ANALYSIS OF FACTORS CONTRIBUTING DELAYS AND CLAIMS IN
CONSTRUCTION PROJECTS
Ketki S. Kamble1
, A. R. Kambekar2
1
PG. Student, Const. Management, 2
Assistant Professor, CED, SPCE Andheri (W), Mumbai 400058, Maharashtra,
ketki08@gmail.com
Abstract
Construction activities are the most competitive and it involves higher risk with minimum profitability due to competition.
Construction of any infrastructural work involves complex management skills related to manpower, materials, plant, machineries,
new technologies etc. It also involves many agencies interdependent on each other like the planners, structural and functional
designers including various types of specialized engineers and it also includes support of financial institutions, insurers, contractors
and specialized contractors. As there are prevailing labour bye laws it needs special care of their well beings. In such kind of complex
and intense framework some disputes is quite natural between the agencies involved in such activities which further results in claims
management as the unsettled dispute finally leads to financial claims. Higher incidences of disputes are generally reported from the
construction contract. Even if there is an appropriate understanding of construction contract clauses from the agencies in the
agreement yet claims seems to be a major crisis in the construction sector. The research reported in this paper aims in identifying the
major factors responsible of project delay that may give rise to claims for delay damages. The in this paper research mainly highlights
on finding the major components of claims with perspective of contractor for delay damages.
Keywords: Claims, delay, damages, construction industry, disputes.
--------------------------------------------------------------------***---------------------------------------------------------------------
1. INTRODUCTION
Claims as per Hughes [1] “It is a demand, a request or
application for something to which a contractor considers,
believes or contends he is entitled but in respect of which
agreement has not yet been reached”. As per Harris [2] the
major five causes of disputes in Asian construction projects
are as follows:
• Failure to make interim awards on extensions of time
and to give associated compensation
• Unrealistic risk transfer from employers to
contractors
• Conflicting party interests
• An unrealistic contract completion date being defined
at tender stage
• Incomplete design information or employer
requirements.
In general it was reported in literature that the construction
sector involves disputes from the sources like changes which
includes variation, alteration, addition, deletion, delays and
suspensions, differing site conditions, unjust enrichment by
owners. It was also observed that there are five potential areas
which can give rise to disputes: document errors, estimation
errors, change in conditions, implied promises and agencies
involved. Claims however fall under two major categories
based on their occurrence i.e. during (i) execution of contract
and (ii) administration of contract. Execution of contract
includes claims due to change in design and drawing, delays in
handing over site/issuance of drawings/getting clearance
certificate from appropriate authorities, claims due to original
scope of work change, claims due to differing site conditions
and claims due to variation in methodology. Similarly during
administration of contract claims may be due to delay in
payment of running account bills and claims due to
foreclosure/termination of contract. Similarly delays in
schedules of construction projects are one of the most
common types of disputes in the construction industry. The
client and contractor works for a common objective i.e. to
complete the project within scheduled time as well as cost.
Time overrun is the most common failure of objective that in
turn leads to cost overrun and hence failure in the objective of
timely completion leads to failure of overall project budget
which ultimately gives rise to disputes. The reasons for delays
could be caused by client, contractor, force majeure i.e. act of
God, change in laws, rules and regulations, improper co-
ordination between client and contractors, non-availability of
required skilled labour, non-availability of required special
material, differing site conditions, non-issuance of working
drawing and changes in work leading to change in
methodology. Delays can be further classified as excusable or
non-excusable. Some of the practical cases of non-excusable
delays are incompetent sub-contractor, financial incompetency
of the contractor, labour disputes hindering work progress,
poor workmanship leading to rework, poor material quality
and delay in handing over the site by client and excusable
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 391
delay includes sudden floods, natural calamities like
earthquake, tsunami etc. riots, labour strike, non-foreseeable
situation. Critical delay are defined as a delay in any given
activity which results in delay of total project and non-critical
delay is defined as delays which may not upset total time
frame of the contract [1].
This paper mainly focuses on delay damage claims related to
additional cost incurred by the contractor due to delay caused
by the client. Evaluation of delay damages are when a
contractor bids for a tender, a number of factors are considered
apart from the labour, material and equipment that are
required to execute the work. In tender the duration required to
complete the work is generally mentioned and hence the
contractor quotes accordingly. The quote includes material
cost, labour cost, plant and machinery cost, shuttering
material, human resource cost, financial cost, site overheads
and above all profit. In an event of prolongation of contract,
the major factors that are affected are additional overheads,
plant and machinery, labour and material cost, loss of
productivity, loss of profit, loss of new business opportunities
and early mobilization.
2. METHODOLOGY ADOPTED
Following methodology is adopted for this research work.
This includes identification of claims that occur, factors
responsible for delay, prolongation claim if any, focus on
factors that are affected due to delay in completion the project,
factors mostly considered while setting up prolongation claim,
ranking based on case studies to understand the major factor
affecting the delay damages claim finally recommendations
based on the study. The delays which occur in construction
projects are due to various reasons. Analysis of three projects
have been carried out details of the same is given in Table 1.
Project cost, value of claims and claim in % of project cost for
(i) construction of mall in Mumbai, (ii) construction of hotel
and casino in Goa and (iii) construction of power transmission
tower in Raigad district of Maharashtra is considered in this
paper. The range of delay claims by contractor was in the
range of around 1.08 % to 400% of the project cost. This may
due to various reasons.
Table1. Analysis of delay damages in construction projects.
Sr. No
Project
description
Project
cost
(Lakhs
Rs.)
Value
of claim
(Lakhs
Rs.)
Claim
in % of
project
cost
1
Construction
of mall in
Mumbai.
4314 623.58 14.45%
2
Construction
of hotel and
casino in
Goa.
3494 37.68 1.08%
3
Construction
of power
transmission
tower
foundation
in Raigad
district.
12.43 49.64 400%
2.1 Project 1: Construction of Mall in Mumbai
Construction of a mall in Mumbai was taken as first case study
for delay claims. The project cost was around 4314 Lakhs Rs.,
claim amount by contractor was 623.58 Lakhs Rs. and delay
was almost of 7 months. Various reasons for claims observed
in this case includes the mainly due to delay in approved
drawings. The total built up area was around 6,77,000 Sq.ft.
and large quantity of MS shuttering material was required to
be deployed on site. Since the work was suspended in the
middle of project, the resources like staff, machinery was
demobilized and transferred to other project, but it was
difficult to transfer the shuttering material to other site since
the cost of transportation for demobilizing and again
mobilizing when the work resumes was observed as a
governing factor. Hence in this project 81% of Claim
constitutes for M.S Shuttering Material. Details of claim for
various reasons in % for project 1 are shown in Table 2. This
includes claims for MS shuttering material, labour, overheads
and machinery. Next section gives similar analysis for
construction of hotel and casino in Goa.
Table2 Details of claim for project 1
Sr.
No.
Description
Claim
amount
(In Lakhs
Rs.)
Claim
in % of
project
cost
Importance
as per
claim
amount
1
M.S.
Shuttering
Material
503.08 81% 1
2 Labour 58.24 9% 2
3 Overheads 47.50 8% 3
4 Machinery 14.75 2% 4
Total claim
(In Lakhs Rs.)
623.58
2.2 Project 2: Construction of Hotel and Casino in
Goa
The construction of hotel and casino in Goa was having
estimated project cost of 3494 Lakhs Rs. and the claim was
37.68 Lakhs Rs with delay of 1 month. It was noted that the
work order given shows the site mobilization within 15 days
and in the tender it was also mentioned the minimum staff
cadre and equipment needs to be deployed on site at the time
of mobilization. Table 3 gives details of claim for various
reasons in % for project 2 showing importance as per claim
IJRET: International Journal of Research in Engineering and Technolo
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @
amount. As per the conditions the contractor mobilized the s
with the required resources but there was a delay of 1 month
in handing over the site. In this case the amount of
M.S. shuttering material, overheads and machinery
same, since the claim was at the start of the project hence the
minimum resources were deployed. The third case study
includes the construction of power transmis
foundation in Raigad district detailed analysis is given in the
next section.
Table3. Details of claim for project 2.
Sr.
No.
Description
Claim
amount
(In
Lakhs
Rs.)
Claim in
% of
project
cost
1
M.S
shuttering
material
10.93 29%
2 Overheads 10.60 28%
3 Machinery 9.55 25%
4 Labour 6.60 18%
Total claim
(In Lakhs Rs.)
37.68
2.3 Project 3. Construction of Power Transmission
Tower Foundation in Raigad District
The scope of work in this case study was to construct RCC
power transmission tower foundation at
locations. Table 4 gives details of claim for project 3.
work was supposed to be executed after getting unhindered
land at all the four locations along with the necessary
9%
2% 8%
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319
__________________________________________________________________________________________
2013, Available @ http://www.ijret.org
ontractor mobilized the site
ut there was a delay of 1 month
this case the amount of claim for
achinery was almost
at the start of the project hence the
The third case study
includes the construction of power transmission tower
foundation in Raigad district detailed analysis is given in the
project 2.
Claim in
project
Importance
as per
claim
amount
1
2
3
4
Power Transmission
was to construct RCC
foundation at four different
Table 4 gives details of claim for project 3. The
to be executed after getting unhindered
along with the necessary
approvals from the local authorities. It was
that all four locations would
project. The duration of project was 45 days. The contractor
mobilized the site with adequate resources
of all the four location was not
working drawing was not issued
local authorities was not taken by the
cost was 12.43 Lakhs Rs., c
and the delay resulted the work to be completed in 14.5
months leading to total delay of
details of claims by contractor for project 1, 2 and 3 on various
elements of the respective projects.
Table4. Details of
Sr.
No.
Description
Claim
amount
(In
Lakhs
Rs.)
1 Labour 21
2
M.S
Shuttering
Material
10
3 Overheads 10
4 Machinery 6.
Total claim
(In Lakhs Rs.)
49
(a)
81%
8%
Project 1.
M.S. Shuttering Material
Labour
Machinery
Overheads
eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
392
from the local authorities. It was also mentioned
ould be made available at the start of
project. The duration of project was 45 days. The contractor
mobilized the site with adequate resources but the possession
location was not allotted to the contractor. The
not issued and the permission from the
not taken by the client. The total project
Rs., claim amount was 49.64 Lakhs Rs.
sulted the work to be completed in 14.5
total delay of 13 months. Figure 1 shows
details of claims by contractor for project 1, 2 and 3 on various
elements of the respective projects.
Details of claim for project 3
Claim
amount
(In
Lakhs
Rs.)
Claim in
% of
project
cost
Importance
as per claim
amount
21.58 40% 1
10.79 20% 2
10.79 20% 2
.47 12% 3
49.64
M.S. Shuttering Material
IJRET: International Journal of Research in Engineering and Technolo
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @
Fig1. Details of claims by contractor for
CONCLUSIONS
The investigation in this work was to identify the major
factors responsible for project delay that may give rise to
claims for delay damages for three major projects of 1.
Construction of mall, 2. Construction of hotel and casino and
3. Construction of power transmission tower at various
locations of India. The main highlights in this study are to find
out the major components of claims with perspective of
contractor for delay damages. For mall project it can be seen
that M.S. shuttering material is most affected factor of delay
damages. This is because normally mall constructions are
wide spread and the area required for construction is more and
hence shuttering required to support the plywood is required in
huge quantities. If the project is suspended or
charges for the material mounts to a huge expenditure. In case
of hotel and casino construction delay in project was
due to handing over of site hence all the M.S shuttering
material, labour, staff, equipment which were mobilized
underutilized. In this case it was observed that all
25%
18%
20%
20%
12%
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319
__________________________________________________________________________________________
2013, Available @ http://www.ijret.org
Details of claims by contractor for (a) project 1, (b) project 2 and (c) project 3 on various elements
The investigation in this work was to identify the major
project delay that may give rise to
claims for delay damages for three major projects of 1.
Construction of mall, 2. Construction of hotel and casino and
wer transmission tower at various
locations of India. The main highlights in this study are to find
out the major components of claims with perspective of
all project it can be seen
ffected factor of delay
damages. This is because normally mall constructions are
wide spread and the area required for construction is more and
hence shuttering required to support the plywood is required in
huge quantities. If the project is suspended or delayed the idle
charges for the material mounts to a huge expenditure. In case
in project was mainly
due to handing over of site hence all the M.S shuttering
which were mobilized but
underutilized. In this case it was observed that all four factors
are equally contributing delay.
for power transmission tower
was due to not handing over
unhindered at the same time
project was supposed to be completed in
time was the key factor and t
complete project but work front
labour factor was the majo
RECOMMENDATIONS
Following are some of the
contractors of the construction projects
(1) Recommendations for Client:
have proper of planning before awarding the work.
The design and drawing should be ready before hand
to avoid any delay in work.
completely handed over instead of piece meal.
analysis of all factors which may lead to delay in
work from their end should be taken
(b)
(c)
29%
28%
18%
Project 2.
M.S. Shuttering Material
Labour
Machinery
Overheads
40%
20%
Project 3.
M.S. Shuttering Material
Labour
Overheads
Machinery
eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
393
3 on various elements
ng delay. In case of claims by contractor
ower foundation project, the delay
handing over of all the four locations
at the same time and delay in drawings. Since the
be completed in one and half months,
the key factor and the contractor mobilized for the
complete project but work front was not given. Hence the
major affected factor in this case.
RECOMMENDATIONS
are some of the recommendations for clients and
contractors of the construction projects
Recommendations for Client: the client should
have proper of planning before awarding the work.
and drawing should be ready before hand
to avoid any delay in work. The site should be
completely handed over instead of piece meal. Risk
analysis of all factors which may lead to delay in
end should be taken care of.
M.S. Shuttering Material
Machinery
Overheads
M.S. Shuttering Material
Overheads
Machinery
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 394
(2) Recommendation for Contractor: It is the duty of
the contractor to validate the drawings given by client
at the time of bidding the tender. The contractor must
also analyze all the factors which may lead to delays
from government bodies, changes in rules and
regulations. The contractor should also be financially
stable to digest the cost overrun leading to delays
REFERENCES
[1] ED-ON Centre lecture notes: “One day workshop on
Contract Administration and Arbitration”. Pages 37-43.
[2] E. C. Harris: “Global Construction Disputes 2012:
Moving in the Right Direction” Pages 3-5 (2012)

More Related Content

What's hot

Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
eSAT Publishing House
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET Journal
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
IJERA Editor
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
Twana Ahmad
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...IAEME Publication
 
Manual construction-risks-alop
Manual construction-risks-alopManual construction-risks-alop
Manual construction-risks-alop
Prince Mello
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
iosrjce
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
Dr. Amarjeet Singh
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Sankalp Swarnkar
 
Risk management
Risk managementRisk management
Risk management
nashaat algrara
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
Dimitrios Kordas
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
IRJET Journal
 

What's hot (18)

Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...Contractual implications of cash flow on owner and contractor in villa constr...
Contractual implications of cash flow on owner and contractor in villa constr...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...Performance evaluation of design build projects with and without agency const...
Performance evaluation of design build projects with and without agency const...
 
Manual construction-risks-alop
Manual construction-risks-alopManual construction-risks-alop
Manual construction-risks-alop
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Risk management
Risk managementRisk management
Risk management
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 

Viewers also liked

Evaluation of 6 noded quareter point element for crack analysis by analytical...
Evaluation of 6 noded quareter point element for crack analysis by analytical...Evaluation of 6 noded quareter point element for crack analysis by analytical...
Evaluation of 6 noded quareter point element for crack analysis by analytical...
eSAT Publishing House
 
Effect of mobile phone and bts radiation on heart rate
Effect of mobile phone and bts radiation on heart rateEffect of mobile phone and bts radiation on heart rate
Effect of mobile phone and bts radiation on heart rate
eSAT Publishing House
 
Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...
eSAT Publishing House
 
Design and implementation of an ancrchitecture of embedded web server for wir...
Design and implementation of an ancrchitecture of embedded web server for wir...Design and implementation of an ancrchitecture of embedded web server for wir...
Design and implementation of an ancrchitecture of embedded web server for wir...
eSAT Publishing House
 
Multisensor data fusion based autonomous mobile
Multisensor data fusion based autonomous mobileMultisensor data fusion based autonomous mobile
Multisensor data fusion based autonomous mobile
eSAT Publishing House
 
Improved method for pattern discovery in text mining
Improved method for pattern discovery in text miningImproved method for pattern discovery in text mining
Improved method for pattern discovery in text mining
eSAT Publishing House
 
Investigations on the performance of diesel in an air
Investigations on the performance of diesel in an airInvestigations on the performance of diesel in an air
Investigations on the performance of diesel in an air
eSAT Publishing House
 
A survey on ranking sql queries using skyline and user
A survey on ranking sql queries using skyline and userA survey on ranking sql queries using skyline and user
A survey on ranking sql queries using skyline and user
eSAT Publishing House
 
Analysis and mitigation of unbalance due to load in
Analysis and mitigation of unbalance due to load inAnalysis and mitigation of unbalance due to load in
Analysis and mitigation of unbalance due to load in
eSAT Publishing House
 
Emission characteristics of a diesel engine using soyabean oil and diesel blends
Emission characteristics of a diesel engine using soyabean oil and diesel blendsEmission characteristics of a diesel engine using soyabean oil and diesel blends
Emission characteristics of a diesel engine using soyabean oil and diesel blends
eSAT Publishing House
 
Parametric study of response of an asymmetric building for various earthquake...
Parametric study of response of an asymmetric building for various earthquake...Parametric study of response of an asymmetric building for various earthquake...
Parametric study of response of an asymmetric building for various earthquake...
eSAT Publishing House
 
Cancer cell segmentation and detection using nc ratio
Cancer cell segmentation and detection using nc ratioCancer cell segmentation and detection using nc ratio
Cancer cell segmentation and detection using nc ratio
eSAT Publishing House
 
Parameter study of stable walking gaits for nao
Parameter study of stable walking gaits for naoParameter study of stable walking gaits for nao
Parameter study of stable walking gaits for nao
eSAT Publishing House
 
Reminiscing cloud computing technology
Reminiscing cloud computing technologyReminiscing cloud computing technology
Reminiscing cloud computing technology
eSAT Publishing House
 
Classification of appendicitis based on ultrasound image
Classification of appendicitis based on ultrasound imageClassification of appendicitis based on ultrasound image
Classification of appendicitis based on ultrasound image
eSAT Publishing House
 
Language identification using g lda
Language identification using g ldaLanguage identification using g lda
Language identification using g lda
eSAT Publishing House
 
Formulating a trip production prediction model for
Formulating a trip production prediction model forFormulating a trip production prediction model for
Formulating a trip production prediction model for
eSAT Publishing House
 
Minimum shear reinforcement for optimum ductility of
Minimum shear reinforcement for optimum ductility ofMinimum shear reinforcement for optimum ductility of
Minimum shear reinforcement for optimum ductility of
eSAT Publishing House
 
Analysis of multi hop relay algorithm for efficient broadcasting in manets
Analysis of multi hop relay algorithm for efficient broadcasting in manetsAnalysis of multi hop relay algorithm for efficient broadcasting in manets
Analysis of multi hop relay algorithm for efficient broadcasting in manets
eSAT Publishing House
 
Security constrained optimal load dispatch using hpso technique for thermal s...
Security constrained optimal load dispatch using hpso technique for thermal s...Security constrained optimal load dispatch using hpso technique for thermal s...
Security constrained optimal load dispatch using hpso technique for thermal s...
eSAT Publishing House
 

Viewers also liked (20)

Evaluation of 6 noded quareter point element for crack analysis by analytical...
Evaluation of 6 noded quareter point element for crack analysis by analytical...Evaluation of 6 noded quareter point element for crack analysis by analytical...
Evaluation of 6 noded quareter point element for crack analysis by analytical...
 
Effect of mobile phone and bts radiation on heart rate
Effect of mobile phone and bts radiation on heart rateEffect of mobile phone and bts radiation on heart rate
Effect of mobile phone and bts radiation on heart rate
 
Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...
 
Design and implementation of an ancrchitecture of embedded web server for wir...
Design and implementation of an ancrchitecture of embedded web server for wir...Design and implementation of an ancrchitecture of embedded web server for wir...
Design and implementation of an ancrchitecture of embedded web server for wir...
 
Multisensor data fusion based autonomous mobile
Multisensor data fusion based autonomous mobileMultisensor data fusion based autonomous mobile
Multisensor data fusion based autonomous mobile
 
Improved method for pattern discovery in text mining
Improved method for pattern discovery in text miningImproved method for pattern discovery in text mining
Improved method for pattern discovery in text mining
 
Investigations on the performance of diesel in an air
Investigations on the performance of diesel in an airInvestigations on the performance of diesel in an air
Investigations on the performance of diesel in an air
 
A survey on ranking sql queries using skyline and user
A survey on ranking sql queries using skyline and userA survey on ranking sql queries using skyline and user
A survey on ranking sql queries using skyline and user
 
Analysis and mitigation of unbalance due to load in
Analysis and mitigation of unbalance due to load inAnalysis and mitigation of unbalance due to load in
Analysis and mitigation of unbalance due to load in
 
Emission characteristics of a diesel engine using soyabean oil and diesel blends
Emission characteristics of a diesel engine using soyabean oil and diesel blendsEmission characteristics of a diesel engine using soyabean oil and diesel blends
Emission characteristics of a diesel engine using soyabean oil and diesel blends
 
Parametric study of response of an asymmetric building for various earthquake...
Parametric study of response of an asymmetric building for various earthquake...Parametric study of response of an asymmetric building for various earthquake...
Parametric study of response of an asymmetric building for various earthquake...
 
Cancer cell segmentation and detection using nc ratio
Cancer cell segmentation and detection using nc ratioCancer cell segmentation and detection using nc ratio
Cancer cell segmentation and detection using nc ratio
 
Parameter study of stable walking gaits for nao
Parameter study of stable walking gaits for naoParameter study of stable walking gaits for nao
Parameter study of stable walking gaits for nao
 
Reminiscing cloud computing technology
Reminiscing cloud computing technologyReminiscing cloud computing technology
Reminiscing cloud computing technology
 
Classification of appendicitis based on ultrasound image
Classification of appendicitis based on ultrasound imageClassification of appendicitis based on ultrasound image
Classification of appendicitis based on ultrasound image
 
Language identification using g lda
Language identification using g ldaLanguage identification using g lda
Language identification using g lda
 
Formulating a trip production prediction model for
Formulating a trip production prediction model forFormulating a trip production prediction model for
Formulating a trip production prediction model for
 
Minimum shear reinforcement for optimum ductility of
Minimum shear reinforcement for optimum ductility ofMinimum shear reinforcement for optimum ductility of
Minimum shear reinforcement for optimum ductility of
 
Analysis of multi hop relay algorithm for efficient broadcasting in manets
Analysis of multi hop relay algorithm for efficient broadcasting in manetsAnalysis of multi hop relay algorithm for efficient broadcasting in manets
Analysis of multi hop relay algorithm for efficient broadcasting in manets
 
Security constrained optimal load dispatch using hpso technique for thermal s...
Security constrained optimal load dispatch using hpso technique for thermal s...Security constrained optimal load dispatch using hpso technique for thermal s...
Security constrained optimal load dispatch using hpso technique for thermal s...
 

Similar to Analysis of factors contributing delays and claims in

A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
Rick Vogel
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
IRJET Journal
 
D012522433
D012522433D012522433
D012522433
IOSR Journals
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
IRJET Journal
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
Abhishek Shah
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
IRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
IOSR Journals
 
B012140812
B012140812B012140812
B012140812
IOSR Journals
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
IJMER
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
Joseph Sangpang
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET Journal
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsIAEME Publication
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET Journal
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET Journal
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
IJSRED
 
A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...
IRJET Journal
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
IOSR Journals
 

Similar to Analysis of factors contributing delays and claims in (20)

A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
D012522433
D012522433D012522433
D012522433
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
 
A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...A Study on the analysis of payment problems in private building sector in Ker...
A Study on the analysis of payment problems in private building sector in Ker...
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 

More from eSAT Publishing House

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
eSAT Publishing House
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
eSAT Publishing House
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
eSAT Publishing House
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
eSAT Publishing House
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
eSAT Publishing House
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
eSAT Publishing House
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
eSAT Publishing House
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
eSAT Publishing House
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
eSAT Publishing House
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
eSAT Publishing House
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
eSAT Publishing House
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
eSAT Publishing House
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
eSAT Publishing House
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
eSAT Publishing House
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
eSAT Publishing House
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
eSAT Publishing House
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
eSAT Publishing House
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
eSAT Publishing House
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
eSAT Publishing House
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
eSAT Publishing House
 

More from eSAT Publishing House (20)

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
 

Recently uploaded

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 

Recently uploaded (20)

Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 

Analysis of factors contributing delays and claims in

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 390 ANALYSIS OF FACTORS CONTRIBUTING DELAYS AND CLAIMS IN CONSTRUCTION PROJECTS Ketki S. Kamble1 , A. R. Kambekar2 1 PG. Student, Const. Management, 2 Assistant Professor, CED, SPCE Andheri (W), Mumbai 400058, Maharashtra, ketki08@gmail.com Abstract Construction activities are the most competitive and it involves higher risk with minimum profitability due to competition. Construction of any infrastructural work involves complex management skills related to manpower, materials, plant, machineries, new technologies etc. It also involves many agencies interdependent on each other like the planners, structural and functional designers including various types of specialized engineers and it also includes support of financial institutions, insurers, contractors and specialized contractors. As there are prevailing labour bye laws it needs special care of their well beings. In such kind of complex and intense framework some disputes is quite natural between the agencies involved in such activities which further results in claims management as the unsettled dispute finally leads to financial claims. Higher incidences of disputes are generally reported from the construction contract. Even if there is an appropriate understanding of construction contract clauses from the agencies in the agreement yet claims seems to be a major crisis in the construction sector. The research reported in this paper aims in identifying the major factors responsible of project delay that may give rise to claims for delay damages. The in this paper research mainly highlights on finding the major components of claims with perspective of contractor for delay damages. Keywords: Claims, delay, damages, construction industry, disputes. --------------------------------------------------------------------***--------------------------------------------------------------------- 1. INTRODUCTION Claims as per Hughes [1] “It is a demand, a request or application for something to which a contractor considers, believes or contends he is entitled but in respect of which agreement has not yet been reached”. As per Harris [2] the major five causes of disputes in Asian construction projects are as follows: • Failure to make interim awards on extensions of time and to give associated compensation • Unrealistic risk transfer from employers to contractors • Conflicting party interests • An unrealistic contract completion date being defined at tender stage • Incomplete design information or employer requirements. In general it was reported in literature that the construction sector involves disputes from the sources like changes which includes variation, alteration, addition, deletion, delays and suspensions, differing site conditions, unjust enrichment by owners. It was also observed that there are five potential areas which can give rise to disputes: document errors, estimation errors, change in conditions, implied promises and agencies involved. Claims however fall under two major categories based on their occurrence i.e. during (i) execution of contract and (ii) administration of contract. Execution of contract includes claims due to change in design and drawing, delays in handing over site/issuance of drawings/getting clearance certificate from appropriate authorities, claims due to original scope of work change, claims due to differing site conditions and claims due to variation in methodology. Similarly during administration of contract claims may be due to delay in payment of running account bills and claims due to foreclosure/termination of contract. Similarly delays in schedules of construction projects are one of the most common types of disputes in the construction industry. The client and contractor works for a common objective i.e. to complete the project within scheduled time as well as cost. Time overrun is the most common failure of objective that in turn leads to cost overrun and hence failure in the objective of timely completion leads to failure of overall project budget which ultimately gives rise to disputes. The reasons for delays could be caused by client, contractor, force majeure i.e. act of God, change in laws, rules and regulations, improper co- ordination between client and contractors, non-availability of required skilled labour, non-availability of required special material, differing site conditions, non-issuance of working drawing and changes in work leading to change in methodology. Delays can be further classified as excusable or non-excusable. Some of the practical cases of non-excusable delays are incompetent sub-contractor, financial incompetency of the contractor, labour disputes hindering work progress, poor workmanship leading to rework, poor material quality and delay in handing over the site by client and excusable
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 391 delay includes sudden floods, natural calamities like earthquake, tsunami etc. riots, labour strike, non-foreseeable situation. Critical delay are defined as a delay in any given activity which results in delay of total project and non-critical delay is defined as delays which may not upset total time frame of the contract [1]. This paper mainly focuses on delay damage claims related to additional cost incurred by the contractor due to delay caused by the client. Evaluation of delay damages are when a contractor bids for a tender, a number of factors are considered apart from the labour, material and equipment that are required to execute the work. In tender the duration required to complete the work is generally mentioned and hence the contractor quotes accordingly. The quote includes material cost, labour cost, plant and machinery cost, shuttering material, human resource cost, financial cost, site overheads and above all profit. In an event of prolongation of contract, the major factors that are affected are additional overheads, plant and machinery, labour and material cost, loss of productivity, loss of profit, loss of new business opportunities and early mobilization. 2. METHODOLOGY ADOPTED Following methodology is adopted for this research work. This includes identification of claims that occur, factors responsible for delay, prolongation claim if any, focus on factors that are affected due to delay in completion the project, factors mostly considered while setting up prolongation claim, ranking based on case studies to understand the major factor affecting the delay damages claim finally recommendations based on the study. The delays which occur in construction projects are due to various reasons. Analysis of three projects have been carried out details of the same is given in Table 1. Project cost, value of claims and claim in % of project cost for (i) construction of mall in Mumbai, (ii) construction of hotel and casino in Goa and (iii) construction of power transmission tower in Raigad district of Maharashtra is considered in this paper. The range of delay claims by contractor was in the range of around 1.08 % to 400% of the project cost. This may due to various reasons. Table1. Analysis of delay damages in construction projects. Sr. No Project description Project cost (Lakhs Rs.) Value of claim (Lakhs Rs.) Claim in % of project cost 1 Construction of mall in Mumbai. 4314 623.58 14.45% 2 Construction of hotel and casino in Goa. 3494 37.68 1.08% 3 Construction of power transmission tower foundation in Raigad district. 12.43 49.64 400% 2.1 Project 1: Construction of Mall in Mumbai Construction of a mall in Mumbai was taken as first case study for delay claims. The project cost was around 4314 Lakhs Rs., claim amount by contractor was 623.58 Lakhs Rs. and delay was almost of 7 months. Various reasons for claims observed in this case includes the mainly due to delay in approved drawings. The total built up area was around 6,77,000 Sq.ft. and large quantity of MS shuttering material was required to be deployed on site. Since the work was suspended in the middle of project, the resources like staff, machinery was demobilized and transferred to other project, but it was difficult to transfer the shuttering material to other site since the cost of transportation for demobilizing and again mobilizing when the work resumes was observed as a governing factor. Hence in this project 81% of Claim constitutes for M.S Shuttering Material. Details of claim for various reasons in % for project 1 are shown in Table 2. This includes claims for MS shuttering material, labour, overheads and machinery. Next section gives similar analysis for construction of hotel and casino in Goa. Table2 Details of claim for project 1 Sr. No. Description Claim amount (In Lakhs Rs.) Claim in % of project cost Importance as per claim amount 1 M.S. Shuttering Material 503.08 81% 1 2 Labour 58.24 9% 2 3 Overheads 47.50 8% 3 4 Machinery 14.75 2% 4 Total claim (In Lakhs Rs.) 623.58 2.2 Project 2: Construction of Hotel and Casino in Goa The construction of hotel and casino in Goa was having estimated project cost of 3494 Lakhs Rs. and the claim was 37.68 Lakhs Rs with delay of 1 month. It was noted that the work order given shows the site mobilization within 15 days and in the tender it was also mentioned the minimum staff cadre and equipment needs to be deployed on site at the time of mobilization. Table 3 gives details of claim for various reasons in % for project 2 showing importance as per claim
  • 3. IJRET: International Journal of Research in Engineering and Technolo __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ amount. As per the conditions the contractor mobilized the s with the required resources but there was a delay of 1 month in handing over the site. In this case the amount of M.S. shuttering material, overheads and machinery same, since the claim was at the start of the project hence the minimum resources were deployed. The third case study includes the construction of power transmis foundation in Raigad district detailed analysis is given in the next section. Table3. Details of claim for project 2. Sr. No. Description Claim amount (In Lakhs Rs.) Claim in % of project cost 1 M.S shuttering material 10.93 29% 2 Overheads 10.60 28% 3 Machinery 9.55 25% 4 Labour 6.60 18% Total claim (In Lakhs Rs.) 37.68 2.3 Project 3. Construction of Power Transmission Tower Foundation in Raigad District The scope of work in this case study was to construct RCC power transmission tower foundation at locations. Table 4 gives details of claim for project 3. work was supposed to be executed after getting unhindered land at all the four locations along with the necessary 9% 2% 8% IJRET: International Journal of Research in Engineering and Technology eISSN: 2319 __________________________________________________________________________________________ 2013, Available @ http://www.ijret.org ontractor mobilized the site ut there was a delay of 1 month this case the amount of claim for achinery was almost at the start of the project hence the The third case study includes the construction of power transmission tower foundation in Raigad district detailed analysis is given in the project 2. Claim in project Importance as per claim amount 1 2 3 4 Power Transmission was to construct RCC foundation at four different Table 4 gives details of claim for project 3. The to be executed after getting unhindered along with the necessary approvals from the local authorities. It was that all four locations would project. The duration of project was 45 days. The contractor mobilized the site with adequate resources of all the four location was not working drawing was not issued local authorities was not taken by the cost was 12.43 Lakhs Rs., c and the delay resulted the work to be completed in 14.5 months leading to total delay of details of claims by contractor for project 1, 2 and 3 on various elements of the respective projects. Table4. Details of Sr. No. Description Claim amount (In Lakhs Rs.) 1 Labour 21 2 M.S Shuttering Material 10 3 Overheads 10 4 Machinery 6. Total claim (In Lakhs Rs.) 49 (a) 81% 8% Project 1. M.S. Shuttering Material Labour Machinery Overheads eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ 392 from the local authorities. It was also mentioned ould be made available at the start of project. The duration of project was 45 days. The contractor mobilized the site with adequate resources but the possession location was not allotted to the contractor. The not issued and the permission from the not taken by the client. The total project Rs., claim amount was 49.64 Lakhs Rs. sulted the work to be completed in 14.5 total delay of 13 months. Figure 1 shows details of claims by contractor for project 1, 2 and 3 on various elements of the respective projects. Details of claim for project 3 Claim amount (In Lakhs Rs.) Claim in % of project cost Importance as per claim amount 21.58 40% 1 10.79 20% 2 10.79 20% 2 .47 12% 3 49.64 M.S. Shuttering Material
  • 4. IJRET: International Journal of Research in Engineering and Technolo __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ Fig1. Details of claims by contractor for CONCLUSIONS The investigation in this work was to identify the major factors responsible for project delay that may give rise to claims for delay damages for three major projects of 1. Construction of mall, 2. Construction of hotel and casino and 3. Construction of power transmission tower at various locations of India. The main highlights in this study are to find out the major components of claims with perspective of contractor for delay damages. For mall project it can be seen that M.S. shuttering material is most affected factor of delay damages. This is because normally mall constructions are wide spread and the area required for construction is more and hence shuttering required to support the plywood is required in huge quantities. If the project is suspended or charges for the material mounts to a huge expenditure. In case of hotel and casino construction delay in project was due to handing over of site hence all the M.S shuttering material, labour, staff, equipment which were mobilized underutilized. In this case it was observed that all 25% 18% 20% 20% 12% IJRET: International Journal of Research in Engineering and Technology eISSN: 2319 __________________________________________________________________________________________ 2013, Available @ http://www.ijret.org Details of claims by contractor for (a) project 1, (b) project 2 and (c) project 3 on various elements The investigation in this work was to identify the major project delay that may give rise to claims for delay damages for three major projects of 1. Construction of mall, 2. Construction of hotel and casino and wer transmission tower at various locations of India. The main highlights in this study are to find out the major components of claims with perspective of all project it can be seen ffected factor of delay damages. This is because normally mall constructions are wide spread and the area required for construction is more and hence shuttering required to support the plywood is required in huge quantities. If the project is suspended or delayed the idle charges for the material mounts to a huge expenditure. In case in project was mainly due to handing over of site hence all the M.S shuttering which were mobilized but underutilized. In this case it was observed that all four factors are equally contributing delay. for power transmission tower was due to not handing over unhindered at the same time project was supposed to be completed in time was the key factor and t complete project but work front labour factor was the majo RECOMMENDATIONS Following are some of the contractors of the construction projects (1) Recommendations for Client: have proper of planning before awarding the work. The design and drawing should be ready before hand to avoid any delay in work. completely handed over instead of piece meal. analysis of all factors which may lead to delay in work from their end should be taken (b) (c) 29% 28% 18% Project 2. M.S. Shuttering Material Labour Machinery Overheads 40% 20% Project 3. M.S. Shuttering Material Labour Overheads Machinery eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ 393 3 on various elements ng delay. In case of claims by contractor ower foundation project, the delay handing over of all the four locations at the same time and delay in drawings. Since the be completed in one and half months, the key factor and the contractor mobilized for the complete project but work front was not given. Hence the major affected factor in this case. RECOMMENDATIONS are some of the recommendations for clients and contractors of the construction projects Recommendations for Client: the client should have proper of planning before awarding the work. and drawing should be ready before hand to avoid any delay in work. The site should be completely handed over instead of piece meal. Risk analysis of all factors which may lead to delay in end should be taken care of. M.S. Shuttering Material Machinery Overheads M.S. Shuttering Material Overheads Machinery
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ IC-RICE Conference Issue | Nov-2013, Available @ http://www.ijret.org 394 (2) Recommendation for Contractor: It is the duty of the contractor to validate the drawings given by client at the time of bidding the tender. The contractor must also analyze all the factors which may lead to delays from government bodies, changes in rules and regulations. The contractor should also be financially stable to digest the cost overrun leading to delays REFERENCES [1] ED-ON Centre lecture notes: “One day workshop on Contract Administration and Arbitration”. Pages 37-43. [2] E. C. Harris: “Global Construction Disputes 2012: Moving in the Right Direction” Pages 3-5 (2012)