International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019
Available at www.ijsred.com
ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 648
Causes of Claims in the Construction Project
Anita Rauzana*, Tripoli**
*(Department of Civil Engineering,Syiah Kuala University, Aceh Province, Indonesia)
**(Department of Civil Engineering,Syiah Kuala University, Aceh Province, Indonesia)
----------------------------------------************************----------------------------------
Abstract:
Claims on construction projects are requests or demands for adding costs, and time of construction. Claims
can trigger a dispute because the implementation of the project is not in accordance with the contract.
Construction contracts are used as guidelines in submitting construction claims. Studies of construction
claims have been carried out by various researchers, and every cause of construction claims is influenced
by location / area, and project characteristics. This study aims to establish the theoretical framework for
the cause of contractor claims for delays in construction projects from literature review, various research
results, literature, and various relevant information. According to a review of several articles / research,
obtained factors that influence claims are design changes.
Keywords – claims, contractors, construction, owners, projects
----------------------------------------************************----------------------------------
I. INTRODUCTION
The construction industry is a complex
industrial sector, and can contribute to economic
growth in Indonesia. The role of the construction
industry is cooperation from various sectors.
However, relations between these sectors often run
less smoothly, due to the construction industry
often having complicated problems, so that
relations with other sectors are disrupted. This is
due to the development of the construction industry
being a complex industry both in terms of forms,
costs, contract systems, and existing resources. For
project owners, especially the government, it avoids
claims, while contractors are reluctant to make
claims, for fear of being recorded as a contracting
company that has poor performance (Yasin, 2004).
This article presents review results of the
causes of claims on private and government
projects. Construction claims occur because one
RESEARCH ARTICLE OPEN ACCESS
International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019
Available at www.ijsred.com
ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 649
party fails to carry out its responsibilities and
obligations. In implementing the project, the
agreement reached is stated in the contract
document. But during this time, there were still
frequent disputes between the owner and the
contractor, or the contractor blamed the consultant.
To minimize the problem, it is very important to
know the risks that can occur in the project, and
whether those risks are covered in the contract
articles. Risk is one of the important things that
must be considered in each project. Risk occurs in
every project and contractor, therefore, it must be
aware of the effects of risk by implementing good
risk management. Risk is a condition that arises
because of uncertainty in the implementation of a
construction project.
Claims is demands, however, the notion of
claims according to Wibowo (2009), that claims are
categorized into three as contractual claims, ex-
contractual claims, and common law claims, as well
as formulating four strategies for contractors so that
claims can be overcome, namely recognizing
claims, providing accurate notifications, collecting
documentation complete, and present claims so that
the owner can grant the claim submitted.
Claims will arise when one party believes that
it has been harmed by another party neglecting its
contractual obligations, therefore it needs to get
compensation (Kuluanga et al., 2000). Claims can
occur with owners, contractors or suppliers (Cox,
1997). The definition of claim is more directed at
the contractor's request to compensate for losses or
avoid liquidated damages (Seeley, 1993).
It can be concluded that claims occur
because of a request for the implementation of a
construction service work between the contractor
and the owner, or with a sub contractor related to
additional costs, time and other compensation.
Yasin (2004) concluded that the main causes of
construction claims are:
1) Inaccurate design information
2) Incomplete design information
3) Investigation of incomplete locations
4) Slow client reactions / responses
5) Poor communication between human resources
6) Time targets that are not realized
7) Imperfect administration
8) Incomplete tender information
9) Unclear risk allocation
10) Late payment
Due to delays in construction projects and
additional costs, it is important to know what
factors contribute to claims in the construction
project.
The incompatibility of the realization with
the expectations of the construction project has the
potential to cause losses to the owner and the
implementing contractor. Incompatibility that
occurs is the time of implementation, namely the
project is completed outside the time set. Parties
who experience losses due to delays must be able to
International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019
Available at www.ijsred.com
ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 650
recognize who should be responsible for the delay
(Arditi 2008), then can take appropriate steps to
reduce or eliminate the losses incurred. Based on
the responsible party, delay can be classified into
three, namely due to owner delays (commonly
known as type E), contractors (type C), and not due
to owners and contractors (type N). Determination
of the responsible party is important to determine
the type of compensation that must be given,
whether time compensation, and cost compensation
(Scott 1997)
II. METHODOLOGY
The purpose of writing this article is to
establish a theoretical framework for potential
construction claims by contractors, conducting
studies from previous studies, journals, and from
relevant literature reviews. The methodology used
in this article is using the study of literature.
III. RESULTS AND DISCUSSION
Identification of potential claims by
contractors on construction projects is carried out
by conducting studies from various literature
studies. The study of construction claims by
contractors to the owners of construction projects is
often done, different results regarding the main
causes of contractor claims to the owners of
construction projects have been investigated by
previous researchers.
Wibowo (2009) presented the results of a
survey of construction service actors about the
practice of contractor claims to project owners,
because the delay was the responsibility of
government construction project owners. Based on
frequency, there are three main reasons why claims
are not submitted by contractors are (1) claims are
not significant, (2) unpreparedness of supporting
claims documents, (3) the need to maintain good
relations with service users. Meanwhile the reason
for service users (project owners) rejecting
contractor's claims is (1) claims not regulated in the
contract, (2) incomplete supporting documents for
claims, (3) budget unavailability.
According to Pasaribu (2009), there are
findings that claims have a correlation of 81.2% on
time performance. There are claims that affect
payments to air conditioning subcontractors,
architectural subcontractors, and interior
subcontractors. Chandra (2005) stated that the main
causes of claims were design changes and added
work carried out by building owners, whereas
contractor claims often took the form of additional
costs, and claim settlement methods, which are
often used by parties are engineering judgment
methods.
According to Satwanirat (2009), building
construction claims submitted by the contractor to
the owner during the construction process almost
frequently occur, and a good understanding of
claim submission is needed which can help
contractors in the process of submitting their
International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019
Available at www.ijsred.com
ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 651
claims, claims get additional time, additional costs
and or compensation.
According to Putri (2013), the
implementation of construction project claims is
divided into the consequences of (1) the actions of
the project owner, (2) the consultant planner's
actions, (3) supervisory counseling, and ( 4)
external factors. According to Nurisra (2009), there
are 7 groups of factors that cause claims, namely: 1)
contract articles that are incomplete and clear, 2)
conflicts in design, specifications and special risks,
3) changes or modifications to the contents of
contracts, 4) weather conditions, 5) differences in
field conditions, 6) changes in schedule by the
owner, 7) delays due to the owner. The most
potential claim in the ranking is higher than usual
rainfall, and the land investigation conducted by the
owner does not describe the project land conditions.
IV. CONCLUSION
Construction claims caused by the owner as
a demand for the contractor, which leads to requests
for additional time to complete, and is still a
problem that is always present in every construction
project. The results of the study on the factors
causing the submission of construction claims from
several articles / studies determine the main rating,
namely the change in design by the owner, and the
delay in approving and submitting the design,
followed by higher than usual rainfall conditions,
and investigations of land that is not according to
field conditions. The impact of submitting these
claims is the addition of work, implementation time,
and compensation.
Claims that occur can be solved by several
mutually agreed methods, and included in the
contract, among others (Malak, 2002; Barrie, 1992;
Edward, 1997) : (1) Engineering Judgement, where
the design consultant appointed by the building
owner is responsible for making the final decision
on the settlement of the claim and binding on all
parties. (2) Negotiation, where the disputing party
seeks a solution without interference from other
parties. (3) Mediation, where the disputing party
uses a neutral mediator and the decision is non-
binding. (4) Arbitration, where the disputing party
appoints the arbitrator and the decision is binding.
(5) Litigation, where disputes are brought to court
and each party is represented by its lawyer. (6)
Mini-trial, where the disputing party is represented
by each project manager and the third party is an
advisor. (7) Dispute review board, where each
disputing party chooses one representative to
appoint a third party and the decision is non-
binding.
According to (Malak, 2002), To control risk
and avoid claims, several ways can be done, namely:
The parties concerned must study the contract as
well as possible, insurance, check the construction
work program before the offering period, choose a
competent construction team, apply the system
International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019
Available at www.ijsred.com
ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 652
management information to identify potential
problems.
REFERENCES
[1] Arditi, D. And Pattanakitchamroon, T.
“Analysis Methods In Time-Based Claims”, J.
Const. Eng. Mgmt., Vol. 134, No.4, 242-252. 2008.
[2] Barrie, D.S., and Paulson, B.C. Professional
Construction Management. Mc. Graw-Hill, New
York. 1992.
[3] Cox. R. K.“Managing change orders and
claims“, J. Mgmt. in Eng., Vol. 13, No.1, 24-29.
1997.
[4] Edward R., Fisk, P.E.Contruction Project
Administration, Fifth Edition, Prentice Hall, New
Jersey. 1997.
[5] Chandra H.P. Study of Submitting Construction
Claims from Contractors to Building Owners,
Journal ofDimensiTeknikSipil, Vol. 7 No. 2, pp. 90-
96. 2005.
[6] Kululanga, G.K.“Construction contractor’s
claim process framework“, J. Constr. Eng. Mgmt.,
Vol. 127, No. 4, 309-314. 2000.
[7] Malak, A., Asem, M.U., El-Saadi, M. M.H.,
Abou-Zeid, M. G. Process Model For
Administrating Construction Claims. Journal of
Construction Engineeringand Management.18(2),
84-94.2002.
[8] Nurisra. Factors Causing Submission of
Claims on Construction Projects, Civil Engineering
Journal, Syiah Kuala University, 7, pp. 93-99. 2009.
[9] Pasaribu, A. Factors Causing the occurrence of
Claims Affecting the Time Performance of Toll
Road Construction Projects in Jabodetabek, Thesis,
University of Indonesia. 2009.
[10] Putri, P.,T.Analysis of Factors Causing
Submission of Claims for Construction
Implementation by Contractors, Civil Engineering
Infrastructure Electronic Scientific Journal, pp.
VI.1-VI.7. 2013
[11] Scott, S. “Delay claims in U.K. contracts”, J.
Constr. Eng. Mgmt., Vol. 123, No. 3, 238-244.
1997.
[12] Seeley, I.V. Civilengineering contract
administration and control, 2nd. Ed., Macmillan
Press, London. 1993.
[13] Yasin, N. Recognizing Construction Claims
and Construction Dispute Settlement, Publisher:
Gramedia, Jakarta. 2004
[14] Wibowo, A. Perception Survey Submitting
Claims for Delays due to Owners on
GovernmentConstruction Projects, National Civil
Engineering Conference 3, pp. M187-193. 2009.

More Related Content

What's hot

National building code
National building codeNational building code
National building codeMayank Rawat
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSSWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSIAEME Publication
 
IRJET- Labour Safety in Construction Industry: A Literature Review
IRJET- Labour Safety in Construction Industry: A Literature ReviewIRJET- Labour Safety in Construction Industry: A Literature Review
IRJET- Labour Safety in Construction Industry: A Literature ReviewIRJET Journal
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 

What's hot (15)

National building code
National building codeNational building code
National building code
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Time overruns
Time overrunsTime overruns
Time overruns
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTSSWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
SWOT ANALYSIS OF ARBITRATION AWARDS IN INDIAN CONSTRUCTION CONTRACTS
 
IRJET- Labour Safety in Construction Industry: A Literature Review
IRJET- Labour Safety in Construction Industry: A Literature ReviewIRJET- Labour Safety in Construction Industry: A Literature Review
IRJET- Labour Safety in Construction Industry: A Literature Review
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
National Building Code 2005
National Building Code 2005National Building Code 2005
National Building Code 2005
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Bye laws fire
Bye   laws fireBye   laws fire
Bye laws fire
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 

Similar to IJSRED-V2I3P74

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsIAEME Publication
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 

Similar to IJSRED-V2I3P74 (20)

"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
Implementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projectsImplementing eichelay formula in govt. construction projects
Implementing eichelay formula in govt. construction projects
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 

More from IJSRED

IJSRED-V3I6P13
IJSRED-V3I6P13IJSRED-V3I6P13
IJSRED-V3I6P13IJSRED
 
School Bus Tracking and Security System
School Bus Tracking and Security SystemSchool Bus Tracking and Security System
School Bus Tracking and Security SystemIJSRED
 
BigBasket encashing the Demonetisation: A big opportunity
BigBasket encashing the Demonetisation: A big opportunityBigBasket encashing the Demonetisation: A big opportunity
BigBasket encashing the Demonetisation: A big opportunityIJSRED
 
Quantitative and Qualitative Analysis of Plant Leaf Disease
Quantitative and Qualitative Analysis of Plant Leaf DiseaseQuantitative and Qualitative Analysis of Plant Leaf Disease
Quantitative and Qualitative Analysis of Plant Leaf DiseaseIJSRED
 
DC Fast Charger and Battery Management System for Electric Vehicles
DC Fast Charger and Battery Management System for Electric VehiclesDC Fast Charger and Battery Management System for Electric Vehicles
DC Fast Charger and Battery Management System for Electric VehiclesIJSRED
 
Growth Path Followed by France
Growth Path Followed by FranceGrowth Path Followed by France
Growth Path Followed by FranceIJSRED
 
Acquisition System
Acquisition SystemAcquisition System
Acquisition SystemIJSRED
 
Parallelization of Graceful Labeling Using Open MP
Parallelization of Graceful Labeling Using Open MPParallelization of Graceful Labeling Using Open MP
Parallelization of Graceful Labeling Using Open MPIJSRED
 
Study of Phenotypic Plasticity of Fruits of Luffa Acutangula Var. Amara
Study of Phenotypic Plasticity of  Fruits of Luffa Acutangula Var. AmaraStudy of Phenotypic Plasticity of  Fruits of Luffa Acutangula Var. Amara
Study of Phenotypic Plasticity of Fruits of Luffa Acutangula Var. AmaraIJSRED
 
Understanding Architecture of Internet of Things
Understanding Architecture of Internet of ThingsUnderstanding Architecture of Internet of Things
Understanding Architecture of Internet of ThingsIJSRED
 
Smart shopping cart
Smart shopping cartSmart shopping cart
Smart shopping cartIJSRED
 
An Emperical Study of Learning How Soft Skills is Essential for Management St...
An Emperical Study of Learning How Soft Skills is Essential for Management St...An Emperical Study of Learning How Soft Skills is Essential for Management St...
An Emperical Study of Learning How Soft Skills is Essential for Management St...IJSRED
 
Smart Canteen Management
Smart Canteen ManagementSmart Canteen Management
Smart Canteen ManagementIJSRED
 
Gandhian trusteeship and Economic Ethics
Gandhian trusteeship and Economic EthicsGandhian trusteeship and Economic Ethics
Gandhian trusteeship and Economic EthicsIJSRED
 
Impacts of a New Spatial Variable on a Black Hole Metric Solution
Impacts of a New Spatial Variable on a Black Hole Metric SolutionImpacts of a New Spatial Variable on a Black Hole Metric Solution
Impacts of a New Spatial Variable on a Black Hole Metric SolutionIJSRED
 
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...IJSRED
 
Inginious Trafalgar Contrivition System
Inginious Trafalgar Contrivition SystemInginious Trafalgar Contrivition System
Inginious Trafalgar Contrivition SystemIJSRED
 
Farmer's Analytical assistant
Farmer's Analytical assistantFarmer's Analytical assistant
Farmer's Analytical assistantIJSRED
 
Functions of Forensic Engineering Investigator in India
Functions of Forensic Engineering Investigator in IndiaFunctions of Forensic Engineering Investigator in India
Functions of Forensic Engineering Investigator in IndiaIJSRED
 
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....IJSRED
 

More from IJSRED (20)

IJSRED-V3I6P13
IJSRED-V3I6P13IJSRED-V3I6P13
IJSRED-V3I6P13
 
School Bus Tracking and Security System
School Bus Tracking and Security SystemSchool Bus Tracking and Security System
School Bus Tracking and Security System
 
BigBasket encashing the Demonetisation: A big opportunity
BigBasket encashing the Demonetisation: A big opportunityBigBasket encashing the Demonetisation: A big opportunity
BigBasket encashing the Demonetisation: A big opportunity
 
Quantitative and Qualitative Analysis of Plant Leaf Disease
Quantitative and Qualitative Analysis of Plant Leaf DiseaseQuantitative and Qualitative Analysis of Plant Leaf Disease
Quantitative and Qualitative Analysis of Plant Leaf Disease
 
DC Fast Charger and Battery Management System for Electric Vehicles
DC Fast Charger and Battery Management System for Electric VehiclesDC Fast Charger and Battery Management System for Electric Vehicles
DC Fast Charger and Battery Management System for Electric Vehicles
 
Growth Path Followed by France
Growth Path Followed by FranceGrowth Path Followed by France
Growth Path Followed by France
 
Acquisition System
Acquisition SystemAcquisition System
Acquisition System
 
Parallelization of Graceful Labeling Using Open MP
Parallelization of Graceful Labeling Using Open MPParallelization of Graceful Labeling Using Open MP
Parallelization of Graceful Labeling Using Open MP
 
Study of Phenotypic Plasticity of Fruits of Luffa Acutangula Var. Amara
Study of Phenotypic Plasticity of  Fruits of Luffa Acutangula Var. AmaraStudy of Phenotypic Plasticity of  Fruits of Luffa Acutangula Var. Amara
Study of Phenotypic Plasticity of Fruits of Luffa Acutangula Var. Amara
 
Understanding Architecture of Internet of Things
Understanding Architecture of Internet of ThingsUnderstanding Architecture of Internet of Things
Understanding Architecture of Internet of Things
 
Smart shopping cart
Smart shopping cartSmart shopping cart
Smart shopping cart
 
An Emperical Study of Learning How Soft Skills is Essential for Management St...
An Emperical Study of Learning How Soft Skills is Essential for Management St...An Emperical Study of Learning How Soft Skills is Essential for Management St...
An Emperical Study of Learning How Soft Skills is Essential for Management St...
 
Smart Canteen Management
Smart Canteen ManagementSmart Canteen Management
Smart Canteen Management
 
Gandhian trusteeship and Economic Ethics
Gandhian trusteeship and Economic EthicsGandhian trusteeship and Economic Ethics
Gandhian trusteeship and Economic Ethics
 
Impacts of a New Spatial Variable on a Black Hole Metric Solution
Impacts of a New Spatial Variable on a Black Hole Metric SolutionImpacts of a New Spatial Variable on a Black Hole Metric Solution
Impacts of a New Spatial Variable on a Black Hole Metric Solution
 
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...
A Study to Assess the Effectiveness of Planned Teaching Programme on Knowledg...
 
Inginious Trafalgar Contrivition System
Inginious Trafalgar Contrivition SystemInginious Trafalgar Contrivition System
Inginious Trafalgar Contrivition System
 
Farmer's Analytical assistant
Farmer's Analytical assistantFarmer's Analytical assistant
Farmer's Analytical assistant
 
Functions of Forensic Engineering Investigator in India
Functions of Forensic Engineering Investigator in IndiaFunctions of Forensic Engineering Investigator in India
Functions of Forensic Engineering Investigator in India
 
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....
Participation Politique Feminine En Competition Électorale Au Congo-Kinshasa....
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 

IJSRED-V2I3P74

  • 1. International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019 Available at www.ijsred.com ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 648 Causes of Claims in the Construction Project Anita Rauzana*, Tripoli** *(Department of Civil Engineering,Syiah Kuala University, Aceh Province, Indonesia) **(Department of Civil Engineering,Syiah Kuala University, Aceh Province, Indonesia) ----------------------------------------************************---------------------------------- Abstract: Claims on construction projects are requests or demands for adding costs, and time of construction. Claims can trigger a dispute because the implementation of the project is not in accordance with the contract. Construction contracts are used as guidelines in submitting construction claims. Studies of construction claims have been carried out by various researchers, and every cause of construction claims is influenced by location / area, and project characteristics. This study aims to establish the theoretical framework for the cause of contractor claims for delays in construction projects from literature review, various research results, literature, and various relevant information. According to a review of several articles / research, obtained factors that influence claims are design changes. Keywords – claims, contractors, construction, owners, projects ----------------------------------------************************---------------------------------- I. INTRODUCTION The construction industry is a complex industrial sector, and can contribute to economic growth in Indonesia. The role of the construction industry is cooperation from various sectors. However, relations between these sectors often run less smoothly, due to the construction industry often having complicated problems, so that relations with other sectors are disrupted. This is due to the development of the construction industry being a complex industry both in terms of forms, costs, contract systems, and existing resources. For project owners, especially the government, it avoids claims, while contractors are reluctant to make claims, for fear of being recorded as a contracting company that has poor performance (Yasin, 2004). This article presents review results of the causes of claims on private and government projects. Construction claims occur because one RESEARCH ARTICLE OPEN ACCESS
  • 2. International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019 Available at www.ijsred.com ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 649 party fails to carry out its responsibilities and obligations. In implementing the project, the agreement reached is stated in the contract document. But during this time, there were still frequent disputes between the owner and the contractor, or the contractor blamed the consultant. To minimize the problem, it is very important to know the risks that can occur in the project, and whether those risks are covered in the contract articles. Risk is one of the important things that must be considered in each project. Risk occurs in every project and contractor, therefore, it must be aware of the effects of risk by implementing good risk management. Risk is a condition that arises because of uncertainty in the implementation of a construction project. Claims is demands, however, the notion of claims according to Wibowo (2009), that claims are categorized into three as contractual claims, ex- contractual claims, and common law claims, as well as formulating four strategies for contractors so that claims can be overcome, namely recognizing claims, providing accurate notifications, collecting documentation complete, and present claims so that the owner can grant the claim submitted. Claims will arise when one party believes that it has been harmed by another party neglecting its contractual obligations, therefore it needs to get compensation (Kuluanga et al., 2000). Claims can occur with owners, contractors or suppliers (Cox, 1997). The definition of claim is more directed at the contractor's request to compensate for losses or avoid liquidated damages (Seeley, 1993). It can be concluded that claims occur because of a request for the implementation of a construction service work between the contractor and the owner, or with a sub contractor related to additional costs, time and other compensation. Yasin (2004) concluded that the main causes of construction claims are: 1) Inaccurate design information 2) Incomplete design information 3) Investigation of incomplete locations 4) Slow client reactions / responses 5) Poor communication between human resources 6) Time targets that are not realized 7) Imperfect administration 8) Incomplete tender information 9) Unclear risk allocation 10) Late payment Due to delays in construction projects and additional costs, it is important to know what factors contribute to claims in the construction project. The incompatibility of the realization with the expectations of the construction project has the potential to cause losses to the owner and the implementing contractor. Incompatibility that occurs is the time of implementation, namely the project is completed outside the time set. Parties who experience losses due to delays must be able to
  • 3. International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019 Available at www.ijsred.com ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 650 recognize who should be responsible for the delay (Arditi 2008), then can take appropriate steps to reduce or eliminate the losses incurred. Based on the responsible party, delay can be classified into three, namely due to owner delays (commonly known as type E), contractors (type C), and not due to owners and contractors (type N). Determination of the responsible party is important to determine the type of compensation that must be given, whether time compensation, and cost compensation (Scott 1997) II. METHODOLOGY The purpose of writing this article is to establish a theoretical framework for potential construction claims by contractors, conducting studies from previous studies, journals, and from relevant literature reviews. The methodology used in this article is using the study of literature. III. RESULTS AND DISCUSSION Identification of potential claims by contractors on construction projects is carried out by conducting studies from various literature studies. The study of construction claims by contractors to the owners of construction projects is often done, different results regarding the main causes of contractor claims to the owners of construction projects have been investigated by previous researchers. Wibowo (2009) presented the results of a survey of construction service actors about the practice of contractor claims to project owners, because the delay was the responsibility of government construction project owners. Based on frequency, there are three main reasons why claims are not submitted by contractors are (1) claims are not significant, (2) unpreparedness of supporting claims documents, (3) the need to maintain good relations with service users. Meanwhile the reason for service users (project owners) rejecting contractor's claims is (1) claims not regulated in the contract, (2) incomplete supporting documents for claims, (3) budget unavailability. According to Pasaribu (2009), there are findings that claims have a correlation of 81.2% on time performance. There are claims that affect payments to air conditioning subcontractors, architectural subcontractors, and interior subcontractors. Chandra (2005) stated that the main causes of claims were design changes and added work carried out by building owners, whereas contractor claims often took the form of additional costs, and claim settlement methods, which are often used by parties are engineering judgment methods. According to Satwanirat (2009), building construction claims submitted by the contractor to the owner during the construction process almost frequently occur, and a good understanding of claim submission is needed which can help contractors in the process of submitting their
  • 4. International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019 Available at www.ijsred.com ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 651 claims, claims get additional time, additional costs and or compensation. According to Putri (2013), the implementation of construction project claims is divided into the consequences of (1) the actions of the project owner, (2) the consultant planner's actions, (3) supervisory counseling, and ( 4) external factors. According to Nurisra (2009), there are 7 groups of factors that cause claims, namely: 1) contract articles that are incomplete and clear, 2) conflicts in design, specifications and special risks, 3) changes or modifications to the contents of contracts, 4) weather conditions, 5) differences in field conditions, 6) changes in schedule by the owner, 7) delays due to the owner. The most potential claim in the ranking is higher than usual rainfall, and the land investigation conducted by the owner does not describe the project land conditions. IV. CONCLUSION Construction claims caused by the owner as a demand for the contractor, which leads to requests for additional time to complete, and is still a problem that is always present in every construction project. The results of the study on the factors causing the submission of construction claims from several articles / studies determine the main rating, namely the change in design by the owner, and the delay in approving and submitting the design, followed by higher than usual rainfall conditions, and investigations of land that is not according to field conditions. The impact of submitting these claims is the addition of work, implementation time, and compensation. Claims that occur can be solved by several mutually agreed methods, and included in the contract, among others (Malak, 2002; Barrie, 1992; Edward, 1997) : (1) Engineering Judgement, where the design consultant appointed by the building owner is responsible for making the final decision on the settlement of the claim and binding on all parties. (2) Negotiation, where the disputing party seeks a solution without interference from other parties. (3) Mediation, where the disputing party uses a neutral mediator and the decision is non- binding. (4) Arbitration, where the disputing party appoints the arbitrator and the decision is binding. (5) Litigation, where disputes are brought to court and each party is represented by its lawyer. (6) Mini-trial, where the disputing party is represented by each project manager and the third party is an advisor. (7) Dispute review board, where each disputing party chooses one representative to appoint a third party and the decision is non- binding. According to (Malak, 2002), To control risk and avoid claims, several ways can be done, namely: The parties concerned must study the contract as well as possible, insurance, check the construction work program before the offering period, choose a competent construction team, apply the system
  • 5. International Journal of Scientific Research and Engineering Development-– Volume 2 Issue 3, May –June 2019 Available at www.ijsred.com ISSN : 2581-7175 ©IJSRED: All Rights are Reserved Page 652 management information to identify potential problems. REFERENCES [1] Arditi, D. And Pattanakitchamroon, T. “Analysis Methods In Time-Based Claims”, J. Const. Eng. Mgmt., Vol. 134, No.4, 242-252. 2008. [2] Barrie, D.S., and Paulson, B.C. Professional Construction Management. Mc. Graw-Hill, New York. 1992. [3] Cox. R. K.“Managing change orders and claims“, J. Mgmt. in Eng., Vol. 13, No.1, 24-29. 1997. [4] Edward R., Fisk, P.E.Contruction Project Administration, Fifth Edition, Prentice Hall, New Jersey. 1997. [5] Chandra H.P. Study of Submitting Construction Claims from Contractors to Building Owners, Journal ofDimensiTeknikSipil, Vol. 7 No. 2, pp. 90- 96. 2005. [6] Kululanga, G.K.“Construction contractor’s claim process framework“, J. Constr. Eng. Mgmt., Vol. 127, No. 4, 309-314. 2000. [7] Malak, A., Asem, M.U., El-Saadi, M. M.H., Abou-Zeid, M. G. Process Model For Administrating Construction Claims. Journal of Construction Engineeringand Management.18(2), 84-94.2002. [8] Nurisra. Factors Causing Submission of Claims on Construction Projects, Civil Engineering Journal, Syiah Kuala University, 7, pp. 93-99. 2009. [9] Pasaribu, A. Factors Causing the occurrence of Claims Affecting the Time Performance of Toll Road Construction Projects in Jabodetabek, Thesis, University of Indonesia. 2009. [10] Putri, P.,T.Analysis of Factors Causing Submission of Claims for Construction Implementation by Contractors, Civil Engineering Infrastructure Electronic Scientific Journal, pp. VI.1-VI.7. 2013 [11] Scott, S. “Delay claims in U.K. contracts”, J. Constr. Eng. Mgmt., Vol. 123, No. 3, 238-244. 1997. [12] Seeley, I.V. Civilengineering contract administration and control, 2nd. Ed., Macmillan Press, London. 1993. [13] Yasin, N. Recognizing Construction Claims and Construction Dispute Settlement, Publisher: Gramedia, Jakarta. 2004 [14] Wibowo, A. Perception Survey Submitting Claims for Delays due to Owners on GovernmentConstruction Projects, National Civil Engineering Conference 3, pp. M187-193. 2009.