SlideShare a Scribd company logo
1
RICS Singapore Branch
CPD Event 19 June 2012
An Overview of the FIDIC
FORMS OF CONTRACT
and Contracts Committee
Activities
© www.asia-masters.com
Objectives
• Educational and informative
• Identify and prioritise industry issues
• Assess barriers, opportunities and risks
• Identify potential actions (by FIDIC/CC)
• Identify milestones, success factors and
how to assess or measure progress
2
© www.asia-masters.com
3
Consultancy Agreements
• Client/Consultant Model Services
Agreement, Fourth Edition 2006
• Sub-Consultancy Agreement, First
Edition 1992
• Joint Venture Agreement, First Edition
1992
• Model Representative Agreement, Test
Edition 2004
© www.asia-masters.com
4
The Traditional FIDIC Forms
of Contract
• Conditions of Contract for Works of Civil
Engineering Construction (Red Book)
Fourth Edition 1987
• Conditions of Contract for Electrical and
Mechanical Works including Erection on
Site (Yellow Book) Third Edition 1987
© www.asia-masters.com
5
Basics
• Between Employer and Contractor
• Red Book: payment monthly for work done
• Yellow Book: lump sum on milestones
• Every project is unique
• Guidelines of ’best practice’
• Part I – General Conditions
• Part II – Conditions of Particular Application
© www.asia-masters.com
6
Fair and balanced approach
• Risk is allocated to the party that is best able
to bear and control that risk
• Compensation and time extension allowed
when uncalculated hindrances occur
• ‘Engineer’ whose job is principally to
supervise and monitor the work
– in strict accordance with the Contract to the
satisfaction of the Engineer
– with formal ‘Engineer’s Decision’
© www.asia-masters.com
7
The Orange Book
• Conditions of Contract for Design-Build and
Turnkey (Orange Book) First Edition 1995
• Employer’s Representative
– not required to be impartial
– determine matters fairly, reasonably and in
accordance with the Contract
• Independent dispute adjudication board
• 1996/7 Supplements for use of DAB (R/Y
Books)
© www.asia-masters.com
8
The 1999 Suite of Standard
Conditions of Contract
• Conditions of Contract for Construction - design
by Employer: The Construction Contract (The
New Red Book)
• Conditions of Contract for Plant and Design-Build
- design by Contractor: The Plant and
Design/Build Contract (The New Yellow Book)
• Conditions of Contract for EPC Turnkey Projects:
The EPC/Turnkey Contract (The Silver Book)
• Short Form of Contract: The Short Form (The
Green Book)
• The FIDIC Contracts Guide (2000)
9
Principles behind the
1999 Books
• More consistent wording, with improved
clarity; user-friendly format and layout
• Balance between legal precision and
practicability; compatible with both
common and civil law concepts
• ‘Manuals of good engineering practice’
• Prepared by engineers for practical use
© www.asia-masters.com
10
Principles (continued)
• Traditional role of ‘the Engineer’ to
make impartial determinations modified
to reflect current practice (Red and
Yellow Books)
• ‘Employer’s Representative’ introduced:
must be fair and reasonable (Silver and
Green Books)
11
Principles (continued)
• Distinction between the Books is based
on:
–who does the design?
–who bears the risk for change in
quantities?
• EPC (Silver Book) provides for the
Contractor taking almost all risks (new
for FIDIC)
• Short Form (Green Book) deals with the
wide demand for a simpler form of
contract © www.asia-masters.com
12
Principles (continued)
• Work must continue, regardless of
differences: amicable settlement
encouraged
• Strong financial management: detailed
claims procedures must be followed
© www.asia-masters.com
13
General Remarks on
the 1999 Books
• Suitable for both ‘international’ and
domestic use
• A framework adaptable to suit local law
• More definitions: harmonised, except
for the Short Form
© www.asia-masters.com
14
General Remarks (continued)
• General Conditions not applicable can
be disregarded
• Example Particular Conditions are given
• Adjudication precedes arbitration
© www.asia-masters.com
15
The 1999 Red and Yellow Books
• Emphasis changed to party responsible for
design
• 1999 Yellow Book replaced both 1987 Yellow
Book and Orange Book
• Traditional competitive tendering procedures
• Risk sharing is balanced
• All claims, from either Party, have to follow a
strict procedure
• Engineer is no longer stated to be ‘impartial’:
he ‘shall be deemed to act for the Employer’,
except when fair determinations are required
16
The 1999 Red Book
• For building and engineering works
designed by the Employer
• Needs of modern multi-discipline
contracts recognised
• Partial Contractor design possible
• Valuation and payment based on
remeasurement of quantities, but lump
sum or cost plus could be used
© www.asia-masters.com
17
1999 Red Book (continued)
• No ‘Clause 67’ Engineer’s decision
• If a dispute arises, reference to DAB
• Dispute resolution procedure is:
adjudication (DAB)>>>amicable
settlement >>>arbitration
© www.asia-masters.com
18
The 1999 Yellow Book
• For E&M plant, and for building and
engineering works, designed by the
Contractor
• Needs of modern multi-discipline
contracts recognised
• Partial Employer design: include in
Employer’s Requirements
© www.asia-masters.com
19
1999 Yellow Book (continued)
• Valuation and payment based on lump
sum with payment plan, but
remeasurement possible
• No ‘Clause 67’ Engineer’s decision
• If a dispute arises, reference to DAB
• Dispute resolution procedure is:
adjudication (DAB)>>>amicable
settlement >>>arbitration
© www.asia-masters.com
20
The Silver Book
(EPCT Contract)
• More certain final price and time required
- balance of risk being changed
- privately financed BOT type
• Contractor asked to cover extra risks
• Employer will have to pay more
• Completely new Book - ‘unbalanced’ risk
• BUT full open acceptance of risk picture
• Starting point for BOT type projects
© www.asia-masters.com
21
The Silver Book (continued)
• The EPCT Contract is suitable for:
particularly E&M and process plant
projects
all types of Employers
civil law jurisdictions
where government employer or private
developer wants a fixed price turnkey
basis and two-party approach
• There is an ‘Introductory Note’ of explanation
© www.asia-masters.com
22
Special Features of the
Silver Book
• Responsibility for design lies with Contractor
• Employer’s Requirements usually a
‘performance specification’ (functional basis)
• Contractor carries out all engineering,
procurement, construction, ready for
operation at the ‘turn of a key’
• No Engineer - instead the Employer
• Lump Sum Contract Price (but adjustments in
limited specified cases)
23
Special Features (continued)
• Testing procedures to demonstrate
achievement of specified end result
• Contractor carries majority of risks, so
Employer pays more
• Final price and time should be more certain
• Small number of tenderers with negotiation
• Contractor given freedom to use own
methods
• Has to prove reliability and performance
24
Special Features (continued)
• These Conditions are not suitable in the following
circumstances:
if time or information is insufficient before Contract
signature
if considerable work underground or difficult to
inspect
if Employer intends to supervise closely or control
or review
if an intermediary certifies interim payments
where part of the Works is designed by Employer
for public bidding without negotiations
• For such circumstances P&DB should be used
instead
© www.asia-masters.com
25
The Green Book
(Short Form of Contract)
• US$ 500,000 and six months’ duration
• Simple and repetitive works
• All provisions necessary in 15 clauses
• Language uncomplicated and simple
• Balanced risk sharing - no Engineer
• Design by either party - all types of
construction
• Payment on lump sum or any other basis
© www.asia-masters.com
26
Dredging and Reclamation
• Design by Employer or Contractor
• Valuation – all main methods available
• Engineer required to act “fairly” in
accordance with Contract
• No defects liability on dredging
• Special insurance provisions
• Adjudication by DAB, then arbitration
© www.asia-masters.com
27
Red Book MDB Harmonised
Version
• Based on 1999 Red Book
• Incorporates main common changes
normally required by MDBs, e.g.-
audits, labour provisions, corruption
avoidance, dispute settlement
• Use subject to Licence Agreement
between FIDIC and participating banks
© www.asia-masters.com
28
Design, Build and Operate
Projects
• Conditions of Contract for Design, Build
and Operate Projects (Gold Book), First
Edition 2008
• Assumes ~20-year operation period
• Modern approach to risk and insurance
• Employer’s Representative
• Adjudication by DAB, then arbitration
© www.asia-masters.com
29
Subcontracts
• Conditions of Subcontract for
Construction, Test Edition 2009
• Intended for use with 1999 Red Book
• General Conditions – Particular
Conditions
• Annexes require provision of relevant
information
© www.asia-masters.com
30
Protection of the
Environment
• The Contractor shall take all reasonable
steps to protect the environment (both
on and off the Site) and to limit damage
and nuisance to people and property
resulting from pollution, noise and other
results of his operations
© www.asia-masters.com
31
Environment (continued)
• The Contractor shall ensure that
emissions, surface discharge and
effluent from the Contractor’s activities
shall not exceed the values indicated in
the Specification, and shall not exceed
the values prescribed by applicable
Laws
© www.asia-masters.com
32
Project Phases
• Initiation
• Study and Evaluation
• Design Development
• Detailed Design
• Contracts
• Construction, Manufacture, Shipping,
Installation, Testing and Commissioning
• Operations and Maintenance
© www.asia-masters.com
33
Initiation
• The Concept
• The Big Decisions
• Policy
• Major Choices
© www.asia-masters.com
34
Study and Evaluation
• Feasibility
• Alternatives
• Strategy
• Statutory Requirements
© www.asia-masters.com
35
Design Development/
Detailed Design
• Specifications
• Special Requirements
• Approvals
• Inclusion of results/outcomes from earlier
Project Phases
© www.asia-masters.com
Contracts Committee
• Mandate from Executive Committee
• Members: Christoph Theune/ Zoltán
Záhonyi/Philip Jenkinson
• Special Advisers: Nael Bunni/ Axel Jaeger/
Michael Mortimer-Hawkins/ Chris Seppala/
Chris Wade
• Task Group Leaders and Members
36
© www.asia-masters.com
Contracts Committee Terms of
Reference
• To recommend to the Executive Committee which Conditions of
Contract and related documents should be prepared or updated
by FIDIC
• To assist the Secretariat in establishing Task Groups as
required, to monitor their work at agreed intervals and to carry
out a final review of the documents for submission to the
Executive Committee
• To assist the Secretariat in handling queries on the
interpretation of documents
• To liaise, in conjunction with the Secretariat, with organisations
interested in the FIDIC Conditions of Contract
• To suggest topics and speakers as appropriate for seminars
and workshops
37
© www.asia-masters.com
Current Workload
• TG1 – DBO Form of Contract
• TG2 – Procurement Procedures Guide
• TG4 – Consultancy Agreements
• TG5 – Subcontract Form (Red Book)
• TG6 – Update of 1999 Suite (Yellow Book first)
• TG7 – Update of Dredging Contract (with IADC)
• TG8 – Update of Short Form (Green Book)
• TG9 – YB/SB Subcontract Forms
• TG10 – Tunnelling (proposed, with ITA)
• TG11 – ODB Form of Contract
• Training Courses
38
© www.asia-masters.com

More Related Content

What's hot

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
Loay Ghazaleh MBA, BSc Civil Eng.
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Moustafa Ismail Abu Dief
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
Jeff B
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Cl presentation
Cl presentationCl presentation
Cl presentation
lucaschinsheng
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
ASHISH KUMAR SINGH
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
M Maged Hegazy, LLM, MBA, CCP, P3O
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
PachyCarmona1
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
Moustafa Ismail Abu Dief
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
Haytham Baraka, PMP, CCP, SP, RMP,APC-RICS Candidate.
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
Francis Ho
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
Gerald R. (Jerry) Genge
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
mohamed Ismail
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
JIT KUMAR GUPTA
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
Hani Saad
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
JIT KUMAR GUPTA
 

What's hot (20)

FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
FIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdfFIDIC Presentation-2016.pdf
FIDIC Presentation-2016.pdf
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Implications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbookImplications of different_types_of_variation_under_fidic_1999_redbook
Implications of different_types_of_variation_under_fidic_1999_redbook
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 

Viewers also liked

Contracts classification
Contracts classificationContracts classification
Contracts classification
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Risk in FIDIC contracts
Risk in FIDIC contracts Risk in FIDIC contracts
Risk in FIDIC contracts
Paul Gogulski
 
Essaf
EssafEssaf
Essaf
Emad Hamed
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
M Maged Hegazy, LLM, MBA, CCP, P3O
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
M Maged Hegazy, LLM, MBA, CCP, P3O
 
الإملاء
الإملاءالإملاء
الإملاء
Emad Hamed
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
M Maged Hegazy, LLM, MBA, CCP, P3O
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
Vimal Daluwatta
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Project Controls Expo
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
Ricardo Viana Vargas
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
katrin enders
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceFrancis Ho
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
Planisware
 

Viewers also liked (19)

Contracts classification
Contracts classificationContracts classification
Contracts classification
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
Risk in FIDIC contracts
Risk in FIDIC contracts Risk in FIDIC contracts
Risk in FIDIC contracts
 
Essaf
EssafEssaf
Essaf
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
الإملاء
الإملاءالإملاء
الإملاء
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 

Similar to An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities

FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
DonaAlisyahSiregar
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
Quigg Golden Limited
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
Association for Project Management
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
ByishimoBTCChef
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Kipcon Inc.
 
Renovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewRenovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewConstruction Cicerone
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
Delhi Technological University
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulationsJulian Swindell
 
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
sheryl90
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
Delhi Technological University
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
drs. ing. George van Bommel MBE, BSc
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
drs. ing. George van Bommel MBE, BSc
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
Browne Jacobson LLP
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
César del Riego y Fuentes
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in ppp
ChhabiYadav2
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
This account is closed
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
AkankshaPendharkar1
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
Melissa Brumback
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
teohwooisin
 

Similar to An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities (20)

FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Renovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner ViewRenovate Repair Legal Issues Owner View
Renovate Repair Legal Issues Owner View
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Building Contracts and CDM regulations
Building Contracts and CDM regulationsBuilding Contracts and CDM regulations
Building Contracts and CDM regulations
 
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
1._pmc_2019_day_1_project_initiation_and_planning_final.pptx
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in ppp
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
Drafting Construction Contracts
Drafting Construction ContractsDrafting Construction Contracts
Drafting Construction Contracts
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 

More from Asia Master Training آسيا ماسترز للتدريب والتطوير

Annual training plan 2018 2018
Annual training plan 2018 2018Annual training plan 2018 2018
Human Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and PlanningHuman Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and Planning
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Purpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview LandscapePurpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview Landscape
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACTNATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication TestingOPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Microsoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills TrainingMicrosoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills Training
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Competency Modeling v. Job Analysis
Competency Modeling v. Job AnalysisCompetency Modeling v. Job Analysis
Competency gaps for Professional Development
Competency gaps for Professional DevelopmentCompetency gaps for Professional Development
Competency Approach to Human Resource Management
Competency Approach to Human Resource ManagementCompetency Approach to Human Resource Management
Competency Approach to Human Resource Management
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Developing a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency FrameworkDeveloping a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency Framework
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Organizational Change and Development
Organizational Change and DevelopmentOrganizational Change and Development
Competency-based Management for the DoD-wide Contracting Community
Competency-based Management for the   DoD-wide Contracting CommunityCompetency-based Management for the   DoD-wide Contracting Community
Competency-based Management for the DoD-wide Contracting Community
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & TeachingCOMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
The Counseling Interview - Principles & Practices
The Counseling Interview - Principles & PracticesThe Counseling Interview - Principles & Practices
The Counseling Interview - Principles & Practices
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality OrganizationBehavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Effective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best PersonEffective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best Person
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Industrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting EmployeesIndustrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting Employees
Asia Master Training آسيا ماسترز للتدريب والتطوير
 
Structuring the Interview - Hiring Skills
Structuring the Interview - Hiring SkillsStructuring the Interview - Hiring Skills

More from Asia Master Training آسيا ماسترز للتدريب والتطوير (20)

Annual training plan 2018 2018
Annual training plan 2018 2018Annual training plan 2018 2018
Annual training plan 2018 2018
 
Human Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and PlanningHuman Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and Planning
 
Purpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview LandscapePurpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview Landscape
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACTNATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
 
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication TestingOPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
 
Microsoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills TrainingMicrosoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills Training
 
Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training
 
Competency Modeling v. Job Analysis
Competency Modeling v. Job AnalysisCompetency Modeling v. Job Analysis
Competency Modeling v. Job Analysis
 
Competency gaps for Professional Development
Competency gaps for Professional DevelopmentCompetency gaps for Professional Development
Competency gaps for Professional Development
 
Competency Approach to Human Resource Management
Competency Approach to Human Resource ManagementCompetency Approach to Human Resource Management
Competency Approach to Human Resource Management
 
Developing a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency FrameworkDeveloping a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency Framework
 
Organizational Change and Development
Organizational Change and DevelopmentOrganizational Change and Development
Organizational Change and Development
 
Competency-based Management for the DoD-wide Contracting Community
Competency-based Management for the   DoD-wide Contracting CommunityCompetency-based Management for the   DoD-wide Contracting Community
Competency-based Management for the DoD-wide Contracting Community
 
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & TeachingCOMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
 
The Counseling Interview - Principles & Practices
The Counseling Interview - Principles & PracticesThe Counseling Interview - Principles & Practices
The Counseling Interview - Principles & Practices
 
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality OrganizationBehavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality Organization
 
Effective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best PersonEffective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best Person
 
Industrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting EmployeesIndustrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting Employees
 
Structuring the Interview - Hiring Skills
Structuring the Interview - Hiring SkillsStructuring the Interview - Hiring Skills
Structuring the Interview - Hiring Skills
 

Recently uploaded

Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
Purushottam Jha
 
How to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the NetherlandsHow to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the Netherlands
BridgeWest.eu
 
Agrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quizAgrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quiz
gaelcabigunda
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
Abdul-Hakim Shabazz
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
ssuser5750e1
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
MwaiMapemba
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
shweeta209
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
KHURRAMWALI
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
ssuser0576e4
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
Finlaw Consultancy Pvt Ltd
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
OmGod1
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
9ib5wiwt
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
Wendy Couture
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
9ib5wiwt
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
9ib5wiwt
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
BRELGOSIMAT
 
ALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdfALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdf
46adnanshahzad
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
AHRP Law Firm
 
DNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptxDNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptx
patrons legal
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
anjalidixit21
 

Recently uploaded (20)

Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.Law Commission Report. Commercial Court Act.
Law Commission Report. Commercial Court Act.
 
How to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the NetherlandsHow to Obtain Permanent Residency in the Netherlands
How to Obtain Permanent Residency in the Netherlands
 
Agrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quizAgrarian Reform Policies in the Philippines: a quiz
Agrarian Reform Policies in the Philippines: a quiz
 
Rokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal OpinionRokita Releases Soccer Stadium Legal Opinion
Rokita Releases Soccer Stadium Legal Opinion
 
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdfDonald_J_Trump_katigoritirio_stormi_daniels.pdf
Donald_J_Trump_katigoritirio_stormi_daniels.pdf
 
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW  AN OVERVIEW in Malawi.pptxEMPLOYMENT LAW  AN OVERVIEW in Malawi.pptx
EMPLOYMENT LAW AN OVERVIEW in Malawi.pptx
 
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptxASHWINI KUMAR UPADHYAY v/s Union of India.pptx
ASHWINI KUMAR UPADHYAY v/s Union of India.pptx
 
WINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of DissolutionWINDING UP of COMPANY, Modes of Dissolution
WINDING UP of COMPANY, Modes of Dissolution
 
Debt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debtDebt Mapping Camp bebas riba to know how much our debt
Debt Mapping Camp bebas riba to know how much our debt
 
Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...Responsibilities of the office bearers while registering multi-state cooperat...
Responsibilities of the office bearers while registering multi-state cooperat...
 
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptxRIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
RIGHTS OF VICTIM EDITED PRESENTATION(SAIF JAVED).pptx
 
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
怎么购买(massey毕业证书)新西兰梅西大学毕业证学位证书注册证明信原版一模一样
 
Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)Business and Corporate Case Update (2024)
Business and Corporate Case Update (2024)
 
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
定制(nus毕业证书)新加坡国立大学毕业证学位证书实拍图原版一模一样
 
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
1比1制作(swansea毕业证书)英国斯旺西大学毕业证学位证书托业成绩单原版一模一样
 
Notes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.docNotes-on-Prescription-Obligations-and-Contracts.doc
Notes-on-Prescription-Obligations-and-Contracts.doc
 
ALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdfALL EYES ON RAFAH BUT WHY Explain more.pdf
ALL EYES ON RAFAH BUT WHY Explain more.pdf
 
Introducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdfIntroducing New Government Regulation on Toll Road.pdf
Introducing New Government Regulation on Toll Road.pdf
 
DNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptxDNA Testing in Civil and Criminal Matters.pptx
DNA Testing in Civil and Criminal Matters.pptx
 
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptxHighlights_of_Bhartiya_Nyaya_Sanhita.pptx
Highlights_of_Bhartiya_Nyaya_Sanhita.pptx
 

An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities

  • 1. 1 RICS Singapore Branch CPD Event 19 June 2012 An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activities © www.asia-masters.com
  • 2. Objectives • Educational and informative • Identify and prioritise industry issues • Assess barriers, opportunities and risks • Identify potential actions (by FIDIC/CC) • Identify milestones, success factors and how to assess or measure progress 2 © www.asia-masters.com
  • 3. 3 Consultancy Agreements • Client/Consultant Model Services Agreement, Fourth Edition 2006 • Sub-Consultancy Agreement, First Edition 1992 • Joint Venture Agreement, First Edition 1992 • Model Representative Agreement, Test Edition 2004 © www.asia-masters.com
  • 4. 4 The Traditional FIDIC Forms of Contract • Conditions of Contract for Works of Civil Engineering Construction (Red Book) Fourth Edition 1987 • Conditions of Contract for Electrical and Mechanical Works including Erection on Site (Yellow Book) Third Edition 1987 © www.asia-masters.com
  • 5. 5 Basics • Between Employer and Contractor • Red Book: payment monthly for work done • Yellow Book: lump sum on milestones • Every project is unique • Guidelines of ’best practice’ • Part I – General Conditions • Part II – Conditions of Particular Application © www.asia-masters.com
  • 6. 6 Fair and balanced approach • Risk is allocated to the party that is best able to bear and control that risk • Compensation and time extension allowed when uncalculated hindrances occur • ‘Engineer’ whose job is principally to supervise and monitor the work – in strict accordance with the Contract to the satisfaction of the Engineer – with formal ‘Engineer’s Decision’ © www.asia-masters.com
  • 7. 7 The Orange Book • Conditions of Contract for Design-Build and Turnkey (Orange Book) First Edition 1995 • Employer’s Representative – not required to be impartial – determine matters fairly, reasonably and in accordance with the Contract • Independent dispute adjudication board • 1996/7 Supplements for use of DAB (R/Y Books) © www.asia-masters.com
  • 8. 8 The 1999 Suite of Standard Conditions of Contract • Conditions of Contract for Construction - design by Employer: The Construction Contract (The New Red Book) • Conditions of Contract for Plant and Design-Build - design by Contractor: The Plant and Design/Build Contract (The New Yellow Book) • Conditions of Contract for EPC Turnkey Projects: The EPC/Turnkey Contract (The Silver Book) • Short Form of Contract: The Short Form (The Green Book) • The FIDIC Contracts Guide (2000)
  • 9. 9 Principles behind the 1999 Books • More consistent wording, with improved clarity; user-friendly format and layout • Balance between legal precision and practicability; compatible with both common and civil law concepts • ‘Manuals of good engineering practice’ • Prepared by engineers for practical use © www.asia-masters.com
  • 10. 10 Principles (continued) • Traditional role of ‘the Engineer’ to make impartial determinations modified to reflect current practice (Red and Yellow Books) • ‘Employer’s Representative’ introduced: must be fair and reasonable (Silver and Green Books)
  • 11. 11 Principles (continued) • Distinction between the Books is based on: –who does the design? –who bears the risk for change in quantities? • EPC (Silver Book) provides for the Contractor taking almost all risks (new for FIDIC) • Short Form (Green Book) deals with the wide demand for a simpler form of contract © www.asia-masters.com
  • 12. 12 Principles (continued) • Work must continue, regardless of differences: amicable settlement encouraged • Strong financial management: detailed claims procedures must be followed © www.asia-masters.com
  • 13. 13 General Remarks on the 1999 Books • Suitable for both ‘international’ and domestic use • A framework adaptable to suit local law • More definitions: harmonised, except for the Short Form © www.asia-masters.com
  • 14. 14 General Remarks (continued) • General Conditions not applicable can be disregarded • Example Particular Conditions are given • Adjudication precedes arbitration © www.asia-masters.com
  • 15. 15 The 1999 Red and Yellow Books • Emphasis changed to party responsible for design • 1999 Yellow Book replaced both 1987 Yellow Book and Orange Book • Traditional competitive tendering procedures • Risk sharing is balanced • All claims, from either Party, have to follow a strict procedure • Engineer is no longer stated to be ‘impartial’: he ‘shall be deemed to act for the Employer’, except when fair determinations are required
  • 16. 16 The 1999 Red Book • For building and engineering works designed by the Employer • Needs of modern multi-discipline contracts recognised • Partial Contractor design possible • Valuation and payment based on remeasurement of quantities, but lump sum or cost plus could be used © www.asia-masters.com
  • 17. 17 1999 Red Book (continued) • No ‘Clause 67’ Engineer’s decision • If a dispute arises, reference to DAB • Dispute resolution procedure is: adjudication (DAB)>>>amicable settlement >>>arbitration © www.asia-masters.com
  • 18. 18 The 1999 Yellow Book • For E&M plant, and for building and engineering works, designed by the Contractor • Needs of modern multi-discipline contracts recognised • Partial Employer design: include in Employer’s Requirements © www.asia-masters.com
  • 19. 19 1999 Yellow Book (continued) • Valuation and payment based on lump sum with payment plan, but remeasurement possible • No ‘Clause 67’ Engineer’s decision • If a dispute arises, reference to DAB • Dispute resolution procedure is: adjudication (DAB)>>>amicable settlement >>>arbitration © www.asia-masters.com
  • 20. 20 The Silver Book (EPCT Contract) • More certain final price and time required - balance of risk being changed - privately financed BOT type • Contractor asked to cover extra risks • Employer will have to pay more • Completely new Book - ‘unbalanced’ risk • BUT full open acceptance of risk picture • Starting point for BOT type projects © www.asia-masters.com
  • 21. 21 The Silver Book (continued) • The EPCT Contract is suitable for: particularly E&M and process plant projects all types of Employers civil law jurisdictions where government employer or private developer wants a fixed price turnkey basis and two-party approach • There is an ‘Introductory Note’ of explanation © www.asia-masters.com
  • 22. 22 Special Features of the Silver Book • Responsibility for design lies with Contractor • Employer’s Requirements usually a ‘performance specification’ (functional basis) • Contractor carries out all engineering, procurement, construction, ready for operation at the ‘turn of a key’ • No Engineer - instead the Employer • Lump Sum Contract Price (but adjustments in limited specified cases)
  • 23. 23 Special Features (continued) • Testing procedures to demonstrate achievement of specified end result • Contractor carries majority of risks, so Employer pays more • Final price and time should be more certain • Small number of tenderers with negotiation • Contractor given freedom to use own methods • Has to prove reliability and performance
  • 24. 24 Special Features (continued) • These Conditions are not suitable in the following circumstances: if time or information is insufficient before Contract signature if considerable work underground or difficult to inspect if Employer intends to supervise closely or control or review if an intermediary certifies interim payments where part of the Works is designed by Employer for public bidding without negotiations • For such circumstances P&DB should be used instead © www.asia-masters.com
  • 25. 25 The Green Book (Short Form of Contract) • US$ 500,000 and six months’ duration • Simple and repetitive works • All provisions necessary in 15 clauses • Language uncomplicated and simple • Balanced risk sharing - no Engineer • Design by either party - all types of construction • Payment on lump sum or any other basis © www.asia-masters.com
  • 26. 26 Dredging and Reclamation • Design by Employer or Contractor • Valuation – all main methods available • Engineer required to act “fairly” in accordance with Contract • No defects liability on dredging • Special insurance provisions • Adjudication by DAB, then arbitration © www.asia-masters.com
  • 27. 27 Red Book MDB Harmonised Version • Based on 1999 Red Book • Incorporates main common changes normally required by MDBs, e.g.- audits, labour provisions, corruption avoidance, dispute settlement • Use subject to Licence Agreement between FIDIC and participating banks © www.asia-masters.com
  • 28. 28 Design, Build and Operate Projects • Conditions of Contract for Design, Build and Operate Projects (Gold Book), First Edition 2008 • Assumes ~20-year operation period • Modern approach to risk and insurance • Employer’s Representative • Adjudication by DAB, then arbitration © www.asia-masters.com
  • 29. 29 Subcontracts • Conditions of Subcontract for Construction, Test Edition 2009 • Intended for use with 1999 Red Book • General Conditions – Particular Conditions • Annexes require provision of relevant information © www.asia-masters.com
  • 30. 30 Protection of the Environment • The Contractor shall take all reasonable steps to protect the environment (both on and off the Site) and to limit damage and nuisance to people and property resulting from pollution, noise and other results of his operations © www.asia-masters.com
  • 31. 31 Environment (continued) • The Contractor shall ensure that emissions, surface discharge and effluent from the Contractor’s activities shall not exceed the values indicated in the Specification, and shall not exceed the values prescribed by applicable Laws © www.asia-masters.com
  • 32. 32 Project Phases • Initiation • Study and Evaluation • Design Development • Detailed Design • Contracts • Construction, Manufacture, Shipping, Installation, Testing and Commissioning • Operations and Maintenance © www.asia-masters.com
  • 33. 33 Initiation • The Concept • The Big Decisions • Policy • Major Choices © www.asia-masters.com
  • 34. 34 Study and Evaluation • Feasibility • Alternatives • Strategy • Statutory Requirements © www.asia-masters.com
  • 35. 35 Design Development/ Detailed Design • Specifications • Special Requirements • Approvals • Inclusion of results/outcomes from earlier Project Phases © www.asia-masters.com
  • 36. Contracts Committee • Mandate from Executive Committee • Members: Christoph Theune/ Zoltán Záhonyi/Philip Jenkinson • Special Advisers: Nael Bunni/ Axel Jaeger/ Michael Mortimer-Hawkins/ Chris Seppala/ Chris Wade • Task Group Leaders and Members 36 © www.asia-masters.com
  • 37. Contracts Committee Terms of Reference • To recommend to the Executive Committee which Conditions of Contract and related documents should be prepared or updated by FIDIC • To assist the Secretariat in establishing Task Groups as required, to monitor their work at agreed intervals and to carry out a final review of the documents for submission to the Executive Committee • To assist the Secretariat in handling queries on the interpretation of documents • To liaise, in conjunction with the Secretariat, with organisations interested in the FIDIC Conditions of Contract • To suggest topics and speakers as appropriate for seminars and workshops 37 © www.asia-masters.com
  • 38. Current Workload • TG1 – DBO Form of Contract • TG2 – Procurement Procedures Guide • TG4 – Consultancy Agreements • TG5 – Subcontract Form (Red Book) • TG6 – Update of 1999 Suite (Yellow Book first) • TG7 – Update of Dredging Contract (with IADC) • TG8 – Update of Short Form (Green Book) • TG9 – YB/SB Subcontract Forms • TG10 – Tunnelling (proposed, with ITA) • TG11 – ODB Form of Contract • Training Courses 38 © www.asia-masters.com