Project Planning
Dr Khalid Sayed
Task Definition for a Road Building Project
Defining Precedence
Relationships Among
Activities
Estimating Resource Requirements for Work Activities
Where,
Rk
ij are the resources of type k required by activity ij,
Dij is the duration of activity ij, Nij is the number of standard crews allocated to activity ij,
Uk
ij is the amount of resource type k used per standard crew.
For example, if an activity required eight hours with two crews assigned and each crew
required three workers, the effort would be R = 8*2*3 = 48 labour-hours.
Resources such as labour requirements will vary in proportion to the work
productivity, Pij
Estimating
Activity
Durations
Figure: A Hierarchical
Estimation Framework for
Masonry Construction
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx

Module 3.1_Project Planning.pptx