SlideShare a Scribd company logo
1 of 36
Source-Kirsten Jørgensen,TheTechnical University of Denmark, Lyngby, DK (email kirj@man.dtu.dk
)
020
ANALYSIS OF
FAILURE IN A
BUILDING PROJECT
Science Art Religion Politics Scholarly Articles For Mathematics
and Productivity
http://www.twitlonger.com/show/n_1sp9pjo?new_post=true
MICROSOFT OneDrive PPT’s PDF’s BOOK LESSONS
Dr f Dejahang BSc CEng, BSc (Hons) Construction Mgmt, MSc,
PhD
THE BOW TIE – AN
ANALYTICAL METHOD
THE BOW TIE – AN
ANALYTICAL METHOD
The bow-tie analysis of failure (ceasing to
function)
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
SCM route
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
The bow-tie analysis of failure (ceasing to
function)
Poor
management of
thepreparation
of thesitefor
construction
Wrong man set to
managethework
Theworknot checked
byaproject leader
Thesizeand extent of
thework
underestimated
Slow handling of the
casebytheauthorities
Delaysin the
start of the
construction
Chose10gradesof
pollution
classification,
which takestime
Thetrackforthe
cranewaslaid
beforethepiles
werecut to theright
heights
Complicated
methodsforthe
excavation
Theuseof timeand
resourcesnot
optimal
Focuson
cost-benefit
optimisationof
own task
Poor planning of
thesequenceof
theprocess,
especiallyfor
bungsand piles
Slow decision-
making when
unforeseen
problemsarise
Too few
employeesforthe
job
Poorfocuson
deadlines
Complication in
thepilecutsand
economiclosses
1
Figure 3
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Slowexcavation
andpreparationof
thegroundforthe
construction
Slowrespons
fromauthorities
Morepolutionin
thegroundthan
expected
Choosetosortthe
polutedearthinto
10classes of
polutioninstead
of4
Poor
managementof
theproject
Forcost
obtimisationfor
thisspecifictask
Incompetent
managerforthe
job
Thepretestwas
notsufficient
Delayedofthe
startingpointfor
theconstruction
site
Delayedof
divingthepiles
Thetracksforthe
cranesplaces
beforethepiles
iscutted
Complications
forcuttingthe
piles
Increasethe
timepressure
fortherestof
theconstruction
process
13
Figure 4
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Figure 5 illustrates the bow-tie analysis of
another consequence of the incompetent
management
the bungs were driven in too early in the
process, which had serious consequences for
later stages.
This shows that the reason for driving the bungs
early was quite reasonable – but also that there
was no adequate process analysis.
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Tooearlydrivingthe
bungs
Itisbesttodrivethe
bungsinbeforethe
excavationprocess
Theentrepreneurhad
freecapacityof
manpoweratanearly
stage
Theconsequenceswere
notevaluated
Theexcavationwent
ontobemost
complicated
Theearly placement
ofthebungs
obstructedaccessfor
cuttingthepiles
Delayedthe
preparationof
thesite
Thisforcedthe
entrepreneursto
usean
inconvenient
methodfor
cuttingthepiles
14
Figure 5
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Figure 6 illustrates that pile driving
came too late in the process, with the
result that other process stages, e.g.
laying the crane tracks, occurred
before the piles were cut, with
consequences for the pile cutting.
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
Delayed
drivingin
thepiles
Thepreparationof the
groundwasmore
complicatedthan
expected
Poormanagementof
thepreparationofthe
ground
Thetrackstothecrane
couldn´t waitandwere
laidbeforethepiles
hadbeencut
Thisdelayedthestart
oftheconstruction
15
Figure6
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
B. Overview of mutual relationships between critical events
Time delaying
Cost consuming
Resource requiring
The client The design process The foundation The shell Ext. accommodation Int. accommodation Delivery
4.Unrealistic
timeframe for
the delivery
2.Overload of
the site manager
for the shell
1.Poor manage-
ment of the
preparation of
the site for
constrution
3.Acceptance of
additional
choice at the
wrong moment
5. Lack ofironin
filigree slab
6.Filigree slab are
thicker than on
drawrings
10.Instalations
overlapping
11.Outlet put in same
place as a pile
12. Achitectural
ironmongery problem
in dobbeltwalls
13. Slow excavation
and preparation ofthe
ground
14.Too early driving
in of the bungs
15. Delayed drivingin
of the piles
16. Broken piles
17. Damage tothe
iron in the piles
18.Excavationfilled
with water
19. Employment
problems
20. Lacks ofprops up
to filigree elements
21.Poor erectionof
concrete elements
22. Lopsidedness of
walls
23.The width of the
filigree elements too
small
24. Wrong placement
of wall in the entrance
25. Slow and poor
finish
26. Poor mainte-
nance, cleaning
27. Delivery failure of
concrete elements
28. Failure in outlet at
the cubicle
29. Wrong chock up
at the cubicle
44.Water in the
corrugated pipes
45.Uneven and slope
of surface
46. Too small room
for batten
47. Wrong masking-
off in wall
48. Few socket outlet
in rooms
49. Damage of wall in
cubicle
50. Diffuculties in
mounting of kitchin
elements
51. The crew for
painting too small
52. A simple
accident
53. Oil pollution
54. Late delivery of
floor materials
55. Defects at the
time for delivery of
the building
7. Lacks in the design
of elect. installations-
30.Poor coordina-
tion of agreements
31.The building
can´t be cloosed
32.Placementof
the crane track
33. Damage to
windows
34. Water intrusion
from the roof
37. No space for
window
36.Humidity of the
plaster
35.Many cut outs
are needed
38. Lacks ofplates
39.Isolations prob.
41. Water inpenth.
42. Damagedpipe
43.Late deliveries
40. The plates on
the roof too high
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
ANALYSIS OF FAILURE IN A
BUILDING PROJECT
It was also possible to clarify the
link between deficient electrical
planning and a number of critical
events later in the construction
phase during the internal fitting
out.
NETWORK PROGRAMMING

More Related Content

What's hot

Advancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniquesAdvancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniquesMECandPMV
 
Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Srishti Wakhloo
 
Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of BridgesAIT Solutions
 
Design and analysis of reinforced concrete multistory commercial building usi...
Design and analysis of reinforced concrete multistory commercial building usi...Design and analysis of reinforced concrete multistory commercial building usi...
Design and analysis of reinforced concrete multistory commercial building usi...Estisharaat Company
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniquesbholu sharma
 
Learning from Failures
Learning from FailuresLearning from Failures
Learning from Failuressefindia
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1Teja Ande
 
Steel connections
Steel connectionsSteel connections
Steel connectionsbabunaveen
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniquesNayana 54321
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structureManish Sharma
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS jay Rathod
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012IAEME Publication
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projectsSULAKSHYA GAUR
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problemdhineshkumar002
 

What's hot (20)

Advancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniquesAdvancements in concrete repair technologies and techniques
Advancements in concrete repair technologies and techniques
 
Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs Design & Construction Errors- Building Maintenance and Repairs
Design & Construction Errors- Building Maintenance and Repairs
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Structural Design of Bridges
Structural Design of BridgesStructural Design of Bridges
Structural Design of Bridges
 
Design and analysis of reinforced concrete multistory commercial building usi...
Design and analysis of reinforced concrete multistory commercial building usi...Design and analysis of reinforced concrete multistory commercial building usi...
Design and analysis of reinforced concrete multistory commercial building usi...
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniques
 
Learning from Failures
Learning from FailuresLearning from Failures
Learning from Failures
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1Failures In Masonry Structures Lec 1
Failures In Masonry Structures Lec 1
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Steel connections
Steel connectionsSteel connections
Steel connections
 
Design of steel structural elements
Design of steel structural elementsDesign of steel structural elements
Design of steel structural elements
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
 
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
DIFFERENT TYPE OF CRACKS AND PREVENTIVE MEASURE ON CRACKS
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
 
case study on failed construction projects
case study on failed construction projectscase study on failed construction projects
case study on failed construction projects
 
Introduction & under ground water tank problem
Introduction & under ground water tank problemIntroduction & under ground water tank problem
Introduction & under ground water tank problem
 

Viewers also liked

Jaya supermarket presentation 2011 latest
Jaya supermarket presentation 2011 latestJaya supermarket presentation 2011 latest
Jaya supermarket presentation 2011 latestKartini Ibrahim
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresRithika Ravishankar
 
Collapse of 4 storied building in begunbari --
Collapse of 4 storied building in begunbari --Collapse of 4 storied building in begunbari --
Collapse of 4 storied building in begunbari --Sumon Dhrubo
 
Constructing High Performing Organisations - Building Blocks, Structures, And...
Constructing High Performing Organisations - Building Blocks, Structures, And...Constructing High Performing Organisations - Building Blocks, Structures, And...
Constructing High Performing Organisations - Building Blocks, Structures, And...Kenny Ong
 
Kemalangan akibat kerja perobohan
Kemalangan akibat kerja perobohanKemalangan akibat kerja perobohan
Kemalangan akibat kerja perobohanAcik Fai Rusz
 
The Hotel New World Collapse
The Hotel New World CollapseThe Hotel New World Collapse
The Hotel New World CollapseParvathy Sunil
 
Six Common Causes of Foundation Failure In Dallas - Fort Worth
Six Common Causes of Foundation Failure In Dallas - Fort WorthSix Common Causes of Foundation Failure In Dallas - Fort Worth
Six Common Causes of Foundation Failure In Dallas - Fort WorthHD Foundations, Inc.
 
Project management failure case study
Project management failure case studyProject management failure case study
Project management failure case studyManisha Mishra
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failureguest70cc59
 
The Decision-making Process, make it your competitive advantage
The Decision-making Process, make it your competitive advantageThe Decision-making Process, make it your competitive advantage
The Decision-making Process, make it your competitive advantageRon McFarland
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESPrabhu Saran
 
Research Writing Methodology
Research Writing MethodologyResearch Writing Methodology
Research Writing MethodologyAiden Yeh
 
Sample Methodology
Sample MethodologySample Methodology
Sample MethodologyAiden Yeh
 

Viewers also liked (17)

Jaya supermarket presentation 2011 latest
Jaya supermarket presentation 2011 latestJaya supermarket presentation 2011 latest
Jaya supermarket presentation 2011 latest
 
Building Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structuresBuilding Failures and its Causes- Theory of structures
Building Failures and its Causes- Theory of structures
 
Collapse of 4 storied building in begunbari --
Collapse of 4 storied building in begunbari --Collapse of 4 storied building in begunbari --
Collapse of 4 storied building in begunbari --
 
Constructing High Performing Organisations - Building Blocks, Structures, And...
Constructing High Performing Organisations - Building Blocks, Structures, And...Constructing High Performing Organisations - Building Blocks, Structures, And...
Constructing High Performing Organisations - Building Blocks, Structures, And...
 
Kemalangan akibat kerja perobohan
Kemalangan akibat kerja perobohanKemalangan akibat kerja perobohan
Kemalangan akibat kerja perobohan
 
The Hotel New World Collapse
The Hotel New World CollapseThe Hotel New World Collapse
The Hotel New World Collapse
 
Six Common Causes of Foundation Failure In Dallas - Fort Worth
Six Common Causes of Foundation Failure In Dallas - Fort WorthSix Common Causes of Foundation Failure In Dallas - Fort Worth
Six Common Causes of Foundation Failure In Dallas - Fort Worth
 
Project management failure case study
Project management failure case studyProject management failure case study
Project management failure case study
 
Foundation Failure
Foundation FailureFoundation Failure
Foundation Failure
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
The Decision-making Process, make it your competitive advantage
The Decision-making Process, make it your competitive advantageThe Decision-making Process, make it your competitive advantage
The Decision-making Process, make it your competitive advantage
 
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURESCASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
CASE STUDY ON CRACKS AND ITS REMEDIAL MEASURES
 
Decision making
Decision makingDecision making
Decision making
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Problem solving& Decision Making
Problem solving& Decision MakingProblem solving& Decision Making
Problem solving& Decision Making
 
Research Writing Methodology
Research Writing MethodologyResearch Writing Methodology
Research Writing Methodology
 
Sample Methodology
Sample MethodologySample Methodology
Sample Methodology
 

Similar to Building failure case study

Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & mariaMaria Archana
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian Rowell
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towerssnookala
 
Final Report
Final Report Final Report
Final Report Jack Ng
 
Digital fabrication solutions
Digital fabrication solutionsDigital fabrication solutions
Digital fabrication solutionsJaekyung Lee
 
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021Plastindustrien
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET Journal
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...IRJET Journal
 
Civil Engineer CV
Civil Engineer CVCivil Engineer CV
Civil Engineer CVAfzal Khan
 
Glass Mix Z Form V1 Glass Mix Concepts
Glass Mix Z Form V1 Glass Mix ConceptsGlass Mix Z Form V1 Glass Mix Concepts
Glass Mix Z Form V1 Glass Mix ConceptsBrij Consulting, LLC
 
Site report assignment
Site report assignmentSite report assignment
Site report assignmentSze Ting Kuek
 
IIT INDORE CUONSTRUCTION OVERVIEW
IIT INDORE CUONSTRUCTION OVERVIEWIIT INDORE CUONSTRUCTION OVERVIEW
IIT INDORE CUONSTRUCTION OVERVIEWdilip patidar
 
Bridging the Instance V1 Marks and Encryptions
Bridging the Instance V1 Marks and EncryptionsBridging the Instance V1 Marks and Encryptions
Bridging the Instance V1 Marks and EncryptionsBrij Consulting, LLC
 
Site visit report
Site visit reportSite visit report
Site visit reportwleying
 
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...IRJET Journal
 
Summary of Comments on Glass Big Push.pdf
Summary of Comments on Glass Big Push.pdfSummary of Comments on Glass Big Push.pdf
Summary of Comments on Glass Big Push.pdfBrij Consulting, LLC
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 

Similar to Building failure case study (20)

Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & maria
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
 
Final Report
Final Report Final Report
Final Report
 
Digital fabrication solutions
Digital fabrication solutionsDigital fabrication solutions
Digital fabrication solutions
 
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
 
IRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case StudyIRJET - Delay Analysis of a Construction Project- A Case Study
IRJET - Delay Analysis of a Construction Project- A Case Study
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Civil Engineer CV
Civil Engineer CVCivil Engineer CV
Civil Engineer CV
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Glass Mix Z Form V1 Glass Mix Concepts
Glass Mix Z Form V1 Glass Mix ConceptsGlass Mix Z Form V1 Glass Mix Concepts
Glass Mix Z Form V1 Glass Mix Concepts
 
Site report assignment
Site report assignmentSite report assignment
Site report assignment
 
IIT INDORE CUONSTRUCTION OVERVIEW
IIT INDORE CUONSTRUCTION OVERVIEWIIT INDORE CUONSTRUCTION OVERVIEW
IIT INDORE CUONSTRUCTION OVERVIEW
 
Bridging the Instance V1 Marks and Encryptions
Bridging the Instance V1 Marks and EncryptionsBridging the Instance V1 Marks and Encryptions
Bridging the Instance V1 Marks and Encryptions
 
Site visit report
Site visit reportSite visit report
Site visit report
 
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...IRJET -  	  Investigation of “Delays Occuring in Construction of Commercial B...
IRJET - Investigation of “Delays Occuring in Construction of Commercial B...
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
CSHE High-Tech - Old Infrastructure
CSHE High-Tech - Old InfrastructureCSHE High-Tech - Old Infrastructure
CSHE High-Tech - Old Infrastructure
 
Summary of Comments on Glass Big Push.pdf
Summary of Comments on Glass Big Push.pdfSummary of Comments on Glass Big Push.pdf
Summary of Comments on Glass Big Push.pdf
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Building failure case study

  • 1. Source-Kirsten Jørgensen,TheTechnical University of Denmark, Lyngby, DK (email kirj@man.dtu.dk ) 020 ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 2. Science Art Religion Politics Scholarly Articles For Mathematics and Productivity http://www.twitlonger.com/show/n_1sp9pjo?new_post=true MICROSOFT OneDrive PPT’s PDF’s BOOK LESSONS Dr f Dejahang BSc CEng, BSc (Hons) Construction Mgmt, MSc, PhD
  • 3. THE BOW TIE – AN ANALYTICAL METHOD
  • 4. THE BOW TIE – AN ANALYTICAL METHOD
  • 5. The bow-tie analysis of failure (ceasing to function)
  • 6. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 7.
  • 9. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 10. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 11. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 12. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 13. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 14. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 15. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 16. The bow-tie analysis of failure (ceasing to function)
  • 17. Poor management of thepreparation of thesitefor construction Wrong man set to managethework Theworknot checked byaproject leader Thesizeand extent of thework underestimated Slow handling of the casebytheauthorities Delaysin the start of the construction Chose10gradesof pollution classification, which takestime Thetrackforthe cranewaslaid beforethepiles werecut to theright heights Complicated methodsforthe excavation Theuseof timeand resourcesnot optimal Focuson cost-benefit optimisationof own task Poor planning of thesequenceof theprocess, especiallyfor bungsand piles Slow decision- making when unforeseen problemsarise Too few employeesforthe job Poorfocuson deadlines Complication in thepilecutsand economiclosses 1 Figure 3
  • 18. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 19. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 21. ANALYSIS OF FAILURE IN A BUILDING PROJECT Figure 5 illustrates the bow-tie analysis of another consequence of the incompetent management the bungs were driven in too early in the process, which had serious consequences for later stages. This shows that the reason for driving the bungs early was quite reasonable – but also that there was no adequate process analysis.
  • 22. ANALYSIS OF FAILURE IN A BUILDING PROJECT Tooearlydrivingthe bungs Itisbesttodrivethe bungsinbeforethe excavationprocess Theentrepreneurhad freecapacityof manpoweratanearly stage Theconsequenceswere notevaluated Theexcavationwent ontobemost complicated Theearly placement ofthebungs obstructedaccessfor cuttingthepiles Delayedthe preparationof thesite Thisforcedthe entrepreneursto usean inconvenient methodfor cuttingthepiles 14 Figure 5
  • 23. ANALYSIS OF FAILURE IN A BUILDING PROJECT Figure 6 illustrates that pile driving came too late in the process, with the result that other process stages, e.g. laying the crane tracks, occurred before the piles were cut, with consequences for the pile cutting.
  • 24. ANALYSIS OF FAILURE IN A BUILDING PROJECT Delayed drivingin thepiles Thepreparationof the groundwasmore complicatedthan expected Poormanagementof thepreparationofthe ground Thetrackstothecrane couldn´t waitandwere laidbeforethepiles hadbeencut Thisdelayedthestart oftheconstruction 15 Figure6
  • 25. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 26. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 27. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 28. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 29. B. Overview of mutual relationships between critical events Time delaying Cost consuming Resource requiring The client The design process The foundation The shell Ext. accommodation Int. accommodation Delivery 4.Unrealistic timeframe for the delivery 2.Overload of the site manager for the shell 1.Poor manage- ment of the preparation of the site for constrution 3.Acceptance of additional choice at the wrong moment 5. Lack ofironin filigree slab 6.Filigree slab are thicker than on drawrings 10.Instalations overlapping 11.Outlet put in same place as a pile 12. Achitectural ironmongery problem in dobbeltwalls 13. Slow excavation and preparation ofthe ground 14.Too early driving in of the bungs 15. Delayed drivingin of the piles 16. Broken piles 17. Damage tothe iron in the piles 18.Excavationfilled with water 19. Employment problems 20. Lacks ofprops up to filigree elements 21.Poor erectionof concrete elements 22. Lopsidedness of walls 23.The width of the filigree elements too small 24. Wrong placement of wall in the entrance 25. Slow and poor finish 26. Poor mainte- nance, cleaning 27. Delivery failure of concrete elements 28. Failure in outlet at the cubicle 29. Wrong chock up at the cubicle 44.Water in the corrugated pipes 45.Uneven and slope of surface 46. Too small room for batten 47. Wrong masking- off in wall 48. Few socket outlet in rooms 49. Damage of wall in cubicle 50. Diffuculties in mounting of kitchin elements 51. The crew for painting too small 52. A simple accident 53. Oil pollution 54. Late delivery of floor materials 55. Defects at the time for delivery of the building 7. Lacks in the design of elect. installations- 30.Poor coordina- tion of agreements 31.The building can´t be cloosed 32.Placementof the crane track 33. Damage to windows 34. Water intrusion from the roof 37. No space for window 36.Humidity of the plaster 35.Many cut outs are needed 38. Lacks ofplates 39.Isolations prob. 41. Water inpenth. 42. Damagedpipe 43.Late deliveries 40. The plates on the roof too high
  • 30. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 31. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 32. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 33. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 34. ANALYSIS OF FAILURE IN A BUILDING PROJECT
  • 35. ANALYSIS OF FAILURE IN A BUILDING PROJECT It was also possible to clarify the link between deficient electrical planning and a number of critical events later in the construction phase during the internal fitting out.