Presentation about Under-construction Mahakali Bridge Project in 3 days Training Program on Construction and Quality Control of PSC Bridges चैत्र ११,१२,१३ ,२०७७ organized by
Federal Road Supervision and Monitoring Office, Surkhet
3. 1.Name of the Project
Ministry of Physical Infrastructure and Transport
Department of Roads
Road Improvement Project
Mahakali Bridge project
2. Objective
Transportation of People and Goods from Mahakali
Motorable Bridge
3. Project Cost
Approximate 4300 Million
4.Funded by
Nepal Government
5. Contractor’s Details
M/s Kumar – CFEC JV, Mahendranagar-18, Kanchanpur
Nrs. 3,279,334,491.40 including VAT
4. 6. Date of Start
06th September 2017
7. Date of Completion
27 February 2022
8.Location
5.6 KM Downstream from Sharada Barrage
2.6 KM Upstream from Suspension Bridge
9. Approach Road Details
Left Bank – H01 (E-W Highway)
Right Bank – Across Indian Boarder upto NH125 (Target)
10. Classification of Road
Asian Highway, Class I (Four Lane) Standard
11. Total Length of Bridge
800 M
12. No. of Span
16
13.Bridge Width
23.87 M
14. Width of carriageway
7.5 m*2
15. Cross slope
2.5%(Unidirectional)
5. 16. Foundation
Pile Foundation(408 Piles)
17. Substructure
Abutment –Rectangular
Pier-Circular
18. Superstructure
Pre-stressed Concrete Box Girder (Double Cell Box)
Box Girder Depth 2.75m
19. Type of Bearing POT/PTFE
20.Grade of Concrete
In Superstructure M45
In SubStructure M35
In Foundation M35
21.Grade of Reinforcement Steel
Fe 500
6. 22. Present Status
(a) Mahakali Bridge
- 408/408 Piles Completed
- 17/32 Deck slab completed
- Substructure All (Except Abutment A1/Chadani side)
-15/32 Prestressing /Grouting work completed.
23. Physical Progress
- 60.22% upto 21th February 2021
7. Agenda
Layouting
River Diversion
Construction of Different components of Bridge
Piles ,Pile caps, Pier , Pier caps ,Deck slab
Quality Control & Tests
Concrete Mix Design
PIT &PLT
Prestressing and Grouting Works
Photographic Presentation
8. Layouting
After the Construction Survey , required Control
points are established with reference to Master BM
within permissible error limit.
The location of each structures are worked out in the
XYZ co-ordinate format
Control of
Horizontal position -By TS
Vertical position- By Level Machine
9. Layout Coordinates for Piles @MRB
Layout Points are always verified
with Measuring Tape as well
Layout Co-ordinates from Cad
14. River Diversion
Very important for works in River like Mahakali
Effective diversion can make the work very easy
Helps in Reducing water current nearby piling and
other structures to be constructed
Need to be very careful during site selection for
diversion
23. Bentonite
tank
•Bentonite be soaked for 24 hrs before use
•Level of driling fluid to be maintained 2 m above water level
•Bentonite consumed at MRB piling : For 1400 l=15 bags of Each 50 kg wt
Bentonite suspension for Stabilization of Bore holes
24. Checking Density of Bentonite at Site
•Density of of bentonite suspension shall be 1.03 to 1.10 g/ ml
•Density may rise to 1.25 g/ml
•To be brought down below 1.25 g/ml before concreting
26. 2.Rebar Cage Installation
•Staggered Lap splices for avoiding
more than 50% lap at the same section
•Master ring(16 mm) at required
spacing
•Sufficient Cover blocks
27. Rebar cage for Piles
Cover block maintaining 75 mm cover
Spacing : Vertical=100 D(D=dia of vertical bar)
: Horizontal: 25d(d=dia of horizontal bar)
Is 2911/Part 1-Sec 1
1.5 m
33. As per Dor Specification for Road and Bridges,2073
34. Helpful Notes
Sufficient head to be given during concreting
Plug to be provided to avoid contact between concrete and
the bentonite fluid in bore hole
Provision of spherical ball for blocking tremie pipe opening
in the beginning
Volumetric Check timely ( Gives idea about ht and tremie
pipe removal during concrete)
Provision of depth checking rope for confirmation of Level
of Concrete
Ensure the concrete is done at least 1.5 m above cutoff level
35. Provisions of Longer casing in high current area &
high water table (Here upto 11 m used )
Use of Anti wash admixture improves the viscosity of
concrete and prevent segregation during pile
concreting( At Mrb 0.5% solid by wt of cement)
Workability of concrete to be taken into account
Adopting sequence during piling is very imp(
Vibrations of machines –strata)
36. SomeProblems encounterd
&Solved
Pile collapsed
Bucket stuck
Problem of High water
current
Redone with bentonite im
Provement
Gone for redesign
11 m linear and bentonite
improvement
57. Sheathing Duct Profiling work
The profiling data and
note s mentioned in
design dwg need to be
followed strictly
As far as possible avoid
joints( If in case use of
coupler need to be
used)
Avoid damage
sheathing duct
Profiling affects
Prestressing !!!
66. Helpful Notes
Workability of concrete
Ensure Proper compaction
Take care during end block concrete work(Highly
stressed region)
Adopt falsework design drawing
Be careful during profiling work
Bearing and Expansion joint installation