Chapter 5
Software Quality Assurance and Security
5.1 Project Scheduling
. In project management, a schedule consist of a list of
project terminal elements, with intended start date
and finish date.
2. The s/w project scheduling distributes estimated
efforts across the planned project period by
allocating the effort to particular s/w engineering
tasks.
3. There are many tasks in a s/w project. The project
manager defines all the task and generates the
schedule.
4. Initially a macroscopic schedule is developed,
identifying all major process framework activities
and then the detailed schedule of specific tasks are
identified and scheduled.
• Work Breakdown Structure (WBS)
• The process of dividing complex project to
simpler and manageable work items is called
Work Breakdown Structure (WBS).
• Work item is also called as task.
• Project managers use this technique for
simplification of project execution.
• In WBS Larger items are broken down to
smaller manageable items and later these
items are easily verified and estimated.
• WBS is not limited to specific project type.
• It can be used for any type of project.
• Factors that delay Project Schedule
Although there are many reasons why software is
fail, most can be traced to one or more of the
following root causes:
1. An unrealistic deadline established by
someone outside the software team and forced
on managers and practitioners.
2. Changing customer requirements that are not
reflected in schedule changes.
3. An honest underestimate of the amount of
effort and/or the number of resources that will
be required to do the job.
Predictable and/or unpredictable risks that were
not considered when project commenced.
5. Technical difficulties that could not have been
foreseen in advance.
6. Human difficulties that could not have been
foreseen in advance.
7. Miscommunication among project staff that
results in delays.
8. A failure by project management to recognize
that the project is falling behind schedule and
a lack of action to correct the problem.
• Principles of Project Scheduling
• Basic principles software project scheduling
are:
• Compartmentalization: The project must be
compartmentalized into a number of
manageable activities and tasks. To accomplish
compartmentalization, both the product and
the process are decomposed.
• Interdependency: The interdependency of
each compartmentalized activity or task must
be determined. Some tasks must occur in
sequence while others can occur in parallel.
• Some activities cannot start until the work
product produced by another is available.
Other activities can occur independently.
• Time allocation: Each task to be scheduled
must be allocated some number of work units
(e.g., person-days of effort). In addition, each
task must be assigned a start date and a
completion date that are a function of the
interdependencies and whether work will be
conducted on a fulltime or part-time basis.
• Effort validation: Every project has a defined
number of staff members. As time allocation
occurs, the project manager must ensure that
no more than the allocated number of people
has been scheduled at any given time.
• Defined responsibilities: Every task that is
scheduled should be assigned to a specific
team member.
• Defined milestones: Every task or group of
tasks should be associated with a project
milestone. Program evaluation and review
technique (PERT) and critical path method
(CPM) are two project scheduling Methods that
can be applied to software development.
• Defined outcomes – Every task that is
scheduled should have a defined outcome for
software projects such as a work product or
part of a work product – Work products are
often combined in deliverables.
• Scheduling Technique
• PERT- Program Evaluation Review Technique -
• CPM - Critical Path Method -
• in projects various activities are executed in
parallel by different teams.
• Some activities are dependent on other and
hence cannot start before other task is
completed
• A critical path in project management is certain
tasks that need to be performed in a clear order
and for a certain period.
• Critical path is the longest sequence of activities
in the project plan which must be completed on
time for the project to complete on due date
• If part of one task can be slowed down or
postponed for a term without leaving work on
others, then such a task is not critical.
• While tasks with a critical value cannot be
delayed during the implementation of the
project and are limited in time.
• Critical Path Method (CPM) is an algorithm for
planning, managing and analyzing the timing
of a project.
• The step-by-step CPM system helps to identify
critical and non-critical tasks from projects’
start to completion and prevents temporary
risks.
• Critical tasks have a zero run-time reserve. If
the duration of these tasks changes, the terms
of the entire project will be ”shifted.”
• That is why critical tasks in project
management require special control and
timely detection of risks.
• Initially critical path method was used for
managing plant maintenance project.
• The original critical path method was
developed for construction project.
• Now, CPM can be used in any project where
there are interdependent activities are
involved
• In the critical path method the critical activities
of the project are first identified.
• Following are the steps in the critical path
method
• There are generally 5 steps involved in the CPM
1. Activity specification - work breakdown
structure
2. Activity sequence reorganization
3. Network diagram
4. Estimate for each activity
5. Identification of the critical path
Program Evaluation Review Technique (PERT)
i. PERT, is used in projects that have
unpredictable tasks and activities such as in
research and development projects.
ii. It utilizes three estimates of the time to
complete the project: the most probable, the
most promising, and the most unfavorable.
iii. It is a probabilistic tool.
iv) It uses several estimates to determine the
time completion of the project and controls
activities so that it will be completed faster
and at a lower cost.
• Difference PERT vs CPM
1. The Program Evaluation and Review Technique (PERT)
is suitable for projects that have unpredictable
activities while the Critical Path Method (CPM) is
suitable for projects that have predictable activities.
2. CPM uses a single estimate for the time that a project
can be completed while PERT uses three estimates for
the time that it can be completed.
3. CPM is a deterministic project management tool while
PERT is a probabilistic project management tool.
4. CPM allows project management planners to
determine which aspect of the project to sacrifice
when a trade-off is needed in order to complete the
project while PERT does not.
• Concept of Activity Network
• A task network, also called an activity network, is a
graphic representation of the task flow for a project.
• It is the mechanism through which task sequence and
dependencies are input to an automated project
scheduling tool.
• In its simplest form, the task network shows major
software engineering tasks.
• The concurrent nature of software engineering
activities leads to a number of important scheduling
requirements.
• In addition, the project manager should be aware of
those tasks that lie on the critical path.
• That is, tasks that must be completed on schedule if the
project as a whole is to be completed on schedule.
5.2 Project Tracking
Tracking: - can be accomplished in different ways:
 Conducting periodic project status meetings in
which each team member reports progress and
problems.
 Evaluating the results of all reviews conducted
throughout the software engineering process.
 Determining whether formal project milestones
have been accomplished by the scheduled date.
 Comparing actual start-date to planned start-
date for each project task.
 Meeting informally with practitioners to obtain
their subjective assessment of progress to date
and problems on the horizon.
• Time-Line Charts or Gantt chart
• A time-line chart can be developed for the
entire project or separate charts can be
developed for each project function or for each
individual working on the project.
• When creating software project schedule, we
begin with a set of tasks. If automated tools are
used, the work breakdown is input as a task
network.
• Effort, duration and start date are then input for
each task, In addition, tasks may be assigned to
specific individuals.
• A time-line chart can be developed for the entire
project.
• Timeline Charts
Tasks Week 1 Week 2 Week 3 Week 4 Week n
Task 1
Task 2
Task 3
Task 4
Task 5
Task 6
Task 7
Task 8
Task 9
Task 10
Task 11
Task 12
• When multiple bars occur at the same time on
the calendar, task concurrency is implied.
• The diamonds indicate milestones.
• All project tasks (for concept scoping) are listed
in the left-hand column.
• The horizontal bars indicate the duration of
each task.
• Once the information necessary for the
generation of a time-line chart has been start.
• a tabular listing of all project tasks, their
planned and actual start and end dates, and a
variety of related information.
• with the help of time-line chart, project tables
enable to track progress of project.
• Application of Gantt Chart
• The clear simplicity and ease-of-access of all
relevant information make Gantt charts an ideal
choice for teams to use them for organizing their
schedules.
• Due to this, Gantt charts are widely used in project
management, IT and development teams.
• Apart from them, marketing, engineering, product
launch, manufacturing teams can also use Gantt
charts to get an overview of how things are rolling
on the work front
• Draw time chart for Libraray management
system System (5 days a week). Consider
broad phases of SDLC.
• Prepare macro time line chart for 15 days of
college management system (5 days a week)
consider phases of SDLC.
• Prepare Macro Timeline chart for 20 days of
Hotel Management system (6 days a week)
consider broad phase of SDLC.
• Earned Value Analysis ( EVA)
• Earned value analysis’s objective is to measure
project performance in terms of scope cost
and time
• It also used for monitoring the progress of
software project.
• Total time required to complete the project is
calculated and each task is given an earn value
based on its estimated
• If the project is not going as per plan and it is
found that there is some delay in the project
• at this time situation is needed to be taken
care by finding out the reasons that are
causing delay and by taking corrective actions.
• Key Elements of EVA
1. Planned Value (PV) - allocated cost for the
project which is approved.
2. Earned Value (EV) - The budgeted value of
the completed work packages
3. Actual Cost(AC) – The actual cost involved
during the execution of project work.
5.3 Software Quality Management
• software quality - Quality means that a product
satisfies the demands of its specifications. It
also means achieving a high level of customer
satisfaction with the product.
• In software systems this is difficult that
Customer quality requirements(e.g. efficiency
or reliability) often conflict with developer
quality requirements (e.g. maintainability or
reusability)
• Quality management or Quality control
• Quality management/control involves series of
inspections, reviews, tests used throughout the
process.
• It includes a feedback loop to the process.
• A key concept of quality management/control
is that all work product have defined,
specifications are compared and feedback loop
is essential to minimize the defects produced.
• It is a procedure that focuses on fulfilling the
quality requested.
• Quality Control: Software quality control is the
set of procedures used by organizations to
ensure that a software product meets its quality
goals at the best value(minimum cost) to the
customer.
• And continually improve the organization's
ability to produce software products in the
future.
• Quality Assurance: Quality assurance assess the
effectiveness and completeness of quality
control activities.
• The goal of Quality assurance is to provide
management with the data necessary about
product quality, gaining confidence that product
quality is meeting its goal.
• If not ,its managements responsibility to address
the problem and apply the necessary resources
to resolve quality issues.
• Quality Assurance: It is a procedure that
focuses on providing assurance that quality
requested will be achieved.
• Quality assurance consists of the auditing and
reporting functions of management.
• Software quality assurance is composed of a
variety of tasks associated with two different
aspects - the software engineers who do
technical work and an SQA group that has
responsibility for quality assurance planning,
record keeping, analysis, and reporting.
• Software engineers address quality (and
perform quality assurance and quality control
activities) by applying technical methods,
conducting formal technical reviews, and
performing well-planned software testing.
• Activities of SQA(Software Quality Assurance)
1. Prepare an SQA plan for a project:- The plan is
developed during project planning and is
reviewed by all interested parties. Quality
assurance activities performed by the software
engineering team and the SQA group are
governed by the plan.
• The plan identifies –
> evaluations to be performed
> audits and reviews to be performed
> standards that are applicable to the project
> procedures for error reporting and tracking
> documents to be produced by the SQA group
> amount of feedback provided to the software
project team
2.Participate in the development of the
project’s software process description:-The
software team selects a process for the work to
be performed. The SQA group reviews the
process description for compliance with
organizational policy and other parts of the
software project plan.
3.Review software engineering activities to
verify compliance with the defined software
process.:- The SQA group identifies, documents,
and tracks deviations from the process and
verifies that corrections have been made.
4. Audits are designed for s/w work products to
verify compliance with those defined as a part of
process. :- verify that corrections have been made
and periodically reports the results of its work to
the project manager.
5.Ensure that deviations in software work and work
products are documented and handled according
to a documented procedure. :- Deviations may be
encountered in the project plan, process
description, applicable standards, or technical work
products.
6. Records any noncompliance and reports to
senior management. Noncompliance items are
tracked until they are resolved.
• Phases of Software Quality Assurance
• SQA Planning.
• Activities.
• Review and Audit.
Software Quality Assurance (QA) Software Quality Control (QC)
It is a procedure that focuses on providing
assurance that quality requested will be
achieved
It is a procedure that focuses on fulfilling
the quality requested.
QA aims to prevent the defect QC aims to identify and fix defects
It is a method to manage the quality-
Verification
It is a method to verify the quality-
Validation
It does not involve executing the program It always involves executing a program
It's a Preventive technique It's a Corrective technique
It's a Proactive measure It's a Reactive measure
It is the procedure to create the
deliverables
It is the procedure to verify that
deliverables
QA involves in full software development life
cycle
QC involves in full software testing life cycle
In order to meet the customer
requirements, QA defines standards and
methodologies
QC confirms that the standards are followed
while working on the product
It is performed before Quality Control It is performed only after QA activity is done
It is a Low-Level Activity, it can identify an
error and mistakes which QC cannot
It is a High-Level Activity, it can identify an
error that QA cannot
Its main motive is to prevent defects in the
system. It is a less time consuming activity
Its main motive is to identify defects or bugs
in the system. It is a more time-consuming
activity
QA ensures that everything is executed in
the right way, and that is why it falls under
verification activity
QC ensures that whatever we have done is
as per the requirement, and that is why it
falls under validation activity
Software Quality Assurance (QA) Software Quality Control (QC)
It requires the involvement of the whole
team
It requires the involvement of the Testing
team
The statistical technique applied on QA is
known as SPC or Statistical Process
Control (SPC)
The statistical technique applied to QC is
known as SQC or Statistical Quality
Control

More Related Content

Similar to Chapt5.pptx it is notes of the 5th chapter

Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and trackingComputer_ at_home
 
Time management pressent
Time management pressentTime management pressent
Time management pressentiklil fairuz
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management toolsDarshak Mehta
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxMdSabujHossen2
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxMdSabujHossen2
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planningShruti Kunwar
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project schedulingMuntha Ulfat
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 

Similar to Chapt5.pptx it is notes of the 5th chapter (20)

Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
PM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptxPM-5 chapter project management (1).pptx
PM-5 chapter project management (1).pptx
 
PM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptxPM-chapter 00005 project management.pptx
PM-chapter 00005 project management.pptx
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Software project scheduling
Software project schedulingSoftware project scheduling
Software project scheduling
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
pm--basic.pptx
pm--basic.pptxpm--basic.pptx
pm--basic.pptx
 
SPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptxSPM_UNIT-1(1).pptx
SPM_UNIT-1(1).pptx
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
06 project time management
06  project time management06  project time management
06 project time management
 

Recently uploaded

Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 

Recently uploaded (20)

Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 

Chapt5.pptx it is notes of the 5th chapter

  • 1. Chapter 5 Software Quality Assurance and Security
  • 2. 5.1 Project Scheduling . In project management, a schedule consist of a list of project terminal elements, with intended start date and finish date. 2. The s/w project scheduling distributes estimated efforts across the planned project period by allocating the effort to particular s/w engineering tasks. 3. There are many tasks in a s/w project. The project manager defines all the task and generates the schedule. 4. Initially a macroscopic schedule is developed, identifying all major process framework activities and then the detailed schedule of specific tasks are identified and scheduled.
  • 3. • Work Breakdown Structure (WBS) • The process of dividing complex project to simpler and manageable work items is called Work Breakdown Structure (WBS). • Work item is also called as task. • Project managers use this technique for simplification of project execution. • In WBS Larger items are broken down to smaller manageable items and later these items are easily verified and estimated. • WBS is not limited to specific project type. • It can be used for any type of project.
  • 4. • Factors that delay Project Schedule Although there are many reasons why software is fail, most can be traced to one or more of the following root causes: 1. An unrealistic deadline established by someone outside the software team and forced on managers and practitioners. 2. Changing customer requirements that are not reflected in schedule changes. 3. An honest underestimate of the amount of effort and/or the number of resources that will be required to do the job.
  • 5. Predictable and/or unpredictable risks that were not considered when project commenced. 5. Technical difficulties that could not have been foreseen in advance. 6. Human difficulties that could not have been foreseen in advance. 7. Miscommunication among project staff that results in delays. 8. A failure by project management to recognize that the project is falling behind schedule and a lack of action to correct the problem.
  • 6. • Principles of Project Scheduling • Basic principles software project scheduling are: • Compartmentalization: The project must be compartmentalized into a number of manageable activities and tasks. To accomplish compartmentalization, both the product and the process are decomposed. • Interdependency: The interdependency of each compartmentalized activity or task must be determined. Some tasks must occur in sequence while others can occur in parallel.
  • 7. • Some activities cannot start until the work product produced by another is available. Other activities can occur independently. • Time allocation: Each task to be scheduled must be allocated some number of work units (e.g., person-days of effort). In addition, each task must be assigned a start date and a completion date that are a function of the interdependencies and whether work will be conducted on a fulltime or part-time basis.
  • 8. • Effort validation: Every project has a defined number of staff members. As time allocation occurs, the project manager must ensure that no more than the allocated number of people has been scheduled at any given time. • Defined responsibilities: Every task that is scheduled should be assigned to a specific team member.
  • 9. • Defined milestones: Every task or group of tasks should be associated with a project milestone. Program evaluation and review technique (PERT) and critical path method (CPM) are two project scheduling Methods that can be applied to software development. • Defined outcomes – Every task that is scheduled should have a defined outcome for software projects such as a work product or part of a work product – Work products are often combined in deliverables.
  • 10. • Scheduling Technique • PERT- Program Evaluation Review Technique - • CPM - Critical Path Method -
  • 11. • in projects various activities are executed in parallel by different teams. • Some activities are dependent on other and hence cannot start before other task is completed • A critical path in project management is certain tasks that need to be performed in a clear order and for a certain period. • Critical path is the longest sequence of activities in the project plan which must be completed on time for the project to complete on due date
  • 12. • If part of one task can be slowed down or postponed for a term without leaving work on others, then such a task is not critical. • While tasks with a critical value cannot be delayed during the implementation of the project and are limited in time. • Critical Path Method (CPM) is an algorithm for planning, managing and analyzing the timing of a project. • The step-by-step CPM system helps to identify critical and non-critical tasks from projects’ start to completion and prevents temporary risks.
  • 13. • Critical tasks have a zero run-time reserve. If the duration of these tasks changes, the terms of the entire project will be ”shifted.” • That is why critical tasks in project management require special control and timely detection of risks. • Initially critical path method was used for managing plant maintenance project. • The original critical path method was developed for construction project. • Now, CPM can be used in any project where there are interdependent activities are involved
  • 14. • In the critical path method the critical activities of the project are first identified. • Following are the steps in the critical path method • There are generally 5 steps involved in the CPM 1. Activity specification - work breakdown structure 2. Activity sequence reorganization 3. Network diagram 4. Estimate for each activity 5. Identification of the critical path
  • 15. Program Evaluation Review Technique (PERT) i. PERT, is used in projects that have unpredictable tasks and activities such as in research and development projects. ii. It utilizes three estimates of the time to complete the project: the most probable, the most promising, and the most unfavorable. iii. It is a probabilistic tool. iv) It uses several estimates to determine the time completion of the project and controls activities so that it will be completed faster and at a lower cost.
  • 16. • Difference PERT vs CPM 1. The Program Evaluation and Review Technique (PERT) is suitable for projects that have unpredictable activities while the Critical Path Method (CPM) is suitable for projects that have predictable activities. 2. CPM uses a single estimate for the time that a project can be completed while PERT uses three estimates for the time that it can be completed. 3. CPM is a deterministic project management tool while PERT is a probabilistic project management tool. 4. CPM allows project management planners to determine which aspect of the project to sacrifice when a trade-off is needed in order to complete the project while PERT does not.
  • 17. • Concept of Activity Network • A task network, also called an activity network, is a graphic representation of the task flow for a project. • It is the mechanism through which task sequence and dependencies are input to an automated project scheduling tool. • In its simplest form, the task network shows major software engineering tasks. • The concurrent nature of software engineering activities leads to a number of important scheduling requirements. • In addition, the project manager should be aware of those tasks that lie on the critical path. • That is, tasks that must be completed on schedule if the project as a whole is to be completed on schedule.
  • 18.
  • 19. 5.2 Project Tracking Tracking: - can be accomplished in different ways:  Conducting periodic project status meetings in which each team member reports progress and problems.  Evaluating the results of all reviews conducted throughout the software engineering process.  Determining whether formal project milestones have been accomplished by the scheduled date.  Comparing actual start-date to planned start- date for each project task.  Meeting informally with practitioners to obtain their subjective assessment of progress to date and problems on the horizon.
  • 20. • Time-Line Charts or Gantt chart • A time-line chart can be developed for the entire project or separate charts can be developed for each project function or for each individual working on the project. • When creating software project schedule, we begin with a set of tasks. If automated tools are used, the work breakdown is input as a task network. • Effort, duration and start date are then input for each task, In addition, tasks may be assigned to specific individuals. • A time-line chart can be developed for the entire project.
  • 21. • Timeline Charts Tasks Week 1 Week 2 Week 3 Week 4 Week n Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Task 9 Task 10 Task 11 Task 12
  • 22. • When multiple bars occur at the same time on the calendar, task concurrency is implied. • The diamonds indicate milestones. • All project tasks (for concept scoping) are listed in the left-hand column. • The horizontal bars indicate the duration of each task. • Once the information necessary for the generation of a time-line chart has been start. • a tabular listing of all project tasks, their planned and actual start and end dates, and a variety of related information.
  • 23. • with the help of time-line chart, project tables enable to track progress of project. • Application of Gantt Chart • The clear simplicity and ease-of-access of all relevant information make Gantt charts an ideal choice for teams to use them for organizing their schedules. • Due to this, Gantt charts are widely used in project management, IT and development teams. • Apart from them, marketing, engineering, product launch, manufacturing teams can also use Gantt charts to get an overview of how things are rolling on the work front
  • 24.
  • 25. • Draw time chart for Libraray management system System (5 days a week). Consider broad phases of SDLC. • Prepare macro time line chart for 15 days of college management system (5 days a week) consider phases of SDLC. • Prepare Macro Timeline chart for 20 days of Hotel Management system (6 days a week) consider broad phase of SDLC.
  • 26.
  • 27.
  • 28. • Earned Value Analysis ( EVA) • Earned value analysis’s objective is to measure project performance in terms of scope cost and time • It also used for monitoring the progress of software project. • Total time required to complete the project is calculated and each task is given an earn value based on its estimated • If the project is not going as per plan and it is found that there is some delay in the project
  • 29. • at this time situation is needed to be taken care by finding out the reasons that are causing delay and by taking corrective actions. • Key Elements of EVA 1. Planned Value (PV) - allocated cost for the project which is approved. 2. Earned Value (EV) - The budgeted value of the completed work packages 3. Actual Cost(AC) – The actual cost involved during the execution of project work.
  • 30. 5.3 Software Quality Management • software quality - Quality means that a product satisfies the demands of its specifications. It also means achieving a high level of customer satisfaction with the product. • In software systems this is difficult that Customer quality requirements(e.g. efficiency or reliability) often conflict with developer quality requirements (e.g. maintainability or reusability)
  • 31. • Quality management or Quality control • Quality management/control involves series of inspections, reviews, tests used throughout the process. • It includes a feedback loop to the process. • A key concept of quality management/control is that all work product have defined, specifications are compared and feedback loop is essential to minimize the defects produced. • It is a procedure that focuses on fulfilling the quality requested.
  • 32. • Quality Control: Software quality control is the set of procedures used by organizations to ensure that a software product meets its quality goals at the best value(minimum cost) to the customer. • And continually improve the organization's ability to produce software products in the future.
  • 33. • Quality Assurance: Quality assurance assess the effectiveness and completeness of quality control activities. • The goal of Quality assurance is to provide management with the data necessary about product quality, gaining confidence that product quality is meeting its goal. • If not ,its managements responsibility to address the problem and apply the necessary resources to resolve quality issues.
  • 34. • Quality Assurance: It is a procedure that focuses on providing assurance that quality requested will be achieved. • Quality assurance consists of the auditing and reporting functions of management. • Software quality assurance is composed of a variety of tasks associated with two different aspects - the software engineers who do technical work and an SQA group that has responsibility for quality assurance planning, record keeping, analysis, and reporting.
  • 35. • Software engineers address quality (and perform quality assurance and quality control activities) by applying technical methods, conducting formal technical reviews, and performing well-planned software testing. • Activities of SQA(Software Quality Assurance) 1. Prepare an SQA plan for a project:- The plan is developed during project planning and is reviewed by all interested parties. Quality assurance activities performed by the software engineering team and the SQA group are governed by the plan.
  • 36. • The plan identifies – > evaluations to be performed > audits and reviews to be performed > standards that are applicable to the project > procedures for error reporting and tracking > documents to be produced by the SQA group > amount of feedback provided to the software project team
  • 37. 2.Participate in the development of the project’s software process description:-The software team selects a process for the work to be performed. The SQA group reviews the process description for compliance with organizational policy and other parts of the software project plan. 3.Review software engineering activities to verify compliance with the defined software process.:- The SQA group identifies, documents, and tracks deviations from the process and verifies that corrections have been made.
  • 38. 4. Audits are designed for s/w work products to verify compliance with those defined as a part of process. :- verify that corrections have been made and periodically reports the results of its work to the project manager. 5.Ensure that deviations in software work and work products are documented and handled according to a documented procedure. :- Deviations may be encountered in the project plan, process description, applicable standards, or technical work products.
  • 39. 6. Records any noncompliance and reports to senior management. Noncompliance items are tracked until they are resolved. • Phases of Software Quality Assurance • SQA Planning. • Activities. • Review and Audit.
  • 40. Software Quality Assurance (QA) Software Quality Control (QC) It is a procedure that focuses on providing assurance that quality requested will be achieved It is a procedure that focuses on fulfilling the quality requested. QA aims to prevent the defect QC aims to identify and fix defects It is a method to manage the quality- Verification It is a method to verify the quality- Validation It does not involve executing the program It always involves executing a program It's a Preventive technique It's a Corrective technique It's a Proactive measure It's a Reactive measure
  • 41. It is the procedure to create the deliverables It is the procedure to verify that deliverables QA involves in full software development life cycle QC involves in full software testing life cycle In order to meet the customer requirements, QA defines standards and methodologies QC confirms that the standards are followed while working on the product It is performed before Quality Control It is performed only after QA activity is done It is a Low-Level Activity, it can identify an error and mistakes which QC cannot It is a High-Level Activity, it can identify an error that QA cannot Its main motive is to prevent defects in the system. It is a less time consuming activity Its main motive is to identify defects or bugs in the system. It is a more time-consuming activity QA ensures that everything is executed in the right way, and that is why it falls under verification activity QC ensures that whatever we have done is as per the requirement, and that is why it falls under validation activity
  • 42. Software Quality Assurance (QA) Software Quality Control (QC) It requires the involvement of the whole team It requires the involvement of the Testing team The statistical technique applied on QA is known as SPC or Statistical Process Control (SPC) The statistical technique applied to QC is known as SQC or Statistical Quality Control