SlideShare a Scribd company logo
1 of 84
Download to read offline
WELCOME YOU TO
PIRPANJAL RAILWAY TUNNEL
SITE
THE LONGEST TRANSPORTATION
TUNNEL IN INDIA
2
• Location Overview
• Salient Features of The Tunnel
• Construction Approach
• Pre-construction Planning
• Usage Of NATM in T-80
• Construction Activities
• Quality Assurance
• Environment Issues
• Social Impact
PRESENTATION COVERS
LOCATION OVERVIEW
4
ALIGNMENT PLAN
JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL
LINK
QAZIGUN
D
SADUR
A
ANANTNAG
BIJBEHARA
PUNZGA
M
AWANTIPORA
KAKPORA
PAMPOR
E
SRINAGA
R
BUDGA
M
RAJWANSHE
R
PATTAN
HAMRE
SOPORE
BARAMULLA
BANIHA
LARPINCHALA
BHATTA
LOALE
KOHLISANGALDAN
BARALA
BASAND
A--DHAR
REASI
KATRA
CHAKARWAH
UDHAMPUR
SALAL
RAMNAGAR
ROAD
MANWA
L
SANGAR
BAJALT
A
JAMM
U
SURUKOT
PIR PANJAL RAIL TUNNEL
Length 11100 mts.
South portal photo
SOUTH PORTAL
5
6
SALIENT FEATURES OF T-80
• Total length – 11 Km
• Adit – 774 m (58 m2 exc. Area)
• Shaft : 55 m depth , 12 m dia
• Maximum overburden - 1.10 Km
• Tunnelling method :NATM (New Austrian
Tunneling Method)
• Completed Cost – 1150 Crores
• Approx. 440 m below existing Jawahar Road
Tunnel(2.75km)
• Underground excavation : 10 lac cubic meter
• Cross section Area : Excavation : 67 to 78 m2 ,
Finished Tunnel : 48 m2
• Investigation Bore Holes depth upto 640 m
7
SALIENT FEATURES OF T-80
(Contd.)
• 3 m wide road in tunnel for maintenance,
emergency rescue & relief.
• High mid point & sloping in both directions for
drainage.
• Provision of system for ventilation, fire fighting &
safety monitoring.
• Adit & shaft for parallel working, to be used for
ventilation, maintenance & emergency relief
during service.
• Extensive instrumentation for monitoring during
tunneling
• Consultants : M/s Geoconsult-RITES JV
8
MANY FIRSTS
• The Longest Transport Tunnel In The Country
(11Km)
• Highest ‘Over- burden’ of 1100M
• Deepest ‘Drill holes’ for Geotechnical
Investigations 640M
• First Large Scale Use of ‘New Austrian Tunneling
Method (NATM)’ in India
• First Use of ‘Road header’ for ‘Tunnel Excavation’
in Railway Tunneling
CONSTRUCTION
APPROACH
10
APPROACH TO CONSTRUCTION
NO ADIT
11
Vertcal Shaft
55m deep,
12m dia
Cross Passage 55 m
Adit 788 m
APPROACH TO CONSTRUCTION
WITH SHAFT AND ADIT
12
Tunnel
Cross
Section:
STRUCTURAL GAUGE
13
TUNNELS
SECTIONS
USED ON
KONKAN
TRACK
14
TYPICAL
RAILWAY
TUNNEL
SECTION
USED ON
JAMMU-
UDHAMPUR
RAIL LINK
SHOTCRETE(25mm+WIRE MESH +50mm)
OR 50mm SFRS
300 TH. C.C. LINING
ISHB 150 @ 500 C/C
50mm TH. R.C.C. LAGGING
Min. EXCAVATION LINE
75Ø @ 2000 C/C
MS PLATE 12mm THICK
ISHB150-2NOS.
INVERT STRUT ISHB150 @ 500mm
ISHB200 @ 750 C/C
1676
R2600
43701312
150
150
Max.
150(max)
50M20
1 in 40
RAIL LEVEL
FINISH LINE
PAY LINE 150 TH. FROM Min. EXCAVATION
25 mm Ø 3 to 5m ROCK BOLTS
AS PER SITE REQUIREMENT
ISHB 150 @ 750 c/c
PRESSURE RELIEF HOLES 5m DEEP @
3m c/c LONGITUDINALLY AS PER SITE
REQUIREMENT
150
PAY LINE
MIN. EXCAV. LINE
BASE PLATE
12mm THICK
R3000
ISHB150@500c/c
SHOTCRETE25mm+
WIREMESH+50mmOR50mmSFRS
50TH.R.C.C.LAGGING
150
PRESSURERELIEFHOLES5m
DEEP@3mc/cLONGITUDINALLY
ARASPERSITEREQUIREMENT
BACKFILLINGM-10
50
FINISHLINE
300TH.CONC.LININGM-20
150
100
900
BLOWER
8Ø @ 150 C/C
50 675 150
100
65
675
25mmØ3mto5m
ROCKBOLTAS
PERSITE
REQUIREMENT
SEC.ATA-A
75
15
LOADING DIAGRAM FOR TUNNEL
TOP PRESSURE-15000KG/M
AND SIDE PRESSURE-5000KG/M
16
BENDING MOMENTS DIAGRAM FOR
D-SHAPE TUNNEL
TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M
MAX BENDING MOMENT = 137KN-M
17
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL
TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
MAX. BENDING MOMENT = 35.80KN-M
COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL
DESCRIPTION MAX.
AXIAL
FORCE
MAX.
BENDING
MOMENT
MAX.
SHEAR
FORCE
MAX.
DISPLACEMENT
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE
5000 KG/M
D-SHAPED
TUNNEL
412.5KN 137KN-M 15129 KG 0.083 M
ELLIPTICAL
TUNNEL
567 KN 35.80KN-M 9025 KG 0.024 M
WITH TOP PRESSURE 15000 KG/M
D-SHAPED
TUNNEL
412.5KN 48.10 KN-M 8565 KG 0.03 M
ELLIPTICAL
TUNNEL
639 KN 35.65 KN-M 9635 KG 0.028 M
19
CONSTRUCTION METHOD
SELECTION
• DRILL AND BLAST
• ROAD HEADER
• TUNNEL BORING MACHINE (TBM)
20
DRILL AND BLAST
• CONVENTIONAL, ART
WHICH COMES WITH
EXPERIENCE
• GOOD IN HARD ROCKY
STRATA
• WITH EXPERIENCE, CAN
DELIVER GOOD PROGRESS
• NON CONTINUOUS- CYCLE
INVOLVES VARIOUS
ACTIVITIES IN SEQUENCE
• MAY SPRING SUDDEN
SURPRISES
21
ROAD HEADER
• CONTINUOUS ADVANCE-
LESS SURPRISES
• MORE CONTROLLED
EXCAVATION- LESS
OVERBREAK/CAVITY
FORMATION
• SUITABLE FOR MEDIUM
HARD ROCK
• CAN BE WITHDRAWN
MID WAY TO GIVE WAY
FOR OTHER METHODS
22
TUNNEL BORING MACHINE
• CONTINUOUS ADVANCE
• CIRCULAR SECTION
• NOT SUITABLE UNDER
SQUEEZING
CONDITIONS
• CANNOT BE
WITHDRAWN MIDWAY
TO GIVE WAY TO
OTHER METHODS
23
WHY NO TBM
• Likelihood of Mixed Geology
• Heavily Faulted Areas and/or Wide
Fault Zones
• High Squeezing Anticipated in middle
with High Overburden (1100 mts.)
• Heavy Water Flow in Lime Stone Zone
with High overburden
• TBM may be Trapped by Ground
Movement Behind the Face
PRE-CONSTRUCTION
PLANNING
25
PRE-CONSTRUCTION
PLANNING
• Engagement of Consultant
– QCB System Of tendering
• Survey and Investigation
• Head start by Taking up ADIT and shaft
works in advance
• Tender Planning
– Key dates
– Multi Method Approach
• Road Header/ D&B
27
USAGE OF NATM IN T-80
• Suitable for poor and Varying Geology of
Himalayan Region
• X-Section designed to develop Maximum Self
Supporting Capacity
• Face Mapping, Probe Hole & Instrumentation
data input for Initial Support Design – RESS
– Primary Support System
• Resilient enough to Accept the deformations and readjustment of
stresses and Strong enough to take the loads
• Deformation Monitoring to assess the stress
redistribution, and stabilization before final
lining
28
INSTRUMENTATION
To provide early information about tunnel behaviour in order to optimize
excavation & support activities during construction and to recognize the requisite
remedial measures.
Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring: With bi-reflex targets to monitor deformation in
tunnel on daily basis
Extensometers: To measure stresses in surrounding rock mass
Radial Pressure Cells: To measure pressure of rockmass on shotcrete
lining
Shotcrete Strain meter: To monitor stresses in shotcrete lining
Piezometer: To monitor hydrostatic pressure during tunneling
29
CONSTRUCTION ACTIVITES
• Open excavation & portal development
• Tunnel mining & primary lining
• Water-proof membrane installation +
drainage system.
• Secondary lining.
• Ventilation, system and safety
installations
• Track laying
30
QUALITY ASSURANCE
• Laid down responsibilities,
procedures and checklists for
various activities through:
–CPM, CQM, SH&EM
–PPM, PSM
–Organogram
–QAP
–ITP
31
QUALITY ASSURANCE (contd…)
• Availability of relevant documentation and defining
the manner of execution of various activities
• Maintaining compliance through appropriate
monitoring
• Ensuring adequate support facilities for successful
& scheduled execution of work.
• Availability of competent/trained personnel to carry
out various activities
• Compliance of statutory/regulatory requirements
related to safety, environment etc.
32
Quality Assurance (contd…)
Check Lists and Forms for Process Control During
Execution of Works:
• Required Excavation and Support Sheet (RESS)
• ATSS/ Shift Report/Blasting clearance report/ R/Bolt
Installation report
• Shotcrete testing by Penetrometer test, Core
crushing test, thickness verification etc.
• Geological mapping (Geological face mapping sheet)
• Lining Air Permeability Test
• All Material Testing at Site Lab
33
ENVIRONMENT ISSUES
• Identified Muck Dumping areas
• Recycling of Excavated Rocks
– aggregate for concrete constn.
• Effluent Settling Tank
– Fit for agriculture discharge
• Ventilation during Construction Stage
– Gas Analyser for air quality monitoring
• Controlled Blasting below Inhabited
areas
• Lined Waterproof Tunnel
– No long term impact on water table/ Aquifers
34
SOCIAL IMPACT
• All weather link, Alternate to Jawahar
Tunnel
• Even at Construction stage, given a
boost to
– local construction-industry
– Employment
– Transportation business
• A boost to Local economy of Banihal
35
Time Line
36
PIR PANJAL TUNNEL-
EXCAVATION PROGRESS
Year Excavation
(mts.)
Remarks
2006 722 Two Faces
2007 1876 Start From 4 Faces
2008 2475
2009 2533
2010 1739 Two Faces after Jan’10
2011 947 High overburden,
Squeezing, Shale
2012 63
40
Miles to go……
“A thing should be made
as simple as possible,
but not simpler”.
Einstein
41
THANKS !
42
ENGAGEMENT OF CONSULTANT
• Investigations for Tunneling Methodology
Assessment
• Initial Design
– Usage of NATM
– Usage of Water proof Membrane for Semi Dry
Tunnel
– Development of 4-Arc Tunnel X-Section
– Additional Access through ADIT and Shaft
– Portal Location Review
• Real Time Monitoring / Instrumentation
and Design Support
43
INVESTIGATIONS & PLANNING
2003 Geological L-Section Profile Submitted by M/s
RITES based on GSI data.-
Used to decide the Bore hole Location.
2003-04 Bore holes by RITES/ MECL-
To Confirm Geological Mapping inference
2004 Consultants engaged in Feb. 2004
Geological Surface Mapping along the entire alignment by -
For Detailed Geological Section
2004 Data input for Tendering and a Decision Support System for
ADIT and Shaft decision
– Adit & Shaft Work Awarded in June 2004
2004 Detailed Topographical Survey for Portal
Location
2005 Main Tunnel Construction Work Awarded in
August 2005
44
45
46
BASIC PRINCIPLES OF NATM
• Rock Mass is the major load bearing
member
• Primary Support shall
 maintain the integrity & strength of Rock Mass
 light, have good and area contact (shotcrete)
 strengthen Rock Mass (bolt, grouting)
 provide protection to workers (steel rib, mesh)
 installed quickly
• Provide always an effective ring closure, if
necessary by an invert if rock is not
suitable
BASIC PRINCIPLES OF NATM (Contd.)
• Rounded shape of Cross-Section
• Continuous control of system behaviour
by monitoring
• Inner lining shall be installed only after
balance of stresses („zero“ deformation)
49
503D Monitoring Targets
51
52
53
EXTENSOMETER
54
FACE MAPPING
55
PROBING SHEET
56
57
58
59
Deformation
Monitoring in Primary
Lining Before start of
Secondary Lining
60
61
62Charging of Face
63Ventilation Duct
64Mucking
65Wire mesh & Lattice Girder Erection
66
Face sealing
Face sealing by Shotcrete
67Drilling for Forepoling
68
Rock Bolting
69
TUNNEL MINING
Activity
Cycle Time (hr.) 2 mt.
RC IV
Cycle time (hr.) 1.25
mt. RC V
Drilling & Excavation 1.7 0.9
Charging , Blasting
& Defuming
2.7 1.5
Mucking 1.1 0.8
Wire Mesh & Lattice
Girder
2.4 2.3
Shotcrete 0.9 0.8
Rock Bolting 1.8 1.0
Preparation of new
face
0.3 0.3
Maintenance 1.6 1.1
Forepoling 1.6 1.7
Total 14.1 10.4
70
71
Kicker Beam Casting
72
Geotextile Fixing
73
PVC Membrane Fixing
74Membrane Stitching
75
Reinforcement for Overt Lining
76
Reinforcement Cage for Inner Lining
77Concrete Lining Gantry
78
View of Finished Lining Concrete
79
Profile Checking with Total Station
80Core Cutting
81Testing of Joints (Membrane)
82
Sedimentation Tank
83
Effluent Quality
Test Report
84

More Related Content

What's hot (20)

Casting yard
Casting yardCasting yard
Casting yard
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Geotechnical investigations for tunnelling
Geotechnical  investigations for tunnellingGeotechnical  investigations for tunnelling
Geotechnical investigations for tunnelling
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
Tunnelling & underground design (Topic5-hard & weak rock tunnelling)
 
Standard Penetration Test
Standard Penetration TestStandard Penetration Test
Standard Penetration Test
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)Tunnel Boring Machines (TBM)
Tunnel Boring Machines (TBM)
 
Embankment
EmbankmentEmbankment
Embankment
 
Well foundation
Well foundationWell foundation
Well foundation
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
 
rock anchor methodology
rock anchor methodologyrock anchor methodology
rock anchor methodology
 
Tunnels and tunneling (Engineering Geology)
Tunnels and tunneling (Engineering Geology)Tunnels and tunneling (Engineering Geology)
Tunnels and tunneling (Engineering Geology)
 
Types of slope failures
Types of slope failuresTypes of slope failures
Types of slope failures
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Geotechnical Engineering - Dams
Geotechnical Engineering - DamsGeotechnical Engineering - Dams
Geotechnical Engineering - Dams
 
Lining of tunnel
Lining of tunnelLining of tunnel
Lining of tunnel
 
Rock Mass Classification
Rock Mass ClassificationRock Mass Classification
Rock Mass Classification
 

Viewers also liked

World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014richardbieniawski
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)Austrian Standards
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessonscoen_van_der_vliet
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridgesSravan Kumar
 
Top down construction
Top down constructionTop down construction
Top down constructionAmulya Kansal
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATMluisaam
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge SystemAltosMarketing
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCommunications Branding
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineFilipe Mello
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel liningMahesh Raj Bhatt
 

Viewers also liked (20)

Tunnels concepts
Tunnels conceptsTunnels concepts
Tunnels concepts
 
Bridge 91 Design
Bridge 91 DesignBridge 91 Design
Bridge 91 Design
 
World Tunnel Conference 2014
World Tunnel Conference 2014World Tunnel Conference 2014
World Tunnel Conference 2014
 
New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)New Austrian Tunnelling Method (NATM)
New Austrian Tunnelling Method (NATM)
 
Shield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and LessonsShield Tail Deformations - Experiences, Mechanics and Lessons
Shield Tail Deformations - Experiences, Mechanics and Lessons
 
segmental construction of bridges
segmental construction of bridgessegmental construction of bridges
segmental construction of bridges
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Tunneling
Tunneling Tunneling
Tunneling
 
Directional Drilling
Directional DrillingDirectional Drilling
Directional Drilling
 
Tunneling Construction - NATM
Tunneling Construction - NATMTunneling Construction - NATM
Tunneling Construction - NATM
 
Dam PPT
Dam PPTDam PPT
Dam PPT
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazine
 
Bridge
BridgeBridge
Bridge
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
Tunneling
Tunneling  Tunneling
Tunneling
 

Similar to Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

Application of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwideApplication of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwideApollo Techno Industries Pvt Ltd
 
Technical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and WorldwideTechnical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and WorldwideApollo Techno Industries Pvt Ltd
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionSuresh Zanwar
 
CONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptxCONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptxDeepakKumar751819
 
SUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUESSUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUESR821992
 
Trenchless Technology a Review
Trenchless Technology a Review Trenchless Technology a Review
Trenchless Technology a Review AkshathaBhandary
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesLaura Anderson
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureStatoil
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...IEI GSC
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningJasmeet Singh Saluja
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructionsVinay Vb
 

Similar to Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India (20)

Application of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwideApplication of Horizontal Directional Drilling Machine in India and worldwide
Application of Horizontal Directional Drilling Machine in India and worldwide
 
Technical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and WorldwideTechnical Features of Apollo HDD Machines In India and Worldwide
Technical Features of Apollo HDD Machines In India and Worldwide
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Quality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline constructionQuality aspects in Cross Country Pipeline construction
Quality aspects in Cross Country Pipeline construction
 
ALEEM MALIK
ALEEM MALIKALEEM MALIK
ALEEM MALIK
 
CONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptxCONVENTIONAL TUNNELLING.pptx
CONVENTIONAL TUNNELLING.pptx
 
SUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUESSUSTAINABLE CONSTRUCTION TECHNIQUES
SUSTAINABLE CONSTRUCTION TECHNIQUES
 
Pms presentation
Pms presentationPms presentation
Pms presentation
 
Trenchless Technology a Review
Trenchless Technology a Review Trenchless Technology a Review
Trenchless Technology a Review
 
TRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGYTRENCHLESS TECHNOLOGY
TRENCHLESS TECHNOLOGY
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project Challenges
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the future
 
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
Integrated Geophysical Approach for Rapid & Cost Effective Site Investigation...
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 

Recently uploaded

KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 

Recently uploaded (20)

KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 

Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India

  • 1. WELCOME YOU TO PIRPANJAL RAILWAY TUNNEL SITE THE LONGEST TRANSPORTATION TUNNEL IN INDIA
  • 2. 2 • Location Overview • Salient Features of The Tunnel • Construction Approach • Pre-construction Planning • Usage Of NATM in T-80 • Construction Activities • Quality Assurance • Environment Issues • Social Impact PRESENTATION COVERS
  • 5. 5
  • 6. 6 SALIENT FEATURES OF T-80 • Total length – 11 Km • Adit – 774 m (58 m2 exc. Area) • Shaft : 55 m depth , 12 m dia • Maximum overburden - 1.10 Km • Tunnelling method :NATM (New Austrian Tunneling Method) • Completed Cost – 1150 Crores • Approx. 440 m below existing Jawahar Road Tunnel(2.75km) • Underground excavation : 10 lac cubic meter • Cross section Area : Excavation : 67 to 78 m2 , Finished Tunnel : 48 m2 • Investigation Bore Holes depth upto 640 m
  • 7. 7 SALIENT FEATURES OF T-80 (Contd.) • 3 m wide road in tunnel for maintenance, emergency rescue & relief. • High mid point & sloping in both directions for drainage. • Provision of system for ventilation, fire fighting & safety monitoring. • Adit & shaft for parallel working, to be used for ventilation, maintenance & emergency relief during service. • Extensive instrumentation for monitoring during tunneling • Consultants : M/s Geoconsult-RITES JV
  • 8. 8 MANY FIRSTS • The Longest Transport Tunnel In The Country (11Km) • Highest ‘Over- burden’ of 1100M • Deepest ‘Drill holes’ for Geotechnical Investigations 640M • First Large Scale Use of ‘New Austrian Tunneling Method (NATM)’ in India • First Use of ‘Road header’ for ‘Tunnel Excavation’ in Railway Tunneling
  • 11. 11 Vertcal Shaft 55m deep, 12m dia Cross Passage 55 m Adit 788 m APPROACH TO CONSTRUCTION WITH SHAFT AND ADIT
  • 14. 14 TYPICAL RAILWAY TUNNEL SECTION USED ON JAMMU- UDHAMPUR RAIL LINK SHOTCRETE(25mm+WIRE MESH +50mm) OR 50mm SFRS 300 TH. C.C. LINING ISHB 150 @ 500 C/C 50mm TH. R.C.C. LAGGING Min. EXCAVATION LINE 75Ø @ 2000 C/C MS PLATE 12mm THICK ISHB150-2NOS. INVERT STRUT ISHB150 @ 500mm ISHB200 @ 750 C/C 1676 R2600 43701312 150 150 Max. 150(max) 50M20 1 in 40 RAIL LEVEL FINISH LINE PAY LINE 150 TH. FROM Min. EXCAVATION 25 mm Ø 3 to 5m ROCK BOLTS AS PER SITE REQUIREMENT ISHB 150 @ 750 c/c PRESSURE RELIEF HOLES 5m DEEP @ 3m c/c LONGITUDINALLY AS PER SITE REQUIREMENT 150 PAY LINE MIN. EXCAV. LINE BASE PLATE 12mm THICK R3000 ISHB150@500c/c SHOTCRETE25mm+ WIREMESH+50mmOR50mmSFRS 50TH.R.C.C.LAGGING 150 PRESSURERELIEFHOLES5m DEEP@3mc/cLONGITUDINALLY ARASPERSITEREQUIREMENT BACKFILLINGM-10 50 FINISHLINE 300TH.CONC.LININGM-20 150 100 900 BLOWER 8Ø @ 150 C/C 50 675 150 100 65 675 25mmØ3mto5m ROCKBOLTAS PERSITE REQUIREMENT SEC.ATA-A 75
  • 15. 15 LOADING DIAGRAM FOR TUNNEL TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M
  • 16. 16 BENDING MOMENTS DIAGRAM FOR D-SHAPE TUNNEL TOP PRESSURE-15000KG/M AND SIDE PRESSURE-5000KG/M MAX BENDING MOMENT = 137KN-M
  • 17. 17 BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M MAX. BENDING MOMENT = 35.80KN-M
  • 18. COMPARISION BETWEEN D-SHAPED AND ELLIPTICAL TUNNEL DESCRIPTION MAX. AXIAL FORCE MAX. BENDING MOMENT MAX. SHEAR FORCE MAX. DISPLACEMENT WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE 5000 KG/M D-SHAPED TUNNEL 412.5KN 137KN-M 15129 KG 0.083 M ELLIPTICAL TUNNEL 567 KN 35.80KN-M 9025 KG 0.024 M WITH TOP PRESSURE 15000 KG/M D-SHAPED TUNNEL 412.5KN 48.10 KN-M 8565 KG 0.03 M ELLIPTICAL TUNNEL 639 KN 35.65 KN-M 9635 KG 0.028 M
  • 19. 19 CONSTRUCTION METHOD SELECTION • DRILL AND BLAST • ROAD HEADER • TUNNEL BORING MACHINE (TBM)
  • 20. 20 DRILL AND BLAST • CONVENTIONAL, ART WHICH COMES WITH EXPERIENCE • GOOD IN HARD ROCKY STRATA • WITH EXPERIENCE, CAN DELIVER GOOD PROGRESS • NON CONTINUOUS- CYCLE INVOLVES VARIOUS ACTIVITIES IN SEQUENCE • MAY SPRING SUDDEN SURPRISES
  • 21. 21 ROAD HEADER • CONTINUOUS ADVANCE- LESS SURPRISES • MORE CONTROLLED EXCAVATION- LESS OVERBREAK/CAVITY FORMATION • SUITABLE FOR MEDIUM HARD ROCK • CAN BE WITHDRAWN MID WAY TO GIVE WAY FOR OTHER METHODS
  • 22. 22 TUNNEL BORING MACHINE • CONTINUOUS ADVANCE • CIRCULAR SECTION • NOT SUITABLE UNDER SQUEEZING CONDITIONS • CANNOT BE WITHDRAWN MIDWAY TO GIVE WAY TO OTHER METHODS
  • 23. 23 WHY NO TBM • Likelihood of Mixed Geology • Heavily Faulted Areas and/or Wide Fault Zones • High Squeezing Anticipated in middle with High Overburden (1100 mts.) • Heavy Water Flow in Lime Stone Zone with High overburden • TBM may be Trapped by Ground Movement Behind the Face
  • 25. 25 PRE-CONSTRUCTION PLANNING • Engagement of Consultant – QCB System Of tendering • Survey and Investigation • Head start by Taking up ADIT and shaft works in advance • Tender Planning – Key dates – Multi Method Approach • Road Header/ D&B
  • 26.
  • 27. 27 USAGE OF NATM IN T-80 • Suitable for poor and Varying Geology of Himalayan Region • X-Section designed to develop Maximum Self Supporting Capacity • Face Mapping, Probe Hole & Instrumentation data input for Initial Support Design – RESS – Primary Support System • Resilient enough to Accept the deformations and readjustment of stresses and Strong enough to take the loads • Deformation Monitoring to assess the stress redistribution, and stabilization before final lining
  • 28. 28 INSTRUMENTATION To provide early information about tunnel behaviour in order to optimize excavation & support activities during construction and to recognize the requisite remedial measures. Instrumentation data is basic input of the NATM, the observational approach. Instrumentation in Pir Panjal Tunnel: Optical 3 D monitoring: With bi-reflex targets to monitor deformation in tunnel on daily basis Extensometers: To measure stresses in surrounding rock mass Radial Pressure Cells: To measure pressure of rockmass on shotcrete lining Shotcrete Strain meter: To monitor stresses in shotcrete lining Piezometer: To monitor hydrostatic pressure during tunneling
  • 29. 29 CONSTRUCTION ACTIVITES • Open excavation & portal development • Tunnel mining & primary lining • Water-proof membrane installation + drainage system. • Secondary lining. • Ventilation, system and safety installations • Track laying
  • 30. 30 QUALITY ASSURANCE • Laid down responsibilities, procedures and checklists for various activities through: –CPM, CQM, SH&EM –PPM, PSM –Organogram –QAP –ITP
  • 31. 31 QUALITY ASSURANCE (contd…) • Availability of relevant documentation and defining the manner of execution of various activities • Maintaining compliance through appropriate monitoring • Ensuring adequate support facilities for successful & scheduled execution of work. • Availability of competent/trained personnel to carry out various activities • Compliance of statutory/regulatory requirements related to safety, environment etc.
  • 32. 32 Quality Assurance (contd…) Check Lists and Forms for Process Control During Execution of Works: • Required Excavation and Support Sheet (RESS) • ATSS/ Shift Report/Blasting clearance report/ R/Bolt Installation report • Shotcrete testing by Penetrometer test, Core crushing test, thickness verification etc. • Geological mapping (Geological face mapping sheet) • Lining Air Permeability Test • All Material Testing at Site Lab
  • 33. 33 ENVIRONMENT ISSUES • Identified Muck Dumping areas • Recycling of Excavated Rocks – aggregate for concrete constn. • Effluent Settling Tank – Fit for agriculture discharge • Ventilation during Construction Stage – Gas Analyser for air quality monitoring • Controlled Blasting below Inhabited areas • Lined Waterproof Tunnel – No long term impact on water table/ Aquifers
  • 34. 34 SOCIAL IMPACT • All weather link, Alternate to Jawahar Tunnel • Even at Construction stage, given a boost to – local construction-industry – Employment – Transportation business • A boost to Local economy of Banihal
  • 36. 36 PIR PANJAL TUNNEL- EXCAVATION PROGRESS Year Excavation (mts.) Remarks 2006 722 Two Faces 2007 1876 Start From 4 Faces 2008 2475 2009 2533 2010 1739 Two Faces after Jan’10 2011 947 High overburden, Squeezing, Shale 2012 63
  • 37.
  • 38.
  • 39.
  • 40. 40 Miles to go…… “A thing should be made as simple as possible, but not simpler”. Einstein
  • 42. 42 ENGAGEMENT OF CONSULTANT • Investigations for Tunneling Methodology Assessment • Initial Design – Usage of NATM – Usage of Water proof Membrane for Semi Dry Tunnel – Development of 4-Arc Tunnel X-Section – Additional Access through ADIT and Shaft – Portal Location Review • Real Time Monitoring / Instrumentation and Design Support
  • 43. 43 INVESTIGATIONS & PLANNING 2003 Geological L-Section Profile Submitted by M/s RITES based on GSI data.- Used to decide the Bore hole Location. 2003-04 Bore holes by RITES/ MECL- To Confirm Geological Mapping inference 2004 Consultants engaged in Feb. 2004 Geological Surface Mapping along the entire alignment by - For Detailed Geological Section 2004 Data input for Tendering and a Decision Support System for ADIT and Shaft decision – Adit & Shaft Work Awarded in June 2004 2004 Detailed Topographical Survey for Portal Location 2005 Main Tunnel Construction Work Awarded in August 2005
  • 44. 44
  • 45. 45
  • 46. 46
  • 47. BASIC PRINCIPLES OF NATM • Rock Mass is the major load bearing member • Primary Support shall  maintain the integrity & strength of Rock Mass  light, have good and area contact (shotcrete)  strengthen Rock Mass (bolt, grouting)  provide protection to workers (steel rib, mesh)  installed quickly • Provide always an effective ring closure, if necessary by an invert if rock is not suitable
  • 48. BASIC PRINCIPLES OF NATM (Contd.) • Rounded shape of Cross-Section • Continuous control of system behaviour by monitoring • Inner lining shall be installed only after balance of stresses („zero“ deformation)
  • 49. 49
  • 51. 51
  • 52. 52
  • 56. 56
  • 57. 57
  • 58. 58
  • 59. 59 Deformation Monitoring in Primary Lining Before start of Secondary Lining
  • 60. 60
  • 61. 61
  • 65. 65Wire mesh & Lattice Girder Erection
  • 69. 69 TUNNEL MINING Activity Cycle Time (hr.) 2 mt. RC IV Cycle time (hr.) 1.25 mt. RC V Drilling & Excavation 1.7 0.9 Charging , Blasting & Defuming 2.7 1.5 Mucking 1.1 0.8 Wire Mesh & Lattice Girder 2.4 2.3 Shotcrete 0.9 0.8 Rock Bolting 1.8 1.0 Preparation of new face 0.3 0.3 Maintenance 1.6 1.1 Forepoling 1.6 1.7 Total 14.1 10.4
  • 70. 70
  • 78. 78 View of Finished Lining Concrete
  • 79. 79 Profile Checking with Total Station
  • 81. 81Testing of Joints (Membrane)
  • 84. 84