effective flow of a project from its start to its close using ITTOs & Knowledge Areas.  in collaboration with the project team are ALWAYS responsible for planning & developing a successful Project Management Process  actively manages each of these interactions to meet the Sponsor, Customer & Stakeholder requirements Project Management Processes Chapter 3
  • 3. PROCESS  “is a set of interrelated actions & activities performed to create a specific product, service or result.”  Project Management has 49 processes PROCESS GROUPS  organize the process functions by their Actions  are the project activities broken down into 5 steps KNOWLEDGE AREAS  organizes the process functions by their Subject Matter  are the process elements broken down into 10 areas  ARE NOT LINEAR !!! ITTOs  “each process is linked & characterized by its INPUTS, TOOLS, TECHNIQUES & OUTPUTS.”  Inputs – information used in the project ex. EEF, OPAs, Charter, etc  Outputs – documents, deliverables, decisions  Tools &Techniques – used to do the work ex. Meetings, Expert, Audits Project Management Processes Chapter 3
  • 4. PHASES  “a set of processes that are ITERATED several times to achieve the required outcome.”  each Phase of the project goes thru all of the 5 Process Groups Sequential Relationship  Phases of the project that happen one after another  Teams work together on each phase Overlapping Relationship  Phases of the project deliver results independently  Teams work on different parts of the project  Complicated to manage due to increased risk & rework Project Management Processes Chapter 3
  • 5. Project Management Process Groups  Initiating  Planning  Executing  Monitoring & Controlling  Closing Project Management Processes Chapter 3
  • 6. Project Management Processes Chapter 3 Project Management Process Groups
  • 7. INITIATING Process Group  Develop the Project Charter  Project Manager is Authorized  Business Case  High level planning – Rough Order of Magnitude estimating  Initial financial resources are committed  Scope is conceptualize – Progressive Elaboration  Identify Stakeholders  Stakeholder Register - List of Internal & External influences  Identify their expectations Project Management Processes Chapter 3
  • 8. PLANNING Process Group “… 24 processes used in the strategy to develop a course of action or path to successfully complete the project or phase. A well managed plan saves resources, time & money and gets the Stakeholder’s buy-in & engagement.” Iterative – each planning process may use the results of the previous process that may affect or change the plan  Project Management Plan  Is an Output that guides the Execution & Control of the project  Project Documents  Are Outputs detailing each of the Knowledge Areas Project Management Processes Chapter 3
  • 9. EXECUTING Process Group “… 10 processes performed to complete the project work defined in the Project Management Plan to meet the project objectives.”  PM coordinates People & Resources to Do the work  Communicates with Stakeholders to manage their expectations  Proactive analysis of baselines, changes in resource availability, productivity, expected durations, budgets, etc  Change requests approvals resulting in Project Doc updates  Deliverables  Changes Requests Project Management Processes Chapter 3
  • 10. MONITORING & CONTROLLING Process Group “… 12 processes required to track & review the progress & performance of the project. ”  Key benefit is that project performance is measured & analyzed at regular intervals to identify variances from the project management plan  Identifies any areas in which changes to the plan are required  Recommending corrective or preventive action in anticipating problems  Approved Change Requests Project Management Processes Chapter 3
  • 11. CLOSING Process Group “… 1 process performed to formally complete the project or contract obligations.”  Obtain acceptance by the Customer or Sponsor to formally Close  Conduct post-project review  Document Lessons Learned & update OPAs  Archive project docs as historical data  Close out procurement activities to terminate agreements  Perform team members’ assessments & release project resources  Close Project  Celebrate Your Success!!! Project Management Processes Chapter 3
  • 12. Process Groups organizes functions by Action  Initiating (2) - Start  Planning (24) - Plan  Executing (10) - Do  Monitoring & Controlling (12) – Check & Act  Closing (1) - End Project Management Processes Chapter 3
  • 13. KNOWLEDGE AREAS  Organizes functions by Subject Matter  “…a complete set of activities that make up a project area of specialization”  “…provide a detailed description of the ITTOs”  10 areas further decomposed into 49 processes  Integrated among the 5 Process Groups  Is NOT Linear Project Management Processes Chapter 3 49
  • 14.
  • 15. Integration Management Chapter 4 “Is the Project Manager’s core responsibilities” “…. is a group of processes required to ensure that the various elements of the project are properly coordinated.” Process Process Group Key Deliverables 4.1 Develop Project Charter Initiating Project Charter 4.2 Develop Project Management Plan Planning Project Management Plan 4.3 Direct and Manage Executing Project Deliverables 4.4 Manage Project Knowledge Executing Document Lessons Learned 4.5 Monitor and Control Project Work Monitoring & Controlling Change Requests 4.6 Perform Integrated Change Control Monitoring & Controlling Approved Change Requests 4.7 Close Project or Phase Closing Finalize Contracts, Payments, Transition
  • 17. Project Integration Management Chapter 4 Develop Project Charter Process 1 Key Points  A project charter formally authorizes the project  Gives the objectives and business case  Identifies & authorizes Project Manager use of organizational resources for project use  Generic enough not to change often  Written by a Manager higher in authority than Project Manager  Includes name, description, deliverables  A project does not start unless it has a Project charter
  • 18. Project Integration Management Chapter 4 Develop Project Charter Process 1 INPUTS  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense TOOLS  Expert Judgement – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision
  • 19. Project Integration Management Chapter 4 Develop Project Charter Process 1
  • 20. Project Integration Management Chapter 4 Develop Project Management Plan (PMP) Process 2 Key Points  Key benefit: creates the central document that defines all of the project work  How the project will be executed, monitored & controlled  Subsidiary plans are integrated into ONE comprehensive PMP  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders.
  • 21. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 22. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 23. Project Integration Management Chapter 4 Develop Project Management Plan Process 2
  • 24. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3 Key Points  Key benefit of this process is to provide overall management of the project work  To lead & perform work as defined in the PMP  Create deliverables to meet planned project work  Manage team members & provide them with training  Obtain, manage & use resources ex. Materials, Equipment, Facilities  Establish & manage communications internal & external channels  Manage Stakeholders, Sellers, Risks, Change Requests
  • 25. Project Integration Management Chapter 4 Direct & Manage Project Work Process 3
  • 26. Project Integration Management Chapter 4 Manage Project Knowledge Process 4 Key Points  Use prior organizational knowledge to produce or improve project outcomes  Knowledge created by the project used to support operations and future projects  Use existing knowledge and create new knowledge  Contribute to organizational lessons learned
  • 27. Project Integration Management Chapter 4 Manage Project Work Process 4
  • 28. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Key benefit: allows stakeholders to understand current state of the project, any steps taken and budget, schedule & scope forecasts  Tracks, reviews & reports actual progress & performance against the PMP objectives  Is conducted from project inception through completion  Control includes corrective & preventative actions  Identify & analyze existing and new risks  Work Authorization System - PM’s system to ensure work is performed at the right time & in the right sequence (found in the EEF – PMIS)
  • 29. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5 Key Points  Change Requests  are submitted when issues are found while project work is being performed  is a formal (written) proposal to modify any document, baseline, deliverable  Change Log – all WRITTEN requests approved or not  PM has authority to make changes IF constraints are not effected  Types of Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong
  • 30. Project Integration Management Chapter 4 Monitor & Control Project Work Process 5
  • 31. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6 Key Points  Key benefit: allows documented changes to be considered in an integrated manner to the overall project while reducing risks to other areas of the project  Reviews, approves & manages all change requests to the PMP, OPA, deliverables, etc  Is conducted from project inception through completion  Is the ultimate responsibility of the Project Manager to carefully & continuously manage changes  Changes can be requested by any stakeholder involved in the project  Every “documented” change must be approved or rejected by a “responsible person”  Or by the CCB – Change Control Board
  • 32. Project Integration Management Chapter 4 Perform Integrated Change Control Process 6
  • 33. Project Integration Management Chapter 4 Close Project or Phase Process 7 Key Points  Provides lessons learned, formal ending of the project work & release of the organization’s resources to pursue new endeavors  Finalizes all activities across all PM Process Groups  PM measures the scope baseline against the PMP  Complete & close all contracts, procurement agreements, financials,  Archive OPA historical records, reports, etc  For projects terminated before completion, PM engages all stakeholders to investigate & document reasons why
  • 34. Project Integration Management Chapter 4 Close Project or Phase Process 7
  • 35. Project Integration Management Chapter 4 Key Points  A project charter formally authorizes the project  Statement of Work (SOW) - from external customer describing project deliverables  Business Case - from internal whether the project’s Cost-Benefit makes sense  Expert Judgment – gaining advice from experts in other dept, outside consultants, industry groups  Facilitation Techniques – brainstorming meetings with stakeholders to get everyone on the same page when making a project decision  Subsidiary plans & Baselines are integrated into ONE comprehensive PMP
  • 36. Project Integration Management Chapter 4 Key Points  The PMP is developed by the Project Manager with inputs from the team, stakeholders & management  Project baseline refers to the original version of the PMP  Once the PMP is baselined, it may only be changed by raising a change request  Progressive Elaboration is the process of taking a project from concept to detailed design  Monitor & Control is conducted from project inception through completion  Control includes corrective & preventative Actions aka Changes  Corrective Action – taken when actual deviations from the performance baseline  Preventive Action – taken when ANTICIPATED or POSSIBLE deviations ex. Influencing Factors, Forecasting  Defect Repair –correcting a mistake in a deliverable, ex. Plan was right, but deliverable was wrong  Changes can be made by Crashing or Fast Tracking
  • 38. Project Management Processes Chapter 4 Group Exercise – The Shuffle Game

Editor's Notes

  1. Processes are either: Operational Process & a Project Management Process
  2. Processes are either: Operational Process & a Project Management Process
  3. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?
  4. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?
  5. This is where the PM walks thru the project & gets organized BEFORE actual work begins
  6. Organizes functions by Action
  7. Int: coordinating all of the work so that it happens correctly
  8. Formally starts a New project or Phase, PM named early so he/she assists in Proj. Charter / High-level planning estimating to see if the proj can be dlvrd by the time & wi/budget that’s requested… basically does the project have a chance to be successful b4 $ & resources are committed?