SlideShare a Scribd company logo
Project Networking
Operations Management
MBA, Fareast International University, Dhaka, Bangladesh
Basics of Project Network Math Solution
Considerations in Drawing Project Network Diagram
During Forward Progress
 ES time of the first activity will be 0.
 EF time of an activity will be considered as ES time of next activity (EF ES)
 In case of 2 or more EF, the highest EF will be considered as ES
During Backward Progress
 Ending EF, ES will be considered as ending LS, LF as it is.
 LS time of an activity will be considered as LF time of next activity (LS LF)
 In case of 2 or more LS, the lowest LS will be considered as LF of burst activity.
Critical Path Identification
The critical path is the path(s) of project network in which all the activities have zero (0) slack time
Float/Slack Time Calculation
In project management, Float or slack is the amount of time that a task in a project network can be
delayed without delaying subsequent tasks.
Slack/float time, SL= LS-ES or (LS-EF)
Note that,
At starting point, ES, EF and LS, LF will be same values
Math 01
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 7
B Hire Coaches A 3
C Reserve Pool A 2
D Announce Program A 1
E Meet with coaches B, D 3
F Order team Members C 4
G Visiting the Project E, F 5
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 01
Here Given,
Activities Duration
A-----------------7
B-----------------3
C-----------------2
D----------------1
E--------------- -3
F--------------- -4
G----------------5
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF
(7,7+3=10)
LS, LF ES, EF
(10-3=7,10) (10,10+3=13)
ES, EF
ES, EF ES, EF (13,13+5=18)
(0,0+7=7) (7,7+1=8) LS, LF
(13-3=10,13)
ES, EF
LS, LF LS, LF (9,9+4=13) LS, LF
(7-7=0,7) (10-1=9,10) (13, 18)
ES, EF
(7,7+2=9) LS, LF
(13-4=9,13)
LS, LF
(9-2=7,9)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-G= 7+3+3+5=18 weeks
A-D-E-G= 7+1+3+5=16 weeks
A-C-F-G= 7+2+4+5=18 weeks
So, the critical paths are A-B-E-G and A-C-F-G as all of activities of these paths has zero slack time and, in both
paths, the expected project completion time is 18 weeks.
Float/Slack Time Calculation
Activities Slack time (LS – ES)
A --------------------- 0-0= 0
B --------------------- 7-7= 0
C --------------------- 7-7= 0
D --------------------- 9-7= 2
E --------------------- 10-10= 0
F --------------------- 9-9= 0
G -------------------- 13-13= 0
A
B
D
C
E
F
G
Math 02
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 1
B Hire Coaches A 2
C Reserve Pool A 5
D Announce Program B, C 3
E Meet with coaches B 4
F Order team Members C 1
G Visiting the Project D 3
H Plan first Practice E, G, F 1
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 02
Here Given,
Activities Duration
A ------------------ 1
B ------------------ 2
C ------------------ 5
D ------------------ 3
E ------------------ 4
F ------------------ 1
G ----------------- 3
H ----------------- 1
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(1, 1+2=3) (3, 3+4=7)
ES, EF LS, LF LS, LF
(0, 0+1=1) (6-2=4, 6) ES, EF (12-4=8, 12) ES, EF
(6, 6+3=9) (9, 9+3=12) ES, EF
(12, 12+1=13)
LS, LF ES, EF LS, LF LS, LF
(1-1=0, 1) (1, 1+5=6) (9-3=6, 9) ES, EF (12-3= 9, 12) LS, LF
(6, 6+1=7) (12,13)
LS, LF LS, LF
(6-5=1, 6) (12-1=11, 12)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-H=1+2+4+1=8 weeks
A-B-D-G-H=1+2+3+3+1=10 weeks
A-C-D-G-H=1+5+3+3+1=13 weeks
A-C-F-H=1+5+1+1=8 weeks
So, the critical path is A-C-D-G-H as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 13 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A ----------------------0-0= 0
B ----------------------4-1= 3
C ----------------------1-1= 0
D ----------------------6-6= 0
E -----------------------8-3= 5
F ----------------------11-6= 5
G ----------------------9-9= 0
H -----------------------12-12= 0
A
B
D
C
E
G
F
H
Math 03
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 3
B Hire Coaches A 2
C Reserve Pool A 1
D Announce Program A 5
E Meet with coaches B, D 1
F Order team Members C 2
G Visiting the Project E, F 7
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 03
Here Given,
Activities Duration
A ------------------ 3
B ------------------ 2
C ------------------ 1
D ------------------ 5
E ------------------ 1
F ------------------ 2
G ----------------- 7
Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(3, 3+2= 5) (8, 8+1= 9)
LS, LF LS, LF
(8-2= 6, 8) (9-1= 8, 9) ES, EF
ES, EF (9, 9+7= 16)
(0, 0+3= 3) ES, EF
(3, 3+5= 8)
LS, LF
LS, LF (9, 16)
(3-3= 0, 3) LS, LF ES, EF
(8-5= 3, 8) (4, 4+2= 6)
ES, EF
(3, 3+1= 4)
LS, LF
(9-2= 7, 9)
LS, LF
(7-1= 6, 7)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-E-G=3+2+1+7= 13 weeks
A-D-E-G=3+5+1+7= 16 weeks
A-C-F-G=3+1+2+7= 13 weeks
So, the critical path is A-D-E-G as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 16 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A ---------------------- 0-0= 0
B ---------------------- 6-3= 3
C ---------------------- 6-3= 3
D ---------------------- 3-3= 0
E ----------------------- 8-8= 0
F ----------------------- 7-4= 3
G ----------------------- 9-9= 0
G
B
C
D
E
F
A
Math 04
Activity Description Immediate Predecessor Time (Weeks)
A Meet With board - 3
B Hire Coaches A 2
C Reserve Pool A 7
D Announce Program A 1
E Meet with coaches D, C 11
F Order team Members B 9
G Visiting the Project D 1
H Plan first Practice E, F, G 2
Queries:
a. Draw a project network.
b. Find out ES, EF and LS, LF.
c. Find out the critical path and expected project completion time.
d. Find out the slack time.
Solution to the Math Problem 04
Here Given,
Activities Duration
A ------------------ 3
B ------------------ 2
C ------------------ 7
D ------------------ 1
E ------------------ 11
F ------------------ 9
G ----------------- 1
H ------------------2 Here in Network Diagram,
ES=Earliest Start Time.
EF=Earliest Finish Time.
LS=Latest Start Time.
LF=Latest Finish Time.
ES, EF ES, EF
(3, 3+2= 5) (5, 5+9= 14)
LS, LF
LS, LF (21-9= 12, 21)
(12-2= 10, 12)
ES, EF ES, EF ES, EF ES, EF
(0, 0+3= 3) (3, 3+1= 4) (4, 4+1= 5) (21, 21+2= 23)
LS, LF LS, LF LS, LF LS, LF
(3-3= 0, 3) (10-1= 9, 10) (21-1= 20, 21) (21, 23)
ES, EF ES, EF
(3, 3+7= 10) (10, 10+11= 21)
LS, LF LS, LF
(10-7= 3, 10) (21-11= 10, 21)
Critical Path & Expected Project Completion Time Calculation
Different Path Completion time(week)
A-B-F-H=3+2+9+2= 16 weeks
A-D-G-H=3+1+1+2=7 weeks
A-D-E-H=3+1+11+2=17 weeks
A-C-E-H=3+7+11+2= 23 weeks
So, the critical path is A-C-E-H as all of activities of this path has zero slack time and, in this path, the expected
project completion time is 23 weeks.
Float/Slack Time Calculation
Activities Slack (LS – ES)
A 0-0= 0
B 10-3= 7
C 3-3= 0
D 9-3= 6
E 10-10 = 0
F 12-5= 7
G 20-4= 16
H 21-21= 0
A
B
F
H
C E
GD

More Related Content

What's hot

Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
mairemic
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
Anand Subramaniam
 
Project Development
Project Development Project Development
Project Development
Jo Balucanag - Bitonio
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
Jeff Hilton
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
Kyle Hammon
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
project management
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
dmdk12
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
Mariam Bedraoui
 
Project Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation SlidesProject Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation Slides
SlideTeam
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
Rodolfo Siles
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
Ishan Gandhi
 
Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)
Kamel Attar
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
Mohamed Loey
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
C K Vishwakarma
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
Anirban Chakraborty
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Simplilearn
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project managementKinshook Chaturvedi
 

What's hot (20)

Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 
Project Development
Project Development Project Development
Project Development
 
Critical Path Ppt
Critical Path PptCritical Path Ppt
Critical Path Ppt
 
Project Management Plan
Project Management PlanProject Management Plan
Project Management Plan
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
Project Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation SlidesProject Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation Slides
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Network Techniques for Project Management
Network Techniques for Project ManagementNetwork Techniques for Project Management
Network Techniques for Project Management
 
Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)
 
PMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management ProcessesPMP Lecture 3: Project Management Processes
PMP Lecture 3: Project Management Processes
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project management
 

Similar to Project network math solution

470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
Nitin137794
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review Technique
Jomari Gingo Selibio
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
UpulHettiarachchi5
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
project management
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
jillmitchell8778
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
cairo university
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Vignesh Jayakumar
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
maggieget
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
GovadaDhana
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
drennanmicah
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
jillmitchell8778
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
LJay7
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
MuhammadAbubakar114879
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Chandi Mohanty
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
Ahmed Gamal
 

Similar to Project network math solution (20)

470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
470614683-CHAPTER-7-Project-Management-and-Network-Analysis-ppt.ppt
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Critical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review TechniqueCritical Path Method/ Program Evaluation and Review Technique
Critical Path Method/ Program Evaluation and Review Technique
 
606CPM1.ppt
606CPM1.ppt606CPM1.ppt
606CPM1.ppt
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
 
Management Network Lec 3
Management Network Lec 3Management Network Lec 3
Management Network Lec 3
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM Chapter 5 - PERT-CPM
Chapter 5 - PERT-CPM
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
CPM.pptx
CPM.pptxCPM.pptx
CPM.pptx
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 

More from Md.Nazrul Islam

Rules of word & sentence stress and intonation
Rules of word & sentence stress and intonationRules of word & sentence stress and intonation
Rules of word & sentence stress and intonation
Md.Nazrul Islam
 
Leaf curl diseases chilli
Leaf curl diseases chilliLeaf curl diseases chilli
Leaf curl diseases chilli
Md.Nazrul Islam
 
Terminology
TerminologyTerminology
Terminology
Md.Nazrul Islam
 
Terminology
TerminologyTerminology
Terminology
Md.Nazrul Islam
 
Valuation of Bond and Shares
Valuation of Bond and SharesValuation of Bond and Shares
Valuation of Bond and Shares
Md.Nazrul Islam
 
Studdy planner
Studdy plannerStuddy planner
Studdy planner
Md.Nazrul Islam
 
ToT on soft skills
ToT on soft skillsToT on soft skills
ToT on soft skills
Md.Nazrul Islam
 
Pronounciation of regular verbs ending with 'ed'
Pronounciation of regular verbs ending with 'ed'Pronounciation of regular verbs ending with 'ed'
Pronounciation of regular verbs ending with 'ed'
Md.Nazrul Islam
 
Rules of syllablication
Rules of syllablicationRules of syllablication
Rules of syllablication
Md.Nazrul Islam
 
Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004
Md.Nazrul Islam
 
Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004
Md.Nazrul Islam
 
Assignment on Essentials of a Successful Trade Union
Assignment on Essentials of a Successful Trade UnionAssignment on Essentials of a Successful Trade Union
Assignment on Essentials of a Successful Trade Union
Md.Nazrul Islam
 
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
Md.Nazrul Islam
 
Presentation industrial relations nazrul_18203004
Presentation industrial relations nazrul_18203004Presentation industrial relations nazrul_18203004
Presentation industrial relations nazrul_18203004
Md.Nazrul Islam
 

More from Md.Nazrul Islam (14)

Rules of word & sentence stress and intonation
Rules of word & sentence stress and intonationRules of word & sentence stress and intonation
Rules of word & sentence stress and intonation
 
Leaf curl diseases chilli
Leaf curl diseases chilliLeaf curl diseases chilli
Leaf curl diseases chilli
 
Terminology
TerminologyTerminology
Terminology
 
Terminology
TerminologyTerminology
Terminology
 
Valuation of Bond and Shares
Valuation of Bond and SharesValuation of Bond and Shares
Valuation of Bond and Shares
 
Studdy planner
Studdy plannerStuddy planner
Studdy planner
 
ToT on soft skills
ToT on soft skillsToT on soft skills
ToT on soft skills
 
Pronounciation of regular verbs ending with 'ed'
Pronounciation of regular verbs ending with 'ed'Pronounciation of regular verbs ending with 'ed'
Pronounciation of regular verbs ending with 'ed'
 
Rules of syllablication
Rules of syllablicationRules of syllablication
Rules of syllablication
 
Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004
 
Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004Assignment scm rmg factories_id-18203004
Assignment scm rmg factories_id-18203004
 
Assignment on Essentials of a Successful Trade Union
Assignment on Essentials of a Successful Trade UnionAssignment on Essentials of a Successful Trade Union
Assignment on Essentials of a Successful Trade Union
 
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
The Practice of `Just-in-Time' Production Model in Toyota Automobile Company ...
 
Presentation industrial relations nazrul_18203004
Presentation industrial relations nazrul_18203004Presentation industrial relations nazrul_18203004
Presentation industrial relations nazrul_18203004
 

Recently uploaded

C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
mulvey2
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
EduSkills OECD
 
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
National Information Standards Organization (NISO)
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Fajar Baskoro
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
RamseyBerglund
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
Steve Thomason
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
National Information Standards Organization (NISO)
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
S. Raj Kumar
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Vivekanand Anglo Vedic Academy
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
zuzanka
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
Nicholas Montgomery
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
danielkiash986
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
melliereed
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
سمير بسيوني
 

Recently uploaded (20)

C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptxC1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
C1 Rubenstein AP HuG xxxxxxxxxxxxxx.pptx
 
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptxBeyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
Beyond Degrees - Empowering the Workforce in the Context of Skills-First.pptx
 
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
Jemison, MacLaughlin, and Majumder "Broadening Pathways for Editors and Authors"
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
 
Pengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptxPengantar Penggunaan Flutter - Dart programming language1.pptx
Pengantar Penggunaan Flutter - Dart programming language1.pptx
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
 
A Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two HeartsA Visual Guide to 1 Samuel | A Tale of Two Hearts
A Visual Guide to 1 Samuel | A Tale of Two Hearts
 
Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"Benner "Expanding Pathways to Publishing Careers"
Benner "Expanding Pathways to Publishing Careers"
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
 
SWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptxSWOT analysis in the project Keeping the Memory @live.pptx
SWOT analysis in the project Keeping the Memory @live.pptx
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
writing about opinions about Australia the movie
writing about opinions about Australia the moviewriting about opinions about Australia the movie
writing about opinions about Australia the movie
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
 
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdfمصحف القراءات العشر   أعد أحرف الخلاف سمير بسيوني.pdf
مصحف القراءات العشر أعد أحرف الخلاف سمير بسيوني.pdf
 

Project network math solution

  • 1. Project Networking Operations Management MBA, Fareast International University, Dhaka, Bangladesh Basics of Project Network Math Solution Considerations in Drawing Project Network Diagram During Forward Progress  ES time of the first activity will be 0.  EF time of an activity will be considered as ES time of next activity (EF ES)  In case of 2 or more EF, the highest EF will be considered as ES During Backward Progress  Ending EF, ES will be considered as ending LS, LF as it is.  LS time of an activity will be considered as LF time of next activity (LS LF)  In case of 2 or more LS, the lowest LS will be considered as LF of burst activity. Critical Path Identification The critical path is the path(s) of project network in which all the activities have zero (0) slack time Float/Slack Time Calculation In project management, Float or slack is the amount of time that a task in a project network can be delayed without delaying subsequent tasks. Slack/float time, SL= LS-ES or (LS-EF) Note that, At starting point, ES, EF and LS, LF will be same values
  • 2. Math 01 Activity Description Immediate Predecessor Time (Weeks) A Meet With board - 7 B Hire Coaches A 3 C Reserve Pool A 2 D Announce Program A 1 E Meet with coaches B, D 3 F Order team Members C 4 G Visiting the Project E, F 5 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 3. Solution to the Math Problem 01 Here Given, Activities Duration A-----------------7 B-----------------3 C-----------------2 D----------------1 E--------------- -3 F--------------- -4 G----------------5 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF (7,7+3=10) LS, LF ES, EF (10-3=7,10) (10,10+3=13) ES, EF ES, EF ES, EF (13,13+5=18) (0,0+7=7) (7,7+1=8) LS, LF (13-3=10,13) ES, EF LS, LF LS, LF (9,9+4=13) LS, LF (7-7=0,7) (10-1=9,10) (13, 18) ES, EF (7,7+2=9) LS, LF (13-4=9,13) LS, LF (9-2=7,9) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-G= 7+3+3+5=18 weeks A-D-E-G= 7+1+3+5=16 weeks A-C-F-G= 7+2+4+5=18 weeks So, the critical paths are A-B-E-G and A-C-F-G as all of activities of these paths has zero slack time and, in both paths, the expected project completion time is 18 weeks. Float/Slack Time Calculation Activities Slack time (LS – ES) A --------------------- 0-0= 0 B --------------------- 7-7= 0 C --------------------- 7-7= 0 D --------------------- 9-7= 2 E --------------------- 10-10= 0 F --------------------- 9-9= 0 G -------------------- 13-13= 0 A B D C E F G
  • 4. Math 02 Activity Description Immediate Predecessor Time (Weeks) A Meet With board - 1 B Hire Coaches A 2 C Reserve Pool A 5 D Announce Program B, C 3 E Meet with coaches B 4 F Order team Members C 1 G Visiting the Project D 3 H Plan first Practice E, G, F 1 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 5. Solution to the Math Problem 02 Here Given, Activities Duration A ------------------ 1 B ------------------ 2 C ------------------ 5 D ------------------ 3 E ------------------ 4 F ------------------ 1 G ----------------- 3 H ----------------- 1 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (1, 1+2=3) (3, 3+4=7) ES, EF LS, LF LS, LF (0, 0+1=1) (6-2=4, 6) ES, EF (12-4=8, 12) ES, EF (6, 6+3=9) (9, 9+3=12) ES, EF (12, 12+1=13) LS, LF ES, EF LS, LF LS, LF (1-1=0, 1) (1, 1+5=6) (9-3=6, 9) ES, EF (12-3= 9, 12) LS, LF (6, 6+1=7) (12,13) LS, LF LS, LF (6-5=1, 6) (12-1=11, 12) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-H=1+2+4+1=8 weeks A-B-D-G-H=1+2+3+3+1=10 weeks A-C-D-G-H=1+5+3+3+1=13 weeks A-C-F-H=1+5+1+1=8 weeks So, the critical path is A-C-D-G-H as all of activities of this path has zero slack time and, in this path, the expected project completion time is 13 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A ----------------------0-0= 0 B ----------------------4-1= 3 C ----------------------1-1= 0 D ----------------------6-6= 0 E -----------------------8-3= 5 F ----------------------11-6= 5 G ----------------------9-9= 0 H -----------------------12-12= 0 A B D C E G F H
  • 6. Math 03 Activity Description Immediate Predecessor Time (Weeks) A Meet With board - 3 B Hire Coaches A 2 C Reserve Pool A 1 D Announce Program A 5 E Meet with coaches B, D 1 F Order team Members C 2 G Visiting the Project E, F 7 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 7. Solution to the Math Problem 03 Here Given, Activities Duration A ------------------ 3 B ------------------ 2 C ------------------ 1 D ------------------ 5 E ------------------ 1 F ------------------ 2 G ----------------- 7 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (3, 3+2= 5) (8, 8+1= 9) LS, LF LS, LF (8-2= 6, 8) (9-1= 8, 9) ES, EF ES, EF (9, 9+7= 16) (0, 0+3= 3) ES, EF (3, 3+5= 8) LS, LF LS, LF (9, 16) (3-3= 0, 3) LS, LF ES, EF (8-5= 3, 8) (4, 4+2= 6) ES, EF (3, 3+1= 4) LS, LF (9-2= 7, 9) LS, LF (7-1= 6, 7) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-E-G=3+2+1+7= 13 weeks A-D-E-G=3+5+1+7= 16 weeks A-C-F-G=3+1+2+7= 13 weeks So, the critical path is A-D-E-G as all of activities of this path has zero slack time and, in this path, the expected project completion time is 16 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A ---------------------- 0-0= 0 B ---------------------- 6-3= 3 C ---------------------- 6-3= 3 D ---------------------- 3-3= 0 E ----------------------- 8-8= 0 F ----------------------- 7-4= 3 G ----------------------- 9-9= 0 G B C D E F A
  • 8. Math 04 Activity Description Immediate Predecessor Time (Weeks) A Meet With board - 3 B Hire Coaches A 2 C Reserve Pool A 7 D Announce Program A 1 E Meet with coaches D, C 11 F Order team Members B 9 G Visiting the Project D 1 H Plan first Practice E, F, G 2 Queries: a. Draw a project network. b. Find out ES, EF and LS, LF. c. Find out the critical path and expected project completion time. d. Find out the slack time.
  • 9. Solution to the Math Problem 04 Here Given, Activities Duration A ------------------ 3 B ------------------ 2 C ------------------ 7 D ------------------ 1 E ------------------ 11 F ------------------ 9 G ----------------- 1 H ------------------2 Here in Network Diagram, ES=Earliest Start Time. EF=Earliest Finish Time. LS=Latest Start Time. LF=Latest Finish Time. ES, EF ES, EF (3, 3+2= 5) (5, 5+9= 14) LS, LF LS, LF (21-9= 12, 21) (12-2= 10, 12) ES, EF ES, EF ES, EF ES, EF (0, 0+3= 3) (3, 3+1= 4) (4, 4+1= 5) (21, 21+2= 23) LS, LF LS, LF LS, LF LS, LF (3-3= 0, 3) (10-1= 9, 10) (21-1= 20, 21) (21, 23) ES, EF ES, EF (3, 3+7= 10) (10, 10+11= 21) LS, LF LS, LF (10-7= 3, 10) (21-11= 10, 21) Critical Path & Expected Project Completion Time Calculation Different Path Completion time(week) A-B-F-H=3+2+9+2= 16 weeks A-D-G-H=3+1+1+2=7 weeks A-D-E-H=3+1+11+2=17 weeks A-C-E-H=3+7+11+2= 23 weeks So, the critical path is A-C-E-H as all of activities of this path has zero slack time and, in this path, the expected project completion time is 23 weeks. Float/Slack Time Calculation Activities Slack (LS – ES) A 0-0= 0 B 10-3= 7 C 3-3= 0 D 9-3= 6 E 10-10 = 0 F 12-5= 7 G 20-4= 16 H 21-21= 0 A B F H C E GD