Indian Railways has undertaken the mega-
project of construction of a new railway line in
the State of Jammu and Kashmir.
The Chenab Bridge is a railway steel and
concrete arch bridge under construction
between Bakkal and Kauri in the Reasi from
Udhampur to Baramulla.
INTRODUCTION
CHENAB BRIDGE
Deck height (height above river) - 359 m (1,178 ft.)
Bridge length - 1,315 m (4,314 ft.)
Arch span - 485m (1,532 ft.)
Total number of span – 17
Maximum height of pier - 133.7m
Description of bridge
Travelling in and around the
mountainous region has been a
great difficulty and dangerous
for locals.
For better transportation
facilities Government of India
Constructing a national
railway project that will
connect J&K with the rest of
India.
Need for the Chenab rail bridge
SITE OF BRIDGE
Site is located in mountainous region of Jammu
Kashmir.
Geology
The Chenab Bridge is located in the trickiest section of the
Jammu-Udhampur-Srinagar-Baramulla rail route, where the
typical geology consists of young Himalaya rock.
 poor quality, broken rock with dolomitic limestone and
firestone lentils with a silicate content.
 Rock class III to V with a strength of 60 to 100MPa and a
volume weight of 2.7t/m³ is encountered
The RMR (rock mass rating) index amounts to 40 to 60.
The planning of this project has been done by WSP group
(Finland) and design of arch is done by sub consultant Leonhardt.
Indian Railway Standards (IRS Standards), IRC, IS have been
used while designing the bridge.
The design speed of the railway was set to be 100 km/h and the
design life had to be 120 years. Fatigue assessment shall be done
as per BS: 5400 Part –10
All conventional railway bridge loads, this bridge has to sustain
special blast loads specified by Indian railway
Design innovation
 Wind loads will be derived
using physical topographic
models of the site and tests in
a wind tunnel laboratory
The bridge is designed to resist
wind speeds of up to
260kmph.
The seismic nature of the
project zone was also
considered during its design.
 Limit state philosophy of
design has been decided to be
followed as per BS codes.
 Provision of long welded rail
(LWR) over the bridges and
resulting force calculation as
per UIC – 774-3R guidelines.
 Deformation limits as per
comfort criteria of UIC –
776-2R and UIC 776 -3R
guidelines.
The bridge’s construction principle entails a large bridge
arch with access viaducts at each side.
The large arch is designed as a 2-fold ribbed arch
comprising steel girders with scaffolding braces produced on
the spot.
 5 bridge pillars for the access viaducts are made of steel and
13 of concrete.
The bridge will consist of about 25000 tonnes of steel
structures, the main portion of which will be used for the
arch bridge section
Construction
 A cable crane will be built
over the valley for
constructing the steel
structures.
 The crane can deliver a
maximum amount of 40
tonnes of steel parts.
FOUNDATION
In order to set up the
foundations for the bridge in
the difficult terrain, Safe
excavation at both sides of
the valley is being prepared
on a grand scale, drilling for
foundation.
The tallest pier is 137.7m tall,
such a tall structure is
required massive foundation
of 150m*36.5m
Slope stabilization
The side slope of the valley
varies from 43 ̊ to 77 ̊
The slope stabilization
measure are design by the
Indian institute of science.
 After excavation rock bolt of
design length of 4m, 8.5m and
11.5m are installed.
 Porus pipes are inserted to prevent the hydrostatic pressure
Guniting with steel reinforcement is provided to strengthen and
stablize the slope.
Challenges in construction
No proper road network in challenging terrain.
The infrastructure of the area are causing additional problems.
Transportation of the construction equipment.
Sensitive region for terrorist attack.
The design of the main arch requires consideration of a number
of additional parameters, such as fatigue, global stability,
second order effects, composite action, etc.
 It also requires that such a bridge is designed to achieve a
consistent level of reliability for all load cases, and that the
design standards match the construction standards.
The Chenab Bridge will be the biggest / the longest-span / the
highest railway arch bridge ever built in the world.
Conclusions
THANK YOU…

More Related Content

What's hot

Chenab Railway Bridge
Chenab Railway BridgeChenab Railway Bridge
Chenab Railway BridgeDanish Mir
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge Hakkim Shajahan
 
Construction challenge of bridge in hilly areas
 Construction challenge of bridge in hilly areas Construction challenge of bridge in hilly areas
Construction challenge of bridge in hilly areasShashank Naruka
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTATUL SHUKLA
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed trainmechanical Singh
 
Government of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysGovernment of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysSanjitBakshi2
 
Indian Railways - Lifeline of the Nation
Indian Railways - Lifeline of the NationIndian Railways - Lifeline of the Nation
Indian Railways - Lifeline of the NationDINESH GERA
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro raillibin paul
 
10 infrastructure projects in india(Chenab bridge)
10 infrastructure  projects in india(Chenab bridge)10 infrastructure  projects in india(Chenab bridge)
10 infrastructure projects in india(Chenab bridge)Kartik Modi
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasShantanu Patil
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in RailwaysAnupama Jha
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in indiaSourav Paul
 
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway Corriodor
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway CorriodorBULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway Corriodor
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway CorriodorTheerumalai Ga
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresBimenpreet Kaur
 

What's hot (20)

Chenab Railway Bridge
Chenab Railway BridgeChenab Railway Bridge
Chenab Railway Bridge
 
Worldhighestrailwaybridge
Worldhighestrailwaybridge Worldhighestrailwaybridge
Worldhighestrailwaybridge
 
Construction challenge of bridge in hilly areas
 Construction challenge of bridge in hilly areas Construction challenge of bridge in hilly areas
Construction challenge of bridge in hilly areas
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
EASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORTEASTERN PERIPHERAL EXPRESSWAY REPORT
EASTERN PERIPHERAL EXPRESSWAY REPORT
 
seminar presentation on high speed train
 seminar presentation on high speed train seminar presentation on high speed train
seminar presentation on high speed train
 
Government of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysGovernment of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & Highways
 
Indian Railways - Lifeline of the Nation
Indian Railways - Lifeline of the NationIndian Railways - Lifeline of the Nation
Indian Railways - Lifeline of the Nation
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 
10 infrastructure projects in india(Chenab bridge)
10 infrastructure  projects in india(Chenab bridge)10 infrastructure  projects in india(Chenab bridge)
10 infrastructure projects in india(Chenab bridge)
 
PAMBAN BRIDGE
PAMBAN BRIDGEPAMBAN BRIDGE
PAMBAN BRIDGE
 
Construction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly AreasConstruction Challenges For Bridges In Hilly Areas
Construction Challenges For Bridges In Hilly Areas
 
Signalling in Railways
Signalling in RailwaysSignalling in Railways
Signalling in Railways
 
Metro rail in india
Metro rail in indiaMetro rail in india
Metro rail in india
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
BMRCL In-Plant Training Report
BMRCL In-Plant Training ReportBMRCL In-Plant Training Report
BMRCL In-Plant Training Report
 
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway Corriodor
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway CorriodorBULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway Corriodor
BULLET TRAIN - A Preview on India's FIRST fastest High-Speed Railway Corriodor
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
 

Similar to my project on chenab bridge

Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Rajesh Prasad
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
Bhupen hazarika setu
Bhupen hazarika setuBhupen hazarika setu
Bhupen hazarika setuRatulDas36
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET Journal
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+linkASHOK KUMAR
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridgejaiveer singh
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...IRJET Journal
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Parametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingParametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingIRJET Journal
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREbabji syed
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 

Similar to my project on chenab bridge (20)

Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...Future fast track model for new road over bridge spanning over railway yard- ...
Future fast track model for new road over bridge spanning over railway yard- ...
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Bhupen hazarika setu
Bhupen hazarika setuBhupen hazarika setu
Bhupen hazarika setu
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Bandra+worli+sea+link
Bandra+worli+sea+linkBandra+worli+sea+link
Bandra+worli+sea+link
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Munger rail cum road bridge
Munger rail cum road bridgeMunger rail cum road bridge
Munger rail cum road bridge
 
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
 
456.pdf
456.pdf456.pdf
456.pdf
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
Review On Parametric Study Of Performance Of Different Types Of Trusses For P...
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Parametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic LoadingParametric Study on Curved Bridges Subjected to Seismic Loading
Parametric Study on Curved Bridges Subjected to Seismic Loading
 
DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDURE
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 

Recently uploaded

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 

Recently uploaded (20)

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

my project on chenab bridge

  • 1. INSTITUTE OFTECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING BANGALORE – 560097 CERTIFICATE Seminar On CHENAB BRIDGE BY KUMAR Under the Guidance of MS. ……. Asst. Professor,Dept. of CIVIL
  • 2. Indian Railways has undertaken the mega- project of construction of a new railway line in the State of Jammu and Kashmir. The Chenab Bridge is a railway steel and concrete arch bridge under construction between Bakkal and Kauri in the Reasi from Udhampur to Baramulla. INTRODUCTION
  • 4. Deck height (height above river) - 359 m (1,178 ft.) Bridge length - 1,315 m (4,314 ft.) Arch span - 485m (1,532 ft.) Total number of span – 17 Maximum height of pier - 133.7m Description of bridge
  • 5.
  • 6. Travelling in and around the mountainous region has been a great difficulty and dangerous for locals. For better transportation facilities Government of India Constructing a national railway project that will connect J&K with the rest of India. Need for the Chenab rail bridge
  • 7. SITE OF BRIDGE Site is located in mountainous region of Jammu Kashmir.
  • 8. Geology The Chenab Bridge is located in the trickiest section of the Jammu-Udhampur-Srinagar-Baramulla rail route, where the typical geology consists of young Himalaya rock.  poor quality, broken rock with dolomitic limestone and firestone lentils with a silicate content.  Rock class III to V with a strength of 60 to 100MPa and a volume weight of 2.7t/m³ is encountered The RMR (rock mass rating) index amounts to 40 to 60.
  • 9. The planning of this project has been done by WSP group (Finland) and design of arch is done by sub consultant Leonhardt. Indian Railway Standards (IRS Standards), IRC, IS have been used while designing the bridge. The design speed of the railway was set to be 100 km/h and the design life had to be 120 years. Fatigue assessment shall be done as per BS: 5400 Part –10 All conventional railway bridge loads, this bridge has to sustain special blast loads specified by Indian railway Design innovation
  • 10.  Wind loads will be derived using physical topographic models of the site and tests in a wind tunnel laboratory The bridge is designed to resist wind speeds of up to 260kmph. The seismic nature of the project zone was also considered during its design.
  • 11.
  • 12.  Limit state philosophy of design has been decided to be followed as per BS codes.  Provision of long welded rail (LWR) over the bridges and resulting force calculation as per UIC – 774-3R guidelines.  Deformation limits as per comfort criteria of UIC – 776-2R and UIC 776 -3R guidelines.
  • 13. The bridge’s construction principle entails a large bridge arch with access viaducts at each side. The large arch is designed as a 2-fold ribbed arch comprising steel girders with scaffolding braces produced on the spot.  5 bridge pillars for the access viaducts are made of steel and 13 of concrete. The bridge will consist of about 25000 tonnes of steel structures, the main portion of which will be used for the arch bridge section Construction
  • 14.  A cable crane will be built over the valley for constructing the steel structures.  The crane can deliver a maximum amount of 40 tonnes of steel parts.
  • 15. FOUNDATION In order to set up the foundations for the bridge in the difficult terrain, Safe excavation at both sides of the valley is being prepared on a grand scale, drilling for foundation. The tallest pier is 137.7m tall, such a tall structure is required massive foundation of 150m*36.5m
  • 16. Slope stabilization The side slope of the valley varies from 43 ̊ to 77 ̊ The slope stabilization measure are design by the Indian institute of science.  After excavation rock bolt of design length of 4m, 8.5m and 11.5m are installed.
  • 17.  Porus pipes are inserted to prevent the hydrostatic pressure
  • 18. Guniting with steel reinforcement is provided to strengthen and stablize the slope.
  • 19. Challenges in construction No proper road network in challenging terrain. The infrastructure of the area are causing additional problems. Transportation of the construction equipment. Sensitive region for terrorist attack.
  • 20. The design of the main arch requires consideration of a number of additional parameters, such as fatigue, global stability, second order effects, composite action, etc.  It also requires that such a bridge is designed to achieve a consistent level of reliability for all load cases, and that the design standards match the construction standards. The Chenab Bridge will be the biggest / the longest-span / the highest railway arch bridge ever built in the world. Conclusions