SlideShare a Scribd company logo
1 of 18
Monitor Risks
Monitor Risks
Coincides with PMBOK 11.7
Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group
4. Project Integration
Management
4.1 Develop Project Charter
4.2 Develop Project Management
Plan
4.3 Direct and Manage Project Work
4.4 Manage Project Knowledge
4.5 Monitor and Control Project Work
4.6 Perform Integrated Change Control
4.7 Close Project or Phase
5. Project Scope
Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Schedule
Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Durations
6.5 Develop Schedule
6.6 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality
Management
8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality
9. Project Resource
Management
9.1 Plan Resource Management
9.2 Estimate Activity Resources
9.3 Acquire Resources
9.4 Develop Team
9.5 Manage Team
9.6 Control Resources
10. Project Communications
Management
10.1 Plan Communications
Management
10.2 Manage Communications 10.3 Monitor Communications
11. Project Risk
Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk
Analysis
11.5 Plan Risk Responses
11.6 Implement Risk Responses 11.7 Monitor Risks
12. Project Procurement
Management
12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder
Management
13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement
13.3 Manage Stakeholder
Engagement
13.4 Monitor Stakeholder Engagement
What is it?
Monitor Risks is the process of monitoring the implementation of
agreed-upon risk response plans, tracking identified risks, identifying
and analysing new risks, and evaluating risk process effectiveness
throughout the project.
Why?
The key benefit of this process is that it enables project decisions to
be based on current information about overall project risk exposure
and individual project risks.
Monitor Risks
Coincides with PMBOK 11.7
Monitor Risks
Coincides with PMBOK 11.7
Inputs Tools & Techniques Outputs
1. Project management plan
• Risk management plan
2. Project documents
• Issue Log
• Lessons learned register
• Risk register
• Risk report
3. Work performance data
4. Work performance report
1. Data Analysis
• Technical performance analysis
• Reserve analysis
2. Audits
3. Meetings
1. Work performance information
2. Change requests
3. Project management plan
updates
• Any component
4. Project documents updates
• Assumption log
• Issue log
• Lessons learned register
• Risk register
• Risk report
5. Organizational process assets
updates
Inputs, Tools & Techniques, Outputs
Monitor Risks
Coincides with PMBOK 11.7
11.7 Monitor
Risks
Project
Management
Plan
• Issue Log
• Lessons learned register
• Risk register
• Risk report
• Work performance reports
Project
Documents
• Change Requests
• Risk management plan
4.6 Perform
Integrated
Change Control
Project
Documents
• Assumption log
• Issue log
• Lessons learned register
• Risk register
• Risk report
4.5 Monitor and
Control Project
Work
• Work performance
information
Project
Management
Plan
Enterprise/Orga
nization • Organizational
process assets
• Any Component
4.3 Direct and
Manage Project
Work
4.5 Monitor and
Control Project
Work
• Work performance data
Overview
The Monitor Risks process uses performance information generated during project execution
to determine if:
• Implemented risk responses are effective
• Level of overall project risk has changed
• Status of identified individual project risks has changed
• New individual project risks have arisen
• Risk management approach is still appropriate
• Project assumptions are still valid
• Risk management policies and procedures are being followed
• Contingency reserves for cost or schedule require modification
• Project strategy is still valid
Coincides with PMBOK 11.7
Monitor Risks
Monitor Risks - Inputs
Coincides with PMBOK 11.7
Project Management Plan
• Project management plan components include but are not limited to
the risk management plan.
• The risk management plan provides guidance on how and when risks
should be reviewed, which policies and procedures should be
followed, the roles and responsibilities in the monitoring process, and
reporting formats.
Monitor Risks - Inputs
Coincides with PMBOK 11.7
Project Documents
Project documents that should be considered as inputs for this process include:
• Issue Log
• Lessons learned register
• Risk register
• Risk report
Coincides with PMBOK 11.7
Work Performance Data
Work performance data contains data on project status such as risk
responses that have been implemented, risks that have occurred, risks
that are active and those that have been closed out.
Monitor Risks - Inputs
Coincides with PMBOK 11.7
Work Performance Reports
Work performance reports provide information from performance
measurements that can be analysed to provide project work performance
information including variance analysis, earned value data, and forecasting
data. This information could be relevant when monitoring performance-related
risks.
Monitor Risks - Inputs
Monitor Risks - Tools & Techniques
Coincides with PMBOK 11.7
Data Analysis
Data analysis techniques that can be used for this process include:
• Technical performance analysis
• Reserve analysis
Monitor Risks - Tools & Techniques
Coincides with PMBOK 11.7
Audits
• Risk audits are a type of audit that may be used to consider the effectiveness of the
risk management process.
• The project manager is responsible for ensuring that risk audits are performed at an
appropriate frequency, as defined in the project’s risk management plan.
• Risk audits may be included during routine project review meetings or may form
part of a risk review meeting, or the team may choose to hold separate risk audit
meetings.
Monitor Risks - Tools & Techniques
Coincides with PMBOK 11.7
Meetings
Meetings that can be used during this process include, risk reviews. Risk reviews are
scheduled regularly and should examine and document the effectiveness of risk responses in
dealing with overall project risk and with identified individual project risks. Risk reviews may
also result in:
• Identification of new individual project risks
• Reassessment of current risks
• The closing of risks that are outdated
• Issues that have arisen as the result of risks that have occurred
• Identification of lessons to be learned for implementation in ongoing phases in the current
project or in similar projects in the future.
Monitor Risks - Outputs
Coincides with PMBOK 11.7
Work Performance Information
Work performance information includes information on how project risk
management is performing by comparing the individual risks that have
occurred with the expectation of how they would occur. This information
indicates the effectiveness of the response planning and response
implementation processes.
Monitor Risks - Outputs
Coincides with PMBOK 11.7
Change Requests
• The Monitor Risks process may result in a change request to the cost and
schedule baselines or other components of the project management plan.
• Change requests are processed for review and disposition through the
Perform Integrated Change Control process.
• Change requests can include recommended corrective and preventive
actions to address the current level of overall project risk or to address
individual project risks.
Monitor Risks - Outputs
Coincides with PMBOK 11.7
Project Management Plan Updates
Any change to the project management plan goes through the
organization’s change control process via a change request. This may
affect any component of the project management plan.
Monitor Risks - Outputs
Coincides with PMBOK 11.7
Project Document Updates
Project documents that may be updated as a result of carrying out this process
include:
• Assumption log
• Issue log
• Lessons learned register
• Risk register
• Risk report
Monitor Risks - Outputs
Coincides with PMBOK 11.7
Organizational Process Assets
Organizational process assets that are updated as a result of the Monitor Risks
process include but are not limited to:
• Templates for the risk management plan, risk register, and risk report
• Risk breakdown structure.

More Related Content

What's hot

PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk ManagementDavidMcLachlan1
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)Ricardo Viana Vargas
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration managementejlp12
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Managementcgautam
 
Standard For Program Management Changes
Standard For Program Management ChangesStandard For Program Management Changes
Standard For Program Management Changesgryasam
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk ResponsesDavidMcLachlan1
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management Krishna Kant
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off PresentationEbru Seiwert
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 

What's hot (20)

PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
11.1 Plan Risk Management
11.1 Plan Risk Management11.1 Plan Risk Management
11.1 Plan Risk Management
 
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
PMBOK® Guide Processes Flow – 6th Edition (Simplified version)
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
11.2 Identify Risks
11.2 Identify Risks11.2 Identify Risks
11.2 Identify Risks
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Standard For Program Management Changes
Standard For Program Management ChangesStandard For Program Management Changes
Standard For Program Management Changes
 
11.5 Plan Risk Responses
11.5 Plan Risk Responses11.5 Plan Risk Responses
11.5 Plan Risk Responses
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
An Introduction to Project Management
An Introduction to Project Management An Introduction to Project Management
An Introduction to Project Management
 
10- PMP Training - Risk Management
10- PMP Training - Risk Management 10- PMP Training - Risk Management
10- PMP Training - Risk Management
 
PMO Kick-Off Presentation
PMO Kick-Off PresentationPMO Kick-Off Presentation
PMO Kick-Off Presentation
 
The Project's Network Diagram
The Project's Network DiagramThe Project's Network Diagram
The Project's Network Diagram
 
PMP Exam Prep 2021 free sample module 1
PMP Exam Prep 2021  free sample module 1PMP Exam Prep 2021  free sample module 1
PMP Exam Prep 2021 free sample module 1
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan
 

Similar to 11.7 Monitor Risks

11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk AnalysisDavidMcLachlan1
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management OverviewDavidMcLachlan1
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management OverviewDavidMcLachlan1
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost ManagementDavidMcLachlan1
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changesPeg Duggan
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...Arlene Smith
 
File 3 removed 4 slides 1
File 3 removed 4 slides 1File 3 removed 4 slides 1
File 3 removed 4 slides 1test prod1
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality ManagementDavidMcLachlan1
 

Similar to 11.7 Monitor Risks (20)

7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis11.4 Perform Quantitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
 
11.0 Project Risk Management Overview
11.0 Project Risk Management Overview11.0 Project Risk Management Overview
11.0 Project Risk Management Overview
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
7.0 Project Cost Management Overview
7.0 Project Cost Management Overview7.0 Project Cost Management Overview
7.0 Project Cost Management Overview
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
7.1 Plan Cost Management
7.1 Plan Cost Management7.1 Plan Cost Management
7.1 Plan Cost Management
 
PMBoK V5 changes
PMBoK V5 changesPMBoK V5 changes
PMBoK V5 changes
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Monitor risks
Monitor risks Monitor risks
Monitor risks
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...2013 Project Management Institute. A Guide To The Project Management Body Of ...
2013 Project Management Institute. A Guide To The Project Management Body Of ...
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
7.3 Determine Budget
7.3 Determine Budget7.3 Determine Budget
7.3 Determine Budget
 
8.3 Control Quality
8.3 Control Quality8.3 Control Quality
8.3 Control Quality
 
File 3 removed 4 slides 1
File 3 removed 4 slides 1File 3 removed 4 slides 1
File 3 removed 4 slides 1
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
 

More from DavidMcLachlan1

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement ContractsDavidMcLachlan1
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct ProcurementsDavidMcLachlan1
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIDavidMcLachlan1
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2DavidMcLachlan1
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2DavidMcLachlan1
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management EnvironmentDavidMcLachlan1
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentDavidMcLachlan1
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core PracticesDavidMcLachlan1
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningDavidMcLachlan1
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean FrameworksDavidMcLachlan1
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean FrameworksDavidMcLachlan1
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile EnvironmentDavidMcLachlan1
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core PracticesDavidMcLachlan1
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principlesDavidMcLachlan1
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...DavidMcLachlan1
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder EngagementDavidMcLachlan1
 

More from DavidMcLachlan1 (20)

10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
12.1 Procurement Contracts
12.1 Procurement Contracts12.1 Procurement Contracts
12.1 Procurement Contracts
 
12.2 Conduct Procurements
12.2 Conduct Procurements12.2 Conduct Procurements
12.2 Conduct Procurements
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPIProject Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
Project Cost Forecasting Techniques with EAC, ETC, VAC, TCPI
 
Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2Scenario - Project Management Processes | 2 of 2
Scenario - Project Management Processes | 2 of 2
 
Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2Scenario - Project Management Processes | 1 of 2
Scenario - Project Management Processes | 1 of 2
 
Scenario - The Project Management Environment
Scenario - The Project Management EnvironmentScenario - The Project Management Environment
Scenario - The Project Management Environment
 
Agile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile EnvironmentAgile Scenarios - Delivering an Agile Environment
Agile Scenarios - Delivering an Agile Environment
 
Agile Scenarios - Core Practices
Agile Scenarios - Core PracticesAgile Scenarios - Core Practices
Agile Scenarios - Core Practices
 
Agile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave PlanningAgile Core Practices - Rolling Wave Planning
Agile Core Practices - Rolling Wave Planning
 
6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks6.0 Auxiliary Agile and Lean Frameworks
6.0 Auxiliary Agile and Lean Frameworks
 
5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks5.0 Core Agile and Lean Frameworks
5.0 Core Agile and Lean Frameworks
 
7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment7.0 Delivering in an Agile Environment
7.0 Delivering in an Agile Environment
 
4.0 The Agile Core Practices
4.0 The Agile Core Practices4.0 The Agile Core Practices
4.0 The Agile Core Practices
 
3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles3.0 The Agile Manifesto and Clarifying principles
3.0 The Agile Manifesto and Clarifying principles
 
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
2.0 The Differences Between Agile and Waterfall, Incremental, Iterative and H...
 
7.2 Estimate Cost
7.2 Estimate Cost7.2 Estimate Cost
7.2 Estimate Cost
 
13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement13.4 Monitor Stakeholder Engagement
13.4 Monitor Stakeholder Engagement
 

Recently uploaded

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

11.7 Monitor Risks

  • 2. Monitor Risks Coincides with PMBOK 11.7 Process Group and Knowledge Area Mapping Knowledge Areas Initiating Planning Process Group Executing Process Group Monitoring and Controlling Process Group Closing Process Group 4. Project Integration Management 4.1 Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct and Manage Project Work 4.4 Manage Project Knowledge 4.5 Monitor and Control Project Work 4.6 Perform Integrated Change Control 4.7 Close Project or Phase 5. Project Scope Management 5.1 Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Schedule Management 6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Durations 6.5 Develop Schedule 6.6 Control Schedule 7. Project Cost Management 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8.1 Plan Quality Management 8.2 Manage Quality 8.3 Control Quality 9. Project Resource Management 9.1 Plan Resource Management 9.2 Estimate Activity Resources 9.3 Acquire Resources 9.4 Develop Team 9.5 Manage Team 9.6 Control Resources 10. Project Communications Management 10.1 Plan Communications Management 10.2 Manage Communications 10.3 Monitor Communications 11. Project Risk Management 11.1 Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Implement Risk Responses 11.7 Monitor Risks 12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 13. Project Stakeholder Management 13.1 Identify Stakeholders 13.2 Plan Stakeholder Engagement 13.3 Manage Stakeholder Engagement 13.4 Monitor Stakeholder Engagement
  • 3. What is it? Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analysing new risks, and evaluating risk process effectiveness throughout the project. Why? The key benefit of this process is that it enables project decisions to be based on current information about overall project risk exposure and individual project risks. Monitor Risks Coincides with PMBOK 11.7
  • 4. Monitor Risks Coincides with PMBOK 11.7 Inputs Tools & Techniques Outputs 1. Project management plan • Risk management plan 2. Project documents • Issue Log • Lessons learned register • Risk register • Risk report 3. Work performance data 4. Work performance report 1. Data Analysis • Technical performance analysis • Reserve analysis 2. Audits 3. Meetings 1. Work performance information 2. Change requests 3. Project management plan updates • Any component 4. Project documents updates • Assumption log • Issue log • Lessons learned register • Risk register • Risk report 5. Organizational process assets updates Inputs, Tools & Techniques, Outputs
  • 5. Monitor Risks Coincides with PMBOK 11.7 11.7 Monitor Risks Project Management Plan • Issue Log • Lessons learned register • Risk register • Risk report • Work performance reports Project Documents • Change Requests • Risk management plan 4.6 Perform Integrated Change Control Project Documents • Assumption log • Issue log • Lessons learned register • Risk register • Risk report 4.5 Monitor and Control Project Work • Work performance information Project Management Plan Enterprise/Orga nization • Organizational process assets • Any Component 4.3 Direct and Manage Project Work 4.5 Monitor and Control Project Work • Work performance data
  • 6. Overview The Monitor Risks process uses performance information generated during project execution to determine if: • Implemented risk responses are effective • Level of overall project risk has changed • Status of identified individual project risks has changed • New individual project risks have arisen • Risk management approach is still appropriate • Project assumptions are still valid • Risk management policies and procedures are being followed • Contingency reserves for cost or schedule require modification • Project strategy is still valid Coincides with PMBOK 11.7 Monitor Risks
  • 7. Monitor Risks - Inputs Coincides with PMBOK 11.7 Project Management Plan • Project management plan components include but are not limited to the risk management plan. • The risk management plan provides guidance on how and when risks should be reviewed, which policies and procedures should be followed, the roles and responsibilities in the monitoring process, and reporting formats.
  • 8. Monitor Risks - Inputs Coincides with PMBOK 11.7 Project Documents Project documents that should be considered as inputs for this process include: • Issue Log • Lessons learned register • Risk register • Risk report
  • 9. Coincides with PMBOK 11.7 Work Performance Data Work performance data contains data on project status such as risk responses that have been implemented, risks that have occurred, risks that are active and those that have been closed out. Monitor Risks - Inputs
  • 10. Coincides with PMBOK 11.7 Work Performance Reports Work performance reports provide information from performance measurements that can be analysed to provide project work performance information including variance analysis, earned value data, and forecasting data. This information could be relevant when monitoring performance-related risks. Monitor Risks - Inputs
  • 11. Monitor Risks - Tools & Techniques Coincides with PMBOK 11.7 Data Analysis Data analysis techniques that can be used for this process include: • Technical performance analysis • Reserve analysis
  • 12. Monitor Risks - Tools & Techniques Coincides with PMBOK 11.7 Audits • Risk audits are a type of audit that may be used to consider the effectiveness of the risk management process. • The project manager is responsible for ensuring that risk audits are performed at an appropriate frequency, as defined in the project’s risk management plan. • Risk audits may be included during routine project review meetings or may form part of a risk review meeting, or the team may choose to hold separate risk audit meetings.
  • 13. Monitor Risks - Tools & Techniques Coincides with PMBOK 11.7 Meetings Meetings that can be used during this process include, risk reviews. Risk reviews are scheduled regularly and should examine and document the effectiveness of risk responses in dealing with overall project risk and with identified individual project risks. Risk reviews may also result in: • Identification of new individual project risks • Reassessment of current risks • The closing of risks that are outdated • Issues that have arisen as the result of risks that have occurred • Identification of lessons to be learned for implementation in ongoing phases in the current project or in similar projects in the future.
  • 14. Monitor Risks - Outputs Coincides with PMBOK 11.7 Work Performance Information Work performance information includes information on how project risk management is performing by comparing the individual risks that have occurred with the expectation of how they would occur. This information indicates the effectiveness of the response planning and response implementation processes.
  • 15. Monitor Risks - Outputs Coincides with PMBOK 11.7 Change Requests • The Monitor Risks process may result in a change request to the cost and schedule baselines or other components of the project management plan. • Change requests are processed for review and disposition through the Perform Integrated Change Control process. • Change requests can include recommended corrective and preventive actions to address the current level of overall project risk or to address individual project risks.
  • 16. Monitor Risks - Outputs Coincides with PMBOK 11.7 Project Management Plan Updates Any change to the project management plan goes through the organization’s change control process via a change request. This may affect any component of the project management plan.
  • 17. Monitor Risks - Outputs Coincides with PMBOK 11.7 Project Document Updates Project documents that may be updated as a result of carrying out this process include: • Assumption log • Issue log • Lessons learned register • Risk register • Risk report
  • 18. Monitor Risks - Outputs Coincides with PMBOK 11.7 Organizational Process Assets Organizational process assets that are updated as a result of the Monitor Risks process include but are not limited to: • Templates for the risk management plan, risk register, and risk report • Risk breakdown structure.

Editor's Notes

  1. This process is performed throughout the project
  2. Issue log - The issue log is used to see if any of the open issues have been updated and necessitate an update to the risk register. Lessons learned register - Risk-related lessons from earlier in the project can be applied to later phases in the project. Risk register - The risk register has key inputs that include identified individual project risks, risk owners, agreed-upon risk responses, and specific implementation actions Risk report - The risk report includes an assessment of the current overall project risk exposure as well as the agreed-upon risk response strategy. It also describes the major individual risks with planned responses and risk owners.
  3. Technical performance analysis - Technical performance analysis compares technical accomplishments during project execution to the schedule of technical achievement. Reserve analysis - Reserve analysis compares the amount of the contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.
  4. The format for the risk audit and its objectives should be clearly defined before the audit is conducted.
  5. The risk review may be conducted as part of a periodic project status meeting or a dedicated risk review meeting may be held, as specified in the risk management plan.
  6. Assumption log - During the Monitor Risks process, new assumptions may be made, new constraints may be identified, and existing assumptions or constraints may be revisited and changed. The assumption log is updated with this new information. Issue log - Where issues are identified as part of the Monitor Risks process, these are recorded in the issue log. Lessons learned register - The lessons learned register is updated with any risk-related lessons learned during risk reviews so these can be used on later phases of the project or in future projects. Risk register - The risk register is updated with information on individual project risks generated during the Monitor Risks process. Risk report - The risk report may also include details of the top individual project risks, agreed- upon responses and owners, and conclusions and recommendations. It may also include conclusions from risk audits on the effectiveness of the risk management process.