ASSIGNMENT NO-1
PRESENTATION ON ATAL
TUNNEL
MANE ADITYA PRASHANT
M.TECH CONSTRUCTION
MANAGEMENT
ROLL N0- 222030008
CONTENT
 PROJECT OVERVIEW
 PROJECT TIMELINE
 NEED FOR PROJECT
 CHIEF ENGINEER
 STANDOUT FEATURES OF ATAL
TUNNEL
 SURVEY AND PREPARATION OF DPR
 CONSTRUCTION OF TUNNEL
 CONSTRUCTION CHALLENGES
 SAFETY FEATURES
 REFRENCES
PROJECT OVERVIEW
 PROJECT NAME :- ROHTANG PASS HIGHWAY TUNNEL WHICH IS NOW KNOWN AS
ATAL TUNNEL
 LOCATION :- PIR PANJAL RANGE OF HIMALAYAS
 CLIENT :- BORDER ROAD ORGANISATION
 CONTRACTOR :- STRABAGS AG – AFCONS
 SHAPE ( CROSS SECTION) OF TUNNEL :- HORSESHOE
 CONSTRUCTION TECHNIQUE :- DRILL & BLAST WITH NATM
 COST OF PROJECT :- 3200 CRORE
 LENGTH, ROAD WIDTH & CARRIAGE WIDTH :-9.02 KM, 10.5 METRE & 4 METRE
 DESIGNED FOR :- 3000 CARS & 1500 TRUCKS PER DAY AT MAX DESIGN SPEED
 DESIGN SPEED OF TUNNEL :- 80 KM/HOUR
 LONGEST ROAD TUNNEL IN WORLD WITH THE ELEVATION OF 10000 FEET ABOVE
MSL
 PROJECT CONNECTIVITY:- FROM LAHAUL SPITTI VALLEY TO OTHER TOURIST
PROJECT TIMELINE
NEED FOR PROJECT
NEED FOR PROJECT
CHIEF ENGINEER
 Chief Engineer KP Purushothaman was the man
who led the construction of Atal tunnel.
 He holds PG Diploma & MBA in Construction
Management, cracked UPSC in 1987 & worked as
a Executive Engineer in Andaman & Nicobar. He
also was the part of many important road projects
on China, Pakistan.
 He is the chief of Border Road Organization.
 3000 workers, 770 engineers, supervisors,
consultants, & contractors working at same time
24 hours in 3 different shifts.
 Under his guidance cost od 800 Crores was saved
from 4000 Crores which was the budget issued.
STANDOUT FEATURES
 The tunnel will provide all-weather
connectivity to remote border areas of
Himachal Pradesh and Ladakh which
otherwise remain cut-off from the rest of the
country for about six months during winters.
 It is also the country’s first tunnel to have an
escape tunnel at every 500m below pavement
(3.5 * 2.25)m.
 The project has almost saved travelling of
almost 46 KM.
 The project is been more significant due to
rising tensions between india and china on
eastern front. The army trucks and army
convoys can now easily travel through tunnel
and can easily overcome hostage situations.
SURVEY & PREPARATION OF DPR
RITES Ltd (Govt PSU of Indian Railway )along
with some geo -consults from Austrian
consultancy firm had the responsibility of Survey
and preparation of DPR. They engaged
themselves in 1990 and submitted the Phase-1
report in April 1994 which included the following
 Surface Studies including Geological, Remote
Sensing, Geomorphological.
 Construction of Exploratory Drift at both
Portals Drill for tunnel alignment and
laboratory tests.
 Fixing of Portal Locations and ground marking
of tunnel alignment.
 Preliminary design based on initial laboratory
tests. Construction planning, equipment,
survey, evaluation of construction material,
RITES Ltd Phase-2 Report- It was submitted
in 1996 and included the following
 Detailed report including civil drawings,
test results, and specifications & Conditions
of contract.
 HVAC and safety system with drawings.
 Design of Tunnel Section, support system,
lighting, etc.
 Preparations of Schedule of Quantities.
conditions of contract and listing of codes
 Construction methods, cost analysis, and
equipment requirement.
 Leakage, dewatering, grouting, blasting,
and support system.
 Construction schedule, supervision of
contract, and maintenance of tunnel.
RITES Ltd Phase-3 Report- following
aspects were covered in Phase-3
 Tunnel alignment and new South
Portal location.
 Geological and Geotechnical
aspects.( Seri Nala flow, Rock
structures & strata, seismic factors
etc)
 EIA & Traffic studies.
 Tunnel design , Ventilation system &
Project cost.
CONSTRUCTION OF ATAL TUNNEL
 Rohtang tunnel construction is based on the
NATM strategy. NATM works on the principle of
continuous observations made after each execution
cycle. As the Himalayan range has varying
geological conditions this is the best suited
methodology for construction of the tunnel.
 The main principle of NATM is that the
surrounding rock provides main support to the
tunnel excavated and additional support if needed
is provided to maintain the strength of rock and
prevent disintegration .
 The surrounding rock itself therefore behaves as a
structural arch which acts as a load bearing
member.
• The main tunneling and construction activities were
organized and carried out as under:
Top heading and half sided benching: The top heading
(or upper half) of the tunnel section is excavated first
and supported by shotcrete (sprayed concrete lining)
and benching (lower half).
Deep invert excavation: Excavation for lowest section of
tunnel i.e., floor. Section of excavation.
 Main tunnel drainage is provided and concreting is
done on egress tunnel (outlet) base slab.
 First lining kicker concreting.
Precast emergency egress structures installation.
 Pavement drainage and pit installation works.
 Second lining kicker concreting and backfilling up to
road level.
 Cable ducts installation and concreting
base of walkway.
 Final arch concreting over lining and
ventilation slab reinforcing and
concreting.
 The road is constructed by pavement
quality concrete with dry lean concrete
laid as base.
 Kerb installations and walkway
(footpath) works.
 Safety installations, Electrical works and
finishing works.
 Storage caverns for fire water and
turning bay caverns.
CONSTRUCTION CHALLENGES
1) Seri Nala fault zone: This is the longest shear zone ever encountered in a single
stretch, approximately 587.5m in any tunnel construction. The tunnel is passing
under Seri Nala, because of which weathering of rock occurs, muck along with
water started to flow from the face. Heavy inflow of water at a rate of 8000 litres
per minute was experienced. So, while tunneling through this zone, the team faced
many unexpected difficulties and overcame them using various solutions based on
the condition at that place.
 Plugging with sandbags, applying a thick layer of shotcrete is done to control the
muck flow in the tunnel.
 Certain holes are provided in the crown region for pressure relief and drainage
purposes, so that water can be channelized and removed.
 Pre-grouting is done through the previously drilled holes with OPC and micro fine
cement through a reasonable pressure as required depending on location.
2) High overburden at North Portal
 Main challenge encountered is due to high stress conditions and resulting pressures due to
surrounding rock.
During excavation due to sudden release of stresses rock were prone to exhibit rock bursting and
rock squeezing around the periphery of opening.
 Even delayed release of stress along these planes caused problems like cracks in lining,
excessive stress on rock bolts and bending of rock bolt plates.
 This varied behavior of rock brought new challenges in front of the team. Therefore, such
behavior of rock is regularly and accurately monitored and these problems are encountered by
taking necessary measures using Lining stress controllers (LSC).
3) Sudden collapse of tunnel:
While construction, the tunnel roof of 50m stretch suddenly collapsed and fortunately it didn’t
cause any loss of life. This caused a hindrance in the progress of work.
 Various measures were taken to avoid collapse of tunnel like rock bolting after
clearing muck, rock bolting with wire mesh and shotcrete were done
monolithically, continuous monitoring of deformations and deflections, piped
roofing to take high overburden.
3) VENTILATION BUILDING:
 The installation of the ventilation building at South Portal became a very
challenging task as it is located in a landslide region.
 Constructing of the building in a stable deep rock cut, anchoring walls of the
ventilation buildings to arrest movement of building and providing measures
against sliding of slope like anchoring after removing loose cover from the
slope, providing an avalanche gallery.
 Even at the north portal installation of the ventilation building has been
challenging as there is no sufficient space available and must be built along
the slope.
 This slope is in a high avalanche prone area. Finally the building was
constructed in a straight alignment along the tunnel on a raft foundation in a
safe zone devoid from avalanche.
4) ALIGNMENT PRECISION WHILE PROGRESSING:
 Construction of the tunnel was carried out from two ends simultaneously.
Electronic total station survey instruments were used for the purpose of
alignment of tunnel.
 Due to their magnetic nature, they were getting affected because of huge
support installations made of steel as the tunneling is being progressed. Inertial
precision technology (gyro-meters) is used to counter after every one km of
excavation.
5) TRANSPORTATION:
 Transportation availability to the site is not a smooth process in this young
Himalayan region.
 Many challenges are faced during material transportation and this somewhat
added to the delay in work execution.
6) EXTREME WEATHER:
 Rohtang valley region remains inaccessible due to heavy snowfall nearly 6
months; as a result construction work can be carried out only for 6 months in one
year. Therefore the project implementation got hindered and delayed.
 Due to extreme cold conditions at site workers were also having bad effects on
health. Medical aid is provided accordingly.
7) COMMUNICATION ISSUE:
 Due to remoteness of the site and extreme weather conditions like snowfall no
proper network is available and wireless communication through radio is not
possible.
 So installing cables is the only option which is done with the help of BSNL.
8) EXCESSIVE SNOWFALL:
 The tunnel project site faces excessive snowfall in the winters and experiences
subzero temperatures accompanied by frequent avalanches.
 North Portal as such remains closed throughout the winters almost 6 months.
SAFETY MEASURES IN TUNNEL
The Tunnel has ample safety features built into it.
Some of the key safety features are
 Tunnel entry barriers at both portals.
 Telephone connections at every 150 Meters for
Emergency communication.
 Fire hydrant mechanisms at every 60 meters.
 Auto incident detection system with CCTV
 cameras at every 250 Meters.
 Air quality monitoring at every 1 Km.
 Evacuation lighting / exit signs at every 25
Meters.
 Broadcasting system throughout the tunnel.
 Fire rated Dampers at every 50 Meters.
 Cameras at every 60 Meters.
REFRENCES
 INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING
RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 Website:
ijiert.org VOLUME 8, ISSUE 8, Aug. -2021.
 Compendium on Atal Tunnel issued by Border Road Organisation.
 https://www.encardio.com/blog/rohtang-pass-tunnel-case-study-geotechnical-
monitoring-instrumentation/
 http://testcf.constrofacilitator.com/the-atal-rohtang-tunnel-a-look-into-the-
construction-marvel/
 https://www.slideshare.net/Bimenpreet/atal-rohtang-tunnel-construction-
process-challenges-and-features
THANK YOU

More Related Content

What's hot

conceptual desig of Chenab bridge
conceptual desig of Chenab bridge conceptual desig of Chenab bridge
conceptual desig of Chenab bridge
muzafar farooq
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway Technology
Pradeep Kumar
 
report
reportreport
report
Ravi Panchal
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
Unni Krishnan
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+link
ASHOK KUMAR
 
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G TaylorThe Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
John Guy Taylor
 
Hindustan construction company
Hindustan construction companyHindustan construction company
Hindustan construction company
Raushan Pandey
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
anjusha muttanthottil
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
Taseem mir
 
GOOGLE HAVING UNIQUE HR PRACTICES STILL LEAD TO HIGH TURNOVER
GOOGLE HAVING UNIQUE HR PRACTICES  STILL LEAD TO HIGH TURNOVERGOOGLE HAVING UNIQUE HR PRACTICES  STILL LEAD TO HIGH TURNOVER
GOOGLE HAVING UNIQUE HR PRACTICES STILL LEAD TO HIGH TURNOVER
Adma MAHARJAN
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
Chenab Railway Bridge
Chenab Railway BridgeChenab Railway Bridge
Chenab Railway Bridge
Danish Mir
 
Blast Design-2.pdf
Blast Design-2.pdfBlast Design-2.pdf
Blast Design-2.pdf
Sreedhar Siddhu
 
Intelligent Mine - Future of Mining
Intelligent Mine - Future of MiningIntelligent Mine - Future of Mining
Intelligent Mine - Future of MiningDmitry Klebanov
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013
Hitesh Khanna
 
Scrum of Scrums Patterns Library
Scrum of Scrums Patterns LibraryScrum of Scrums Patterns Library
Scrum of Scrums Patterns Library
David Hanson
 

What's hot (20)

conceptual desig of Chenab bridge
conceptual desig of Chenab bridge conceptual desig of Chenab bridge
conceptual desig of Chenab bridge
 
Chenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway TechnologyChenab Bridge, Jammu and Kashmir - Railway Technology
Chenab Bridge, Jammu and Kashmir - Railway Technology
 
The Suez Canal
The Suez CanalThe Suez Canal
The Suez Canal
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
report
reportreport
report
 
Burj Khalifa
Burj KhalifaBurj Khalifa
Burj Khalifa
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+link
 
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G TaylorThe Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
The Evolution of Sublevel Caving at Trojan Mine, Bindura, Zimbabwe, J G Taylor
 
Hindustan construction company
Hindustan construction companyHindustan construction company
Hindustan construction company
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
my project on chenab bridge
my project on chenab bridge my project on chenab bridge
my project on chenab bridge
 
GOOGLE HAVING UNIQUE HR PRACTICES STILL LEAD TO HIGH TURNOVER
GOOGLE HAVING UNIQUE HR PRACTICES  STILL LEAD TO HIGH TURNOVERGOOGLE HAVING UNIQUE HR PRACTICES  STILL LEAD TO HIGH TURNOVER
GOOGLE HAVING UNIQUE HR PRACTICES STILL LEAD TO HIGH TURNOVER
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Chenab Railway Bridge
Chenab Railway BridgeChenab Railway Bridge
Chenab Railway Bridge
 
Blast Design-2.pdf
Blast Design-2.pdfBlast Design-2.pdf
Blast Design-2.pdf
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Intelligent Mine - Future of Mining
Intelligent Mine - Future of MiningIntelligent Mine - Future of Mining
Intelligent Mine - Future of Mining
 
Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013Tunnel ventilation ppt tunnel asia 2013
Tunnel ventilation ppt tunnel asia 2013
 
Scrum of Scrums Patterns Library
Scrum of Scrums Patterns LibraryScrum of Scrums Patterns Library
Scrum of Scrums Patterns Library
 

Similar to ATAL TUNNEL.pptx

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
IJERA Editor
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
SubratDash37
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
Jayanta Sen
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
Amir Amdani
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
Ujwal Ujwal
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Ishant Gautam.
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
1 sethi
1 sethi1 sethi
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
Rabindra Shrestha
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
AGNIVORAY1
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
Vinay Vb
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
Vishweshwar Rao Narla
 
World longest Highway Tunnel Construction
World longest Highway Tunnel ConstructionWorld longest Highway Tunnel Construction
World longest Highway Tunnel Construction
PRINCEMAURYA44
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
IRJET Journal
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Hitesh Khanna
 
Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"
Dr. Ezzat Elsayed Gomaa
 

Similar to ATAL TUNNEL.pptx (20)

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Presentation on Millau viaduct
Presentation on Millau viaductPresentation on Millau viaduct
Presentation on Millau viaduct
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
1 sethi
1 sethi1 sethi
1 sethi
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
World longest Highway Tunnel Construction
World longest Highway Tunnel ConstructionWorld longest Highway Tunnel Construction
World longest Highway Tunnel Construction
 
laos-tj-2016
laos-tj-2016laos-tj-2016
laos-tj-2016
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"Introduction to Hydraulics "Engineering is your job"
Introduction to Hydraulics "Engineering is your job"
 

More from Aditya Mane

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
Aditya Mane
 
Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptx
Aditya Mane
 
CCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptxCCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptx
Aditya Mane
 
CCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptxCCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptx
Aditya Mane
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
Aditya Mane
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
Aditya Mane
 
WBS OF TUNNEL.pptx
WBS OF TUNNEL.pptxWBS OF TUNNEL.pptx
WBS OF TUNNEL.pptx
Aditya Mane
 
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptxModule 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Aditya Mane
 
Rehabilitation ppt.pptx
Rehabilitation ppt.pptxRehabilitation ppt.pptx
Rehabilitation ppt.pptx
Aditya Mane
 
queuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdfqueuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdf
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 

More from Aditya Mane (11)

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptx
 
CCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptxCCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptx
 
CCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptxCCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptx
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
 
WBS OF TUNNEL.pptx
WBS OF TUNNEL.pptxWBS OF TUNNEL.pptx
WBS OF TUNNEL.pptx
 
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptxModule 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
 
Rehabilitation ppt.pptx
Rehabilitation ppt.pptxRehabilitation ppt.pptx
Rehabilitation ppt.pptx
 
queuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdfqueuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdf
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 

Recently uploaded

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

ATAL TUNNEL.pptx

  • 1. ASSIGNMENT NO-1 PRESENTATION ON ATAL TUNNEL MANE ADITYA PRASHANT M.TECH CONSTRUCTION MANAGEMENT ROLL N0- 222030008
  • 2. CONTENT  PROJECT OVERVIEW  PROJECT TIMELINE  NEED FOR PROJECT  CHIEF ENGINEER  STANDOUT FEATURES OF ATAL TUNNEL  SURVEY AND PREPARATION OF DPR  CONSTRUCTION OF TUNNEL  CONSTRUCTION CHALLENGES  SAFETY FEATURES  REFRENCES
  • 3. PROJECT OVERVIEW  PROJECT NAME :- ROHTANG PASS HIGHWAY TUNNEL WHICH IS NOW KNOWN AS ATAL TUNNEL  LOCATION :- PIR PANJAL RANGE OF HIMALAYAS  CLIENT :- BORDER ROAD ORGANISATION  CONTRACTOR :- STRABAGS AG – AFCONS  SHAPE ( CROSS SECTION) OF TUNNEL :- HORSESHOE  CONSTRUCTION TECHNIQUE :- DRILL & BLAST WITH NATM  COST OF PROJECT :- 3200 CRORE  LENGTH, ROAD WIDTH & CARRIAGE WIDTH :-9.02 KM, 10.5 METRE & 4 METRE  DESIGNED FOR :- 3000 CARS & 1500 TRUCKS PER DAY AT MAX DESIGN SPEED  DESIGN SPEED OF TUNNEL :- 80 KM/HOUR  LONGEST ROAD TUNNEL IN WORLD WITH THE ELEVATION OF 10000 FEET ABOVE MSL  PROJECT CONNECTIVITY:- FROM LAHAUL SPITTI VALLEY TO OTHER TOURIST
  • 7. CHIEF ENGINEER  Chief Engineer KP Purushothaman was the man who led the construction of Atal tunnel.  He holds PG Diploma & MBA in Construction Management, cracked UPSC in 1987 & worked as a Executive Engineer in Andaman & Nicobar. He also was the part of many important road projects on China, Pakistan.  He is the chief of Border Road Organization.  3000 workers, 770 engineers, supervisors, consultants, & contractors working at same time 24 hours in 3 different shifts.  Under his guidance cost od 800 Crores was saved from 4000 Crores which was the budget issued.
  • 8. STANDOUT FEATURES  The tunnel will provide all-weather connectivity to remote border areas of Himachal Pradesh and Ladakh which otherwise remain cut-off from the rest of the country for about six months during winters.  It is also the country’s first tunnel to have an escape tunnel at every 500m below pavement (3.5 * 2.25)m.  The project has almost saved travelling of almost 46 KM.  The project is been more significant due to rising tensions between india and china on eastern front. The army trucks and army convoys can now easily travel through tunnel and can easily overcome hostage situations.
  • 9. SURVEY & PREPARATION OF DPR RITES Ltd (Govt PSU of Indian Railway )along with some geo -consults from Austrian consultancy firm had the responsibility of Survey and preparation of DPR. They engaged themselves in 1990 and submitted the Phase-1 report in April 1994 which included the following  Surface Studies including Geological, Remote Sensing, Geomorphological.  Construction of Exploratory Drift at both Portals Drill for tunnel alignment and laboratory tests.  Fixing of Portal Locations and ground marking of tunnel alignment.  Preliminary design based on initial laboratory tests. Construction planning, equipment, survey, evaluation of construction material,
  • 10. RITES Ltd Phase-2 Report- It was submitted in 1996 and included the following  Detailed report including civil drawings, test results, and specifications & Conditions of contract.  HVAC and safety system with drawings.  Design of Tunnel Section, support system, lighting, etc.  Preparations of Schedule of Quantities. conditions of contract and listing of codes  Construction methods, cost analysis, and equipment requirement.  Leakage, dewatering, grouting, blasting, and support system.  Construction schedule, supervision of contract, and maintenance of tunnel.
  • 11. RITES Ltd Phase-3 Report- following aspects were covered in Phase-3  Tunnel alignment and new South Portal location.  Geological and Geotechnical aspects.( Seri Nala flow, Rock structures & strata, seismic factors etc)  EIA & Traffic studies.  Tunnel design , Ventilation system & Project cost.
  • 12. CONSTRUCTION OF ATAL TUNNEL  Rohtang tunnel construction is based on the NATM strategy. NATM works on the principle of continuous observations made after each execution cycle. As the Himalayan range has varying geological conditions this is the best suited methodology for construction of the tunnel.  The main principle of NATM is that the surrounding rock provides main support to the tunnel excavated and additional support if needed is provided to maintain the strength of rock and prevent disintegration .  The surrounding rock itself therefore behaves as a structural arch which acts as a load bearing member.
  • 13.
  • 14.
  • 15. • The main tunneling and construction activities were organized and carried out as under: Top heading and half sided benching: The top heading (or upper half) of the tunnel section is excavated first and supported by shotcrete (sprayed concrete lining) and benching (lower half). Deep invert excavation: Excavation for lowest section of tunnel i.e., floor. Section of excavation.  Main tunnel drainage is provided and concreting is done on egress tunnel (outlet) base slab.  First lining kicker concreting. Precast emergency egress structures installation.  Pavement drainage and pit installation works.  Second lining kicker concreting and backfilling up to road level.
  • 16.  Cable ducts installation and concreting base of walkway.  Final arch concreting over lining and ventilation slab reinforcing and concreting.  The road is constructed by pavement quality concrete with dry lean concrete laid as base.  Kerb installations and walkway (footpath) works.  Safety installations, Electrical works and finishing works.  Storage caverns for fire water and turning bay caverns.
  • 17. CONSTRUCTION CHALLENGES 1) Seri Nala fault zone: This is the longest shear zone ever encountered in a single stretch, approximately 587.5m in any tunnel construction. The tunnel is passing under Seri Nala, because of which weathering of rock occurs, muck along with water started to flow from the face. Heavy inflow of water at a rate of 8000 litres per minute was experienced. So, while tunneling through this zone, the team faced many unexpected difficulties and overcame them using various solutions based on the condition at that place.  Plugging with sandbags, applying a thick layer of shotcrete is done to control the muck flow in the tunnel.  Certain holes are provided in the crown region for pressure relief and drainage purposes, so that water can be channelized and removed.  Pre-grouting is done through the previously drilled holes with OPC and micro fine cement through a reasonable pressure as required depending on location.
  • 18.
  • 19. 2) High overburden at North Portal  Main challenge encountered is due to high stress conditions and resulting pressures due to surrounding rock. During excavation due to sudden release of stresses rock were prone to exhibit rock bursting and rock squeezing around the periphery of opening.  Even delayed release of stress along these planes caused problems like cracks in lining, excessive stress on rock bolts and bending of rock bolt plates.  This varied behavior of rock brought new challenges in front of the team. Therefore, such behavior of rock is regularly and accurately monitored and these problems are encountered by taking necessary measures using Lining stress controllers (LSC). 3) Sudden collapse of tunnel: While construction, the tunnel roof of 50m stretch suddenly collapsed and fortunately it didn’t cause any loss of life. This caused a hindrance in the progress of work.
  • 20.  Various measures were taken to avoid collapse of tunnel like rock bolting after clearing muck, rock bolting with wire mesh and shotcrete were done monolithically, continuous monitoring of deformations and deflections, piped roofing to take high overburden.
  • 21. 3) VENTILATION BUILDING:  The installation of the ventilation building at South Portal became a very challenging task as it is located in a landslide region.  Constructing of the building in a stable deep rock cut, anchoring walls of the ventilation buildings to arrest movement of building and providing measures against sliding of slope like anchoring after removing loose cover from the slope, providing an avalanche gallery.  Even at the north portal installation of the ventilation building has been challenging as there is no sufficient space available and must be built along the slope.  This slope is in a high avalanche prone area. Finally the building was constructed in a straight alignment along the tunnel on a raft foundation in a safe zone devoid from avalanche.
  • 22.
  • 23. 4) ALIGNMENT PRECISION WHILE PROGRESSING:  Construction of the tunnel was carried out from two ends simultaneously. Electronic total station survey instruments were used for the purpose of alignment of tunnel.  Due to their magnetic nature, they were getting affected because of huge support installations made of steel as the tunneling is being progressed. Inertial precision technology (gyro-meters) is used to counter after every one km of excavation. 5) TRANSPORTATION:  Transportation availability to the site is not a smooth process in this young Himalayan region.  Many challenges are faced during material transportation and this somewhat added to the delay in work execution.
  • 24. 6) EXTREME WEATHER:  Rohtang valley region remains inaccessible due to heavy snowfall nearly 6 months; as a result construction work can be carried out only for 6 months in one year. Therefore the project implementation got hindered and delayed.  Due to extreme cold conditions at site workers were also having bad effects on health. Medical aid is provided accordingly. 7) COMMUNICATION ISSUE:  Due to remoteness of the site and extreme weather conditions like snowfall no proper network is available and wireless communication through radio is not possible.  So installing cables is the only option which is done with the help of BSNL.
  • 25. 8) EXCESSIVE SNOWFALL:  The tunnel project site faces excessive snowfall in the winters and experiences subzero temperatures accompanied by frequent avalanches.  North Portal as such remains closed throughout the winters almost 6 months.
  • 26. SAFETY MEASURES IN TUNNEL The Tunnel has ample safety features built into it. Some of the key safety features are  Tunnel entry barriers at both portals.  Telephone connections at every 150 Meters for Emergency communication.  Fire hydrant mechanisms at every 60 meters.  Auto incident detection system with CCTV  cameras at every 250 Meters.  Air quality monitoring at every 1 Km.  Evacuation lighting / exit signs at every 25 Meters.  Broadcasting system throughout the tunnel.  Fire rated Dampers at every 50 Meters.  Cameras at every 60 Meters.
  • 27.
  • 28.
  • 29. REFRENCES  INTERNATIONAL JOURNAL OF INNOVATIONS IN ENGINEERING RESEARCH AND TECHNOLOGY [IJIERT] ISSN: 2394-3696 Website: ijiert.org VOLUME 8, ISSUE 8, Aug. -2021.  Compendium on Atal Tunnel issued by Border Road Organisation.  https://www.encardio.com/blog/rohtang-pass-tunnel-case-study-geotechnical- monitoring-instrumentation/  http://testcf.constrofacilitator.com/the-atal-rohtang-tunnel-a-look-into-the- construction-marvel/  https://www.slideshare.net/Bimenpreet/atal-rohtang-tunnel-construction- process-challenges-and-features