The Presentation Covers the General Technical Features of Tunnel T 80 across Pir Panjal Mountain Range, for Kashmir Rail Link. This presentation was made at Civil Engineering Society, IIT Kanpur on 30th September 2013.
2. 2
• Location Overview
• Salient Features of The Tunnel
• Construction Approach
• Pre-construction Planning
• Usage Of NATM in T-80
• Construction Activities
• Quality Assurance
• Environment Issues
• Social Impact
PRESENTATION COVERS
6. 6
SALIENT FEATURES OF T-80
• Total length – 11 Km
• Adit – 774 m (58 m2 exc. Area)
• Shaft : 55 m depth , 12 m dia
• Maximum overburden - 1.10 Km
• Tunnelling method :NATM (New Austrian
Tunneling Method)
• Completed Cost – 1150 Crores
• Approx. 440 m below existing Jawahar Road
Tunnel(2.75km)
• Underground excavation : 10 lac cubic meter
• Cross section Area : Excavation : 67 to 78 m2 ,
Finished Tunnel : 48 m2
• Investigation Bore Holes depth upto 640 m
7. 7
SALIENT FEATURES OF T-80
(Contd.)
• 3 m wide road in tunnel for maintenance,
emergency rescue & relief.
• High mid point & sloping in both directions for
drainage.
• Provision of system for ventilation, fire fighting &
safety monitoring.
• Adit & shaft for parallel working, to be used for
ventilation, maintenance & emergency relief
during service.
• Extensive instrumentation for monitoring during
tunneling
• Consultants : M/s Geoconsult-RITES JV
8. 8
MANY FIRSTS
• The Longest Transport Tunnel In The Country
(11Km)
• Highest ‘Over- burden’ of 1100M
• Deepest ‘Drill holes’ for Geotechnical
Investigations 640M
• First Large Scale Use of ‘New Austrian Tunneling
Method (NATM)’ in India
• First Use of ‘Road header’ for ‘Tunnel Excavation’
in Railway Tunneling
16. 16
BENDING MOMENTS DIAGRAM FOR
D-SHAPE TUNNEL
TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M
MAX BENDING MOMENT = 137KN-M
17. 17
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL
TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
MAX. BENDING MOMENT = 35.80KN-M
18. COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL
DESCRIPTION MAX.
AXIAL
FORCE
MAX.
BENDING
MOMENT
MAX.
SHEAR
FORCE
MAX.
DISPLACEMENT
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE
5000 KG/M
D-SHAPED
TUNNEL
412.5KN 137KN-M 15129 KG 0.083 M
ELLIPTICAL
TUNNEL
567 KN 35.80KN-M 9025 KG 0.024 M
WITH TOP PRESSURE 15000 KG/M
D-SHAPED
TUNNEL
412.5KN 48.10 KN-M 8565 KG 0.03 M
ELLIPTICAL
TUNNEL
639 KN 35.65 KN-M 9635 KG 0.028 M
20. 20
DRILL AND BLAST
• CONVENTIONAL, ART
WHICH COMES WITH
EXPERIENCE
• GOOD IN HARD ROCKY
STRATA
• WITH EXPERIENCE, CAN
DELIVER GOOD PROGRESS
• NON CONTINUOUS- CYCLE
INVOLVES VARIOUS
ACTIVITIES IN SEQUENCE
• MAY SPRING SUDDEN
SURPRISES
21. 21
ROAD HEADER
• CONTINUOUS ADVANCE-
LESS SURPRISES
• MORE CONTROLLED
EXCAVATION- LESS
OVERBREAK/CAVITY
FORMATION
• SUITABLE FOR MEDIUM
HARD ROCK
• CAN BE WITHDRAWN
MID WAY TO GIVE WAY
FOR OTHER METHODS
22. 22
TUNNEL BORING MACHINE
• CONTINUOUS ADVANCE
• CIRCULAR SECTION
• NOT SUITABLE UNDER
SQUEEZING
CONDITIONS
• CANNOT BE
WITHDRAWN MIDWAY
TO GIVE WAY TO
OTHER METHODS
23. 23
WHY NO TBM
• Likelihood of Mixed Geology
• Heavily Faulted Areas and/or Wide
Fault Zones
• High Squeezing Anticipated in middle
with High Overburden (1100 mts.)
• Heavy Water Flow in Lime Stone Zone
with High overburden
• TBM may be Trapped by Ground
Movement Behind the Face
25. 25
PRE-CONSTRUCTION
PLANNING
• Engagement of Consultant
– QCB System Of tendering
• Survey and Investigation
• Head start by Taking up ADIT and shaft
works in advance
• Tender Planning
– Key dates
– Multi Method Approach
• Road Header/ D&B
26.
27. 27
USAGE OF NATM IN T-80
• Suitable for poor and Varying Geology of
Himalayan Region
• X-Section designed to develop Maximum Self
Supporting Capacity
• Face Mapping, Probe Hole & Instrumentation
data input for Initial Support Design – RESS
– Primary Support System
• Resilient enough to Accept the deformations and readjustment of
stresses and Strong enough to take the loads
• Deformation Monitoring to assess the stress
redistribution, and stabilization before final
lining
28. 28
INSTRUMENTATION
To provide early information about tunnel behaviour in order to optimize
excavation & support activities during construction and to recognize the requisite
remedial measures.
Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring: With bi-reflex targets to monitor deformation in
tunnel on daily basis
Extensometers: To measure stresses in surrounding rock mass
Radial Pressure Cells: To measure pressure of rockmass on shotcrete
lining
Shotcrete Strain meter: To monitor stresses in shotcrete lining
Piezometer: To monitor hydrostatic pressure during tunneling
29. 29
CONSTRUCTION ACTIVITES
• Open excavation & portal development
• Tunnel mining & primary lining
• Water-proof membrane installation +
drainage system.
• Secondary lining.
• Ventilation, system and safety
installations
• Track laying
30. 30
QUALITY ASSURANCE
• Laid down responsibilities,
procedures and checklists for
various activities through:
–CPM, CQM, SH&EM
–PPM, PSM
–Organogram
–QAP
–ITP
31. 31
QUALITY ASSURANCE (contd…)
• Availability of relevant documentation and defining
the manner of execution of various activities
• Maintaining compliance through appropriate
monitoring
• Ensuring adequate support facilities for successful
& scheduled execution of work.
• Availability of competent/trained personnel to carry
out various activities
• Compliance of statutory/regulatory requirements
related to safety, environment etc.
32. 32
Quality Assurance (contd…)
Check Lists and Forms for Process Control During
Execution of Works:
• Required Excavation and Support Sheet (RESS)
• ATSS/ Shift Report/Blasting clearance report/ R/Bolt
Installation report
• Shotcrete testing by Penetrometer test, Core
crushing test, thickness verification etc.
• Geological mapping (Geological face mapping sheet)
• Lining Air Permeability Test
• All Material Testing at Site Lab
33. 33
ENVIRONMENT ISSUES
• Identified Muck Dumping areas
• Recycling of Excavated Rocks
– aggregate for concrete constn.
• Effluent Settling Tank
– Fit for agriculture discharge
• Ventilation during Construction Stage
– Gas Analyser for air quality monitoring
• Controlled Blasting below Inhabited
areas
• Lined Waterproof Tunnel
– No long term impact on water table/ Aquifers
34. 34
SOCIAL IMPACT
• All weather link, Alternate to Jawahar
Tunnel
• Even at Construction stage, given a
boost to
– local construction-industry
– Employment
– Transportation business
• A boost to Local economy of Banihal
42. 42
ENGAGEMENT OF CONSULTANT
• Investigations for Tunneling Methodology
Assessment
• Initial Design
– Usage of NATM
– Usage of Water proof Membrane for Semi Dry
Tunnel
– Development of 4-Arc Tunnel X-Section
– Additional Access through ADIT and Shaft
– Portal Location Review
• Real Time Monitoring / Instrumentation
and Design Support
43. 43
INVESTIGATIONS & PLANNING
2003 Geological L-Section Profile Submitted by M/s
RITES based on GSI data.-
Used to decide the Bore hole Location.
2003-04 Bore holes by RITES/ MECL-
To Confirm Geological Mapping inference
2004 Consultants engaged in Feb. 2004
Geological Surface Mapping along the entire alignment by -
For Detailed Geological Section
2004 Data input for Tendering and a Decision Support System for
ADIT and Shaft decision
– Adit & Shaft Work Awarded in June 2004
2004 Detailed Topographical Survey for Portal
Location
2005 Main Tunnel Construction Work Awarded in
August 2005
47. BASIC PRINCIPLES OF NATM
• Rock Mass is the major load bearing
member
• Primary Support shall
maintain the integrity & strength of Rock Mass
light, have good and area contact (shotcrete)
strengthen Rock Mass (bolt, grouting)
provide protection to workers (steel rib, mesh)
installed quickly
• Provide always an effective ring closure, if
necessary by an invert if rock is not
suitable
48. BASIC PRINCIPLES OF NATM (Contd.)
• Rounded shape of Cross-Section
• Continuous control of system behaviour
by monitoring
• Inner lining shall be installed only after
balance of stresses („zero“ deformation)