Project Networking
Operations Management
MBA, Fareast International University, Dhaka, Bangladesh
Basics of Project Network Math Solution
Considerations in Drawing Project Network Diagram
During Forward Progress
 ES time of the first activity will be 0.
 EF time of an activity will be considered as ES time of next activity (EF ES)
 In case of 2 or more EF, the highest EF will be considered as ES
During Backward Progress
 Ending EF, ES will be considered as ending LS, LF as it is.
 LS time of an activity will be considered as LF time of next activity (LS LF)
 In case of 2 or more LS, the lowest LS will be considered as LF of burst activity.
Critical Path Identification
The critical path is the path(s) of project network in which all the activities have zero (0) slack time
Float/Slack Time Calculation
In project management, Float or slack is the amount of time that a task in a project network can be
delayed without delaying subsequent tasks.
Slack/float time, SL= LS-ES or (LS-EF)
Note that,
At starting point, ES, EF and LS, LF will be same values
Math 01
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 7
B Hire Coaches A 3
C Reserve Pool A 2
D Announce Program A 1
E Meet with coaches B, D 3
F Order team Members C 4
G Visiting the Project E, F 5
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 01
Here Given,
Activities Duration
A-----------------7
B-----------------3
C-----------------2
D----------------1
E--------------- -3
F--------------- -4
G----------------5
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF
(7,7+3=10)
LS, LF ES, EF
(10-3=7,10) (10,10+3=13)
ES, EF
ES, EF ES, EF (13,13+5=18)
(0,0+7=7) (7,7+1=8) LS, LF
(13-3=10,13)
ES, EF
LS, LF LS, LF (9,9+4=13) LS, LF
(7-7=0,7) (10-1=9,10) (13, 18)
ES, EF
(7,7+2=9) LS, LF
(13-4=9,13)
LS, LF
(9-2=7,9)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-G= 7+3+3+5=18 weeks
A-D-E-G= 7+1+3+5=16 weeks
A-C-F-G= 7+2+4+5=18 weeks
So, the critical paths are A-B-E-G and A-C-F-G as all of activities of these paths has zero slack time and, in both
paths, the expected project completion time is 18 weeks.
Float/Slack Time Calculation
Activities Slack time (LS – ES)
A --------------------- 0-0= 0
B --------------------- 7-7= 0
C --------------------- 7-7= 0
D --------------------- 9-7= 2
E --------------------- 10-10= 0
F --------------------- 9-9= 0
G -------------------- 13-13= 0
A
B
D
C
E
F
G
Math 02
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 1
B Hire Coaches A 2
C Reserve Pool A 5
D Announce Program B, C 3
E Meet with coaches B 4
F Order team Members C 1
G Visiting the Project D 3
H Plan first Practice E, G, F 1
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 02
Here Given,
Activities Duration
A ------------------ 1
B ------------------ 2
C ------------------ 5
D ------------------ 3
E ------------------ 4
F ------------------ 1
G ----------------- 3
H ----------------- 1
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(1, 1+2=3) (3, 3+4=7)
ES, EF LS, LF LS, LF
(0, 0+1=1) (6-2=4, 6) ES, EF (12-4=8, 12) ES, EF
(6, 6+3=9) (9, 9+3=12) ES, EF
(12, 12+1=13)
LS, LF ES, EF LS, LF LS, LF
(1-1=0, 1) (1, 1+5=6) (9-3=6, 9) ES, EF (12-3= 9, 12) LS, LF
(6, 6+1=7) (12,13)
LS, LF LS, LF
(6-5=1, 6) (12-1=11, 12)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-H=1+2+4+1=8 weeks
A-B-D-G-H=1+2+3+3+1=10 weeks
A-C-D-G-H=1+5+3+3+1=13 weeks
A-C-F-H=1+5+1+1=8 weeks
So, the critical path is A-C-D-G-H as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 13 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A ----------------------0-0= 0
B ----------------------4-1= 3
C ----------------------1-1= 0
D ----------------------6-6= 0
E -----------------------8-3= 5
F ----------------------11-6= 5
G ----------------------9-9= 0
H -----------------------12-12= 0
A
B
D
C
E
G
F
H
Math 03
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 3
B Hire Coaches A 2
C Reserve Pool A 1
D Announce Program A 5
E Meet with coaches B, D 1
F Order team Members C 2
G Visiting the Project E, F 7
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 03
Here Given,
Activities Duration
A ------------------ 3
B ------------------ 2
C ------------------ 1
D ------------------ 5
E ------------------ 1
F ------------------ 2
G ----------------- 7
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(3, 3+2= 5) (8, 8+1= 9)
LS, LF LS, LF
(8-2= 6, 8) (9-1= 8, 9) ES, EF
ES, EF (9, 9+7= 16)
(0, 0+3= 3) ES, EF
(3, 3+5= 8)
LS, LF
LS, LF (9, 16)
(3-3= 0, 3) LS, LF ES, EF
(8-5= 3, 8) (4, 4+2= 6)
ES, EF
(3, 3+1= 4)
LS, LF
(9-2= 7, 9)
LS, LF
(7-1= 6, 7)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-G=3+2+1+7= 13 weeks
A-D-E-G=3+5+1+7= 16 weeks
A-C-F-G=3+1+2+7= 13 weeks
So, the critical path is A-D-E-G as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 16 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A ---------------------- 0-0= 0
B ---------------------- 6-3= 3
C ---------------------- 6-3= 3
D ---------------------- 3-3= 0
E ----------------------- 8-8= 0
F ----------------------- 7-4= 3
G ----------------------- 9-9= 0
G
B
C
D
E
F
A
Math 04
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 3
B Hire Coaches A 2
C Reserve Pool A 7
D Announce Program A 1
E Meet with coaches D, C 11
F Order team Members B 9
G Visiting the Project D 1
H Plan first Practice E, F, G 2
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 04
Here Given,
Activities Duration
A ------------------ 3
B ------------------ 2
C ------------------ 7
D ------------------ 1
E ------------------ 11
F ------------------ 9
G ----------------- 1
H ------------------2 Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(3, 3+2= 5) (5, 5+9= 14)
LS, LF
LS, LF (21-9= 12, 21)
(12-2= 10, 12)
ES, EF ES, EF ES, EF ES, EF
(0, 0+3= 3) (3, 3+1= 4) (4, 4+1= 5) (21, 21+2= 23)
LS, LF LS, LF LS, LF LS, LF
(3-3= 0, 3) (10-1= 9, 10) (21-1= 20, 21) (21, 23)
ES, EF ES, EF
(3, 3+7= 10) (10, 10+11= 21)
LS, LF LS, LF
(10-7= 3, 10) (21-11= 10, 21)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-F-H=3+2+9+2= 16 weeks
A-D-G-H=3+1+1+2=7 weeks
A-D-E-H=3+1+11+2=17 weeks
A-C-E-H=3+7+11+2= 23 weeks
So, the critical path is A-C-E-H as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 23 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A 0-0= 0
B 10-3= 7
C 3-3= 0
D 9-3= 6
E 10-10 = 0
F 12-5= 7
G 20-4= 16
H 21-21= 0
A
B
F
H
C E
GD

Project network math solution

  • 1.
    Project Networking Operations Management MBA,Fareast International University, Dhaka, Bangladesh Basics of Project Network Math Solution Considerations in Drawing Project Network Diagram During Forward Progress  ES time of the first activity will be 0.  EF time of an activity will be considered as ES time of next activity (EF ES)  In case of 2 or more EF, the highest EF will be considered as ES During Backward Progress  Ending EF, ES will be considered as ending LS, LF as it is.  LS time of an activity will be considered as LF time of next activity (LS LF)  In case of 2 or more LS, the lowest LS will be considered as LF of burst activity. Critical Path Identification The critical path is the path(s) of project network in which all the activities have zero (0) slack time Float/Slack Time Calculation In project management, Float or slack is the amount of time that a task in a project network can be delayed without delaying subsequent tasks. Slack/float time, SL= LS-ES or (LS-EF) Note that, At starting point, ES, EF and LS, LF will be same values
  • 2.
    Math 01 Activity DescriptionImmediate Predecessor Time (Weeks) A Meet With board - 7 B Hire Coaches A 3 C Reserve Pool A 2 D Announce Program A 1 E Meet with coaches B, D 3 F Order team Members C 4 G Visiting the Project E, F 5 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 3.
    Solution to theMath Problem 01 Here Given, Activities Duration A-----------------7 B-----------------3 C-----------------2 D----------------1 E--------------- -3 F--------------- -4 G----------------5 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF (7,7+3=10) LS, LF ES, EF (10-3=7,10) (10,10+3=13) ES, EF ES, EF ES, EF (13,13+5=18) (0,0+7=7) (7,7+1=8) LS, LF (13-3=10,13) ES, EF LS, LF LS, LF (9,9+4=13) LS, LF (7-7=0,7) (10-1=9,10) (13, 18) ES, EF (7,7+2=9) LS, LF (13-4=9,13) LS, LF (9-2=7,9) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-G= 7+3+3+5=18 weeks A-D-E-G= 7+1+3+5=16 weeks A-C-F-G= 7+2+4+5=18 weeks So, the critical paths are A-B-E-G and A-C-F-G as all of activities of these paths has zero slack time and, in both paths, the expected project completion time is 18 weeks. Float/Slack Time Calculation Activities Slack time (LS – ES) A --------------------- 0-0= 0 B --------------------- 7-7= 0 C --------------------- 7-7= 0 D --------------------- 9-7= 2 E --------------------- 10-10= 0 F --------------------- 9-9= 0 G -------------------- 13-13= 0 A B D C E F G
  • 4.
    Math 02 Activity DescriptionImmediate Predecessor Time (Weeks) A Meet With board - 1 B Hire Coaches A 2 C Reserve Pool A 5 D Announce Program B, C 3 E Meet with coaches B 4 F Order team Members C 1 G Visiting the Project D 3 H Plan first Practice E, G, F 1 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 5.
    Solution to theMath Problem 02 Here Given, Activities Duration A ------------------ 1 B ------------------ 2 C ------------------ 5 D ------------------ 3 E ------------------ 4 F ------------------ 1 G ----------------- 3 H ----------------- 1 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (1, 1+2=3) (3, 3+4=7) ES, EF LS, LF LS, LF (0, 0+1=1) (6-2=4, 6) ES, EF (12-4=8, 12) ES, EF (6, 6+3=9) (9, 9+3=12) ES, EF (12, 12+1=13) LS, LF ES, EF LS, LF LS, LF (1-1=0, 1) (1, 1+5=6) (9-3=6, 9) ES, EF (12-3= 9, 12) LS, LF (6, 6+1=7) (12,13) LS, LF LS, LF (6-5=1, 6) (12-1=11, 12) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-H=1+2+4+1=8 weeks A-B-D-G-H=1+2+3+3+1=10 weeks A-C-D-G-H=1+5+3+3+1=13 weeks A-C-F-H=1+5+1+1=8 weeks So, the critical path is A-C-D-G-H as all of activities of this path has zero slack time and, in this path, the expected project completion time is 13 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A ----------------------0-0= 0 B ----------------------4-1= 3 C ----------------------1-1= 0 D ----------------------6-6= 0 E -----------------------8-3= 5 F ----------------------11-6= 5 G ----------------------9-9= 0 H -----------------------12-12= 0 A B D C E G F H
  • 6.
    Math 03 Activity DescriptionImmediate Predecessor Time (Weeks) A Meet With board - 3 B Hire Coaches A 2 C Reserve Pool A 1 D Announce Program A 5 E Meet with coaches B, D 1 F Order team Members C 2 G Visiting the Project E, F 7 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 7.
    Solution to theMath Problem 03 Here Given, Activities Duration A ------------------ 3 B ------------------ 2 C ------------------ 1 D ------------------ 5 E ------------------ 1 F ------------------ 2 G ----------------- 7 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (3, 3+2= 5) (8, 8+1= 9) LS, LF LS, LF (8-2= 6, 8) (9-1= 8, 9) ES, EF ES, EF (9, 9+7= 16) (0, 0+3= 3) ES, EF (3, 3+5= 8) LS, LF LS, LF (9, 16) (3-3= 0, 3) LS, LF ES, EF (8-5= 3, 8) (4, 4+2= 6) ES, EF (3, 3+1= 4) LS, LF (9-2= 7, 9) LS, LF (7-1= 6, 7) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-G=3+2+1+7= 13 weeks A-D-E-G=3+5+1+7= 16 weeks A-C-F-G=3+1+2+7= 13 weeks So, the critical path is A-D-E-G as all of activities of this path has zero slack time and, in this path, the expected project completion time is 16 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A ---------------------- 0-0= 0 B ---------------------- 6-3= 3 C ---------------------- 6-3= 3 D ---------------------- 3-3= 0 E ----------------------- 8-8= 0 F ----------------------- 7-4= 3 G ----------------------- 9-9= 0 G B C D E F A
  • 8.
    Math 04 Activity DescriptionImmediate Predecessor Time (Weeks) A Meet With board - 3 B Hire Coaches A 2 C Reserve Pool A 7 D Announce Program A 1 E Meet with coaches D, C 11 F Order team Members B 9 G Visiting the Project D 1 H Plan first Practice E, F, G 2 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 9.
    Solution to theMath Problem 04 Here Given, Activities Duration A ------------------ 3 B ------------------ 2 C ------------------ 7 D ------------------ 1 E ------------------ 11 F ------------------ 9 G ----------------- 1 H ------------------2 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (3, 3+2= 5) (5, 5+9= 14) LS, LF LS, LF (21-9= 12, 21) (12-2= 10, 12) ES, EF ES, EF ES, EF ES, EF (0, 0+3= 3) (3, 3+1= 4) (4, 4+1= 5) (21, 21+2= 23) LS, LF LS, LF LS, LF LS, LF (3-3= 0, 3) (10-1= 9, 10) (21-1= 20, 21) (21, 23) ES, EF ES, EF (3, 3+7= 10) (10, 10+11= 21) LS, LF LS, LF (10-7= 3, 10) (21-11= 10, 21) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-F-H=3+2+9+2= 16 weeks A-D-G-H=3+1+1+2=7 weeks A-D-E-H=3+1+11+2=17 weeks A-C-E-H=3+7+11+2= 23 weeks So, the critical path is A-C-E-H as all of activities of this path has zero slack time and, in this path, the expected project completion time is 23 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A 0-0= 0 B 10-3= 7 C 3-3= 0 D 9-3= 6 E 10-10 = 0 F 12-5= 7 G 20-4= 16 H 21-21= 0 A B F H C E GD