There are many organizations which are on way of implementing agile/scum as there development process. Though there is distinct context for every organization, still there are various things that they can learn from others experiences.
This session will focus on experiences of agile implementation journey at MakeMyTrip.
Project management, then, is the application of knowledge, process, methods, skills, tools, and techniques to project activities to meet the project requirements.
The first of the two parts Article enlists all the benefits of PMI-ACP certification, to help you discover what you can gain with PMI's Agile certification.
Top 50 Product Owner Interview Question and Answers | EdurekaEdureka!
YouTube Link: https://youtu.be/UlW2xCZpeRM
** CSPO® Certification Training: https://www.edureka.co/cspo-certification-training **
This Edureka video on "Product Owner Interview Questions" will help you prepare for your scrum job interviews. The topics discussed in this course are listed below:
Beginner Level Product Owner Interview Questions
Advances Level Product Owner Interview Questions
Comparison Based Product Owner Interview Questions
Real-World Scenario Based Product Owner Interview Questions
Follow us to never miss an update in the future.
YouTube: https://www.youtube.com/user/edurekaIN
Instagram: https://www.instagram.com/edureka_learning/
Facebook: https://www.facebook.com/edurekaIN/
Twitter: https://twitter.com/edurekain
LinkedIn: https://www.linkedin.com/company/edureka
Castbox: https://castbox.fm/networks/505?country=in
Project management, then, is the application of knowledge, process, methods, skills, tools, and techniques to project activities to meet the project requirements.
The first of the two parts Article enlists all the benefits of PMI-ACP certification, to help you discover what you can gain with PMI's Agile certification.
Top 50 Product Owner Interview Question and Answers | EdurekaEdureka!
YouTube Link: https://youtu.be/UlW2xCZpeRM
** CSPO® Certification Training: https://www.edureka.co/cspo-certification-training **
This Edureka video on "Product Owner Interview Questions" will help you prepare for your scrum job interviews. The topics discussed in this course are listed below:
Beginner Level Product Owner Interview Questions
Advances Level Product Owner Interview Questions
Comparison Based Product Owner Interview Questions
Real-World Scenario Based Product Owner Interview Questions
Follow us to never miss an update in the future.
YouTube: https://www.youtube.com/user/edurekaIN
Instagram: https://www.instagram.com/edureka_learning/
Facebook: https://www.facebook.com/edurekaIN/
Twitter: https://twitter.com/edurekain
LinkedIn: https://www.linkedin.com/company/edureka
Castbox: https://castbox.fm/networks/505?country=in
I was brought on to produce some high-fidelity wireframes for one section of a large travel app -- the checkout process after the user had selected a hotel. A lot of assumptions had to be made and many factors had to be carefully considered while creating the app flow and wireframes.
Hi,
This is Vikapla Case Study - Makemytrip. Deep Kalra, Founder and Chief Executive Officer, Travel and Tourism Market , Online Travel Services (OTS), Promotion.
Credits - Sanjay Kumar Kar is an Assistant Professor in Marketing and Assistant Dean (Academic Affairs) at the Department of Management.
From an idea that sparked a change in the way a country uses bus travel to an INR 800 crores acquisition–take the Red Bus journey with 10,000 Start-ups.
Flipkart vs Jabong vs Myntra - Holiday Social Media Engagement Report IndiaIdeateLabs
A comparative study of the 3 of the largest E Commerce Giants in India and their engagement with their customers on Social Media, Facebook in particular. Flipkart vs Myntra vs Jabong, by the team at IdeateLabs.
Track SMS Plugin is an advanced plugin for your SMS account which enables you to track each and every SMS, providing you with detailed insights regarding how your customers are engaging with your SMS. It's a perfect tool to measure the reach and success of your SMS Campaigns.
I was brought on to produce some high-fidelity wireframes for one section of a large travel app -- the checkout process after the user had selected a hotel. A lot of assumptions had to be made and many factors had to be carefully considered while creating the app flow and wireframes.
Hi,
This is Vikapla Case Study - Makemytrip. Deep Kalra, Founder and Chief Executive Officer, Travel and Tourism Market , Online Travel Services (OTS), Promotion.
Credits - Sanjay Kumar Kar is an Assistant Professor in Marketing and Assistant Dean (Academic Affairs) at the Department of Management.
From an idea that sparked a change in the way a country uses bus travel to an INR 800 crores acquisition–take the Red Bus journey with 10,000 Start-ups.
Flipkart vs Jabong vs Myntra - Holiday Social Media Engagement Report IndiaIdeateLabs
A comparative study of the 3 of the largest E Commerce Giants in India and their engagement with their customers on Social Media, Facebook in particular. Flipkart vs Myntra vs Jabong, by the team at IdeateLabs.
Track SMS Plugin is an advanced plugin for your SMS account which enables you to track each and every SMS, providing you with detailed insights regarding how your customers are engaging with your SMS. It's a perfect tool to measure the reach and success of your SMS Campaigns.
Art of Product Management - how we can achieve !!
Product Management and its 2 faces of coin
Product Discovery and Management Brief
Kano Model, BVR and Weighted Matrix prioritization
Real time scenario to understand MVP, MVE, MLP
Sample case understanding using Amazon
Agile Scrum Master is an advanced level Agile Project Management course that is ideal for individuals and enterprises that are looking to gain a comprehensive understanding of Agile methodologies and Scrum practices and covers Scrum Master role with regards to facilitating the Scrum team that adheres to Scrum theory, practices, and rules.
Agile and Scrum Master Certification training course accredited by EXIN is ideal for software developers, project team members, team leads, architects, project managers, scrum team members, scrum managers, scrum masters, teams transitioning to scrum, and any one who is part of IT and project management teams working on projects.
To know more about Agile Scrum Master Certification training worldwide,
please contact us at -
Email: support@invensislearning.com
Phone - US +1-910-726-3695,
Website: https://www.invensislearning.com
How to Jumpstart Enterprise Agile AdoptionTechWell
Want to get a jumpstart on agile adoption in your organization? Begin by leveraging a roadmap that Intuit has used for rolling out enterprise agile to its business units. While there is no single way to bring enterprise agile into your organization, Alan Padula describes a model that has worked repeatedly. The important first step is to create a vision of what full agile adoption looks like. Once a rich vision is created describing what people will be doing and how they will be doing it, create a roadmap, a time-sequenced plan with milestones. Each milestone has a description of everyone’s job responsibilities, the measurements to take along the way, the personal and business benefit, and the set of activities planned in order to achieve each succeeding milestone. Key transition activities include training, infrastructure, change leadership, planning, and governance. Join Alan for the jumpstart you need to successfully adopt agile in your organization.
how small entrepreneurs/small companies could make more money, how quality, capacity & competency could be made world class, how to set up skill center.contact us: vhpsenterprises@gmail.com,919718598887,9818524206
SAIsej brings inbound knowledge of trainer of widerexperience in the respective dimension related to PMI-PMP and help the professionals in project management skills & help ready for PMI-PMP exam.
Kanban Methodologist Certification at XebiaPooja Gulati
Kanban is a Lean-agile method also referred to as a second-generation agile methodology. It adapts to your organization and project needs very rapidly and allows your team to operate at a very high level of productivity due to its evolutionary approach to manage change in the organization. It has proven to accelerate maturity through high visualization, control over the amount of work being done, acknowledgement and effective handling of the diversity of activities in your project, and root cause analysis through quantification.
Similar to Agile Implementation @ MakeMyTrip : Presented By Manoj Jain (20)
How Scrum Master can help the team in quitting 'SMOKING' - Talk by Bhanu Golc...oGuild .
During Discuss Agile Day Delhi 2019 - One Day Conference (14 September), Bhanu Golconda & Vamsi Krishna presented their talk on "How Scrum Master can help the team in quitting 'SMOKING'". Check out the exclusive Interview of Bhanu Golconda & Vamsi Krishna at the last slide.
Talk description: We all know ‘Smoking is injurious to health’ but in this session we are going to discuss about ‘How SMOKING is injurious to teams’ health’ and how Scrum Master can help the team in quitting 'SMOKING'.
-Are you satisfied with mediocre or above par performance? No?
-Do you need the best out of everyone? Yes?
-Have you ever realized about the bad practices that crept in. Yes or No?
We have brainstormed with more than 30 Scrum teams and collated the SMOKING patterns. So, in this session we are going to discuss in detail about tried and tested recommendations to trash those SMOKING patterns with which we can increase efficiency and also break the monotony in Scrum events.
Culture and You - Talk by Hariharaganesh (Discuss Agile Day Delhi 2019)oGuild .
During Discuss Agile Day Delhi 2019 - One Day Conference (14 September), Hariharaganesh presented his talk on Culture and You. Check out the exclusive Interview of Hariharganesh at the last slide.
Talk Description: Organization's culture is the sum of belief and behaviors of all employees. It is built on values and drives Organizational effectiveness through Competitive advantage. The visible part of cultural iceberg drives us to think what we see and believe in our Organization constitutes the culture. There is also big portion of cultural iceberg that is not visible to the employees that drives the hard reality.
Culture is a soft concept and like strategy it cannot be copied. Is there a way to measure culture? If not, then how do we say whether particular culture is good or bad? As an individual how often do we change our behavior to adapt to a new situation? If changing one’s behavior is tough, then how difficult is to change behavior of big Organization?
Discuss Agile an user group of Scrum Alliance conducted an One Day Conference On 14th of September, 2019. This was the 5th conference organized by Discuss Agile & sponsored by iZenBridge Consultancy in Delhi. Discuss Agile Day is an one day event of like-minded Agile practitioners, trainers, coaches, and enthusiasts.
Webinar on Big Data Challenges : Presented by Raj KasturioGuild .
Big data is huge! with billions and billions of data sets and a need to analyze and apply that to real-life problem-solving is a challenge. Are traditional methods successful in solving big data problems?
Let’s take a look at the current state of big data, if traditional methodologies are providing the necessary answers quick enough. Is Agile/Scrum a good fit for big data?
– big data in any industry
– high data availability, real time analytics, data warehousing
– agile spectrum and where do my projects fall?
– big data complexity and empirical process control theory
– current industry trends
– metrics
Leadership in Agile : by Karthik Mahadevan & Ramakrishnan SitaramanoGuild .
The bottom line to a agile (self organizing high performing) team is constant flow of energy. This guarantees optimal pace of quality deliverables.
To maintain this creative equilibrium, leaders can look at”Engaging” directly or “Enable” individuals or by “Empowering” the team without compromising team autonomy.
As a leader
When you “Engage” its not about you, its about the team / individual
When you “Enable” its not about who / what .. Its about Why
When you “Empower” its not about it being leaving for the team’s choice but its about setting the right stage / context for them to act.
Kanban for Self Development : Presented by Sundaresan SethuramanoGuild .
1. Kanban – Workflow in brief followed by
2. Generic time management aspects
3. Work-life balance/integration
4. How to beat laziness/procrastination and
5. Use Kanban to real positive effect for personal growth
An Agile Coach plays a vital role in bringing in that change in mindset. But how does the coach do it? This session is just not philosophy but provides relevant and real-time examples that audience can relate to. It describes in details the definition of coach, Agile coach, how a coach can generate insights, leading to awareness and ultimately change in mindset.
Art of Doing Effective Scrum : Presented by Mohammed JavidoGuild .
The team dynamics takes the team through the stages of transition from forming, storming, norming to performing.
Each member of the team also passes through the individual phases of forming, storming, norming to performing.
The Scrum guide has listed the roles, events, artifacts, rules in a short document which needs to be adhered, irrespective
of the stage that the team is or the stage that the individual team member is. It will quickly bring the visibility on the current stage of the team and will provide opportunity for inspection and adaption.
The topic will cover the scenarios related to the dynamics of the team and roles.
The suggestions(actionable guidance) will be provided along with the scenarios.
The message to the audience will be on the lines of ‘Own Your Baby’, Avoiding instances of ‘Operation Successful, but Patient Died’
The bottom line will be to refer back to Scrum guide as and when the team needs clarity on roles, events, artifacts, rules of Scrum. At the same time the target is not on doing Scrum but on being Scrum, the target is to get the working software and Scrum is one of the enablers towards it. Scrum too mentions the importance of working software at great depth.
Agility Beyond Framework and Dev Team : by Anubhav SinhaoGuild .
Agility and Lean-Agile practices plays a vital role if people understand and give a continuous learning pattern. We can have agility in Pre-sales for identifying Bid Cycle or, Employment Engagement Experience rather than only HR etc. Senior Folks to become Leader rather than bosses. Co-working folks to interact rather than Peer, that may lead to identification of a solution appearance rather than problem creator.
Key Takeaways:
– a role thought as Imaginary PO for Pre-sales engagements
– how all members of pre-sales coordinates
– how HR can turn to 3E
– Incremental and evolving – From 3S to Collaborative
– Few metrics to understand
Influential Leadership : Presented by Ramanathan YegyanarayananoGuild .
Leadership is the process of influencing others to understand and agree about what needs to be done and how to do it, and the process of facilitating individual and collective efforts to accomplish shared objectives.
Influential Leadership is the KEY to developing a raving fan culture. Influential Leadership is the ability of a leader to incite action in others simply through mastering the skills of communication and motivation tailored to an individual person.
we can have a wonderful team if there is a right person who can influence others and groom a leader in the community. This is the intent of the topic being chosen for this conference by me.
Agile Inception Strategies : Presented by Khaarthigha SubramanianoGuild .
Agile Inception using Innovative and Collaborative techniques & Gamification came for rescue, But now this is also diluted a lot and becoming in-effective. But used well, this is highly effective even to discover more than what we are focusing and help channel the investments for the clients.
We took a real world problem that is meaningful to all attendees and used the following techniques as a real inception
– Describing the objectives of inception and inception outcomes
– Setting the vision
– Identify Competing constraints and decouple them
– Understand nuances of client relationship and being dynamic in modelling the solution
– Stakeholder mapping and communication plan
– Assumption mapping and hypotheses prioritisation
– Traceability of user needs to business goals through impact mapping.
Becoming Successful Product Owner : Presented by Arne AhlanderoGuild .
It is common for new Product Owners to be left without instructions or ideas of how to succeed. The role of the PO is different from traditional roles and in order to survive as a PO new learning is necessary. In order to become a successful PO you don’t only need a vision, you also need good tools, principles and practices.
Here Arne presents principles, tools and practices to help you become more successful in your role regardless if you are new or more experienced.
Agile Transformation and The Metrics Drama : Presented by Deepak GururajaoGuild .
As more and more companies are embarking on the journey of Agile Transformation, leaders are on the constant lookout for various kinds of metrics to measure the progress. Newer and more improved Metrics are being created everyday. Some of them are naive, while the others are complicated to measure. Most metrics are focused on execution. Through his experience, Deepak have seen multiple perspectives for measuring transformation.
Deepak shared his perspective about measurement, and offered the participants, his understanding of Agile Transformation. He discussed about the metrics that make sense from a business perspective.
At the end of the day, its not only the Technology/Engineering leaders, but, also business leaders who fund the transformation and business gets equal share of their benefits form the transformation.
Appreciative Enquiry : Presented by Sridharan VembuoGuild .
As we all know, Agile, at it’s core, emphasizes on team work. And, if you look at any successful Agile story, the key to it’s success would be a self-oragnized, cohesive team and other factors only add to this.
More often than not, Retrospectives are probably the only forum where the entire team comes together as a single unit and these meetings usually end up being crib (and ranting) sessions. And, because of that, teams are not very enthusiastic about retrospectives and these meetings become more of a ritual than being productive and useful.
As the name ‘Appreciative Enquiry’ suggests, the focus of this meeting was on things that created a positive impact on the team and the project. Sridhar shared few real life examples from his projects, the effective of doing regular Appreciative Enquiries and also guided the participants how they can successfully adopt this technique in their team.
The Objective of this Manifesto is to define guiding principles around the Customer-Supplier working environment with regards to working on Scrum projects. The assumptions made are
•The environment is customer-supplier (i.e. an outsourced environment)
•The environment is distributed and may not be co-located
•The environment involves multiple vendors
The Customers and Suppliers are integrated elements of a working environment in a project. The Customers and Suppliers will work together with a common goal and that is “Producing Value for the End Customer”. This manifesto supports the Agile Manifesto Value “Customer Collaboration over Contract Negotiation”.
Design Thinking & Innovation Games : Presented by Cedric MainguyoGuild .
Accelerate Innovation: Learn why it matters and how it’s done.
Design Thinking can be used to design products, user experiences, corporate strategy or public services… Innovation Games, whose primary intent is not pure entertainment, can be applied to a broad spectrum of areas like training, hiring, generating new ideas, gathering feedback about a product or change management… The list goes on.
An increasing number of organizations have realized the enormous potential of human-centered and playful approach to innovation design and development. The growing success of Agile methods, which put a strong emphasis on people interactions, on fun and on building a creativity-friendly environment, have made Design Thinking and Innovation Games even more popular.
Killing Agile Software Development : Presented by Rizky Syaiful oGuild .
Last month (June 2016), I helped a well-known higher education institute in Indonesia. I train the lecturers there, so that their students can practice agile software development.
[I show the audience some photos and videos as the proofs]
Can you imagine a condition when all our CS/IT students already get the real experiences of proper Scrum, Automated Testing, etc?
In that imaginary world, agile software development is already the norm! In the other side, there is no more room for Waterfall’s Big-Design-Up-Front style. Because we know that any software problem is inherently a design problem—or complex problem in Cynefin framework. You can’t solve that kind of problem by designing a big-fixed solution up in the front.
And if almost every software development is already agile—as it was visioned back then in 2001 manifesto, why would we still use ‘agile’ term?
We invent words to categorize things. Before ‘agile’ was proposed in the 2001 manifesto, they called it ‘lightweight’. Because it’s different with the previous heavy weight Waterfall.
Now, when I say the word ‘computer’, what would your brain emulate? A mainframe computer? Or a personal computer? Both of them are literally a computing machine. I put my money on personal computer. Because almost everyone see personal computer in daily basis. And they haven’t seen any mainframe computer once in their life.
Just as the dead of ‘personal’ term, in ‘personal computer’—I don’t count PC because that’s an abbreviation—‘agile’ in ‘agile software development’ will also be dead.
Not because it’s bad. On the contrary, that’s because agility the best option for software development.
In 2026 I, believe, we will call it simply as ‘software development’.
Please help the world to reach that kind of utopia, at least by telling your ex-lecturers, “you should teach agile software development properly”.
We should be so proud for standing here. Being a part of agile software development movement, of the 21st century.
Why?
Because a good movement always has a goal,
this agile software development movement also has a clear end.
If You Need To Run A Project You've Already Failed : Presented by Evan LeybournoGuild .
I want to be controversial for a moment and propose an end to IT projects, project management & project managers. I propose that the entire project process is flawed from the start for one simple reason. If you need to run a project, you’ve already failed.
By definition, an IT project is a temporary structure to govern and deliver a complex change (such as a new product or platform) into an organisation. However, to be truly competitive, an organisation needs to be able to deliver a continuous stream of change. Managed properly, this negates the need for a project and the associated cost overheads.
This is fundamentally what #noprojects is. The approach, structure, tactics and techniques available to successfully deliver continuous change. At its core, #noprojects is predicated on the alignment of activities to outcomes, measured by value, constrained by guiding principles and supported by continuous delivery technologies.
This presentation introduces you to #noprojects. You learn how to define an outcome and create an Outcome Profile. You also learn how to manage change within the context of an outcome through the Activity Canvas.
The Day I Realized I Was Not Yet An Agile Coach : Presented by Sylvain MaheoGuild .
I remember that morning, 6 or 7 years ago. I had been practicing Agile for a couple of years and I had decided to update my LinkedIn profile. I opened my profile, edited my headline and replaced “Scrum Master” with “Agile Coach”.
That was a lie. But I didn’t know it at that time. I really believed I had become a coach. In reality I was a consultant, a trainer, sometimes a mentor.
A few years later I decided to go back to school -a coaching school- and it changed my life.
In this talk, I shared my personal journey to become an (Agile) Coach and shared what I’ve learned along the way:
• What is the difference between consulting, training, coaching and why we should care?
• Why by calling ourselves coaches we are not doing any good to the coach profession?
• What can we do about it?
• How did I become a coach?
• What are my coaching tools?
• Does your organization really need a coach?
Introduction to Management 3.0 : Presented by Ralph van RoosmalenoGuild .
Management 3.0 is a movement of innovation, leadership and management. Management 3.0 is redefining the definition of leadership with management as a group responsibility. It’s about working together to find the most efficient way for a business to achieve its goals while maintaining the happiness of workers as a priority.
Management 3.0 is a global management revolution that brings together thousands of project managers, mid-level managers, CEOs and entrepreneurs, developing solutions together, using games to encourage employee feedback and team collaboration.
Learning Objectives :
# Understand what is Devops, why devops and what is it’s history
# What are it’s core principles and practices
# Understand key steps you need to take if you are planning to implement Dev-ops in your organization
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Explore the innovative world of trenchless pipe repair with our comprehensive guide, "The Benefits and Techniques of Trenchless Pipe Repair." This document delves into the modern methods of repairing underground pipes without the need for extensive excavation, highlighting the numerous advantages and the latest techniques used in the industry.
Learn about the cost savings, reduced environmental impact, and minimal disruption associated with trenchless technology. Discover detailed explanations of popular techniques such as pipe bursting, cured-in-place pipe (CIPP) lining, and directional drilling. Understand how these methods can be applied to various types of infrastructure, from residential plumbing to large-scale municipal systems.
Ideal for homeowners, contractors, engineers, and anyone interested in modern plumbing solutions, this guide provides valuable insights into why trenchless pipe repair is becoming the preferred choice for pipe rehabilitation. Stay informed about the latest advancements and best practices in the field.
Courier management system project report.pdfKamal Acharya
It is now-a-days very important for the people to send or receive articles like imported furniture, electronic items, gifts, business goods and the like. People depend vastly on different transport systems which mostly use the manual way of receiving and delivering the articles. There is no way to track the articles till they are received and there is no way to let the customer know what happened in transit, once he booked some articles. In such a situation, we need a system which completely computerizes the cargo activities including time to time tracking of the articles sent. This need is fulfilled by Courier Management System software which is online software for the cargo management people that enables them to receive the goods from a source and send them to a required destination and track their status from time to time.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Final project report on grocery store management system..pdfKamal Acharya
In today’s fast-changing business environment, it’s extremely important to be able to respond to client needs in the most effective and timely manner. If your customers wish to see your business online and have instant access to your products or services.
Online Grocery Store is an e-commerce website, which retails various grocery products. This project allows viewing various products available enables registered users to purchase desired products instantly using Paytm, UPI payment processor (Instant Pay) and also can place order by using Cash on Delivery (Pay Later) option. This project provides an easy access to Administrators and Managers to view orders placed using Pay Later and Instant Pay options.
In order to develop an e-commerce website, a number of Technologies must be studied and understood. These include multi-tiered architecture, server and client-side scripting techniques, implementation technologies, programming language (such as PHP, HTML, CSS, JavaScript) and MySQL relational databases. This is a project with the objective to develop a basic website where a consumer is provided with a shopping cart website and also to know about the technologies used to develop such a website.
This document will discuss each of the underlying technologies to create and implement an e- commerce website.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...Amil Baba Dawood bangali
Contact with Dawood Bhai Just call on +92322-6382012 and we'll help you. We'll solve all your problems within 12 to 24 hours and with 101% guarantee and with astrology systematic. If you want to take any personal or professional advice then also you can call us on +92322-6382012 , ONLINE LOVE PROBLEM & Other all types of Daily Life Problem's.Then CALL or WHATSAPP us on +92322-6382012 and Get all these problems solutions here by Amil Baba DAWOOD BANGALI
#vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore#blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #blackmagicforlove #blackmagicformarriage #aamilbaba #kalajadu #kalailam #taweez #wazifaexpert #jadumantar #vashikaranspecialist #astrologer #palmistry #amliyaat #taweez #manpasandshadi #horoscope #spiritual #lovelife #lovespell #marriagespell#aamilbabainpakistan #amilbabainkarachi #powerfullblackmagicspell #kalajadumantarspecialist #realamilbaba #AmilbabainPakistan #astrologerincanada #astrologerindubai #lovespellsmaster #kalajaduspecialist #lovespellsthatwork #aamilbabainlahore #Amilbabainuk #amilbabainspain #amilbabaindubai #Amilbabainnorway #amilbabainkrachi #amilbabainlahore #amilbabaingujranwalan #amilbabainislamabad
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSEDuvanRamosGarzon1
AIRCRAFT GENERAL
The Single Aisle is the most advanced family aircraft in service today, with fly-by-wire flight controls.
The A318, A319, A320 and A321 are twin-engine subsonic medium range aircraft.
The family offers a choice of engines
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
Maintaining high-quality standards in the production of TMT bars is crucial for ensuring structural integrity in construction. Addressing common defects through careful monitoring, standardized processes, and advanced technology can significantly improve the quality of TMT bars. Continuous training and adherence to quality control measures will also play a pivotal role in minimizing these defects.
6. MakeMyTrip – Quick Overview
India’s leading Online Travel Agency (OTA)
Started in 2000, India business launched in 2005
Most Visited Online Travel Website in India
Highest hotel bookings of any domestic Indian OTA
1 in 8 of all domestic air passengers booked through MakeMyTrip
High Rates of Direct & Repeat Traffic
6
10. Things to mind!
Understand business context and be convinced if agile will really help
Not just process change but mind/behavior change
Having a champion at management level will be of great help
Identify and understand supporters, neutrals & non-supporters
Avoid big-bang and take baby steps
Be sensitive about learning curve of audience
In case of resistance; go beyond what you see and what you listen
Tolerance for failures; focus on winning war than all battles
Keep everyone updated of progress being made including management
10
11. Our approach
Commenced in April 2014
Got support from management
Infrastructure availability viz. Dlist, Collaboration Site, Tools & Training
Imparting training to key members for basic hygiene
Started with DSM and gradually conducting sprint retrospectives
Unit wise implementation and avoided big-bang implementation
Started with units who are supporters of agile
Keep sharing collaterals on regular basis
Planned for CSM & CSPO training & certification
Had regular 1-o-1 with key stakeholders to seek feedback
Educated teams and avoided PUSH mode
Strengthen QA automation
Enabling CI/CD
Journey is still on…
11