SlideShare a Scribd company logo
Welcome To The
Prof. Muzette Charles, PMP
mcharles2@pace.edu
Certified Associate Project Management
CAPM® Exam Prep – Week 1
Welcome
Prof. Muzette Charles, PMP
20 year professional career managing financial portfolios and
non-profit fund development projects
Pace University – Adjunct Professor, PMP / CAPM
Media Solutions – Project Manager, Finance & Marketing
Morgan Stanley – Financial Advisor
U.S.P.S. – National Account Manager
Project Management Professional – PMP / PMI Certified
B.S. Electrical Engineering – Fairleigh Dickinson University
Why take the CAPM® ?
 Regardless of your career stage, the Certified Associate in Project Management
(CAPM)® is an asset that will distinguish you in the job market and enhance your
credibility and effectiveness working on — or with — project teams.
 Project management is a rapidly growing profession. Through 2020, 1.57 million
new jobs will be created each year and qualified practitioners are in demand.
With the CAPM, you’ll be on the fast track to opportunity.
 If you’d like to manage larger projects and gain more responsibility or add project
management skills into your current role, then the Certified Associate in Project
Management (CAPM) is right for you.
Comparison between
PMP ® and CAPM® Exams
Tricks of the Trade
Studying for the CAPM® Exam
Chapter 1
 Pass the exam on your first try
 Learn, not just memorize
 Shorten your study time
 Determine the gaps in your knowledge
 Gain insider tips on the exam
 Make sense of the topics on the exam
 Apply to Project Management Institute - PMI
 Authorization Notice to make appointment to take exam
 Designated Computerized Testing Sites
 One year from date of Authorization Notice to pass exam
 Can take exam up to 3x within that one year
 If you fail all 3x times, must wait one year to reapply
Tricks of the Trade
Studying for the CAPM® Exam
Chapter 1
Rita Mulcahy’s CAPM® Exam Prep
This book combines full knowledge area
coverage, Quicktest reviews, practice
questions and creative ways to reinforce
your understanding of Process inputs, tools
and techniques, and outputs (ITTOs) with
page references to the PMBOK ® Guide.
Tricks of the Trade
Studying for the CAPM® Exam
Chapter 1
PMBOK® Guide
“CAPM candidates need to read (and
study) the PMBOK® Guide at least once, if
not twice. It is the primary source for exam
questions, so you need to be familiar with
it.”
Tricks of the Trade
Studying for the CAPM® Exam
Chapter 1
Tricks of the Trade
How is the CAPM® Exam Scored?
Chapter 1
 150 multiple-choice questions with 4
answer choices per question
 3 hours to complete exam
 15 experimental questions randomly
placed & not scored!!
 Questions weighted by Knowledge Area
 No penalty for wrong answers
 135 questions scored on PASS / FAIL
Tricks of the Trade
How is the CAPM® Exam Scored?
Chapter 1
 General PMI-isms
 Planning the Project
 While the Project Work is Being Done
 Closing the Project
Tricks of the Trade
Studying for the CAPM® Exam
Chapter 2
 Project
 Project Management
 Program
 Portfolio
 Operations vs. Projects
 Enterprise Environment Factors
 Organizational Process Assets
 Work Performance Data, Information &
Reports
 Organizational Structure: Functional,
Projectized, Matrix
 Project Life Cycle: Predictive, Iterative,
Adaptive
 Project Management Process
 Project Management Office (PMO)
 Stakeholders
 Constraints
Project Management Framework
QUICKTEST – Chapter 2
What is a Project?
“A project is a temporary endeavor undertaken to create a unique
product, service or result. The temporary nature of projects
indicates that a project has a definite beginning and end. The end
is reached when the project’s objectives have been achieved or
when the project is terminated because its objectives will not or
cannot be met or when the need for the project no longer exists.”
Project Management Framework
Chapter 2
Project Managers
 “… keep the team focused on the business value the project is providing. By constantly
helping each team member to understand how his or her work impacts the project’s
value, the PM makes sure that everyone on the team makes the best decisions to keep the
project on track.”
 Interpersonal Skills
 Leadership
 Motivation
 Team Building & Trust Building
 Influencing
 Coaching
 Conflict Management
 Political & Cultural Awareness
Project Management Framework
Chapter 2
Business Value
is the sum of all of the resources a
company is made of; its people,
equipment and the intellectual
property they produce.
Portfolio - Strategic Goals
Program - Shared Benefits
Project – Deliverables
Project Management Framework
Chapter 2
Project Management Office (PMO)
 Supports Project Managers
 Manage shared resources across all
projects
 Coaching, training, mentoring, oversight
 Monitor & periodic reviews compliance
by AUDITS
 Develop & manage shared docs (OPAs)
Project Management Framework
Chapter 2
OPERATIONS vs.
 Work is REPEATABLE &
ONGOING to produce goods or
services in support of the
business/organization.
 Supports the day-to-day business to
achieve the company’s strategic goals.
 Ex: production, accounting,
software support, maintenance,
manufacturing
PROJECTS
 Gathers a team together to do
TEMPORARY work to create a
UNIQUE RESULT and is
PROGRESSIVELY ELABORATED that
ends when the project is closed
 Produces a product that is handed off
to operations
 Require PM activities & skill sets
 Are not always successful
Project Management Framework
Chapter 2
 Stakeholders
 “… include all members of the project team as
well as interested entities that are internal &
external to the organization…. that can have a
positive or negative influence.”
 The team that actually does the work
 The people who pay for the work
 Everybody who will use the product when
the project is done
 Everyone who may be impacted by the
project along the way
 90% of PM’s job is communicating with
everyone to make sure their needs are met
Project Management Framework
Chapter 2
Project Constraints
 Any limitation, change or addition that a Stakeholder tries to place on a project.
 PM is responsible to analyze each change & the impact on the other constraints
thru Integrated Change Control.
Project Management Framework
Chapter 2
Enterprise Environmental Factors
 “…refer to conditions, not under the control of the project team, that
influence, constrain or direct the project.”
 The company culture, existing systems, “baggage”
 Are INPUTS to most planning processes
Project Management Framework
Chapter 2
Organizational Process Assets
 “… are the plans, processes, policies, procedures & knowledge bases
specific to & used by the performing org.”
 aka Corporate Knowledge Base
 Are INPUTS to most planning processes
Project Management Framework
Chapter 2
Organizational Structure
 Functional
 Most common, grouped by function/department – Acctg, Mktg,
 PM has no direct reports & Team members work in a “Silo”
 Matrix
 Maximizes strength of both functional & projectized structures
BALANCED - PM shares authority with Func. Mgr & Team members have “Two Bosses”
WEAK MATRIX
 Expeditor – Cannot make/enforce decisions, is a Staff Asst/Communications Coord.
 Coordinator – Has some authority to make decisions & reports to a higher level Mgr
 Projectized
 PM controls the project & Team members have “No Home”
Project Management Framework
Chapter 2
Organizational Structure
Project Management Framework
Chapter 2
Project Life Cycle
 What you need to do to DO the work!!
 “…is a series of phases that a project passes thru
from its initiation to its closure.”
 “…provides a basic framework for managing the
project regardless of the specific work being
done.”
 “Projects vary in size & complexity, but all follow
the Generic Life Cycle structure”
Project Management Framework
Chapter 2
Project Life Cycle
 PREDICTIVE – aka Traditional / Waterfall
are Plan-Driven Projects where Scope, Cost, Time are defined in the beginning
 INCREMENTAL & ITERATIVE – Rolling Wave Planning / Progressive Elaboration
enough early planning to create Time & Cost estimates. Successive iterations/levels of
details to create a usable product.
 ADAPTIVE – aka Agile
are Change-Driven where Time & Cost are defined early, but Scope is defined over many
iterations. Stakeholder changes highly involved & prioritized as a “Backlog”
Project Management Framework
Chapter 2
Project Management Process
… is what you need to do to MANAGE the work!!
Only ONE Project Management Process, regardless of the life cycle
Project Management Framework
Chapter 2
Project Information
 Work Performance Data – raw observations & measurements
 % completion
 Start & finish dates of activities
 Actual costs & durations
 # of change requests
 Work Performance Information – data collected from control processes analyzed & integrated
 Status of deliverables
 Forecasted estimates to completion
 Work Performance Reports – information compiled into Project Docs to generate decisions, raise issues,
actions or awareness
 Project Status Reports
 Memos
 eDashboards, KPIs, etc
Project Management Framework
Chapter 2
Project Management Process
The Goal…
- Deliver the product on time
- Within budget
- Fulfill the customer’s needs & expectations
- Maintain a happy & well-functioning team
Project Management Framework
Chapter 2
What makes a great Project Mgr ?

More Related Content

What's hot

Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project management
REHMAT ULLAH
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadirPMI_IREP_TP
 
Manage complex projects to success using CMMI, Lean and Scrum
Manage complex projects to success using CMMI, Lean and ScrumManage complex projects to success using CMMI, Lean and Scrum
Manage complex projects to success using CMMI, Lean and Scrum
Systematic
 
Overview of PRINCE2
Overview of PRINCE2Overview of PRINCE2
Overview of PRINCE2
iHub
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
Mike Cottmeyer
 
SoftPMO Project Management Toolkit for Microsoft Project Server
SoftPMO Project Management Toolkit for Microsoft Project ServerSoftPMO Project Management Toolkit for Microsoft Project Server
SoftPMO Project Management Toolkit for Microsoft Project Server
Michael Kaplan
 
Realizing the value of Agile in an Offshore PMO Setup
Realizing the value of Agile in an Offshore PMO SetupRealizing the value of Agile in an Offshore PMO Setup
Realizing the value of Agile in an Offshore PMO Setup
Gurpreet Singh SPC, CSP, CSM, LSSGB
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandraPMI_IREP_TP
 
Prince2 resources e-book 1
Prince2 resources e-book 1Prince2 resources e-book 1
Prince2 resources e-book 1
Knowledge Train
 
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About It
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About ItWhy Project Managers (Understandably) Hate the CMMI -- and What to Do About It
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About It
Leading Edge Process Consultants LLC
 
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningOpenLearningLab
 
Brightwork Project Management Introductory Guide - From Atidan
Brightwork Project Management Introductory Guide - From AtidanBrightwork Project Management Introductory Guide - From Atidan
Brightwork Project Management Introductory Guide - From Atidan
David J Rosenthal
 
Understanding Agile Project Management (APM)
Understanding Agile Project Management (APM)Understanding Agile Project Management (APM)
Understanding Agile Project Management (APM)
Ahmed Alnaqaa
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuramPMI_IREP_TP
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
Robert McGeachy
 
Agile Project Management for IT Projects
Agile Project Management for IT ProjectsAgile Project Management for IT Projects
Agile Project Management for IT Projectsrachna_nainani
 
21 Steering Group
21 Steering Group21 Steering Group
21 Steering GroupPAVO
 
Agile Practice Guide Notes
Agile Practice Guide NotesAgile Practice Guide Notes
Agile Practice Guide Notes
Mahmoud BEN TAHAR
 

What's hot (20)

Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project management
 
Presentation by suhail qadir
Presentation by suhail qadirPresentation by suhail qadir
Presentation by suhail qadir
 
Manage complex projects to success using CMMI, Lean and Scrum
Manage complex projects to success using CMMI, Lean and ScrumManage complex projects to success using CMMI, Lean and Scrum
Manage complex projects to success using CMMI, Lean and Scrum
 
Overview of PRINCE2
Overview of PRINCE2Overview of PRINCE2
Overview of PRINCE2
 
Agile Project Management
Agile Project ManagementAgile Project Management
Agile Project Management
 
Prince2 quick guide
Prince2 quick guidePrince2 quick guide
Prince2 quick guide
 
SoftPMO Project Management Toolkit for Microsoft Project Server
SoftPMO Project Management Toolkit for Microsoft Project ServerSoftPMO Project Management Toolkit for Microsoft Project Server
SoftPMO Project Management Toolkit for Microsoft Project Server
 
Realizing the value of Agile in an Offshore PMO Setup
Realizing the value of Agile in an Offshore PMO SetupRealizing the value of Agile in an Offshore PMO Setup
Realizing the value of Agile in an Offshore PMO Setup
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
 
Prince2 resources e-book 1
Prince2 resources e-book 1Prince2 resources e-book 1
Prince2 resources e-book 1
 
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About It
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About ItWhy Project Managers (Understandably) Hate the CMMI -- and What to Do About It
Why Project Managers (Understandably) Hate the CMMI -- and What to Do About It
 
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
 
Brightwork Project Management Introductory Guide - From Atidan
Brightwork Project Management Introductory Guide - From AtidanBrightwork Project Management Introductory Guide - From Atidan
Brightwork Project Management Introductory Guide - From Atidan
 
Understanding Agile Project Management (APM)
Understanding Agile Project Management (APM)Understanding Agile Project Management (APM)
Understanding Agile Project Management (APM)
 
Presentation by pavan adipuram
Presentation by pavan adipuramPresentation by pavan adipuram
Presentation by pavan adipuram
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
 
Agile Project Management for IT Projects
Agile Project Management for IT ProjectsAgile Project Management for IT Projects
Agile Project Management for IT Projects
 
Business Process Design 2008
Business Process Design 2008Business Process Design 2008
Business Process Design 2008
 
21 Steering Group
21 Steering Group21 Steering Group
21 Steering Group
 
Agile Practice Guide Notes
Agile Practice Guide NotesAgile Practice Guide Notes
Agile Practice Guide Notes
 

Similar to CAPM Muzette Charles_Week1_Chapter1-2

PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
Muzette Charles, PMP
 
CAPM week 1 chapter 2
CAPM week 1 chapter 2CAPM week 1 chapter 2
CAPM week 1 chapter 2
Muzette Charles, PMP
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
Krishna Murthy RVN
 
Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Antonio Caforio
 
Project Management Career Seminar
Project Management Career SeminarProject Management Career Seminar
Project Management Career Seminar
Ojiugo Ajunwa
 
Project management career seminar
Project management career seminarProject management career seminar
Project management career seminar
Ojiugo Ajunwa
 
Project management
Project managementProject management
Project management
Susmitha RANGU
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
Md. Masudur Rahman, PMP
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
Ahmad Hamid
 
The Next Generation PMO
The Next Generation PMOThe Next Generation PMO
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
KenMartin18
 
1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx
RAJU852744
 
1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx
aulasnilda
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009
Manish Chaurasia
 
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
PDUs2Go.com
 
Pmo
PmoPmo
Pmo
ammody
 
PMP Refresher Course
PMP Refresher CoursePMP Refresher Course
PMP Refresher Course
Edureka!
 
P3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management FrameworkP3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management Framework
Robert M. Buhrman, Jr. PMP, PgMP, CSM, SPC, ITIL
 
You have a project manager yay
You have a project manager   yayYou have a project manager   yay
You have a project manager yay
Martin Bailey
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
JustAcademy
 

Similar to CAPM Muzette Charles_Week1_Chapter1-2 (20)

PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM week 1 chapter 2
CAPM week 1 chapter 2CAPM week 1 chapter 2
CAPM week 1 chapter 2
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224Project management in IBM EG - lecce_20140224
Project management in IBM EG - lecce_20140224
 
Project Management Career Seminar
Project Management Career SeminarProject Management Career Seminar
Project Management Career Seminar
 
Project management career seminar
Project management career seminarProject management career seminar
Project management career seminar
 
Project management
Project managementProject management
Project management
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
The Next Generation PMO
The Next Generation PMOThe Next Generation PMO
The Next Generation PMO
 
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
25 BENEFITS OF A PROJECT MANAGEMENT OFFICE
 
1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx
 
1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx1PJM6000 Week 1Project Management PracticesProfess.docx
1PJM6000 Week 1Project Management PracticesProfess.docx
 
Project management 02112009
Project management 02112009Project management 02112009
Project management 02112009
 
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
Jennifer Whitt, PMP speaks to PMPs for PDUs on Achieving Success using the Pr...
 
Pmo
PmoPmo
Pmo
 
PMP Refresher Course
PMP Refresher CoursePMP Refresher Course
PMP Refresher Course
 
P3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management FrameworkP3M - Project, Program, Portfolio Management Framework
P3M - Project, Program, Portfolio Management Framework
 
You have a project manager yay
You have a project manager   yayYou have a project manager   yay
You have a project manager yay
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
Muzette Charles, PMP
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
Muzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
Muzette Charles, PMP
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
Muzette Charles, PMP
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
Muzette Charles, PMP
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
Muzette Charles, PMP
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
Muzette Charles, PMP
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
Muzette Charles, PMP
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
Muzette Charles, PMP
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
Muzette Charles, PMP
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
Muzette Charles, PMP
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 

Recently uploaded

The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 

Recently uploaded (20)

The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 

CAPM Muzette Charles_Week1_Chapter1-2

  • 1. Welcome To The Prof. Muzette Charles, PMP mcharles2@pace.edu Certified Associate Project Management CAPM® Exam Prep – Week 1
  • 2. Welcome Prof. Muzette Charles, PMP 20 year professional career managing financial portfolios and non-profit fund development projects Pace University – Adjunct Professor, PMP / CAPM Media Solutions – Project Manager, Finance & Marketing Morgan Stanley – Financial Advisor U.S.P.S. – National Account Manager Project Management Professional – PMP / PMI Certified B.S. Electrical Engineering – Fairleigh Dickinson University
  • 3. Why take the CAPM® ?  Regardless of your career stage, the Certified Associate in Project Management (CAPM)® is an asset that will distinguish you in the job market and enhance your credibility and effectiveness working on — or with — project teams.  Project management is a rapidly growing profession. Through 2020, 1.57 million new jobs will be created each year and qualified practitioners are in demand. With the CAPM, you’ll be on the fast track to opportunity.  If you’d like to manage larger projects and gain more responsibility or add project management skills into your current role, then the Certified Associate in Project Management (CAPM) is right for you.
  • 4. Comparison between PMP ® and CAPM® Exams
  • 5. Tricks of the Trade Studying for the CAPM® Exam Chapter 1  Pass the exam on your first try  Learn, not just memorize  Shorten your study time  Determine the gaps in your knowledge  Gain insider tips on the exam  Make sense of the topics on the exam
  • 6.  Apply to Project Management Institute - PMI  Authorization Notice to make appointment to take exam  Designated Computerized Testing Sites  One year from date of Authorization Notice to pass exam  Can take exam up to 3x within that one year  If you fail all 3x times, must wait one year to reapply Tricks of the Trade Studying for the CAPM® Exam Chapter 1
  • 7. Rita Mulcahy’s CAPM® Exam Prep This book combines full knowledge area coverage, Quicktest reviews, practice questions and creative ways to reinforce your understanding of Process inputs, tools and techniques, and outputs (ITTOs) with page references to the PMBOK ® Guide. Tricks of the Trade Studying for the CAPM® Exam Chapter 1
  • 8. PMBOK® Guide “CAPM candidates need to read (and study) the PMBOK® Guide at least once, if not twice. It is the primary source for exam questions, so you need to be familiar with it.” Tricks of the Trade Studying for the CAPM® Exam Chapter 1
  • 9. Tricks of the Trade How is the CAPM® Exam Scored? Chapter 1
  • 10.  150 multiple-choice questions with 4 answer choices per question  3 hours to complete exam  15 experimental questions randomly placed & not scored!!  Questions weighted by Knowledge Area  No penalty for wrong answers  135 questions scored on PASS / FAIL Tricks of the Trade How is the CAPM® Exam Scored? Chapter 1
  • 11.  General PMI-isms  Planning the Project  While the Project Work is Being Done  Closing the Project Tricks of the Trade Studying for the CAPM® Exam Chapter 2
  • 12.  Project  Project Management  Program  Portfolio  Operations vs. Projects  Enterprise Environment Factors  Organizational Process Assets  Work Performance Data, Information & Reports  Organizational Structure: Functional, Projectized, Matrix  Project Life Cycle: Predictive, Iterative, Adaptive  Project Management Process  Project Management Office (PMO)  Stakeholders  Constraints Project Management Framework QUICKTEST – Chapter 2
  • 13. What is a Project? “A project is a temporary endeavor undertaken to create a unique product, service or result. The temporary nature of projects indicates that a project has a definite beginning and end. The end is reached when the project’s objectives have been achieved or when the project is terminated because its objectives will not or cannot be met or when the need for the project no longer exists.” Project Management Framework Chapter 2
  • 14. Project Managers  “… keep the team focused on the business value the project is providing. By constantly helping each team member to understand how his or her work impacts the project’s value, the PM makes sure that everyone on the team makes the best decisions to keep the project on track.”  Interpersonal Skills  Leadership  Motivation  Team Building & Trust Building  Influencing  Coaching  Conflict Management  Political & Cultural Awareness Project Management Framework Chapter 2
  • 15. Business Value is the sum of all of the resources a company is made of; its people, equipment and the intellectual property they produce. Portfolio - Strategic Goals Program - Shared Benefits Project – Deliverables Project Management Framework Chapter 2
  • 16. Project Management Office (PMO)  Supports Project Managers  Manage shared resources across all projects  Coaching, training, mentoring, oversight  Monitor & periodic reviews compliance by AUDITS  Develop & manage shared docs (OPAs) Project Management Framework Chapter 2
  • 17. OPERATIONS vs.  Work is REPEATABLE & ONGOING to produce goods or services in support of the business/organization.  Supports the day-to-day business to achieve the company’s strategic goals.  Ex: production, accounting, software support, maintenance, manufacturing PROJECTS  Gathers a team together to do TEMPORARY work to create a UNIQUE RESULT and is PROGRESSIVELY ELABORATED that ends when the project is closed  Produces a product that is handed off to operations  Require PM activities & skill sets  Are not always successful Project Management Framework Chapter 2
  • 18.  Stakeholders  “… include all members of the project team as well as interested entities that are internal & external to the organization…. that can have a positive or negative influence.”  The team that actually does the work  The people who pay for the work  Everybody who will use the product when the project is done  Everyone who may be impacted by the project along the way  90% of PM’s job is communicating with everyone to make sure their needs are met Project Management Framework Chapter 2
  • 19. Project Constraints  Any limitation, change or addition that a Stakeholder tries to place on a project.  PM is responsible to analyze each change & the impact on the other constraints thru Integrated Change Control. Project Management Framework Chapter 2
  • 20. Enterprise Environmental Factors  “…refer to conditions, not under the control of the project team, that influence, constrain or direct the project.”  The company culture, existing systems, “baggage”  Are INPUTS to most planning processes Project Management Framework Chapter 2
  • 21. Organizational Process Assets  “… are the plans, processes, policies, procedures & knowledge bases specific to & used by the performing org.”  aka Corporate Knowledge Base  Are INPUTS to most planning processes Project Management Framework Chapter 2
  • 22. Organizational Structure  Functional  Most common, grouped by function/department – Acctg, Mktg,  PM has no direct reports & Team members work in a “Silo”  Matrix  Maximizes strength of both functional & projectized structures BALANCED - PM shares authority with Func. Mgr & Team members have “Two Bosses” WEAK MATRIX  Expeditor – Cannot make/enforce decisions, is a Staff Asst/Communications Coord.  Coordinator – Has some authority to make decisions & reports to a higher level Mgr  Projectized  PM controls the project & Team members have “No Home” Project Management Framework Chapter 2
  • 24. Project Life Cycle  What you need to do to DO the work!!  “…is a series of phases that a project passes thru from its initiation to its closure.”  “…provides a basic framework for managing the project regardless of the specific work being done.”  “Projects vary in size & complexity, but all follow the Generic Life Cycle structure” Project Management Framework Chapter 2
  • 25. Project Life Cycle  PREDICTIVE – aka Traditional / Waterfall are Plan-Driven Projects where Scope, Cost, Time are defined in the beginning  INCREMENTAL & ITERATIVE – Rolling Wave Planning / Progressive Elaboration enough early planning to create Time & Cost estimates. Successive iterations/levels of details to create a usable product.  ADAPTIVE – aka Agile are Change-Driven where Time & Cost are defined early, but Scope is defined over many iterations. Stakeholder changes highly involved & prioritized as a “Backlog” Project Management Framework Chapter 2
  • 26. Project Management Process … is what you need to do to MANAGE the work!! Only ONE Project Management Process, regardless of the life cycle Project Management Framework Chapter 2
  • 27. Project Information  Work Performance Data – raw observations & measurements  % completion  Start & finish dates of activities  Actual costs & durations  # of change requests  Work Performance Information – data collected from control processes analyzed & integrated  Status of deliverables  Forecasted estimates to completion  Work Performance Reports – information compiled into Project Docs to generate decisions, raise issues, actions or awareness  Project Status Reports  Memos  eDashboards, KPIs, etc Project Management Framework Chapter 2
  • 28. Project Management Process The Goal… - Deliver the product on time - Within budget - Fulfill the customer’s needs & expectations - Maintain a happy & well-functioning team Project Management Framework Chapter 2
  • 29. What makes a great Project Mgr ?

Editor's Notes

  1. The Sponsor, Seller, Business Partner who provides training Consumers Users, Organ. Groups, Functional Mgr
  2. Time: durations, dependencies, critical path Cost: $, budget, profits Scope: Proj size, goals Resources: Ppl, Equip, Material Customer satisfaction
  3. Pg 20: Lessons learned: What was right or wrong about how we completed the work to produce the product? How did we do w/the WBS creation, risk planning…? How did we do with communications leadership as a PM?
  4. Pg 22: Functional think Silo , Projectized Teams – PM choose Team Mbrs & releases them when Project is Closed
  5. Pg 22: Functional think Silo , Projectized think “no home”
  6. Don’t confuse with Product Life Cycle…. From its conception to its withdrawal from the marketplace
  7. Iterations aka Phases means Executing 1 Phase while Planning another… Can be OVERLAPPING or SEQUENTIAL
  8. Pg 21: DATA; an activity took 10 hrs & was completed on July 21. INFO; how does data compare to the project plan of 12hrs & 7/22? REPORT: status reports