SlideShare a Scribd company logo
12 PROJECT PROCUREMENT MANAGEMENT 
Objective of This Chapter: 
Procurement management in construction / real estate project includes the processes 
necessary to purchase or acquire products, services, or results needed from outside the project 
organization (builder). The size and complexity of the project. 
Procurement management includes contract management and change control processes 
required to develop and administer contracts or purchase orders issued by authorised project 
team member. 
Characteristics of Project Procurement Management are 
 Material procurement for real estate project is done both by builder as well as 
contractors. Builder manages procurement of key materials like cement, steel etc. The 
contractor manages procurement of plumbing, electrical fittings etc 
 The builder is responsible for inspecting quality irrespective of whether the product is 
bought by builder or contractor. 
 Procurement includes the contract management and change control processes required 
to develop and administer Agreements or purchase orders issued by authorized project 
team members. 
 Bidders are generally called using referrals but in case of big / complex project open 
tendering through media advertising is also used 
 Head office purchase department plays critical role in project procurement activities. 
The project management team may seek support early from specialists in contracting, 
purchasing, law, and technical disciplines. Such involvement can be mandated by an 
organization's policies 
 It is the project management team's responsibility to make certain that all 
procurements meet the specific needs of the project while adhering to organizational 
procurement policies. 
 Request for quote (RFQ) is used for procurement of standard items like cement, steel , 
tiles, fittings etc 
Objective of this chapter is to understand best practices in procurement and contract 
management for products and services in construction and real estate industry. 
Contract 
Separate contractors are selected for each construction activity i,e. foundation, RCC, brick 
work, plastering, water proofing, plumbing, flooring (tile work ), windows and doors, 
electric work, painting, interior, landscaping, facilities management and security etc. 
Competitive bidding is one method of determining the least cost for performing work 
defined by the construction documents. The bid states the price that the bidder will contract 
for to perform the work based on the work shown and described in the bidding documents. 
Bids are prepared in confidence by each bidder. They are usually sealed when submitted to 
the builder (or, in the case of subcontractors, to the bidding contractors). At a specified time 
and date, all bids are opened, competitively examined, and compared. Unless there are 
compelling reasons to do otherwise, the builder (contractor in the case of subcontractors) 
usually enters into an agreement to have the work performed by the bidder submitting the 
lowest price. Before bids may be received, prospective bidders need to be identified and 
made aware of the project. In certain cases the builder may or may not wish to prequalify
bidders. In those cases where prequalification is required, the architect can have meaningful 
input in the process based on past experience with potential bidders. The terms bid and 
proposal are synonymous. Although proposal may imply an opportunity for more 
consideration and discussion with the builder, architect, or engineer. 
Generally the builder qualify at least two bidders in each category for final negotiation. 
Builder project team member might visit sites completed by prospective bidder to verify 
quality of their work or talk to previous clients. 
After final negotiation bidders may elect to change their bid on the basis of certain 
conditions, such as errors in the bid, changes in product cost, changes in labor rates etc. Each 
bidder is responsible for providing for any eventuality during the period the bid is open for 
acceptance. 
For small projects one bidder is selected for each activity for final contracts. The number of 
contractors may go up as the project size increases. 
A contract represents a mutually binding agreement that obligates the seller to provide the 
specified products, services, or results, and obligates the buyer to provide monetary or other 
valuable consideration. The agreement can be simple or complex, and can reflect the 
simplicity or complexity of the deliverables and required effort. 
Procurement Agreement will include terms and conditions, and may incorporate other items 
that the buyer specifies to establish what the seller is to perform or provide 
Contract can also be called an agreement, an understanding, a subcontract, or a purchase 
order. 
The seller can be called a contractor, subcontractor, vendor, service provider, or supplier. 
The buyer can be called a builder, customer, prime contractor, acquiring organization, 
service requestor, or purchaser. 
Managing Contractor / Suppliers 
Real estate / construction project involves following procurement : 
 Construction Supplies : Material like cement, steel , sand and other material 
 Construction Services: Architect, security and other consulting services 
 Engineering And Construction Works : RCC, electrical , plumbing and other technical 
services. These contractors provide skilled / unskilled workers and machinery to 
execute the work. Plumbing and electrical contractors can also provide material as per 
specification given by builder. 
Contractors working for builder are required to plan, manage, supervise and monitor their 
own work and that of their workers to ensure not only delivery of contracted job but also take 
care of their labour force properly. Following diagram shows contractor / supplier 
management process
For all projects contractors / consultants must: 
 Satisfy themselves that they and anyone they employ or engage are competent and 
adequately resourced; 
 Plan, manage and monitor their own work to make sure that workers adhere to work 
procedures and safety norms 
 Ensure that any sub-contractor who they appoint or engage to work on the project is 
with the permission of the builder’s project manager/supervisor and are informed of 
the minimum amount of time which will be allowed for them to plan and prepare 
before starting work on site 
 Ensure that any work they do complies with policies and procedures prescribed by 
builder 
 Comply with any requirements regulations that apply to their work 
 Co-operate with others and co-ordinate their work with others contractors working on 
the project 
 Ensure the workforce is properly consulted on matters affecting their health and safety 
 Obtain specialist advice (for example from a structural engineer or architect) where 
necessary when planning high-risk work – for example alterations that could result in 
structural failure or hazard to individuals during or after project work 
 When undertaking hazardous work provide the builder’s project manager/supervisor 
with a copy of their risk assessment and method statement designed to avoid or 
minimise the danger to those carrying out the work or who may be affected by the 
work. 
 Report any notifiable issue or concern to builder’s project manager/supervisor 
immediately 
 Report work progress at agreed frequency and standards 
 Present payment invoices and claims as per the agreed process in the contract
Contract Management 
Several factors may influence which type of Contract is appropriate. Contract flexibility, the 
incentives for quality and cost reduction, and the allocation of procurement risk as the most 
important dimensions influencing the builder’s choice of the procurement contract. Following 
are three broad categories of Contract: 
1. Fixed price (also called lump sum): Appropriate when the product is well-defined and 
the risks are generally felt to be low. Generally activities like landscaping or facility 
management are awarded using this contract type. Risk is borne by the seller because 
they are legally obligated to deliver the specified product even if they incur a loss in 
doing so. Following are some variants of fixed price contract. 
 Fixed Price with Economic Price Adjustment (FP-EPA): lf the performance period 
spans multiple years, concerns may exist about inflation and significant price changes 
for key materials or supplies. This type of contract allows adjustments to compensate 
for these uncertainties. An EPA clause ties pricing to an agreed financial index (e.g. 
consumer price index) and final prices are adjusted according to whether the index 
went up, down, or remained stable. 
 Fixed Price Incentive Fee (FPIF): Provides the seller with a fixed price plus a 
calculated fee based on performance. This contract type is similar in concept to CPIF 
in that there is a sharing arrangement that provides an incentive to control costs. 
However, in a CPIF arrangement, the seller is guaranteed a minimum profit. In an 
FPIF arrangement, it is possible for the seller to lose money. Therefore, risk is shifting 
onto the seller in this type of Agreement. FPIF contracts also have a ceiling price and 
a point of total assumption (PTA). The PTA is the level of cost at which the sharing 
arrangement ceases and any further costs come 100 percent from the seller’s profit. 
2. Cost reimbursement (Cost-Sharing): Appropriate when the scope is initially difficult 
to define (e.g electrical and plumbing work) and when risk is high. Buyers agree to 
reimburse the seller’s actual costs plus guaranteeing a profit. Risk is borne by the 
buyer. The costs include both direct costs and indirect costs. Following are some 
variants of cost reimbursement contract. 
 Cost Plus Fixed Fee (CPFF): Provides for reimbursement of allowable costs plus a 
fixed fee paid proportionately as the work progresses- Risk mostly on the buyer; used 
for research and development in which risk is quite high at the beginning of the work. 
CPFF contracts usually have a ceiling price that establishes an upper limit on the 
buyer’s financial obligation. There is no financial reward provided to the seller for 
keeping costs low. 
 Cost Plus Incentive Fee (CPIF): Provides for reimbursement of allowable costs plus a 
calculated fee based on performance. The seller has an incentive to control costs 
through a negotiated sharing arrangement. Minimum and maximum levels of profit 
are established at the outset. Again, there is often a ceiling price established by the 
Agreement.
 Cost Plus Award Fee (CPAF): As always, legitimate and allowable costs are 
reimbursed and an additional fee is paid. In this case, qualitative performance criteria 
are defined in the contract and the fee is paid based on the buyer’s subjective 
judgment of the seller’s performance. The buyer’s decision is not usually subject to 
appeal. Buyers like this arrangement because it gives them enormous leverage with 
their sellers. 
 Cost Plus Percentage of Cost (CPPC): Provides for reimbursement of allowable costs 
plus an agreed percentage of the costs (as the seller’s profit). This type of contract 
does not provide the type of incentives that most buyers look for in a contractual 
arrangement. 
3. Time and material (T&M): A hybrid arrangement with elements of both fixed price 
and cost reimbursement. On the fixed price side, the seller is paid a preset amount per 
unit of service (50 per cubic yard of gravel delivered, 200 per hour for professional 
services, and so on). On the cost reimbursement side, the value is based on how much 
material or time is actually used. Work like RCC and foundation is awarded using this 
contract type. 
Selecting Contract Types 
Risk - Degree and Timing of Contractor Responsibility 
Reward - Amount & Nature of Profit Incentive Encouraging Contractor to Achieve Goal 
Cost Plus Percentage of Cost (CPPC) 
Cost-Plus-Fixed-Fee (CPFF) 
Cost-Plus-Award-Fee (CPAF) 
Cost-Plus-Incentiv e-Fee (CPIF) 
Cost-Sharing (CS) 
Greatest Risk on Client 
Cost Risk And Contract Type 
Cost Risk High Low 
Requirement Definition Vague Well-defined 
Scenarios Exploratory Development, 
Basic Research 
Test/ Demonstration, Full-scale 
Development 
Known product or 
service 
Fixed-Price-Incentiv e (FPI) 
Firm-Fixed-Price (FFP) 
Sharing Risk 
Greatest Risk on Contractor 
Time and Material
Contract Type CPFF, CPPC CPIF, FPIF, , FFP FFP, FPIF, FPEPA 
12.1 Plan Procurement Management 
Procurement planning involves deciding which products or services should be procured from 
outside the organization, specifying the approach and identifying potential sellers. The 
questions to answer are whether, how, what, when and how much to procure. The process 
should consider the following:
12.1.1 Inputs
12.1.1.1 Project Management Plan : It includes but not limited to scope baseline contents: 
 Scope statement: Includes information such as requirements, constraints, assumptions, 
list of deliverables, acceptance criteria, required delivery dates, and available 
resources. 
 WBS: Describes and organizes the work. Is a major factor in deciding what to 
outsource. 
 WBS dictionary: Provides the details for each work package and control account. 
12.1.1.2 Requirements Documentation: Some requirements may have contractual or legal 
implications; such as environmental, intellectual property rights, health and safety, etc. 
12.1.1.3 Risk Register: Some contractual agreements are chosen as a risk mitigation strategy 
and, in any case, the risk register identifies specific risk concerns. 
12.1.1.4 Activity Resource Requirements: Identifies facilities, equipment, and people needed 
to handle the work. If these resources are not available in-house, the work may be outsourced 
. 
12.1.1.5 Project Schedule: Contains required timelines that may also become the rationale for 
entering into a contract (cannot meet the deadline with in-house sources) or may be needed to 
evaluate the ability of a prospective contractor to meet the schedule. 
12.1.1.6 Activity Cost Estimates: lf in-house costs are high, this may be a reason to outsource 
or, conversely, the information may be needed to evaluate proposals from prospective 
contractors. 
12.1.1.7 Stakeholder Register : Defines project participants and their interests in the project 
12.1.1.8 EEFs: Factors that may affect procurement planning includes conditions of the 
marketplace, product or service availability in the marketplace, reputable contractor 
available, typical terms and conditions and unique local requirements 
12.1.1.9 OPAs: Organizational Process Assets may include procurement policies and 
constraints, buying department details, any requirements that certain Agreements be set aside 
for small and disadvantaged business, procedures for selecting Agreement type, established 
supplier system and/or pre-qualified sellers 
12.1.2 Tools And Techniques 
12.1.2.1 Make-or-Buy Analysis: Determining the cost effectiveness of producing an item in-house 
(make) versus procuring it from an outside organization (buy). The analysis should 
consider both the direct costs as well as the indirect costs and is influenced by project budget 
12.1.2.2 Expert Judgment: Subject matter experts are needed to develop appropriate 
evaluation criteria and judge proposals that are received. 
12.1.2.3 Market Research : Project team can get information from conferences, online 
reviews 
12.1.2.4 Meetings 
12.1.3. Outputs
12.1.3.1 Procurement Management Plan: The plan may include all or portions of the 
following: 
 Types of Agreements 
 Whether independent estimates will be used 
 Constraints, assumptions, and supplier lead times 
 Risk management 
 Formats for the statement of work and WBS 
 Coordinating procurement with resource needs, schedules, costs, and lead times 
 Standardize procurement documents 
 Managing multiple suppliers 
12.1.3.2 Procurement Statements of Work (SOW): Is developed from scope baseline and 
contains only that portion of project scope that is included in related contract. Should contain 
enough detail so that prospective contractors can evaluate their own ability to meet the stated 
needs. Also called a statement of requirements or a statement of objectives in some areas. 
The use of an SOR or an SOO often refers to a procurement item presented as a problem to 
be solved (rather than a product to be purchased). 
The SOW contains information such as specifications, quantity and quality, period of 
performance and location, required collateral services (management activities such as 
performance reporting, earned value, or change control) 
12.1.3.3 Make-or-Buy Decisions: Written documentation of these decisions with supporting 
rationale. 
12.1.3.4 Procurement Documents: Used to request proposals from prospective sellers. Key 
points include: 
 When the procurement is price driven, the terms bid and quotation are used. 
 When the procurement is influenced by technical considerations and other non-financial 
concerns, the term proposal is used. 
 Procurement can be initiated as a unilateral Agreement, which usually means a 
purchase order for routine items at standard (catalog) prices. Purchase orders become 
enforceable at the time the supplier ships the requested items. 
 Alternatively, procurement can be initiated as a bilateral Agreement using one of four 
approaches: 
o Request for information (RFI): This approach is not actually an official 
request for a bid. Instead, it asks for "expressions of interest," solicits feedback 
regarding capacity and capability to perform the work, and so on. The RFI 
responses may be useful in developing the qualified sellers list. 
o Invitation for Bid (Sealed Bid): Used for routine, well-defined items. Buyer 
wants bids to get the best price. Does not usually involve negotiations and no 
discussion is allowed. 
o Request for Quotation: Used for relatively low dollar purchases of commodity 
items. Discussion between buyer and seller is permitted. This approach may 
be considered a "best value" search, which compares price to other factors 
such as schedule, technical merit and past performance of potential 
Agreementors. 
o Request for Proposal: used for complex, nonstandard items of high dollar 
value. Discussion and negotiation are usually involved.
12.1.3.4 Source Selection Criteria: Used to rate or score proposals. The criteria may be 
objective or subjective. Sample criteria include understanding of need, warranty , life 
cycle cost, technical capability, management approach, financial and production 
capacity, past performance , production capability , intellectual proprietary rights , industry 
referrals and business size 
12.1.3.5 Change Requests 
12.1.3.6 Project Document Update : which includes requirement documentation, requirement 
traceability matrix and risk register 
12.2 Conduct Procurements 
This process obtains information such as bids and proposals from prospective sellers, selects 
the winning response and awards a legally binding Agreement. Agreement aligns 
expectations of internal and external stakeholders. 
Other key points: 
 Proposals are often organized into different sections or volumes that are evaluated 
separately by different experts. For example, common sections evaluated separately 
are technical approach, price, schedule, management approach and past performance. 
 In some instance, organizations prefer (as a risk mitigation strategy or as a cost 
competition factor) to have multiple suppliers for certain products.
12.2.1 Inputs 
12.2.1.1 Project Management Plan: Contains the procurement management plan which was 
an output of the previous process 
12.2.1.2 Procurement Documents: an appropriate document is chosen to request seller 
responses (IFB, RFQ and RFP). 
12.2.1.3 Source Selection Criteria: Used to actually evaluate and compare the various bids or 
proposals. 
12.2.1.4 Seller Proposals: Prepared and submitted in response to the buyer’s procurement 
document package (PDP). 
12.2.1.5 Project Documents: Project documents that may be considered at this point include 
the risk and any risk-related contract decisions.
12.2.1.6 Make-Or-Buy Decisions: Described in previous section 
12.2.1.7 Procurement Statement Of Work: It is an important document in procurement 
process and can be modified until the final agreement is in place. The statement of work 
includes but not limited to specifications, quantity desired, quality level, performance data, 
period of performance, work location and other requirements 
12.2.1.8 OPAs: Organizational Process Assets that may be relevant include qualified lists, 
information on relevant past experience with specific sellers 
12.2.2 Tools And Techniques 
12.2.2.1 Bidder Conferences: Used to ensure all prospective sellers share a clear, common 
understanding of technical and contractual requirements. Most organizations are careful to 
ensure that all potential sellers are given equal treatment and information. 
12.2.2.2 Proposal Evaluation Techniques: Most organizations that conduct major 
procurements have established source selection procedures. Evaluation committee will make 
selection for approval by management prior to award. 
12.2.2.3 Independent Estimates: Procurement organization prepares its own estimates as a 
cross-check or verification that the bids are fair and reasonable. Also called “should cost” 
estimates, this tool is especially important for non-competitive procurements (e.g. sole 
source). 
12.2.2.4 Expert Judgment: A multi-disciplinary team of experts (financial, technical, 
management) is usually required to effectively evaluate proposals. 
12.2.2.5 Advertising: The use of general circulation sources such as newspapers and 
professional journals and newsletters to expand the potential pool of sellers. 
Analytical techniques : These help to access the readiness of the vendor the desired end state , 
expected cost and avoid cost overrun 
12.2.2.6 Procurement Negotiations: Clarification and mutual agreement on the structure and 
requirements of the contract prior to signing. Common negotiation tactics are 
 Deadline: "We have to catch a flight at 5:00 p.m. and must complete the deal before 
we leave." 
 Fait accompli: Pretending that some condition is essentially a "done deal" or not 
negotiable at all. 
 Missing man: "I'm sorry, only my boss can agree to that request and he or she isn't 
here. Let's agree to do___________ instead. I can agree to that." 
 Limited authority: "l can't agree the price by 100,000. I'm only authorized to offer 
80,000." 
 Delay: "Let's handle that issue at the next meeting." May be a ploy leading to a 
deadline tactic. "Oops, we're running out of time, so let's sign this deal and work out 
any issues later." 
 Personal insults: Designed to intimidate and/or undermine confidence. 
 Fair and reasonable: A personal appeal that may be posed with a great deal of charm 
and be reasonable. 
12.2.3 Output
12.2.3.1 Selected Sellers: Sellers who have been chosen as being in the competitive range and 
who have submitted a proposal that has been accepted. The proposal becomes the basis for 
the contract (subject to any last-minute negotiating of terms and conditions). 
12.2.3.2 Agreements: A legal relationship subject to remedy in the courts. An agreement is a 
mutually binding that obligates the seller to provide the specified product and obligates the 
buyer to pay for it. 
While there may be differences, the major components in most agreements include the 
following: 
 Statement of work or deliverables 
 Period of performance and schedule baseline 
 Required performance reporting 
 Roles and responsibilities 
 Place of performance and delivery 
 Pricing and payment terms 
 Warranty and product support 
 Penalties and incentives 
 Subcontractor approvals 
 Handling of change requests 
 Insurance and performance bonds 
 Dispute resolution procedures 
 Termination procedures 
12.2.3.3 Resource Calendars: Specific quantity and availability of contracted resources. 
12.2.3.4 Change Requests: lf change requests are generated during the procurement, they 
must be handled using integrated change control procedures. 
12.2.3.5 Project Management Plan Updates: Elements of the plan that may be changed 
include cost, schedule, scope baselines. Procurement management plan and communication 
management plan. 
12.2.3.6 Project Document Updates: Documents that may be updated include 
requirements documentation, requirements traceability documentation, risk register 
12.3 Control Procurements 
This is the process of managing procurement relationships, monitoring contract performance 
and making changes and corrections to contract as appropriate. Both buyer and seller will 
administer the contract. Contract administrator may be part of project team but may report to 
different department. Due to varying organization structures, many organizations treat 
contract administration as an administrative function separate from project organization. The 
same process may be applicable for financial management of contract. 
Agreements can be amended at any time prior to contract closure in accordance with change 
control terms of the agreement.
12.3.1 Inputs 
12.3.1.1 Project Management Plan: contains the procurement management plan which 
describes how each procurement process is to be handled. 
12.3.1.2 Procurement Documents: The procurement contract awards and the SOW are two of 
the most important documents that would guide Agreement administration. 
Agreements: Described in previous section
12.3.1.3 Work Performance Reports: Seller performance documentation in the areas of 
technical achievement and performance reports (cost, schedule, resource variances and 
forecasts). 
12.3.1.4 Approved Change Requests: May include modifications to agreement terms and 
conditions with the most important being any effect on the triple constraint (scope, schedule 
and cost). Verbally discussed but undocumented change requests should not be processed or 
implemented. 
12.3.1.5 Work Performance Data: Addresses whether quality standards are being met, what 
costs have been incurred, the completion status of deliverable, and what interim payments 
have been requested and/or paid. 
12.3.2 Tools And Techniques 
12.3.2.1 Contract Change Control System: As always, establishes the procedures by which 
changes can be approved. Includes paperwork, tracking, approval levels and dispute 
resolution procedures. 
12.3.2.2 Procurement Performance Reviews: A structured review of the seller's progress 
(cost, schedule, scope, quality). The purpose of these reviews is to document successes and 
failures as well as demonstrate whether the seller is able to complete the work. 
12.3.2.3 Inspections And Audits: These quality management techniques are used to check for 
compliance with Agreement requirements. Inspections and audits are usually required by the 
buyer and supported by information from the seller. 
12.3.2.4 Performance Reporting: Documents the contractor's relative effectiveness in 
achieving agreed objectives. 
12.3.2.5 Payment Systems: The payment system includes appropriate reviews and approvals 
so that interim and final payments can be made as appropriate. Payment systems are 
sometimes handled by the project (larger programs) but are frequently handled by the 
accounts payable department in the overall organization. 
12.3.2.6 Claims Administration: Contested or constructive changes are those where the buyer 
and seller cannot agree on the terms (cost, schedule) for a change. In Some cases, a dispute 
arises over whether work item is a change in scope or is a legitimate part of the original 
scope. 
If the parties cannot resolve a claim themselves, the matter is then handled through whatever 
dispute resolution procedures were established in the agreement. Dispute resolution can occur 
during project performance or after a project has been closed. 
12.3.2.7 Records Management System: Used to manage contract, documents and records. 
Usually involves an index of contract documents with methods for retrieval, archiving and 
automation. 
12.3.3 Outputs 
12.3.3.1 Work Performance Information : Includes reporting compliance of contacts, tracking 
expected deliverables received from vendor. It improves communication with vendor.
12.3.3.2 Change Requests: Processed using integrated change control. Disputed changes are 
usually given special attention and documented separately. 
Project Management Plan updates: Elements of the plan that may be updated include: 
 Procurement management plan (to reflect approved change requests, especially those 
affecting costs or schedules) 
 Baseline schedule (to reflect any significant variances from the baseline or revisions 
to the baseline because of approved changes) 
12.3.3.3 Project Documents Update : Mainly includes procurement documents 
12.3.3.4 OPA Updates: Key correspondence concerning audits, inspections, change requests, 
warnings for unsatisfactory performance, and key decisions. Information about payment 
schedules and how seller performance is documented would also be updated at this stage. 
12.4 Close Procurements: 
Agreements closure supports the close project or phase process . It involves product 
verification (was the work completed correctly?) and administrative closeout (updating and 
archiving of records). Early termination is a special case of contract closure and can result 
from a mutual decision, from default by one of the parties, or for convenience of the buyer. 
The rights of the parties should be defined in a terminations clause in the contract.
12.4.1 Inputs 
12.4.1.1 Project Management Plan 
12.4.1.2 Procurement Documentation: All documentation is collected, indexed, and filed 
according to established procedures. The information can be used for lessons learned, 
estimating future contracts, and evaluating contractors for future procurements. 
12.4.2 Tools And Techniques 
12.4.2.1 Procurement Audits: Structured reviews of the procurement process to identify 
successes and failures. The information is used to improve the current project, future projects, 
and the overall organization. Procurement audits are also known as lessons learned in some 
areas. 
12.4.2.2 Procurement Negotiations: Final settlement of all outstanding issues, claims, and 
disputes using negotiation if possible. Alternate dispute resolution (ADR) is used only when 
necessary. 
12.4.2.3 Records Management System: Used by project manager to manage contract, 
procurement documentation and records 
12.4.3 Outputs 
12.4.3.1 Closed Procurements: The buyer provides formal, written notice that the contract has 
been completed. 
12.4.3.2 OPA Updates: include the following: 
 Procurement file: An official, complete set of indexed contract documentation. 
 Deliverable acceptance: Formal, written notice that deliverables have been accepted 
or rejected. Instructions on how to handle non- conforming deliverables should be 
provided.
 Lessons learned documentation: Post-project evaluation is important because it 
provides historical records that help in contractor selection on future contracts (a past 
performance database to support the select sellers process).

More Related Content

What's hot

Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Unanet
 
types of contracts
 types of contracts types of contracts
types of contractsKEVINMISTRY8
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsKunal Kacholiya
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts fritzlejarso
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consultingThis account is closed
 

What's hot (20)

Contractors
ContractorsContractors
Contractors
 
Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types Government Contracts 101 - Understanding the Basics of Contract Types
Government Contracts 101 - Understanding the Basics of Contract Types
 
types of contracts
 types of contracts types of contracts
types of contracts
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
Cost Plus Contract
Cost Plus ContractCost Plus Contract
Cost Plus Contract
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
rate contract
rate contractrate contract
rate contract
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Construction contract
Construction contract Construction contract
Construction contract
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 

Similar to 2.12 procurement management 1

Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpmKaila Turla
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-completeYong Sy
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsConstruction in Focus
 
Project management chapter 8
Project management chapter 8Project management chapter 8
Project management chapter 8VancityInstitute
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt2cd
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaGuta Mengesha
 

Similar to 2.12 procurement management 1 (20)

PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Group 1 presentation intro to cpm
Group 1 presentation intro to cpmGroup 1 presentation intro to cpm
Group 1 presentation intro to cpm
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp 1-report-complete
Pp 1-report-completePp 1-report-complete
Pp 1-report-complete
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Procurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery modelsProcurement in Focus - the pros and cons of various project delivery models
Procurement in Focus - the pros and cons of various project delivery models
 
Project management chapter 8
Project management chapter 8Project management chapter 8
Project management chapter 8
 
Unit-1_Contracts
Unit-1_ContractsUnit-1_Contracts
Unit-1_Contracts
 
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy pptCON_CONTRACTS_all_till_mid. bgf uggttyy ppt
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 

More from reddvise

Rera highlights
Rera highlightsRera highlights
Rera highlightsreddvise
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )reddvise
 
Silent feature regulation bill act 2016
Silent feature regulation bill act 2016Silent feature regulation bill act 2016
Silent feature regulation bill act 2016reddvise
 
Rera highlights
Rera highlightsRera highlights
Rera highlightsreddvise
 
Real estate regulation bill act 2016
Real estate regulation bill act 2016Real estate regulation bill act 2016
Real estate regulation bill act 2016reddvise
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )reddvise
 
Maha rera overview
Maha rera overviewMaha rera overview
Maha rera overviewreddvise
 
Maharashtra rera act 2017
Maharashtra rera act 2017Maharashtra rera act 2017
Maharashtra rera act 2017reddvise
 
Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2reddvise
 
Iref hl sims final
Iref hl sims finalIref hl sims final
Iref hl sims finalreddvise
 
Sales -introducation
Sales  -introducationSales  -introducation
Sales -introducationreddvise
 
Marketing -introducation
Marketing  -introducationMarketing  -introducation
Marketing -introducationreddvise
 
Real estate sector over view sims edp
Real estate sector over view  sims edpReal estate sector over view  sims edp
Real estate sector over view sims edpreddvise
 
Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13reddvise
 
1 managing real estate
1 managing real estate1 managing real estate
1 managing real estatereddvise
 
Real estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshReal estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshreddvise
 
Edp real estate services business guidelines
Edp  real estate services business guidelinesEdp  real estate services business guidelines
Edp real estate services business guidelinesreddvise
 
Edp sims business development
Edp sims  business developmentEdp sims  business development
Edp sims business developmentreddvise
 
01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims01 managing real estate srevices business edp sims
01 managing real estate srevices business edp simsreddvise
 
Lead generation and customer targeting with technology
Lead generation and customer targeting with technologyLead generation and customer targeting with technology
Lead generation and customer targeting with technologyreddvise
 

More from reddvise (20)

Rera highlights
Rera highlightsRera highlights
Rera highlights
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )
 
Silent feature regulation bill act 2016
Silent feature regulation bill act 2016Silent feature regulation bill act 2016
Silent feature regulation bill act 2016
 
Rera highlights
Rera highlightsRera highlights
Rera highlights
 
Real estate regulation bill act 2016
Real estate regulation bill act 2016Real estate regulation bill act 2016
Real estate regulation bill act 2016
 
Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )Real estate regulation ( a ca overview )
Real estate regulation ( a ca overview )
 
Maha rera overview
Maha rera overviewMaha rera overview
Maha rera overview
 
Maharashtra rera act 2017
Maharashtra rera act 2017Maharashtra rera act 2017
Maharashtra rera act 2017
 
Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2Sims real-estate-young-leadership-program-2
Sims real-estate-young-leadership-program-2
 
Iref hl sims final
Iref hl sims finalIref hl sims final
Iref hl sims final
 
Sales -introducation
Sales  -introducationSales  -introducation
Sales -introducation
 
Marketing -introducation
Marketing  -introducationMarketing  -introducation
Marketing -introducation
 
Real estate sector over view sims edp
Real estate sector over view  sims edpReal estate sector over view  sims edp
Real estate sector over view sims edp
 
Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13Entrepreneurship matrix blue print 13
Entrepreneurship matrix blue print 13
 
1 managing real estate
1 managing real estate1 managing real estate
1 managing real estate
 
Real estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupakshReal estate construction profitability analysis iref virupaksh
Real estate construction profitability analysis iref virupaksh
 
Edp real estate services business guidelines
Edp  real estate services business guidelinesEdp  real estate services business guidelines
Edp real estate services business guidelines
 
Edp sims business development
Edp sims  business developmentEdp sims  business development
Edp sims business development
 
01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims01 managing real estate srevices business edp sims
01 managing real estate srevices business edp sims
 
Lead generation and customer targeting with technology
Lead generation and customer targeting with technologyLead generation and customer targeting with technology
Lead generation and customer targeting with technology
 

Recently uploaded

2024_Student Session 2_ Set Plan Preparation.pptx
2024_Student Session 2_ Set Plan Preparation.pptx2024_Student Session 2_ Set Plan Preparation.pptx
2024_Student Session 2_ Set Plan Preparation.pptxmansk2
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxDenish Jangid
 
Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportAvinash Rai
 
slides CapTechTalks Webinar May 2024 Alexander Perry.pptx
slides CapTechTalks Webinar May 2024 Alexander Perry.pptxslides CapTechTalks Webinar May 2024 Alexander Perry.pptx
slides CapTechTalks Webinar May 2024 Alexander Perry.pptxCapitolTechU
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPCeline George
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chipsGeoBlogs
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfVivekanand Anglo Vedic Academy
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345beazzy04
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxricssacare
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxakshayaramakrishnan21
 
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringBasic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringDenish Jangid
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxRaedMohamed3
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfbu07226
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsCol Mukteshwar Prasad
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfTamralipta Mahavidyalaya
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...Denish Jangid
 
The Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational ResourcesThe Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational Resourcesaileywriter
 

Recently uploaded (20)

2024_Student Session 2_ Set Plan Preparation.pptx
2024_Student Session 2_ Set Plan Preparation.pptx2024_Student Session 2_ Set Plan Preparation.pptx
2024_Student Session 2_ Set Plan Preparation.pptx
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
 
Industrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training ReportIndustrial Training Report- AKTU Industrial Training Report
Industrial Training Report- AKTU Industrial Training Report
 
slides CapTechTalks Webinar May 2024 Alexander Perry.pptx
slides CapTechTalks Webinar May 2024 Alexander Perry.pptxslides CapTechTalks Webinar May 2024 Alexander Perry.pptx
slides CapTechTalks Webinar May 2024 Alexander Perry.pptx
 
Mattingly "AI & Prompt Design: Limitations and Solutions with LLMs"
Mattingly "AI & Prompt Design: Limitations and Solutions with LLMs"Mattingly "AI & Prompt Design: Limitations and Solutions with LLMs"
Mattingly "AI & Prompt Design: Limitations and Solutions with LLMs"
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptx
 
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & EngineeringBasic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
Basic Civil Engg Notes_Chapter-6_Environment Pollution & Engineering
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdfINU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
INU_CAPSTONEDESIGN_비밀번호486_업로드용 발표자료.pdf
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
 
NCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdfNCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdf
 
The Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational ResourcesThe Benefits and Challenges of Open Educational Resources
The Benefits and Challenges of Open Educational Resources
 

2.12 procurement management 1

  • 1. 12 PROJECT PROCUREMENT MANAGEMENT Objective of This Chapter: Procurement management in construction / real estate project includes the processes necessary to purchase or acquire products, services, or results needed from outside the project organization (builder). The size and complexity of the project. Procurement management includes contract management and change control processes required to develop and administer contracts or purchase orders issued by authorised project team member. Characteristics of Project Procurement Management are  Material procurement for real estate project is done both by builder as well as contractors. Builder manages procurement of key materials like cement, steel etc. The contractor manages procurement of plumbing, electrical fittings etc  The builder is responsible for inspecting quality irrespective of whether the product is bought by builder or contractor.  Procurement includes the contract management and change control processes required to develop and administer Agreements or purchase orders issued by authorized project team members.  Bidders are generally called using referrals but in case of big / complex project open tendering through media advertising is also used  Head office purchase department plays critical role in project procurement activities. The project management team may seek support early from specialists in contracting, purchasing, law, and technical disciplines. Such involvement can be mandated by an organization's policies  It is the project management team's responsibility to make certain that all procurements meet the specific needs of the project while adhering to organizational procurement policies.  Request for quote (RFQ) is used for procurement of standard items like cement, steel , tiles, fittings etc Objective of this chapter is to understand best practices in procurement and contract management for products and services in construction and real estate industry. Contract Separate contractors are selected for each construction activity i,e. foundation, RCC, brick work, plastering, water proofing, plumbing, flooring (tile work ), windows and doors, electric work, painting, interior, landscaping, facilities management and security etc. Competitive bidding is one method of determining the least cost for performing work defined by the construction documents. The bid states the price that the bidder will contract for to perform the work based on the work shown and described in the bidding documents. Bids are prepared in confidence by each bidder. They are usually sealed when submitted to the builder (or, in the case of subcontractors, to the bidding contractors). At a specified time and date, all bids are opened, competitively examined, and compared. Unless there are compelling reasons to do otherwise, the builder (contractor in the case of subcontractors) usually enters into an agreement to have the work performed by the bidder submitting the lowest price. Before bids may be received, prospective bidders need to be identified and made aware of the project. In certain cases the builder may or may not wish to prequalify
  • 2. bidders. In those cases where prequalification is required, the architect can have meaningful input in the process based on past experience with potential bidders. The terms bid and proposal are synonymous. Although proposal may imply an opportunity for more consideration and discussion with the builder, architect, or engineer. Generally the builder qualify at least two bidders in each category for final negotiation. Builder project team member might visit sites completed by prospective bidder to verify quality of their work or talk to previous clients. After final negotiation bidders may elect to change their bid on the basis of certain conditions, such as errors in the bid, changes in product cost, changes in labor rates etc. Each bidder is responsible for providing for any eventuality during the period the bid is open for acceptance. For small projects one bidder is selected for each activity for final contracts. The number of contractors may go up as the project size increases. A contract represents a mutually binding agreement that obligates the seller to provide the specified products, services, or results, and obligates the buyer to provide monetary or other valuable consideration. The agreement can be simple or complex, and can reflect the simplicity or complexity of the deliverables and required effort. Procurement Agreement will include terms and conditions, and may incorporate other items that the buyer specifies to establish what the seller is to perform or provide Contract can also be called an agreement, an understanding, a subcontract, or a purchase order. The seller can be called a contractor, subcontractor, vendor, service provider, or supplier. The buyer can be called a builder, customer, prime contractor, acquiring organization, service requestor, or purchaser. Managing Contractor / Suppliers Real estate / construction project involves following procurement :  Construction Supplies : Material like cement, steel , sand and other material  Construction Services: Architect, security and other consulting services  Engineering And Construction Works : RCC, electrical , plumbing and other technical services. These contractors provide skilled / unskilled workers and machinery to execute the work. Plumbing and electrical contractors can also provide material as per specification given by builder. Contractors working for builder are required to plan, manage, supervise and monitor their own work and that of their workers to ensure not only delivery of contracted job but also take care of their labour force properly. Following diagram shows contractor / supplier management process
  • 3. For all projects contractors / consultants must:  Satisfy themselves that they and anyone they employ or engage are competent and adequately resourced;  Plan, manage and monitor their own work to make sure that workers adhere to work procedures and safety norms  Ensure that any sub-contractor who they appoint or engage to work on the project is with the permission of the builder’s project manager/supervisor and are informed of the minimum amount of time which will be allowed for them to plan and prepare before starting work on site  Ensure that any work they do complies with policies and procedures prescribed by builder  Comply with any requirements regulations that apply to their work  Co-operate with others and co-ordinate their work with others contractors working on the project  Ensure the workforce is properly consulted on matters affecting their health and safety  Obtain specialist advice (for example from a structural engineer or architect) where necessary when planning high-risk work – for example alterations that could result in structural failure or hazard to individuals during or after project work  When undertaking hazardous work provide the builder’s project manager/supervisor with a copy of their risk assessment and method statement designed to avoid or minimise the danger to those carrying out the work or who may be affected by the work.  Report any notifiable issue or concern to builder’s project manager/supervisor immediately  Report work progress at agreed frequency and standards  Present payment invoices and claims as per the agreed process in the contract
  • 4. Contract Management Several factors may influence which type of Contract is appropriate. Contract flexibility, the incentives for quality and cost reduction, and the allocation of procurement risk as the most important dimensions influencing the builder’s choice of the procurement contract. Following are three broad categories of Contract: 1. Fixed price (also called lump sum): Appropriate when the product is well-defined and the risks are generally felt to be low. Generally activities like landscaping or facility management are awarded using this contract type. Risk is borne by the seller because they are legally obligated to deliver the specified product even if they incur a loss in doing so. Following are some variants of fixed price contract.  Fixed Price with Economic Price Adjustment (FP-EPA): lf the performance period spans multiple years, concerns may exist about inflation and significant price changes for key materials or supplies. This type of contract allows adjustments to compensate for these uncertainties. An EPA clause ties pricing to an agreed financial index (e.g. consumer price index) and final prices are adjusted according to whether the index went up, down, or remained stable.  Fixed Price Incentive Fee (FPIF): Provides the seller with a fixed price plus a calculated fee based on performance. This contract type is similar in concept to CPIF in that there is a sharing arrangement that provides an incentive to control costs. However, in a CPIF arrangement, the seller is guaranteed a minimum profit. In an FPIF arrangement, it is possible for the seller to lose money. Therefore, risk is shifting onto the seller in this type of Agreement. FPIF contracts also have a ceiling price and a point of total assumption (PTA). The PTA is the level of cost at which the sharing arrangement ceases and any further costs come 100 percent from the seller’s profit. 2. Cost reimbursement (Cost-Sharing): Appropriate when the scope is initially difficult to define (e.g electrical and plumbing work) and when risk is high. Buyers agree to reimburse the seller’s actual costs plus guaranteeing a profit. Risk is borne by the buyer. The costs include both direct costs and indirect costs. Following are some variants of cost reimbursement contract.  Cost Plus Fixed Fee (CPFF): Provides for reimbursement of allowable costs plus a fixed fee paid proportionately as the work progresses- Risk mostly on the buyer; used for research and development in which risk is quite high at the beginning of the work. CPFF contracts usually have a ceiling price that establishes an upper limit on the buyer’s financial obligation. There is no financial reward provided to the seller for keeping costs low.  Cost Plus Incentive Fee (CPIF): Provides for reimbursement of allowable costs plus a calculated fee based on performance. The seller has an incentive to control costs through a negotiated sharing arrangement. Minimum and maximum levels of profit are established at the outset. Again, there is often a ceiling price established by the Agreement.
  • 5.  Cost Plus Award Fee (CPAF): As always, legitimate and allowable costs are reimbursed and an additional fee is paid. In this case, qualitative performance criteria are defined in the contract and the fee is paid based on the buyer’s subjective judgment of the seller’s performance. The buyer’s decision is not usually subject to appeal. Buyers like this arrangement because it gives them enormous leverage with their sellers.  Cost Plus Percentage of Cost (CPPC): Provides for reimbursement of allowable costs plus an agreed percentage of the costs (as the seller’s profit). This type of contract does not provide the type of incentives that most buyers look for in a contractual arrangement. 3. Time and material (T&M): A hybrid arrangement with elements of both fixed price and cost reimbursement. On the fixed price side, the seller is paid a preset amount per unit of service (50 per cubic yard of gravel delivered, 200 per hour for professional services, and so on). On the cost reimbursement side, the value is based on how much material or time is actually used. Work like RCC and foundation is awarded using this contract type. Selecting Contract Types Risk - Degree and Timing of Contractor Responsibility Reward - Amount & Nature of Profit Incentive Encouraging Contractor to Achieve Goal Cost Plus Percentage of Cost (CPPC) Cost-Plus-Fixed-Fee (CPFF) Cost-Plus-Award-Fee (CPAF) Cost-Plus-Incentiv e-Fee (CPIF) Cost-Sharing (CS) Greatest Risk on Client Cost Risk And Contract Type Cost Risk High Low Requirement Definition Vague Well-defined Scenarios Exploratory Development, Basic Research Test/ Demonstration, Full-scale Development Known product or service Fixed-Price-Incentiv e (FPI) Firm-Fixed-Price (FFP) Sharing Risk Greatest Risk on Contractor Time and Material
  • 6. Contract Type CPFF, CPPC CPIF, FPIF, , FFP FFP, FPIF, FPEPA 12.1 Plan Procurement Management Procurement planning involves deciding which products or services should be procured from outside the organization, specifying the approach and identifying potential sellers. The questions to answer are whether, how, what, when and how much to procure. The process should consider the following:
  • 8. 12.1.1.1 Project Management Plan : It includes but not limited to scope baseline contents:  Scope statement: Includes information such as requirements, constraints, assumptions, list of deliverables, acceptance criteria, required delivery dates, and available resources.  WBS: Describes and organizes the work. Is a major factor in deciding what to outsource.  WBS dictionary: Provides the details for each work package and control account. 12.1.1.2 Requirements Documentation: Some requirements may have contractual or legal implications; such as environmental, intellectual property rights, health and safety, etc. 12.1.1.3 Risk Register: Some contractual agreements are chosen as a risk mitigation strategy and, in any case, the risk register identifies specific risk concerns. 12.1.1.4 Activity Resource Requirements: Identifies facilities, equipment, and people needed to handle the work. If these resources are not available in-house, the work may be outsourced . 12.1.1.5 Project Schedule: Contains required timelines that may also become the rationale for entering into a contract (cannot meet the deadline with in-house sources) or may be needed to evaluate the ability of a prospective contractor to meet the schedule. 12.1.1.6 Activity Cost Estimates: lf in-house costs are high, this may be a reason to outsource or, conversely, the information may be needed to evaluate proposals from prospective contractors. 12.1.1.7 Stakeholder Register : Defines project participants and their interests in the project 12.1.1.8 EEFs: Factors that may affect procurement planning includes conditions of the marketplace, product or service availability in the marketplace, reputable contractor available, typical terms and conditions and unique local requirements 12.1.1.9 OPAs: Organizational Process Assets may include procurement policies and constraints, buying department details, any requirements that certain Agreements be set aside for small and disadvantaged business, procedures for selecting Agreement type, established supplier system and/or pre-qualified sellers 12.1.2 Tools And Techniques 12.1.2.1 Make-or-Buy Analysis: Determining the cost effectiveness of producing an item in-house (make) versus procuring it from an outside organization (buy). The analysis should consider both the direct costs as well as the indirect costs and is influenced by project budget 12.1.2.2 Expert Judgment: Subject matter experts are needed to develop appropriate evaluation criteria and judge proposals that are received. 12.1.2.3 Market Research : Project team can get information from conferences, online reviews 12.1.2.4 Meetings 12.1.3. Outputs
  • 9. 12.1.3.1 Procurement Management Plan: The plan may include all or portions of the following:  Types of Agreements  Whether independent estimates will be used  Constraints, assumptions, and supplier lead times  Risk management  Formats for the statement of work and WBS  Coordinating procurement with resource needs, schedules, costs, and lead times  Standardize procurement documents  Managing multiple suppliers 12.1.3.2 Procurement Statements of Work (SOW): Is developed from scope baseline and contains only that portion of project scope that is included in related contract. Should contain enough detail so that prospective contractors can evaluate their own ability to meet the stated needs. Also called a statement of requirements or a statement of objectives in some areas. The use of an SOR or an SOO often refers to a procurement item presented as a problem to be solved (rather than a product to be purchased). The SOW contains information such as specifications, quantity and quality, period of performance and location, required collateral services (management activities such as performance reporting, earned value, or change control) 12.1.3.3 Make-or-Buy Decisions: Written documentation of these decisions with supporting rationale. 12.1.3.4 Procurement Documents: Used to request proposals from prospective sellers. Key points include:  When the procurement is price driven, the terms bid and quotation are used.  When the procurement is influenced by technical considerations and other non-financial concerns, the term proposal is used.  Procurement can be initiated as a unilateral Agreement, which usually means a purchase order for routine items at standard (catalog) prices. Purchase orders become enforceable at the time the supplier ships the requested items.  Alternatively, procurement can be initiated as a bilateral Agreement using one of four approaches: o Request for information (RFI): This approach is not actually an official request for a bid. Instead, it asks for "expressions of interest," solicits feedback regarding capacity and capability to perform the work, and so on. The RFI responses may be useful in developing the qualified sellers list. o Invitation for Bid (Sealed Bid): Used for routine, well-defined items. Buyer wants bids to get the best price. Does not usually involve negotiations and no discussion is allowed. o Request for Quotation: Used for relatively low dollar purchases of commodity items. Discussion between buyer and seller is permitted. This approach may be considered a "best value" search, which compares price to other factors such as schedule, technical merit and past performance of potential Agreementors. o Request for Proposal: used for complex, nonstandard items of high dollar value. Discussion and negotiation are usually involved.
  • 10. 12.1.3.4 Source Selection Criteria: Used to rate or score proposals. The criteria may be objective or subjective. Sample criteria include understanding of need, warranty , life cycle cost, technical capability, management approach, financial and production capacity, past performance , production capability , intellectual proprietary rights , industry referrals and business size 12.1.3.5 Change Requests 12.1.3.6 Project Document Update : which includes requirement documentation, requirement traceability matrix and risk register 12.2 Conduct Procurements This process obtains information such as bids and proposals from prospective sellers, selects the winning response and awards a legally binding Agreement. Agreement aligns expectations of internal and external stakeholders. Other key points:  Proposals are often organized into different sections or volumes that are evaluated separately by different experts. For example, common sections evaluated separately are technical approach, price, schedule, management approach and past performance.  In some instance, organizations prefer (as a risk mitigation strategy or as a cost competition factor) to have multiple suppliers for certain products.
  • 11. 12.2.1 Inputs 12.2.1.1 Project Management Plan: Contains the procurement management plan which was an output of the previous process 12.2.1.2 Procurement Documents: an appropriate document is chosen to request seller responses (IFB, RFQ and RFP). 12.2.1.3 Source Selection Criteria: Used to actually evaluate and compare the various bids or proposals. 12.2.1.4 Seller Proposals: Prepared and submitted in response to the buyer’s procurement document package (PDP). 12.2.1.5 Project Documents: Project documents that may be considered at this point include the risk and any risk-related contract decisions.
  • 12. 12.2.1.6 Make-Or-Buy Decisions: Described in previous section 12.2.1.7 Procurement Statement Of Work: It is an important document in procurement process and can be modified until the final agreement is in place. The statement of work includes but not limited to specifications, quantity desired, quality level, performance data, period of performance, work location and other requirements 12.2.1.8 OPAs: Organizational Process Assets that may be relevant include qualified lists, information on relevant past experience with specific sellers 12.2.2 Tools And Techniques 12.2.2.1 Bidder Conferences: Used to ensure all prospective sellers share a clear, common understanding of technical and contractual requirements. Most organizations are careful to ensure that all potential sellers are given equal treatment and information. 12.2.2.2 Proposal Evaluation Techniques: Most organizations that conduct major procurements have established source selection procedures. Evaluation committee will make selection for approval by management prior to award. 12.2.2.3 Independent Estimates: Procurement organization prepares its own estimates as a cross-check or verification that the bids are fair and reasonable. Also called “should cost” estimates, this tool is especially important for non-competitive procurements (e.g. sole source). 12.2.2.4 Expert Judgment: A multi-disciplinary team of experts (financial, technical, management) is usually required to effectively evaluate proposals. 12.2.2.5 Advertising: The use of general circulation sources such as newspapers and professional journals and newsletters to expand the potential pool of sellers. Analytical techniques : These help to access the readiness of the vendor the desired end state , expected cost and avoid cost overrun 12.2.2.6 Procurement Negotiations: Clarification and mutual agreement on the structure and requirements of the contract prior to signing. Common negotiation tactics are  Deadline: "We have to catch a flight at 5:00 p.m. and must complete the deal before we leave."  Fait accompli: Pretending that some condition is essentially a "done deal" or not negotiable at all.  Missing man: "I'm sorry, only my boss can agree to that request and he or she isn't here. Let's agree to do___________ instead. I can agree to that."  Limited authority: "l can't agree the price by 100,000. I'm only authorized to offer 80,000."  Delay: "Let's handle that issue at the next meeting." May be a ploy leading to a deadline tactic. "Oops, we're running out of time, so let's sign this deal and work out any issues later."  Personal insults: Designed to intimidate and/or undermine confidence.  Fair and reasonable: A personal appeal that may be posed with a great deal of charm and be reasonable. 12.2.3 Output
  • 13. 12.2.3.1 Selected Sellers: Sellers who have been chosen as being in the competitive range and who have submitted a proposal that has been accepted. The proposal becomes the basis for the contract (subject to any last-minute negotiating of terms and conditions). 12.2.3.2 Agreements: A legal relationship subject to remedy in the courts. An agreement is a mutually binding that obligates the seller to provide the specified product and obligates the buyer to pay for it. While there may be differences, the major components in most agreements include the following:  Statement of work or deliverables  Period of performance and schedule baseline  Required performance reporting  Roles and responsibilities  Place of performance and delivery  Pricing and payment terms  Warranty and product support  Penalties and incentives  Subcontractor approvals  Handling of change requests  Insurance and performance bonds  Dispute resolution procedures  Termination procedures 12.2.3.3 Resource Calendars: Specific quantity and availability of contracted resources. 12.2.3.4 Change Requests: lf change requests are generated during the procurement, they must be handled using integrated change control procedures. 12.2.3.5 Project Management Plan Updates: Elements of the plan that may be changed include cost, schedule, scope baselines. Procurement management plan and communication management plan. 12.2.3.6 Project Document Updates: Documents that may be updated include requirements documentation, requirements traceability documentation, risk register 12.3 Control Procurements This is the process of managing procurement relationships, monitoring contract performance and making changes and corrections to contract as appropriate. Both buyer and seller will administer the contract. Contract administrator may be part of project team but may report to different department. Due to varying organization structures, many organizations treat contract administration as an administrative function separate from project organization. The same process may be applicable for financial management of contract. Agreements can be amended at any time prior to contract closure in accordance with change control terms of the agreement.
  • 14. 12.3.1 Inputs 12.3.1.1 Project Management Plan: contains the procurement management plan which describes how each procurement process is to be handled. 12.3.1.2 Procurement Documents: The procurement contract awards and the SOW are two of the most important documents that would guide Agreement administration. Agreements: Described in previous section
  • 15. 12.3.1.3 Work Performance Reports: Seller performance documentation in the areas of technical achievement and performance reports (cost, schedule, resource variances and forecasts). 12.3.1.4 Approved Change Requests: May include modifications to agreement terms and conditions with the most important being any effect on the triple constraint (scope, schedule and cost). Verbally discussed but undocumented change requests should not be processed or implemented. 12.3.1.5 Work Performance Data: Addresses whether quality standards are being met, what costs have been incurred, the completion status of deliverable, and what interim payments have been requested and/or paid. 12.3.2 Tools And Techniques 12.3.2.1 Contract Change Control System: As always, establishes the procedures by which changes can be approved. Includes paperwork, tracking, approval levels and dispute resolution procedures. 12.3.2.2 Procurement Performance Reviews: A structured review of the seller's progress (cost, schedule, scope, quality). The purpose of these reviews is to document successes and failures as well as demonstrate whether the seller is able to complete the work. 12.3.2.3 Inspections And Audits: These quality management techniques are used to check for compliance with Agreement requirements. Inspections and audits are usually required by the buyer and supported by information from the seller. 12.3.2.4 Performance Reporting: Documents the contractor's relative effectiveness in achieving agreed objectives. 12.3.2.5 Payment Systems: The payment system includes appropriate reviews and approvals so that interim and final payments can be made as appropriate. Payment systems are sometimes handled by the project (larger programs) but are frequently handled by the accounts payable department in the overall organization. 12.3.2.6 Claims Administration: Contested or constructive changes are those where the buyer and seller cannot agree on the terms (cost, schedule) for a change. In Some cases, a dispute arises over whether work item is a change in scope or is a legitimate part of the original scope. If the parties cannot resolve a claim themselves, the matter is then handled through whatever dispute resolution procedures were established in the agreement. Dispute resolution can occur during project performance or after a project has been closed. 12.3.2.7 Records Management System: Used to manage contract, documents and records. Usually involves an index of contract documents with methods for retrieval, archiving and automation. 12.3.3 Outputs 12.3.3.1 Work Performance Information : Includes reporting compliance of contacts, tracking expected deliverables received from vendor. It improves communication with vendor.
  • 16. 12.3.3.2 Change Requests: Processed using integrated change control. Disputed changes are usually given special attention and documented separately. Project Management Plan updates: Elements of the plan that may be updated include:  Procurement management plan (to reflect approved change requests, especially those affecting costs or schedules)  Baseline schedule (to reflect any significant variances from the baseline or revisions to the baseline because of approved changes) 12.3.3.3 Project Documents Update : Mainly includes procurement documents 12.3.3.4 OPA Updates: Key correspondence concerning audits, inspections, change requests, warnings for unsatisfactory performance, and key decisions. Information about payment schedules and how seller performance is documented would also be updated at this stage. 12.4 Close Procurements: Agreements closure supports the close project or phase process . It involves product verification (was the work completed correctly?) and administrative closeout (updating and archiving of records). Early termination is a special case of contract closure and can result from a mutual decision, from default by one of the parties, or for convenience of the buyer. The rights of the parties should be defined in a terminations clause in the contract.
  • 17. 12.4.1 Inputs 12.4.1.1 Project Management Plan 12.4.1.2 Procurement Documentation: All documentation is collected, indexed, and filed according to established procedures. The information can be used for lessons learned, estimating future contracts, and evaluating contractors for future procurements. 12.4.2 Tools And Techniques 12.4.2.1 Procurement Audits: Structured reviews of the procurement process to identify successes and failures. The information is used to improve the current project, future projects, and the overall organization. Procurement audits are also known as lessons learned in some areas. 12.4.2.2 Procurement Negotiations: Final settlement of all outstanding issues, claims, and disputes using negotiation if possible. Alternate dispute resolution (ADR) is used only when necessary. 12.4.2.3 Records Management System: Used by project manager to manage contract, procurement documentation and records 12.4.3 Outputs 12.4.3.1 Closed Procurements: The buyer provides formal, written notice that the contract has been completed. 12.4.3.2 OPA Updates: include the following:  Procurement file: An official, complete set of indexed contract documentation.  Deliverable acceptance: Formal, written notice that deliverables have been accepted or rejected. Instructions on how to handle non- conforming deliverables should be provided.
  • 18.  Lessons learned documentation: Post-project evaluation is important because it provides historical records that help in contractor selection on future contracts (a past performance database to support the select sellers process).