SlideShare a Scribd company logo
1 of 30
Project Management Professional
PMP® Exam Prep – Week 5
Prof. Muzette Charles, PMP | mcharles2@pace.edu
Risk Management
Chapter 11
“… increase the likelihood & impact of positive events & decrease the likelihood & impact of negative events in
the project.”
• “Risk is an uncertain event that if it occurs, has a positive or negative effect on 1 or more of the project
objectives of scope, schedule, cost & quality.”
• Planned Risk Response: Known risks that are identified & analyzed
• Contingency Reserve : Assigned for KNOWN risks that cannot be managed proactively
• Management Reserve : Assigned for UNKNOWN risks that cannot be managed proactively
• Positive risks = Opportunities
• Negative risks = Threats  90% of Threats can be eliminated => if occur are known as Issues
• Levels of Risks: Appetite, Tolerance, Threshold, Averse
Process Process Group Key Deliverables
11.1 Plan Risk Management Planning Risk Management Plan
11.2 Identify Risks Planning Risk Register
11.3 Perform Qualitative Risk Analysis Planning Project Documents updates
11.4 Perform Quantitative Risk Analysis Planning Project Documents updates
11.5 Plan Risk Responses Planning Project Management Plan updates
11.6 Implement Risks Responses Executing Change requests
11.7 Monitor Risks Monitoring & Controlling Change requests
Risk Management
Chapter 11
Organization’s Risk Attitude
How much overall project risk is the organization willing to accept?
 Risk-averse
 Risk-seeking
 Risk-neutral
Risk Appetite Risk Tolerance Risk Threshold
Degree of risk the
organization is
willing to take on
Organization’s
readiness to bear
the risk
Organization’s chosen
level above or below
which a risk should be
addressed
Risk Management
Chapter 11
Plan Risk Management
Process 1 Key Points
 “… process is vital to communicate with & obtain agreement & support from all stakeholders to ensure
risk mgmt process is supported & performed over the project life cycle.”
 Risk Mgmt Plan: Methodology, Roles & responsibilities, Budget, Timing, Risk Categories, Definitions of
probability & impact (low to high/numerical), Stakeholder tolerances, Reporting & Tracking
 Risk Categories aka Sources of Risks: external, internal (constraints), technical, unforeseeable (10%)
Risk Catergories
Risk Breakdown Structure (RBS)
Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017,
Figure 11-4, Page 406. Material from this publication has been reproduced with the permission of PMI.
Risk Management
Chapter 11Plan Risk Management
Process 1
Probability and Impact Matrix
Very Low
(10%)
Low
(30%)
Moderate
(50%)
High
(70%)
Very
High
(90%)
5% 9% 18% 36% 72%
4% 7% 14% 28% 56%
3% 5% 10% 20% 40%
2% 3% 6% 12% 24%
1% 1% 2% 4% 8%
Low
(10%)
Moderate
(20%)
High
(40%)
Very
High
(80%)
Very
High
(80%)
High
(40%)
Moderate
(20%)
Low
(10%)
Very
Low
(5%)
= Exploit, enhance, or share
= Use expert judgment
= Accept
Avoid, transfer, or mitigate =
Use expert judgment =
Accept =
Risks (Threats) Opportunities
56% 28% 14% 7% 4%
40% 20% 10% 5% 3%
24% 12% 6% 3% 2%
8% 4% 2% 1% 1%
72% 36% 18% 9% 5%
Probability
Impact
Very
Low
(5%)
Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017,
Figure 11-5, Page 408. Material from this publication has been reproduced with the permission of PMI.
Risk Management
Chapter 11Plan Risk Management
Process 1
Risk Management Plan
 Risk strategy
 Methodology
 Roles and responsibilities
 Funding
 Timing
 Risk categories
 Stakeholder risk appetite
 Definitions of risk probability
and impacts
 Probability and impact matrix
 Reporting and tracking
Plan components:
Risk Management
Chapter 11Plan Risk Management
Process 1
Risk Management
Chapter 11Identify Risks
Process 2 Key Points
 “… process of documenting existing risks & the knowledge & ability it provides the project team to
anticipate events.”
 “… is an iterative process, because new risks may evolve or become known as the project progresses.”
 Tools: Info Gathering (see Scope tools), Diagramming (see Quality tools), SWOT
 Risk Register: lists of risks, potential responses, root causes & updates
Risk Register
Living document that includes:
 All identified risks
 Risk analysis results
 Planned responses
 Issues/response outcomes
Risk Management
Chapter 11Identify Risks
Process 2
Risk Management
Chapter 11
Perform Qualitative Risk Analysis
Process 3
Not all risks are created equal
 Some are more likely than others.
 Some are more urgent than others.
 Some have a greater impact than others.
Ranking of
HIGH, MEDIUM, LOW
Project Risk Evaluators
Risk Management
Chapter 11
Key Points
 “… process of prioritizing risks by assessing their probability of occurrence & impact… to reduce the
level of uncertainty & to focus on high-priority risks.”
 Cost-Effective: way to quickly prioritize risks
 Short-Listed Risks: those risks that have a high impact on project & warrant a response
 Risk Urgency: those high impact risks that may occur soon and/or take a long time to plan a response
 Risk Probability & Impact / Matrix: is Subjective, varies on the risk bias of the person doing the rating!!
 Watch List: non-critical risks that are documented on the Risk Register & reviewed in Control Risks
Perform Qualitative Risk Analysis
Process 3
Risk Management
Chapter 11
Project Risk Evaluators
Perform Quantitative Risk Analysis
Process 4
Ranking of
NUMERICAL RATING
 Numerical analysis of risks
 Quantified according to their expected monetary value (EMV)
 Reduces project uncertainty through better decision making
Risk Management
Chapter 11
Key Points
 “… process of assigning a numerical priority rating to those risks prioritized in Qualitative Risk Analysis.”
 Risk Assessment is Objective: each risk based on actual probability of occurring & the impact (amount at stake)
 Risk Analysis Tools: Sensitivity/Tornado Diagram, Expected Money Value (EMV=PxI), Monte Carlo/Probability
Perform Quantitative Risk Analysis
Process 4
Risk Management
Chapter 11
Perform Quantitative Risk Analysis
Process 4
EMV = Probability × Impact
Expected Monetary Value (EMV)
Principal method for quantifying risk in a project
Example 1:
A risk with a 30 percent chance of occurring that could increase budgeted costs by US$100,000.
Example 2:
A corresponding opportunity with a 70 percent chance of decreasing budgeted costs by US$400,000.
EMVRisk = 0.3 × – $100,000 = – $30,000
EMVOpportunity = 0.7 × $400,000 = $280,000
Net EMV = –$30,000 + $280,000 = $250,000
Risk Management
Chapter 11
Qualitative Risk Analysis - Risk Probability & Impact Matrix
IMPACT
Quantitative Risk Analysis – Expected Money Value (EMV)
RISKS PROBABILITY IMPACT
High Winds 30% Cost $500 to replace equipment
Landslide 5% Lose $80,000 in damage costs
Wind generator is usable 20% Save $8,000 in battery costs
Truck rental unavailable 10% Cost $300 for last-minute rental
Wild animals eat rations 10% Costs $100 for replacements
Unseasonably warm weather 15% Saves $50,000 in excavation costs
RISKS PROBABILITY IMPACT
Landslide .1 .9
Winds .7 .9
No Truck .3 .7
Storms .5 .3
Supplies .1 .5
Illness .1 .1
Probability & Impact Matrix
.9 .09 .27 .45 .63 .69
.7 .07 .21 .35 .49 .63
.5 .05 .15 .25 .35 .45
.3 .03 .09 .15 .21 .27
.1 .01 .03 .05 .07 .09
.1 .3 .5 .7 .9
You are managing a facility renovation project. There is an 80
percent chance that supplier availability will cause a two-day delay
costing US$9,000. There is also a 30 percent chance that the price of
building materials will drop, which could save you US$15,000.
What is the project’s EMV?
A. –$7,200
B. –$2,700
C. $4,500
D. $11,700
Discussion Question
Answer: B
EMVRisk = 0.8 × –$9,000 = –$7,200
EMVOpportunity = 0.3 × $15,000 = $4,500
Net EMV = –$7,200 + $4,500 = –$2,700
Chapter 11, Topic 4
Tornado Diagram
Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 11-14, Page 434. Material
from this publication has been reproduced with the permission of PMI.
Risk Management
Chapter 11
Perform Quantitative Risk Analysis
Process 4
Risk Management
Chapter 11
Key Points
 “… process enhances opportunities & reduce threats by inserting resources & activities into the budget, schedule & project
management plan as needed.”
 Tools:
 Strategies for Negative Risks/Threats: Avoid or Mitigate (used for high priority/impact), Transfer, Accept (workarounds)
 Strategies for Positive Risks/Opportunities: Exploit (take advantage), Enhance (influence triggers), Share, Accept
 Outputs:
 PMP Updates and Risk Register Updates: Residual Risks, Contingency Plans, Fallback Plans, Risk Owners, Secondary
Risks, Risk triggers, Contracts, Reserves (contingency)
 * Management Reserves: generally are 5% of the project budget to cover Unknown Risks
Plan Risk Responses
Process 5
Response Strategies for Threats
•Higher-level authority accepts responsibility for risk/responseEscalate
•Eliminate threat by changing the plan.
•Isolate objectives from impact or change an objective in jeopardy.Avoid
•Third party knowingly accepts some or all of the risk/response.
•Usually requires a risk premium (e.g., insurance payments).Transfer
•Reduce probability and/or impact to within threshold limits.
•Respond early, before issue, for best effect.Mitigate
•Acknowledge the risk but do nothing because it has a low risk
rating or it has no viable or cost-effective response.Accept
Risk Management
Chapter 11Plan Risk Responses
Process 5
Response Strategies for Opportunities
Risk Management
Chapter 11Plan Risk Responses
Process 5
•Ensure that opportunity outside project scope is realized.
•Identify relevant higher-level authority and communicate details appropriately.Escalate
•Ensure that opportunity is realized by applying existing resources (e.g., available contingency
funds).
•Eliminate uncertainty and go for it.
Exploit
•Third party adds expertise to ensure that opportunity is realized for the benefit of the project.
•All parties can have a net gain, but rewards are shared.Share
•Increase probability and/or impact of opportunity by influencing root causes of
probability/impact (e.g., obtaining additional funding from management to increase current
and future capability/capacity).
Enhance
•Acknowledge the opportunity but do not actively pursue because it has a low rating or it has
no viable or cost-effective response.Accept
Which is not a valid way to respond to a threat?
A. Avoid
B. Exploit
C. Mitigate
D. Accept
Discussion Question
Answer: B
Exploit is a response strategy for handling opportunities, not
threats. It may be selected for risks with positive impacts,
where the organization wants to ensure that the opportunity
definitely happens.
Chapter 11, Topic 5
Risk Response Planning Outputs
 Change requests
 Project management plan updates
 Changing baselines
 Updating schedule, cost, quality, resource,
and procurement management plans
 Project documents updates
 Risk Register
– Owner
– Trigger events and responses added
– New risks identified; watch list updated
 Residual
 Secondary
 Risk report
 Assumptions log updates
 Cost, schedule, team assignments
 Lessons learned
Risk Management
Chapter 11Plan Risk Responses
Process 5
What is used to monitor low priority risks?
A. Delphi technique
B. Monte Carlo analysis
C. Watch list
D. Probability and impact matrix
Discussion Question
Answer: C
Risks with low ratings of probability and impact are
included in the risk register as part of the watch list for
future monitoring.
Chapter 11, Topic 5
Risk Management
Chapter 11
Key Points
 “…implement agreed upon risk responses as planned to minimize project threats and maximize project
opportunities.”
 Specific risk responses are executed as planned
 Risk owner executes required action
Implement Risk Responses
Process 6
Risk Management
Chapter 11
Key Points
 “… process of implementing risk response plans, tracking identified risks, monitoring residual risks &
identifying new risks throughout the project life cycle to continuously optimize risk response.”
 Tools: Risk Audits (documented effectiveness of risk responses), Meetings (agenda item at status mtgs)
Monitor Risks
Process 7
 Are assumptions still valid?
 Have the risks become more or less probable?
 Have the risks become more or less impactful?
 Can any of the risks be retired?
 Are there any new risks to be added?
 Are the risk management policies and
procedures being followed?
Risk Management
Chapter 11Monitor Risks
Process 7
Reserve Analysis
Comparison
VS.
Amount of
contingency reserves
remaining
Outstanding risks
and their expected
monetary values
If inadequate = change request.
Risk Management
Chapter 11Monitor Risks
Process 7
Meetings
 Project risk management should be a regular
agenda item at project status meetings.
 Status of risks and responses reviewed
and updated for
relevance and
priority level.
Risk Management
Chapter 11Monitor Risks
Process 7
 Workarounds
– Unplanned corrective actions
– Address unknown risks
– Impromptu response
 Retiring risks
– For risks no longer relevant
to the project
– Expired risks
– Related to events that have come to pass
Risk Management
Chapter 11Monitor Risks
Process 7
Risk Register Updates
Risk Management
Chapter 11

More Related Content

What's hot

A Day of the Life of a Project Manager
A Day of the Life of a Project ManagerA Day of the Life of a Project Manager
A Day of the Life of a Project Managerreeza fazily
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...GlobalSkillup
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project managementMindGenius
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementAbdullah Ahmed, PMP, RMP
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysisWakas Khalid
 
Introduction to project management framework v2
Introduction to project management framework v2Introduction to project management framework v2
Introduction to project management framework v2Qussay Karam
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...Pinnacle Strategies
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project ManagementJohn Goodpasture
 
Multi-project management problems & their solutions whitepaper
Multi-project management problems & their solutions whitepaperMulti-project management problems & their solutions whitepaper
Multi-project management problems & their solutions whitepaperStefan Ondek, PMP, CSPM
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management SilibusIzah Asmadi
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Good Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process MaturityGood Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process MaturityMichael Edson
 

What's hot (20)

A Day of the Life of a Project Manager
A Day of the Life of a Project ManagerA Day of the Life of a Project Manager
A Day of the Life of a Project Manager
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
6. project human resource management
6. project human resource management6. project human resource management
6. project human resource management
 
Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...Online PMP Training Material for PMP Exam - Communications Management Knowled...
Online PMP Training Material for PMP Exam - Communications Management Knowled...
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Project Management case analysis
Project Management case analysisProject Management case analysis
Project Management case analysis
 
Introduction to project management framework v2
Introduction to project management framework v2Introduction to project management framework v2
Introduction to project management framework v2
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...
 
Top Five Ideas for Project Management
Top Five Ideas for Project ManagementTop Five Ideas for Project Management
Top Five Ideas for Project Management
 
Multi-project management problems & their solutions whitepaper
Multi-project management problems & their solutions whitepaperMulti-project management problems & their solutions whitepaper
Multi-project management problems & their solutions whitepaper
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Project Management Silibus
Project Management SilibusProject Management Silibus
Project Management Silibus
 
M08_Hazard ID ebook
M08_Hazard ID ebookM08_Hazard ID ebook
M08_Hazard ID ebook
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Good Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process MaturityGood Projects Gone Bad: an Introduction to Process Maturity
Good Projects Gone Bad: an Introduction to Process Maturity
 

Similar to PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk

PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Risk Management
Risk ManagementRisk Management
Risk Managementrajuinstru
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptBetshaTizazu2
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxGeorgeKabongah2
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and applicationMarco De Santis, PMP, CFPP
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Managementabhinayverma
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptavisha23
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.pptAyidAlmgati
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptDorraLamouchi1
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)Serdar Temiz
 
Risk management overview
Risk management overviewRisk management overview
Risk management overviewHossam Maghrabi
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best PracticesPMILebanonChapter
 
Kuala Lumpur - PMI Global Congress 2009 - Risk Management
Kuala Lumpur - PMI Global Congress 2009 - Risk ManagementKuala Lumpur - PMI Global Congress 2009 - Risk Management
Kuala Lumpur - PMI Global Congress 2009 - Risk ManagementTorsten Koerting
 
Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptAyidAlmgati
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentationRaven Morgan
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Liana Underwood
 

Similar to PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk (20)

CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
11 risk management
11 risk management11 risk management
11 risk management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project/Program Risk management
Project/Program Risk managementProject/Program Risk management
Project/Program Risk management
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Project risk management - Methodology and application
Project risk management - Methodology and applicationProject risk management - Methodology and application
Project risk management - Methodology and application
 
Beyond PMP: Risk Management
Beyond PMP: Risk ManagementBeyond PMP: Risk Management
Beyond PMP: Risk Management
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.ppt
 
Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Kuala Lumpur - PMI Global Congress 2009 - Risk Management
Kuala Lumpur - PMI Global Congress 2009 - Risk ManagementKuala Lumpur - PMI Global Congress 2009 - Risk Management
Kuala Lumpur - PMI Global Congress 2009 - Risk Management
 
Schwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.pptSchwalbe-11ProjectRisk.ppt
Schwalbe-11ProjectRisk.ppt
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
Susan Parente Presents: Busting Barriers to Risk Management: PM Reston Lunche...
 

More from Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

More from Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 
CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9CAPM Week 3 Chapter 9
CAPM Week 3 Chapter 9
 
CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8CAPM Week 3 Chapter 8
CAPM Week 3 Chapter 8
 
CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7
 

Recently uploaded

Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Recently uploaded (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk

  • 1. Project Management Professional PMP® Exam Prep – Week 5 Prof. Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Risk Management Chapter 11 “… increase the likelihood & impact of positive events & decrease the likelihood & impact of negative events in the project.” • “Risk is an uncertain event that if it occurs, has a positive or negative effect on 1 or more of the project objectives of scope, schedule, cost & quality.” • Planned Risk Response: Known risks that are identified & analyzed • Contingency Reserve : Assigned for KNOWN risks that cannot be managed proactively • Management Reserve : Assigned for UNKNOWN risks that cannot be managed proactively • Positive risks = Opportunities • Negative risks = Threats  90% of Threats can be eliminated => if occur are known as Issues • Levels of Risks: Appetite, Tolerance, Threshold, Averse Process Process Group Key Deliverables 11.1 Plan Risk Management Planning Risk Management Plan 11.2 Identify Risks Planning Risk Register 11.3 Perform Qualitative Risk Analysis Planning Project Documents updates 11.4 Perform Quantitative Risk Analysis Planning Project Documents updates 11.5 Plan Risk Responses Planning Project Management Plan updates 11.6 Implement Risks Responses Executing Change requests 11.7 Monitor Risks Monitoring & Controlling Change requests
  • 3. Risk Management Chapter 11 Organization’s Risk Attitude How much overall project risk is the organization willing to accept?  Risk-averse  Risk-seeking  Risk-neutral Risk Appetite Risk Tolerance Risk Threshold Degree of risk the organization is willing to take on Organization’s readiness to bear the risk Organization’s chosen level above or below which a risk should be addressed
  • 4. Risk Management Chapter 11 Plan Risk Management Process 1 Key Points  “… process is vital to communicate with & obtain agreement & support from all stakeholders to ensure risk mgmt process is supported & performed over the project life cycle.”  Risk Mgmt Plan: Methodology, Roles & responsibilities, Budget, Timing, Risk Categories, Definitions of probability & impact (low to high/numerical), Stakeholder tolerances, Reporting & Tracking  Risk Categories aka Sources of Risks: external, internal (constraints), technical, unforeseeable (10%)
  • 5. Risk Catergories Risk Breakdown Structure (RBS) Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 11-4, Page 406. Material from this publication has been reproduced with the permission of PMI. Risk Management Chapter 11Plan Risk Management Process 1
  • 6. Probability and Impact Matrix Very Low (10%) Low (30%) Moderate (50%) High (70%) Very High (90%) 5% 9% 18% 36% 72% 4% 7% 14% 28% 56% 3% 5% 10% 20% 40% 2% 3% 6% 12% 24% 1% 1% 2% 4% 8% Low (10%) Moderate (20%) High (40%) Very High (80%) Very High (80%) High (40%) Moderate (20%) Low (10%) Very Low (5%) = Exploit, enhance, or share = Use expert judgment = Accept Avoid, transfer, or mitigate = Use expert judgment = Accept = Risks (Threats) Opportunities 56% 28% 14% 7% 4% 40% 20% 10% 5% 3% 24% 12% 6% 3% 2% 8% 4% 2% 1% 1% 72% 36% 18% 9% 5% Probability Impact Very Low (5%) Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 11-5, Page 408. Material from this publication has been reproduced with the permission of PMI. Risk Management Chapter 11Plan Risk Management Process 1
  • 7. Risk Management Plan  Risk strategy  Methodology  Roles and responsibilities  Funding  Timing  Risk categories  Stakeholder risk appetite  Definitions of risk probability and impacts  Probability and impact matrix  Reporting and tracking Plan components: Risk Management Chapter 11Plan Risk Management Process 1
  • 8. Risk Management Chapter 11Identify Risks Process 2 Key Points  “… process of documenting existing risks & the knowledge & ability it provides the project team to anticipate events.”  “… is an iterative process, because new risks may evolve or become known as the project progresses.”  Tools: Info Gathering (see Scope tools), Diagramming (see Quality tools), SWOT  Risk Register: lists of risks, potential responses, root causes & updates
  • 9. Risk Register Living document that includes:  All identified risks  Risk analysis results  Planned responses  Issues/response outcomes Risk Management Chapter 11Identify Risks Process 2
  • 10. Risk Management Chapter 11 Perform Qualitative Risk Analysis Process 3 Not all risks are created equal  Some are more likely than others.  Some are more urgent than others.  Some have a greater impact than others. Ranking of HIGH, MEDIUM, LOW Project Risk Evaluators
  • 11. Risk Management Chapter 11 Key Points  “… process of prioritizing risks by assessing their probability of occurrence & impact… to reduce the level of uncertainty & to focus on high-priority risks.”  Cost-Effective: way to quickly prioritize risks  Short-Listed Risks: those risks that have a high impact on project & warrant a response  Risk Urgency: those high impact risks that may occur soon and/or take a long time to plan a response  Risk Probability & Impact / Matrix: is Subjective, varies on the risk bias of the person doing the rating!!  Watch List: non-critical risks that are documented on the Risk Register & reviewed in Control Risks Perform Qualitative Risk Analysis Process 3
  • 12. Risk Management Chapter 11 Project Risk Evaluators Perform Quantitative Risk Analysis Process 4 Ranking of NUMERICAL RATING  Numerical analysis of risks  Quantified according to their expected monetary value (EMV)  Reduces project uncertainty through better decision making
  • 13. Risk Management Chapter 11 Key Points  “… process of assigning a numerical priority rating to those risks prioritized in Qualitative Risk Analysis.”  Risk Assessment is Objective: each risk based on actual probability of occurring & the impact (amount at stake)  Risk Analysis Tools: Sensitivity/Tornado Diagram, Expected Money Value (EMV=PxI), Monte Carlo/Probability Perform Quantitative Risk Analysis Process 4
  • 14. Risk Management Chapter 11 Perform Quantitative Risk Analysis Process 4 EMV = Probability × Impact Expected Monetary Value (EMV) Principal method for quantifying risk in a project Example 1: A risk with a 30 percent chance of occurring that could increase budgeted costs by US$100,000. Example 2: A corresponding opportunity with a 70 percent chance of decreasing budgeted costs by US$400,000. EMVRisk = 0.3 × – $100,000 = – $30,000 EMVOpportunity = 0.7 × $400,000 = $280,000 Net EMV = –$30,000 + $280,000 = $250,000
  • 15. Risk Management Chapter 11 Qualitative Risk Analysis - Risk Probability & Impact Matrix IMPACT Quantitative Risk Analysis – Expected Money Value (EMV) RISKS PROBABILITY IMPACT High Winds 30% Cost $500 to replace equipment Landslide 5% Lose $80,000 in damage costs Wind generator is usable 20% Save $8,000 in battery costs Truck rental unavailable 10% Cost $300 for last-minute rental Wild animals eat rations 10% Costs $100 for replacements Unseasonably warm weather 15% Saves $50,000 in excavation costs RISKS PROBABILITY IMPACT Landslide .1 .9 Winds .7 .9 No Truck .3 .7 Storms .5 .3 Supplies .1 .5 Illness .1 .1 Probability & Impact Matrix .9 .09 .27 .45 .63 .69 .7 .07 .21 .35 .49 .63 .5 .05 .15 .25 .35 .45 .3 .03 .09 .15 .21 .27 .1 .01 .03 .05 .07 .09 .1 .3 .5 .7 .9
  • 16. You are managing a facility renovation project. There is an 80 percent chance that supplier availability will cause a two-day delay costing US$9,000. There is also a 30 percent chance that the price of building materials will drop, which could save you US$15,000. What is the project’s EMV? A. –$7,200 B. –$2,700 C. $4,500 D. $11,700 Discussion Question Answer: B EMVRisk = 0.8 × –$9,000 = –$7,200 EMVOpportunity = 0.3 × $15,000 = $4,500 Net EMV = –$7,200 + $4,500 = –$2,700 Chapter 11, Topic 4
  • 17. Tornado Diagram Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 11-14, Page 434. Material from this publication has been reproduced with the permission of PMI. Risk Management Chapter 11 Perform Quantitative Risk Analysis Process 4
  • 18. Risk Management Chapter 11 Key Points  “… process enhances opportunities & reduce threats by inserting resources & activities into the budget, schedule & project management plan as needed.”  Tools:  Strategies for Negative Risks/Threats: Avoid or Mitigate (used for high priority/impact), Transfer, Accept (workarounds)  Strategies for Positive Risks/Opportunities: Exploit (take advantage), Enhance (influence triggers), Share, Accept  Outputs:  PMP Updates and Risk Register Updates: Residual Risks, Contingency Plans, Fallback Plans, Risk Owners, Secondary Risks, Risk triggers, Contracts, Reserves (contingency)  * Management Reserves: generally are 5% of the project budget to cover Unknown Risks Plan Risk Responses Process 5
  • 19. Response Strategies for Threats •Higher-level authority accepts responsibility for risk/responseEscalate •Eliminate threat by changing the plan. •Isolate objectives from impact or change an objective in jeopardy.Avoid •Third party knowingly accepts some or all of the risk/response. •Usually requires a risk premium (e.g., insurance payments).Transfer •Reduce probability and/or impact to within threshold limits. •Respond early, before issue, for best effect.Mitigate •Acknowledge the risk but do nothing because it has a low risk rating or it has no viable or cost-effective response.Accept Risk Management Chapter 11Plan Risk Responses Process 5
  • 20. Response Strategies for Opportunities Risk Management Chapter 11Plan Risk Responses Process 5 •Ensure that opportunity outside project scope is realized. •Identify relevant higher-level authority and communicate details appropriately.Escalate •Ensure that opportunity is realized by applying existing resources (e.g., available contingency funds). •Eliminate uncertainty and go for it. Exploit •Third party adds expertise to ensure that opportunity is realized for the benefit of the project. •All parties can have a net gain, but rewards are shared.Share •Increase probability and/or impact of opportunity by influencing root causes of probability/impact (e.g., obtaining additional funding from management to increase current and future capability/capacity). Enhance •Acknowledge the opportunity but do not actively pursue because it has a low rating or it has no viable or cost-effective response.Accept
  • 21. Which is not a valid way to respond to a threat? A. Avoid B. Exploit C. Mitigate D. Accept Discussion Question Answer: B Exploit is a response strategy for handling opportunities, not threats. It may be selected for risks with positive impacts, where the organization wants to ensure that the opportunity definitely happens. Chapter 11, Topic 5
  • 22. Risk Response Planning Outputs  Change requests  Project management plan updates  Changing baselines  Updating schedule, cost, quality, resource, and procurement management plans  Project documents updates  Risk Register – Owner – Trigger events and responses added – New risks identified; watch list updated  Residual  Secondary  Risk report  Assumptions log updates  Cost, schedule, team assignments  Lessons learned Risk Management Chapter 11Plan Risk Responses Process 5
  • 23. What is used to monitor low priority risks? A. Delphi technique B. Monte Carlo analysis C. Watch list D. Probability and impact matrix Discussion Question Answer: C Risks with low ratings of probability and impact are included in the risk register as part of the watch list for future monitoring. Chapter 11, Topic 5
  • 24. Risk Management Chapter 11 Key Points  “…implement agreed upon risk responses as planned to minimize project threats and maximize project opportunities.”  Specific risk responses are executed as planned  Risk owner executes required action Implement Risk Responses Process 6
  • 25. Risk Management Chapter 11 Key Points  “… process of implementing risk response plans, tracking identified risks, monitoring residual risks & identifying new risks throughout the project life cycle to continuously optimize risk response.”  Tools: Risk Audits (documented effectiveness of risk responses), Meetings (agenda item at status mtgs) Monitor Risks Process 7
  • 26.  Are assumptions still valid?  Have the risks become more or less probable?  Have the risks become more or less impactful?  Can any of the risks be retired?  Are there any new risks to be added?  Are the risk management policies and procedures being followed? Risk Management Chapter 11Monitor Risks Process 7
  • 27. Reserve Analysis Comparison VS. Amount of contingency reserves remaining Outstanding risks and their expected monetary values If inadequate = change request. Risk Management Chapter 11Monitor Risks Process 7
  • 28. Meetings  Project risk management should be a regular agenda item at project status meetings.  Status of risks and responses reviewed and updated for relevance and priority level. Risk Management Chapter 11Monitor Risks Process 7
  • 29.  Workarounds – Unplanned corrective actions – Address unknown risks – Impromptu response  Retiring risks – For risks no longer relevant to the project – Expired risks – Related to events that have come to pass Risk Management Chapter 11Monitor Risks Process 7 Risk Register Updates