SlideShare a Scribd company logo
1 of 61
EIA Process, IEE, TOREIA Process, IEE, TOR
oshal khosooshal khoso
The Environmental Impact Assessment
Process
 Major steps in the EIA process are:
 Screening
 Initial Environmental Examination (IEE)
 Scoping
 Full-Scale Assessment
 EIA Review and Decision Making
 Monitoring and Follow-Up
2
3
Screening
Initial Environmental
Examination (IEE)
EIA Not
Required
EIA
Required
Monitoring
EIA Audit and
Evaluation
IEE
Review
Scoping/
Terms of
Reference
Full-Scale
EIA
Evaluate
Options
EIA Not
Approved
EIA
Review
Decision
Making
EIA
Approved
You are here
Screening
 It would be time consuming and a waste of resources for all proposed projects and
activities to undergo EIA
 Not all development projects require an EIA, as some projects may not pose an
environmental threat
 Screening is the process used to determine whether a proposed project or activity
requires an EIA and, if so, what level of environmental review is necessary
4
Purpose
 Identify those projects or activities that may cause potential significant impacts
 Identify special conditions/analyses that may be required by international
funding bodies
 Categorize the project as one where:
 Full-Scale EIA required
 Some further environmental analysis required
 No further environmental analysis required
5
Typical Proposals
Requiring Full-Scale EIA
 Infrastructure projects
 Large-scale industrial activities
 Resource extractive industries and activities
 Waste management and disposal
 Substantial changes in farming or fishing practices
6
Screening Techniques
 Assessor or decision-maker discretion
 Project lists with thresholds and triggers
 Exclusion project lists
 Preliminary or initial EIAs
 Combination of these techniques
7
Screening Criteria
 Screening criteria typically consider:
 Project type, location, size (e.g., capital
investment, number of people affected,
project capacity, areal extent)
 Receiving environment characteristics
 Strength of community opinion
 Confidence in prediction of impacts8
Project Location
Requirements for screening:
 The screening checklist should include a section on site location characteristics,
including, at a minimum, the four categories of environmentally critical areas:
 National Parks
 Indigenous people’s area
 Tourist area
 Ecologically sensitive area
9
Project Location (Cont’d)
 Site selection defines the location of the study area and the specific environmental
resource base to be examined
 Often the single most important factor contributing to a project’s potential negative
impacts
 Regional development plans should be used as guides to select project locations
where environmental conditions will be minimally impacted
10
Asian Development Bank (ADB) Screening
Categories
All Projects
Category A
Projects that
typically require an
EIA study
Category C
Projects that
typically do not
require an IEE
Category B
Projects that
typically require
only an IEE
Examples:
• Forestry Research &
Extension
• Rural Health Services
• Marine Sciences
Education
Examples:
• Forest Industries
• Water Impoundment
• Industries
Examples:
• Renewable Energy
• Aquaculture
• Tourism Development
• Infrastructure
Rehabilitation
Palestinian Law
12
Prepare the work plan for the initial
environmental examination (IEE)
Project type on project screening
checklist?
Get specific IAA
requirements
Project scale above the
screening threshold?
Project located in a critical
area?
IAA funding, or any other special
circumstances?
NO
NO
NO
NO
NO
YES
YES
No initial
environmental
examination
required (IEE)
YES
Project Screening Flow Chart
Will the project be funded by
an IAA?
YES
YES
NO
14
Screening
Initial Environmental
Examination (IEE)
EIA Not
Required
EIA
Required
Monitoring
EIA Audit and
Evaluation
IEE
Review
Scoping/
Terms of
Reference
Full-Scale
EIA
Evaluate
Options
EIA Not
Approved
EIA
Review
Decision
Making
EIA
Approved
You are here
Initial Environmental Examination
 Initial environmental examination (IEE)
is intended as a low-cost environmental
evaluation that makes use of
information already available
15
Purpose of IEE
 Describes the proposed project or activity and examines alternatives
 Identifies and addresses community concerns to extent possible
 Identifies and assesses potential environmental effects
 Directs future action
16
Objectives of IEE
 Identify all potential environmental concerns relating to a proposed project or
activity
 Identify all significant environmental issues (SEIs)
 Resolve simple SEIs
 Develop the focus for follow-up studies based on unresolved SEIs
17
Possible IEE Outcomes
1. No requirement for further environmental study; proposal not anticipated to have
significant impact.
2. Limited environmental study needed; environmental impacts are known and can
be easily mitigated.
3. Full-scale EIA required; impacts unknown or likely to be significant.
18
IEE in the Overall EIA Process
Project
Screening
Identifies projects
that typically contain
potential significant
issues
Initial Environmental Examination
1. Identifies potential significant
environmental issues associated with a
project
2. Grades effects and identifies actual
Significant Environmental Issues
(SEIs)
3. Resolves simple SEIs
4. Recommends further action for
resolving outstanding SEIs
Full-Scale EIA or Other
Additional Study
Resolves any remaining significant
environmental issues
IEE Flow Chart
1. Identify Potential Significant
Environmental Issues
2. Obtain Information
3. Effects Classification/
Identification of Significant
Environmental Issues (SEIs)
4. Resolve SEIs Where Possible
(Review Alternatives/Develop
Environmental Management Plans
and Protection Measures)
The IEE makes
recommendations for
further study:
Full-Scale EIA
IEE is the final EIA
Report, including:
1. SEIs
2. EPM
3. EMP
5. Are all SEIs
resolved?
YES NO
Identification of Potential Significant
Issues
1. Identify valued environmental/ecosystem components (VECs)
 Professional judgment/past experience
 Legislative requirements
 Stakeholder and community values
2.Identify the potential for impacts to each VEC
3. Identify potential for cumulative impacts (i.e.,to the site as a whole and to
the region)
21
Commonly Considered VECs
22
 Natural physical resources (e.g., surface and
groundwater, air, climate, soil)
 Natural biological resources (e.g., forests,
wetlands, river and lake ecology)
 Economic development resources (e.g.,
agriculture, industry, infrastructure, tourism)
 Quality of life (e.g., public health, socio-
economic, cultural, aesthetics)
 National commitments (e.g., endangered
species protection)
Methods for Identifying Potential
Impacts to VECs
 Matrices
» Sectoral
» Project type
 Checklists
 Professional expertise and experience with similar project types
 Combination of techniques
23
Sectoral Matrix Example
Ports and Harbours
Airports
Rapid Transit
Highways
Oil/Gas Pipelines
Development
Projects
Valued Env.
Component
(VEC)
SurfaceWaterQuality
AirQuality
Seismology/Geology
Erosion
LandQuality
Fisheries
Forests
TerrestrialWildlife
Noise
LandUse
Aesthetics
Industries
Resettlement
Archaeological/Historical
PublicHealth
Socioeconomic
Insignificant ImpactSignificant Impact Moderate - Significant Impact
Project Checklist Example
EIA Procedures and Decision Making 25
Potential Damages:
Actions Affecting
Resources and Values:
1. Disruption of Hydrology
2. Resettlement
3. Encroachment on Precious
Ecology
4. Encroachment on Historic/
Cultural Values
5. Cooling Tower Obstruction
6. Regional Flooding Hazard
7. Waste Emissions Related to
Siting
1. Impairment of Other Beneficial
Water Uses
2. Social Inequities
3. Loss of these Values
4. Loss of these Values
5. Conflicts with Other Beneficial
Water Uses
6. Hazard to Plant Operations
7. Intensification of Problems of
Pollution Control
Considerations in Determining
Potential Effects
 Impacts to:
 individual VECs
 entire site (i.e., impacts to all VECs combined)
 cumulative impacts to the area (i.e., considering other existing and planned projects)
 Impacts from all phases of the project (i.e., construction, operation,
decommissioning)
 Impacts on different time-scales
 Impacts from different orders of impact
26
Orders of Impact Example
Loss of Fisheries Income
Social Tension and Poverty Intensified
Loss of Plain Fisheries
Dry Flood Plains
River Embankment
First Order
Second Order
Third Order
Fourth Order
Data Requirements
 Project
» Type
» Size
» Location
 Area of potential impact
» Physical resources
» Biological resources
» Economic development resources
» Quality of life
» Other existing and planned projects
28
Sources of Information
 Existing reports on environmental resources in the area
 Previous assessment reports
» IEE and EIA reports on similar project types
» Reports on other projects in the region that may
cause similar disturbances
 Regional planning, policy and other reports
 Field studies
 Local citizens and traditional knowledge
29
Effects Classification
Effects vary in significance, depending on their:
 Nature: positive, negative, direct, indirect, cumulative, synergistic
 Magnitude
 Extent/location: area/volume covered, distribution
 Timing: during construction, operation, decommissioning, immediate, delayed, rate
of change
30
Effects Classification (Cont’d)
 Duration: short-term, long-term, intermittent, continuous
 Reversibility/irreversibility
 Likelihood: risk, uncertainty or confidence in the prediction
31
Criteria for Evaluating
Potential Effects
 Importance of affected resource
 Magnitude and extent of disturbance
 Duration and frequency
 Risk/likelihood of occurrence
 Reversibility
 Contribution to cumulative impacts
32
Examples of Project Alternatives
 No-build alternative
 Demand alternatives (e.g., using existing energy capacity more efficiency rather
than building more capacity)
 Activity alternatives (e.g., providing public transport rather than increasing road
capacity)
 Location alternatives
33
More Examples of
Project Alternatives
 Process alternatives (e.g., re-use of process water, reducing waste, different
logging methods)
 Scheduling alternatives (e.g., timing of project construction)
 Input alternatives (e.g., use of different raw materials or sources of energy)
34
Effects Significance Grading
No effect
Insignificant effect
Unknown significant effect
Significant effect, resolution is within the scope of the IEE
Significant effect, resolution is outside the scope of the IEE
35
Increasing
Severity
Issues with: No Effect
Issues with: Insignificant Effect
Issues with: Unknown
Significant Effect
Issues with: Significant Effects
within the Scope of the IEE
Where To from Here?
Issues with: Significant Effects
outside the Scope of the IEE
No Further Action
Required:
Write up
findings in brief IEE
Write up findings and
recommendations in IEE report
Action Required:
Develop the
Environmental
Management Plan &
Protection Measures to
Resolve Issues
Action Required:
Identify Information Needs
and Tasks Required to
Resolve Outstanding Issues
In Additional Studies
Example IEE Report Contents
1. Description of the Project
2. Description of the Environment
3. Screening of Potential Environmental Issues and Rationale for their Significance
Grading
4. Environmental Protection Measures
5. Environmental Monitoring and Institutional Requirements
6. Recommendations for Additional Studies
7. Conclusions
37
38
Screening Initial Environmental
Examination (IEE)
EIA Not
Required
EIA
Required
Monitoring
EIA Audit and
Evaluation
IEE
Review
Scoping/
Terms of
Reference
Full-Scale
EIA
Evaluate
Options
EIA Not
Approved
EIA
Review
Decision
Making
EIA
Approved
You are here
Terms of Reference Context
IEE
Project
Proceeds
according to
terms of IEE
Terms of Reference
1. Background
2. Impact Issues
Significant Issues
Relevant Resources
Report Formatting
3. Work Plan
When/Who/How of Task Completion
Full-Scale
EIA
Yes
No
IEE Review:
All potential
SEIs resolved
Scoping
 A process of interaction between government agencies and project proponents
 Identifies:
 spatial and temporal boundaries for the EIA
 important issues and concern
 information necessary for decision making
 significant effects and factors to be considered
40
 Establishes Terms of Reference for full-scale EIA
Importance of Scoping
 Serves to facilitate efficient EIA by identifying appropriate areas for consideration
(e.g, key issues, concerns, alternatives)
 Reduces likelihood of deficiencies in EIA (e.g., ensures that important issues are not
overlooked)
 Prevents unnecessary expenditures and time delays from oversights or unnecessary
areas of study
41
Terms of Reference Content
Background information section should include:
 Project Description (i.e., type, magnitude, location, alternatives and constraints)
 Environmental Setting (i.e., delineation of study area, listing of environmental
resources and sensitive or special value areas)
 Background Reports (e.g., aspects of the environmental setting, previous projects
with relevant impacts or resources)
42
Terms of Reference Content (Cont’d)
Specific EIA requirements typically include:
 EIA objectives
 Institutional context (i.e., legal and policy requirements)
 Significant issues of concern (SEIs)
 Required information and data,
methodologies for impact assessment
 Process for incorporating public input
43
Work Plan Example
Month 1 Month 2 Month 3 Month 4 Month 5Detailed Task Assignment
1. Waterlogging and Soil Salinity
2. Field Data: Collate, Fill Gaps, Organize
3. Models: Review, Verify, Reconcile
4. Drainage: Develop Final Criteria,
Perform Design
5. Compile Report
6. Land Acquisition and Resettlement
7. Project Proponent Document: Review
and Verify
8. Environmental Impact
9. Social Impact and Equity
10. Public Participation
11. Monitoring and Evaluation
EIA Procedures and Decision Making 45
Screening
Initial Environmental
Examination (IEE)
EIA Not
Required
EIA
Required
Monitoring
EIA Audit and
Evaluation
IEE
Review
Scoping/
Terms of
Reference
Full-Scale
EIA
Evaluate
Options
EIA Not
Approved
EIA
Review
Decision
Making
EIA
Approved
You are here
EIA in the Project Cycle
46
Reconnaissance Survey
Pre-feasibility Study
Feasibility Study
Final Design
Construction
Operation
Conventional Project
Planning
Monitoring Operations and
Environmental Effects
CorrespondingEnvironmental
Protection Activity
Initial Environmental
Examination
Environmental Impact
Assessment
Checking Design
Monitoring Construction
Project
Screening
47
Evaluate the IEE’s Treatment of Significant Issues
Identify Information Gaps Review Impact Pathways
Conduct Field Research
Conduct Public Participation
Perform Impact Prediction
Perform Risk Assessment
Evaluate Economic Impacts Review Applicable Standards
Design Environmental Protection Measures
Prepare Environmental Management Plan
Design Monitoring Program
Full-Scale EIA Overview
 Input = Outstanding SEIs from IEE
 Assessment phase:
 Qualitative/quantitative analysis of SEI
 SEI impact significance
 Mitigation development phase:
 Select appropriate mitigation measures
 Residual impact significance
48
EIA Impact Identification Methods
Checklists
Matrices
Networks
Overlays/GIS
ExpertSystems
RiskAssessment 49Qualitative Quantitative
Selection of Appropriate Methods
 Type and size of proposal
 Type of alternatives being assessed
 Nature of likely impacts
 Experience using EIA methods
 Resources available
 Nature of public involvement
 Procedural/administrative requirements
50
Checklists
ADVANTAGES
 Simple to
understand and use
 Good for site
selection and
priority setting
DISADVANTAGES
 Do not distinguish
between direct and
indirect impacts
 Do not link action and
impact
 Qualitative
51
Matrices
ADVANTAGES
Link action to
impact
Good method for
displaying EIA
results
DISADVANTAGES
Difficult to
distinguish direct
and indirect impacts
Significant potential
for double-counting
of impacts
Qualitative
52
Networks
ADVANTAGES
Link action to
impact
Useful in simplified
form in checking
for second order
impacts
Handles direct and
indirect impacts
DISADVANTAGES
Can become overly
complex if used
beyond simplified
version
Qualitative
53
Overlays
ADVANTAGES
Easy to understand
and use
Good display
method
Good for site
selection setting
DISADVANTAGES
Address only direct
impacts
Do not address
impact duration or
probability
54
Expert Systems
ADVANTAGES
Excellent for
impact
identification and
analysis
Good for
experimenting
Semi-quantitative
to quantitative
DISADVANTAGES
Heavy reliance on
knowledge and
data
Often complex and
expensive
55
Impact Significance Determination
56
Impact
Characteristics
(e.g., spatial extent)
Impact
Importance
(e.g., value)
x =
Impact
Significance
Characteristics Affecting
Impact Significance
 Nature of impact (e.g., positive, negative, synergistic)
 Extent and magnitude
 Timing (i.e., construction, operation, closure)
 Duration (i.e., short, chronic, intermittent)
 Reversibility/irreversibility
 Likelihood (i.e., probability, uncertainty)
57
Some Criteria for Significance
 Importance: the value that is attached to the affected environmental component
 Extent of disturbance: the area expected to be impacted
 Duration and frequency of disturbance
 Reversibility
 Risk: probability of an unplanned incident caused by the project
58
Assessing Significance
 Considerable expert judgment and technical knowledge are often required to fully
understand the nature and extent of environmental impacts
 Categories of significance include:
 no impact » unknown impact
 significant impact » mitigated impact
 insignificant impact
59
Guidelines for Assessing Significance
 Use rational and objective methods
 Provide consistency for comparison of project alternatives
 Document values and beliefs used in making judgement decisions
 Apply impact significance criteria, e.g.,
 Ecological importance/sustainability criteria
 Social importance
 Environmental standards
60
Ecological Importance
 Effect on plant and animal habitat
 Rare and endangered species
 Ecosystem resilience, sensitivity, biodiversity and carrying capacity
 Population viability
 Community viability
61

More Related Content

What's hot

Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessmentSayyid Ina
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTgoswamikusum
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessmentParth Patel
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)eAmbiente
 
Environment impact assessment.ppt
Environment impact assessment.pptEnvironment impact assessment.ppt
Environment impact assessment.pptApoorva Mathur
 
Baseline study for EIA
Baseline study for EIABaseline study for EIA
Baseline study for EIAJenson Samraj
 
Biological environmental impact analysis
Biological environmental impact analysisBiological environmental impact analysis
Biological environmental impact analysisArvind Kumar
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIAbishal sapkota
 
environmental impact assesment
environmental impact assesment environmental impact assesment
environmental impact assesment Nisha Jindal
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management PlanShehab Sajeeb
 
Environmental impact assessment concept
Environmental impact assessment conceptEnvironmental impact assessment concept
Environmental impact assessment conceptIntan Ayuna
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd Kumar
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentPrateek Bansal
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)KASHYAP V
 

What's hot (20)

Environmental impact assessment
Environmental impact assessmentEnvironmental impact assessment
Environmental impact assessment
 
ENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENTENVIRONMENT IMPACT ASSESSMENT
ENVIRONMENT IMPACT ASSESSMENT
 
EIA
EIAEIA
EIA
 
Eia - environmental impact assessment
Eia - environmental impact assessmentEia - environmental impact assessment
Eia - environmental impact assessment
 
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
 
EIA Process
EIA ProcessEIA Process
EIA Process
 
Environment impact assessment.ppt
Environment impact assessment.pptEnvironment impact assessment.ppt
Environment impact assessment.ppt
 
Baseline study for EIA
Baseline study for EIABaseline study for EIA
Baseline study for EIA
 
Biological environmental impact analysis
Biological environmental impact analysisBiological environmental impact analysis
Biological environmental impact analysis
 
Iee
IeeIee
Iee
 
EIA Methods
EIA MethodsEIA Methods
EIA Methods
 
IEE and screening in EIA
IEE and screening in EIAIEE and screening in EIA
IEE and screening in EIA
 
environmental impact assesment
environmental impact assesment environmental impact assesment
environmental impact assesment
 
Environmental Management Plan
Environmental Management PlanEnvironmental Management Plan
Environmental Management Plan
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
Esia
EsiaEsia
Esia
 
Environmental impact assessment concept
Environmental impact assessment conceptEnvironmental impact assessment concept
Environmental impact assessment concept
 
Unit 7 eia and sd
Unit 7 eia and sd Unit 7 eia and sd
Unit 7 eia and sd
 
Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 

Similar to EIA-process

Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact AssessmentBahadur Prasad
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfChandanLawrence
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment Pramoda Raj
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfssusereef268
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptxKalaimani
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessmentVivek Sivarajan
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentArunAngadi5
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5Bibhabasu Mohanty
 
Environmental Impact assessment
Environmental Impact assessmentEnvironmental Impact assessment
Environmental Impact assessmentDavis Ciprikis
 
Session4Presentation.ppt
Session4Presentation.pptSession4Presentation.ppt
Session4Presentation.pptBlackworld7
 
Environmental impact assessment
Environmental impact assessment Environmental impact assessment
Environmental impact assessment BiplobDas38
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfTausifAhmad53
 

Similar to EIA-process (20)

Environmental Impact Assessment
Environmental Impact AssessmentEnvironmental Impact Assessment
Environmental Impact Assessment
 
manunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdfmanunath1-copy-170405123133 (1).pdf
manunath1-copy-170405123133 (1).pdf
 
environmental impact assessment
environmental impact assessment environmental impact assessment
environmental impact assessment
 
Eia and its process
Eia and its processEia and its process
Eia and its process
 
Environmental Impact Assessment (EIA).pdf
Environmental Impact Assessment (EIA).pdfEnvironmental Impact Assessment (EIA).pdf
Environmental Impact Assessment (EIA).pdf
 
environmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdfenvironmentalimpactassessmenteia-210826024951.pdf
environmentalimpactassessmenteia-210826024951.pdf
 
FUNCTIONS OF EPA
FUNCTIONS OF EPAFUNCTIONS OF EPA
FUNCTIONS OF EPA
 
Environemental Impact Assessment.pptx
Environemental Impact Assessment.pptxEnvironemental Impact Assessment.pptx
Environemental Impact Assessment.pptx
 
Environment impact assessment
Environment impact assessmentEnvironment impact assessment
Environment impact assessment
 
Environment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessmentEnvironment impact assessment in environment impact assessment
Environment impact assessment in environment impact assessment
 
Environmental impact assessment m5
Environmental impact assessment m5Environmental impact assessment m5
Environmental impact assessment m5
 
PEISS
PEISSPEISS
PEISS
 
Aniket seminar ppt.pdf
Aniket seminar ppt.pdfAniket seminar ppt.pdf
Aniket seminar ppt.pdf
 
Evs eia
Evs eiaEvs eia
Evs eia
 
Environmental Impact assessment
Environmental Impact assessmentEnvironmental Impact assessment
Environmental Impact assessment
 
Session4Presentation.ppt
Session4Presentation.pptSession4Presentation.ppt
Session4Presentation.ppt
 
EIA PPT.pptx
EIA PPT.pptxEIA PPT.pptx
EIA PPT.pptx
 
EIA PPT.pdf
EIA PPT.pdfEIA PPT.pdf
EIA PPT.pdf
 
Environmental impact assessment
Environmental impact assessment Environmental impact assessment
Environmental impact assessment
 
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdfBasConcept of  Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
BasConcept of Eic nvironmental Impact Assessment-pages-2-13,18-65.pdf
 

More from Oshal Khan

component of environment
component of environmentcomponent of environment
component of environmentOshal Khan
 
Energy tecnologies
Energy tecnologiesEnergy tecnologies
Energy tecnologiesOshal Khan
 
Energy tecnologies
Energy tecnologiesEnergy tecnologies
Energy tecnologiesOshal Khan
 
Applied ecology
Applied ecology Applied ecology
Applied ecology Oshal Khan
 
Species Relationship
Species RelationshipSpecies Relationship
Species RelationshipOshal Khan
 
Air Atmosphere
Air AtmosphereAir Atmosphere
Air AtmosphereOshal Khan
 
Air borne diseases.
Air borne diseases. Air borne diseases.
Air borne diseases. Oshal Khan
 
Environmental Monitoring
Environmental MonitoringEnvironmental Monitoring
Environmental MonitoringOshal Khan
 

More from Oshal Khan (11)

component of environment
component of environmentcomponent of environment
component of environment
 
Inflarion
InflarionInflarion
Inflarion
 
Energy tecnologies
Energy tecnologiesEnergy tecnologies
Energy tecnologies
 
Energy tecnologies
Energy tecnologiesEnergy tecnologies
Energy tecnologies
 
Applied ecology
Applied ecology Applied ecology
Applied ecology
 
Species Relationship
Species RelationshipSpecies Relationship
Species Relationship
 
Air Atmosphere
Air AtmosphereAir Atmosphere
Air Atmosphere
 
Mosquito Fish
Mosquito FishMosquito Fish
Mosquito Fish
 
Air borne diseases.
Air borne diseases. Air borne diseases.
Air borne diseases.
 
Environmental Monitoring
Environmental MonitoringEnvironmental Monitoring
Environmental Monitoring
 
Mosquito fish
Mosquito fishMosquito fish
Mosquito fish
 

Recently uploaded

Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"syalehistoricalreview
 
Philippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyPhilippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyKristineRoseCorrales
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012sapnasaifi408
 
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527nagunakhan
 
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxPoly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxAgrodome projects LLP
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girlsssuser7cb4ff
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Timedelhimodelshub1
 
Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp202215407
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Open Access Research Paper
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170simranguptaxx69
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfTheaMan11
 
Air pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionAir pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionrgxv72jrgc
 

Recently uploaded (20)

Along the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"sAlong the Lakefront, "Menacing Unknown"s
Along the Lakefront, "Menacing Unknown"s
 
Philippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copyPhilippines-Native-Chicken.pptx file copy
Philippines-Native-Chicken.pptx file copy
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
Call Girls South Delhi Delhi reach out to us at ☎ 9711199012
 
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
Sexy Call Girls Patel Nagar New Delhi +918448380779 Call Girls Service in Del...
 
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
Private Escorts Aliganj \ 9548273370 Indian Call Girls Service Lucknow ₹,9527
 
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Serviceyoung call girls in Janakpuri🔝 9953056974 🔝 escort Service
young call girls in Janakpuri🔝 9953056974 🔝 escort Service
 
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptxPoly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
Poly-film-Prefab cover agricultural greenhouse-polyhouse structure.pptx
 
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call GirlsHi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
Hi FI Call Girl Ahmedabad 7397865700 Independent Call Girls
 
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Kalighat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Kalighat 👉 8250192130 Available With Room
 
Call Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any TimeCall Girls Abids 7001305949 all area service COD available Any Time
Call Girls Abids 7001305949 all area service COD available Any Time
 
Abu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community ppAbu Dhabi Sea Beach Visitor Community pp
Abu Dhabi Sea Beach Visitor Community pp
 
Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...Determination of antibacterial activity of various broad spectrum antibiotics...
Determination of antibacterial activity of various broad spectrum antibiotics...
 
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort ServiceHot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
Hot Sexy call girls in Nehru Place, 🔝 9953056974 🔝 escort Service
 
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
Call Girls Sarovar Portico Naraina Hotel, New Delhi 9873777170
 
Thessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdfThessaly master plan- WWF presentation_18.04.24.pdf
Thessaly master plan- WWF presentation_18.04.24.pdf
 
Air pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollutionAir pollution soli pollution water pollution noise pollution land pollution
Air pollution soli pollution water pollution noise pollution land pollution
 
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi NcrCall Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
Call Girls In R.K. Puram 9953056974 Escorts ServiCe In Delhi Ncr
 

EIA-process

  • 1. EIA Process, IEE, TOREIA Process, IEE, TOR oshal khosooshal khoso
  • 2. The Environmental Impact Assessment Process  Major steps in the EIA process are:  Screening  Initial Environmental Examination (IEE)  Scoping  Full-Scale Assessment  EIA Review and Decision Making  Monitoring and Follow-Up 2
  • 3. 3 Screening Initial Environmental Examination (IEE) EIA Not Required EIA Required Monitoring EIA Audit and Evaluation IEE Review Scoping/ Terms of Reference Full-Scale EIA Evaluate Options EIA Not Approved EIA Review Decision Making EIA Approved You are here
  • 4. Screening  It would be time consuming and a waste of resources for all proposed projects and activities to undergo EIA  Not all development projects require an EIA, as some projects may not pose an environmental threat  Screening is the process used to determine whether a proposed project or activity requires an EIA and, if so, what level of environmental review is necessary 4
  • 5. Purpose  Identify those projects or activities that may cause potential significant impacts  Identify special conditions/analyses that may be required by international funding bodies  Categorize the project as one where:  Full-Scale EIA required  Some further environmental analysis required  No further environmental analysis required 5
  • 6. Typical Proposals Requiring Full-Scale EIA  Infrastructure projects  Large-scale industrial activities  Resource extractive industries and activities  Waste management and disposal  Substantial changes in farming or fishing practices 6
  • 7. Screening Techniques  Assessor or decision-maker discretion  Project lists with thresholds and triggers  Exclusion project lists  Preliminary or initial EIAs  Combination of these techniques 7
  • 8. Screening Criteria  Screening criteria typically consider:  Project type, location, size (e.g., capital investment, number of people affected, project capacity, areal extent)  Receiving environment characteristics  Strength of community opinion  Confidence in prediction of impacts8
  • 9. Project Location Requirements for screening:  The screening checklist should include a section on site location characteristics, including, at a minimum, the four categories of environmentally critical areas:  National Parks  Indigenous people’s area  Tourist area  Ecologically sensitive area 9
  • 10. Project Location (Cont’d)  Site selection defines the location of the study area and the specific environmental resource base to be examined  Often the single most important factor contributing to a project’s potential negative impacts  Regional development plans should be used as guides to select project locations where environmental conditions will be minimally impacted 10
  • 11. Asian Development Bank (ADB) Screening Categories All Projects Category A Projects that typically require an EIA study Category C Projects that typically do not require an IEE Category B Projects that typically require only an IEE Examples: • Forestry Research & Extension • Rural Health Services • Marine Sciences Education Examples: • Forest Industries • Water Impoundment • Industries Examples: • Renewable Energy • Aquaculture • Tourism Development • Infrastructure Rehabilitation
  • 13. Prepare the work plan for the initial environmental examination (IEE) Project type on project screening checklist? Get specific IAA requirements Project scale above the screening threshold? Project located in a critical area? IAA funding, or any other special circumstances? NO NO NO NO NO YES YES No initial environmental examination required (IEE) YES Project Screening Flow Chart Will the project be funded by an IAA? YES YES NO
  • 14. 14 Screening Initial Environmental Examination (IEE) EIA Not Required EIA Required Monitoring EIA Audit and Evaluation IEE Review Scoping/ Terms of Reference Full-Scale EIA Evaluate Options EIA Not Approved EIA Review Decision Making EIA Approved You are here
  • 15. Initial Environmental Examination  Initial environmental examination (IEE) is intended as a low-cost environmental evaluation that makes use of information already available 15
  • 16. Purpose of IEE  Describes the proposed project or activity and examines alternatives  Identifies and addresses community concerns to extent possible  Identifies and assesses potential environmental effects  Directs future action 16
  • 17. Objectives of IEE  Identify all potential environmental concerns relating to a proposed project or activity  Identify all significant environmental issues (SEIs)  Resolve simple SEIs  Develop the focus for follow-up studies based on unresolved SEIs 17
  • 18. Possible IEE Outcomes 1. No requirement for further environmental study; proposal not anticipated to have significant impact. 2. Limited environmental study needed; environmental impacts are known and can be easily mitigated. 3. Full-scale EIA required; impacts unknown or likely to be significant. 18
  • 19. IEE in the Overall EIA Process Project Screening Identifies projects that typically contain potential significant issues Initial Environmental Examination 1. Identifies potential significant environmental issues associated with a project 2. Grades effects and identifies actual Significant Environmental Issues (SEIs) 3. Resolves simple SEIs 4. Recommends further action for resolving outstanding SEIs Full-Scale EIA or Other Additional Study Resolves any remaining significant environmental issues
  • 20. IEE Flow Chart 1. Identify Potential Significant Environmental Issues 2. Obtain Information 3. Effects Classification/ Identification of Significant Environmental Issues (SEIs) 4. Resolve SEIs Where Possible (Review Alternatives/Develop Environmental Management Plans and Protection Measures) The IEE makes recommendations for further study: Full-Scale EIA IEE is the final EIA Report, including: 1. SEIs 2. EPM 3. EMP 5. Are all SEIs resolved? YES NO
  • 21. Identification of Potential Significant Issues 1. Identify valued environmental/ecosystem components (VECs)  Professional judgment/past experience  Legislative requirements  Stakeholder and community values 2.Identify the potential for impacts to each VEC 3. Identify potential for cumulative impacts (i.e.,to the site as a whole and to the region) 21
  • 22. Commonly Considered VECs 22  Natural physical resources (e.g., surface and groundwater, air, climate, soil)  Natural biological resources (e.g., forests, wetlands, river and lake ecology)  Economic development resources (e.g., agriculture, industry, infrastructure, tourism)  Quality of life (e.g., public health, socio- economic, cultural, aesthetics)  National commitments (e.g., endangered species protection)
  • 23. Methods for Identifying Potential Impacts to VECs  Matrices » Sectoral » Project type  Checklists  Professional expertise and experience with similar project types  Combination of techniques 23
  • 24. Sectoral Matrix Example Ports and Harbours Airports Rapid Transit Highways Oil/Gas Pipelines Development Projects Valued Env. Component (VEC) SurfaceWaterQuality AirQuality Seismology/Geology Erosion LandQuality Fisheries Forests TerrestrialWildlife Noise LandUse Aesthetics Industries Resettlement Archaeological/Historical PublicHealth Socioeconomic Insignificant ImpactSignificant Impact Moderate - Significant Impact
  • 25. Project Checklist Example EIA Procedures and Decision Making 25 Potential Damages: Actions Affecting Resources and Values: 1. Disruption of Hydrology 2. Resettlement 3. Encroachment on Precious Ecology 4. Encroachment on Historic/ Cultural Values 5. Cooling Tower Obstruction 6. Regional Flooding Hazard 7. Waste Emissions Related to Siting 1. Impairment of Other Beneficial Water Uses 2. Social Inequities 3. Loss of these Values 4. Loss of these Values 5. Conflicts with Other Beneficial Water Uses 6. Hazard to Plant Operations 7. Intensification of Problems of Pollution Control
  • 26. Considerations in Determining Potential Effects  Impacts to:  individual VECs  entire site (i.e., impacts to all VECs combined)  cumulative impacts to the area (i.e., considering other existing and planned projects)  Impacts from all phases of the project (i.e., construction, operation, decommissioning)  Impacts on different time-scales  Impacts from different orders of impact 26
  • 27. Orders of Impact Example Loss of Fisheries Income Social Tension and Poverty Intensified Loss of Plain Fisheries Dry Flood Plains River Embankment First Order Second Order Third Order Fourth Order
  • 28. Data Requirements  Project » Type » Size » Location  Area of potential impact » Physical resources » Biological resources » Economic development resources » Quality of life » Other existing and planned projects 28
  • 29. Sources of Information  Existing reports on environmental resources in the area  Previous assessment reports » IEE and EIA reports on similar project types » Reports on other projects in the region that may cause similar disturbances  Regional planning, policy and other reports  Field studies  Local citizens and traditional knowledge 29
  • 30. Effects Classification Effects vary in significance, depending on their:  Nature: positive, negative, direct, indirect, cumulative, synergistic  Magnitude  Extent/location: area/volume covered, distribution  Timing: during construction, operation, decommissioning, immediate, delayed, rate of change 30
  • 31. Effects Classification (Cont’d)  Duration: short-term, long-term, intermittent, continuous  Reversibility/irreversibility  Likelihood: risk, uncertainty or confidence in the prediction 31
  • 32. Criteria for Evaluating Potential Effects  Importance of affected resource  Magnitude and extent of disturbance  Duration and frequency  Risk/likelihood of occurrence  Reversibility  Contribution to cumulative impacts 32
  • 33. Examples of Project Alternatives  No-build alternative  Demand alternatives (e.g., using existing energy capacity more efficiency rather than building more capacity)  Activity alternatives (e.g., providing public transport rather than increasing road capacity)  Location alternatives 33
  • 34. More Examples of Project Alternatives  Process alternatives (e.g., re-use of process water, reducing waste, different logging methods)  Scheduling alternatives (e.g., timing of project construction)  Input alternatives (e.g., use of different raw materials or sources of energy) 34
  • 35. Effects Significance Grading No effect Insignificant effect Unknown significant effect Significant effect, resolution is within the scope of the IEE Significant effect, resolution is outside the scope of the IEE 35 Increasing Severity
  • 36. Issues with: No Effect Issues with: Insignificant Effect Issues with: Unknown Significant Effect Issues with: Significant Effects within the Scope of the IEE Where To from Here? Issues with: Significant Effects outside the Scope of the IEE No Further Action Required: Write up findings in brief IEE Write up findings and recommendations in IEE report Action Required: Develop the Environmental Management Plan & Protection Measures to Resolve Issues Action Required: Identify Information Needs and Tasks Required to Resolve Outstanding Issues In Additional Studies
  • 37. Example IEE Report Contents 1. Description of the Project 2. Description of the Environment 3. Screening of Potential Environmental Issues and Rationale for their Significance Grading 4. Environmental Protection Measures 5. Environmental Monitoring and Institutional Requirements 6. Recommendations for Additional Studies 7. Conclusions 37
  • 38. 38 Screening Initial Environmental Examination (IEE) EIA Not Required EIA Required Monitoring EIA Audit and Evaluation IEE Review Scoping/ Terms of Reference Full-Scale EIA Evaluate Options EIA Not Approved EIA Review Decision Making EIA Approved You are here
  • 39. Terms of Reference Context IEE Project Proceeds according to terms of IEE Terms of Reference 1. Background 2. Impact Issues Significant Issues Relevant Resources Report Formatting 3. Work Plan When/Who/How of Task Completion Full-Scale EIA Yes No IEE Review: All potential SEIs resolved
  • 40. Scoping  A process of interaction between government agencies and project proponents  Identifies:  spatial and temporal boundaries for the EIA  important issues and concern  information necessary for decision making  significant effects and factors to be considered 40  Establishes Terms of Reference for full-scale EIA
  • 41. Importance of Scoping  Serves to facilitate efficient EIA by identifying appropriate areas for consideration (e.g, key issues, concerns, alternatives)  Reduces likelihood of deficiencies in EIA (e.g., ensures that important issues are not overlooked)  Prevents unnecessary expenditures and time delays from oversights or unnecessary areas of study 41
  • 42. Terms of Reference Content Background information section should include:  Project Description (i.e., type, magnitude, location, alternatives and constraints)  Environmental Setting (i.e., delineation of study area, listing of environmental resources and sensitive or special value areas)  Background Reports (e.g., aspects of the environmental setting, previous projects with relevant impacts or resources) 42
  • 43. Terms of Reference Content (Cont’d) Specific EIA requirements typically include:  EIA objectives  Institutional context (i.e., legal and policy requirements)  Significant issues of concern (SEIs)  Required information and data, methodologies for impact assessment  Process for incorporating public input 43
  • 44. Work Plan Example Month 1 Month 2 Month 3 Month 4 Month 5Detailed Task Assignment 1. Waterlogging and Soil Salinity 2. Field Data: Collate, Fill Gaps, Organize 3. Models: Review, Verify, Reconcile 4. Drainage: Develop Final Criteria, Perform Design 5. Compile Report 6. Land Acquisition and Resettlement 7. Project Proponent Document: Review and Verify 8. Environmental Impact 9. Social Impact and Equity 10. Public Participation 11. Monitoring and Evaluation
  • 45. EIA Procedures and Decision Making 45 Screening Initial Environmental Examination (IEE) EIA Not Required EIA Required Monitoring EIA Audit and Evaluation IEE Review Scoping/ Terms of Reference Full-Scale EIA Evaluate Options EIA Not Approved EIA Review Decision Making EIA Approved You are here
  • 46. EIA in the Project Cycle 46 Reconnaissance Survey Pre-feasibility Study Feasibility Study Final Design Construction Operation Conventional Project Planning Monitoring Operations and Environmental Effects CorrespondingEnvironmental Protection Activity Initial Environmental Examination Environmental Impact Assessment Checking Design Monitoring Construction Project Screening
  • 47. 47 Evaluate the IEE’s Treatment of Significant Issues Identify Information Gaps Review Impact Pathways Conduct Field Research Conduct Public Participation Perform Impact Prediction Perform Risk Assessment Evaluate Economic Impacts Review Applicable Standards Design Environmental Protection Measures Prepare Environmental Management Plan Design Monitoring Program
  • 48. Full-Scale EIA Overview  Input = Outstanding SEIs from IEE  Assessment phase:  Qualitative/quantitative analysis of SEI  SEI impact significance  Mitigation development phase:  Select appropriate mitigation measures  Residual impact significance 48
  • 49. EIA Impact Identification Methods Checklists Matrices Networks Overlays/GIS ExpertSystems RiskAssessment 49Qualitative Quantitative
  • 50. Selection of Appropriate Methods  Type and size of proposal  Type of alternatives being assessed  Nature of likely impacts  Experience using EIA methods  Resources available  Nature of public involvement  Procedural/administrative requirements 50
  • 51. Checklists ADVANTAGES  Simple to understand and use  Good for site selection and priority setting DISADVANTAGES  Do not distinguish between direct and indirect impacts  Do not link action and impact  Qualitative 51
  • 52. Matrices ADVANTAGES Link action to impact Good method for displaying EIA results DISADVANTAGES Difficult to distinguish direct and indirect impacts Significant potential for double-counting of impacts Qualitative 52
  • 53. Networks ADVANTAGES Link action to impact Useful in simplified form in checking for second order impacts Handles direct and indirect impacts DISADVANTAGES Can become overly complex if used beyond simplified version Qualitative 53
  • 54. Overlays ADVANTAGES Easy to understand and use Good display method Good for site selection setting DISADVANTAGES Address only direct impacts Do not address impact duration or probability 54
  • 55. Expert Systems ADVANTAGES Excellent for impact identification and analysis Good for experimenting Semi-quantitative to quantitative DISADVANTAGES Heavy reliance on knowledge and data Often complex and expensive 55
  • 56. Impact Significance Determination 56 Impact Characteristics (e.g., spatial extent) Impact Importance (e.g., value) x = Impact Significance
  • 57. Characteristics Affecting Impact Significance  Nature of impact (e.g., positive, negative, synergistic)  Extent and magnitude  Timing (i.e., construction, operation, closure)  Duration (i.e., short, chronic, intermittent)  Reversibility/irreversibility  Likelihood (i.e., probability, uncertainty) 57
  • 58. Some Criteria for Significance  Importance: the value that is attached to the affected environmental component  Extent of disturbance: the area expected to be impacted  Duration and frequency of disturbance  Reversibility  Risk: probability of an unplanned incident caused by the project 58
  • 59. Assessing Significance  Considerable expert judgment and technical knowledge are often required to fully understand the nature and extent of environmental impacts  Categories of significance include:  no impact » unknown impact  significant impact » mitigated impact  insignificant impact 59
  • 60. Guidelines for Assessing Significance  Use rational and objective methods  Provide consistency for comparison of project alternatives  Document values and beliefs used in making judgement decisions  Apply impact significance criteria, e.g.,  Ecological importance/sustainability criteria  Social importance  Environmental standards 60
  • 61. Ecological Importance  Effect on plant and animal habitat  Rare and endangered species  Ecosystem resilience, sensitivity, biodiversity and carrying capacity  Population viability  Community viability 61

Editor's Notes

  1. SLIDE 9 NOTES ANNEX A ASIAN DEVELOPMENT BANK PROJECT CATEGORIES 1.OVERVIEW This slide shows the categories used by the Asian Development Bank (ADB) to differentiate between projects which require different levels of environmental review. For projects that are anticipated to be funded by ADB, every effort should be made to adhere to ADB procedure from the earliest project development stages. The categorization procedure is explained in Section 21 of ADB's Operations Manual entitled "Environmental Considerations in Bank Operations". The band uses the categorization to prioritize projects that will require the involvement of ADB environmental specialists. Project categorization can be incorporated into a country's national procedures for project screening to facilitate the prioritization of environmental resource assessment expertise. Section 21 of ADB's Operations Manual is reproduced in full in Annex B. 2.PROJECT CATEGORY A Projects in this category typically require an EIA. The project type, scale and location determine this designation. The potential significant environmental issues for these projects may lead to significant changes in land use, as well as changes to the social, physical, and biological environment. ADB suggests that an environmental specialist's advice will be required to determine the scope of the EIA necessary for compliance with ADB's environmental policies. Bank personnel are involved in this category of project from early field reconnaissance through EIA review. Additional examples of projects which fall under this category are provided in Section 21 of ADB's Operations Manual which is reproduced in full in Annex B. 3.PROJECT CATEGORY B This category is for projects that usually require an Initial Environmental Examination, but not an EIA study. Often the only difference between projects in this category and those in category A is the scale. Large power plant projects fall under category A; medium-sized power plant projects are in category B. The environmental impacts from these projects are generally less severe than projects in category A, and these projects are not located in environmentally sensitive areas. Mitigation measures for these projects are more easily prescribed. The Bank suggests that an environmental specialist will be required to assist in formulating the Terms of Reference for the IEE so that the IEE report will comply with the bank policies. Additional examples of projects which fall under this category are provided in Section 21 of ADB's Operations Manual which is reproduced in full in Annex B. 4.PROJECT CATEGORY C This category is for projects that typically do not require an environmental assessment. These projects are unlikely to have adverse environmental impacts.
  2. OBJECTIVES OF THE INITIAL ENVIRONMENTAL EXAMINATION (IEE) 1. OVERVIEW The objectives of the IEE are to: (1) identify all of the potential environmental issues associated with the project type and location; (2) from the complete set of potential SEIs, determine which are applicable to the specific project; (3) evaluate the significance of each issue's impact on environmental resources, (4) decide which issues may be resolved in the IEE and which require an EIA, (5) resolve all issues possible within the scope of the IEE, (6) develop recommendations for additional studies to resolve outstanding issues. 2. IDENTIFY ALL POTENTIAL SIGNIFICANT ENVIRONMENTAL ISSUES (SEIs) AND DETERMINE THOSE THAT APPLY TO A SPECIFIC PROJECT The IEE, as its name suggests, is the initial examination of a project's environmental issues. The examination should be time and resource efficient, using existing information on the environmental resources of the area whenever possible. This function of the IEE may be viewed as a low-cost scoping study that identifies environmental issues to be resolved. A number of methods may be used to facilitate the identification of potential SEIs typical to specific project types, or projects of a particular development sector. These methods are discussed in later slides. The potential SEIs are checked against the project and study area information to determine the actual environmental issues for a particular project. The issues must be evaluated and graded according to their significance and complexity of resolution. 3. RESOLVE ALL SIMPLE SIGNIFICANT ENVIRONMENTAL ISSUES A work plan should be created for the simple SEIs that may be resolved within the scope of the IEE. These are the SEIs that may be resolved by easily identified and applied environmental protection measures. For these types of SEIs, the IEE can take the place of an EIA, and if no complex SEIs are found, an EIA may not be necessary. 4. DEVELOP FOCUS FOR FOLLOW-UP STUDIES Complex SEIs must be resolved through follow-up studies whose scope allow for extensive field work, in-depth analysis, and whatever else is required. Recommendations to resolve these issues must be developed and included in the IEE report. If these recommendations are accepted by reviewing agencies, the IEE will have additional responsibility of creating a complete terms of reference for the recommended study.
  3. SLIDE 2 NOTES FLOW CHART LINKING THE FUNCTIONS OF PROJECT SCREENING INITIAL ENVIRONMENTAL EXAMINATION AND ENVIRONMENTAL IMPACT ASSESSMENT 1. OVERVIEW This slide shows the functional linkage between these three steps in the Environmental Impact Assessment process. 2. PROJECT SCREENING Project screening identifies the projects that typically contain potential Significant Environmental Issues. The projects are identified, or selected, using screening criteria based on project type, size, and location. Projects that are selected must pass through an Initial Environmental Examination (IEE) so that Significant Environmental Issues (SEIs) may be identified, and when possible, resolved. 3. INITIAL ENVIRONMENTAL EXAMINATION The IEE performs four important functions. 1) It identifies the potential SEIs associated with a project. These potential SEIs are effects on environmental resources that may result from various components of a project. They may be related to the design, the construction, or the operation phase of the project. 2) It determines the actual environmental issues for the specific project and grades them according to their significance and whether or not they may be resolved within the scope of the IEE. 3) The SEIs that are simple enough to be resolved within the scope of the IEE are pursued. Environmental protection measures and an environmental management plan are developed. Projects for which all issues have been resolved in the IEE use the IEE in place of an EIA. 4) For SEIs that cannot be resolved within the scope of the IEE, recommendations are made for the work required for resolution. 4. THE EIA The EIA is used to resolve complex environmental issues. The IEE is very important for the EIA because it focuses the tasks to be performed in the study on specific complex issues, and develops the background on these issues. The EIA is a much more efficient study when it can draw on the work of the IEE.
  4. SLIDE 3.1 NOTES FLOW CHART OF THE FUNCTIONAL STEPS IN THE INITIAL ENVIRONMENTAL EXAMINATION 1. OVERVIEW This slide shows the steps involved in performing an Initial Environmental Examination. Each of these steps will be described in the slide series. 2. USE OF THIS SLIDE The information contained in this slide was for the most part presented in the previous slide. This graphical representation may aid some participants' comprehension through reiteration of the steps in a pictorial format. In addition, the critical step of data collection is included here.
  5. CLASSIFICATION OF ENVIRONMENTAL RESOURCES 1. OVERVIEW This listing of environmental resources is useful as a general checklist, but as with environmental screening checklists, it lacks situation specific information. 2. CLASSIFICATION
  6. SLIDE 3.2.1 NOTES SECTORAL MATRICES FOR IDENTIFYING POTENTIAL SEIs 1. OVERVIEW This slide is an environmental screening matrix for the transportation sector. The impacts listed are typical of the project types. They may or may not pose an actual environmental issue to be resolved depending on the specifics of any given project and its location.
  7. SLIDE 3.2.3 NOTES PROJECT CHECKLIST FOR IDENTIFYING POTENTIAL SEIs 1. OVERVIEW This slide shows a portion of an environmental screening checklist that may be used to identify potential SEIs. The example is a checklist for a thermal power project. The portion shown relates to the issues resulting from the selection of project location. Additional sections deal with other design considerations as well as other project implementation phases. The checklist includes a section containing general suggestions for environmental protection measures. The suggestions can be especially useful to inexperienced IEE staff.
  8. THE ORDER OF ENVIRONMENTAL EFFECTS (IMPACTS) 1. OVERVIEW This slide shows an important EIA concept utilized extensively at the IEE stage. This is an important technique in identifying SEIs. It is a chain reaction effect caused by impacts to interdependent resources. In this example, the project activity that initiates the environmental impact chain is a river embankment which usually overflows during the rainy season and supports an extensive flood plains fisheries. This is a common occurrence in many deltaic areas. 2. FIRST ORDER EFFECT The river embankment causes the flood plains to dry up during the rainy season. This is an obvious first order impact. In the past, when only conventional project planning process was utilized (i.e. without an EIA) in river training schemes, consideration of environmental effects went no further than this stage. In fact, the drying up of the flood plains was the purpose of the river embankment scheme in the first place. 3. SECOND ORDER EFFECT The second order effect would be the loss of flood plain fisheries. Although this is obvious to an environmental scientist, it may not be so to an engineer in an office in the city. 4. THIRD ORDER EFFECT The third order effect is the impact on the local people who rely upon the fisheries for consumption and for income. The loss of the fisheries might have a substantial impact on them. 5. FOURTH ORDER EFFECT The fourth order effect might be an increase in social tension which could lead to violence. For instance, if the fishermen were mainly landless farmers who relied on the fisheries for most of their income, the reclamation of the land for agricultural purposes might make the large landowners wealthier and the landless fishermen poorer. This is a social equity issue. 6. CONCLUSION The chain of impacts can quickly become very complicated. The purpose of the IEE and the role of the expert is to determine which issues are substantial and where to draw boundaries on the analysis. For instance, there may or may not be productive fisheries in the flood plains; there may or may not be a substantial population which relies on the fisheries for their income and food; and there may or may not be alternative livelihoods readily available for the displaced fishermen. Through this process, all environmental issues for a project are identified.
  9. COLLECTION OF INFORMATION ON THE PROJECT AND STUDY AREA 1. PROJECT INFORMATION Project information should be available from the project pre-feasibility team. Project type, size (or scale), and proposed location are the most important information areas. 2. STUDY AREA INFORMATION Information on the environmental resources in the study area is critical for determining the significant environmental issues (SEIs). Depending on the area, there may or may not be reports describing these resources. If there are no existing reports and the area is rich in environmental resources, the SEIs will probably have to be resolved by a full-scale EIA. 4. PREVIOUS REPORTS ON SIMILAR PROJECTS Reports on similar project types, or projects that may cause similar environmental disturbances, should be reviewed. These reports may include valuable baseline data on environmental resources as well as environmental impact assessment methodology. IEE and EIA reports are the most applicable, but feasibility studies and project permitting reports may also be useful.
  10. OBTAINING INFORMATION ON THE ISSUES 1. OVERVIEW Sufficient information must be collected to determine which of the potential significant environmental issues pose impacts to environmental resources for the specific project in question. Where possible, the information should also be used to determine the level of significance of issues and provide a basis for developing environmental protection measures. Because the IEE is not a full-scale assessment, the information should come primarily from existing reports, whenever possible. Field data may be collected, depending on the scope of the IEE. If the IEE has the potential to act as the EIA final report, then field data is usually collected. 2. EXAMPLE REPORTS Examples of environmental resource reports are presented below. These are only a few of the many kinds of reports which may be produced on environmental resources. 2.1 Natural Physical Resources: * hydrologic surveys, geophysical surveys, soil surveys 2.2 Natural Biological Resources * timber inventories, flora and fauna inventories 2.3 Economic Development Resources * agricultural production summaries, fisheries catch statistics census data, industrial production reports, tourism statistics 2.4 Quality of Life * income stratification statistics, public health statistics
  11. CRITERIA FOR EVALUATING THE ANTICIPATED EFFECTS (IMPACTS) OF SIGNIFICANT ENVIRONMENTAL ISSUES 1. OVERVIEW This is one of the many steps in the IEE which require professional judgment. The categories of evaluation are somewhat subjective in their interpretation. Governmental agency guidelines, and the guidelines of international assistance agencies (IAAs), when applicable, should be referred to. 2. IMPORTANCE OF AFFECTED RESOURCE How much value is attached to the resource in its current condition? This question may have notable differences at the local, regional, national and global levels. If IAAs are involved in the project, this is a criteria for which they often specify conditions. 3. EXTENT OF DISTURBANCE How far does the disturbance of environmental resources extend? Disturbances to resources may extend a large distance but diminish rapidly beyond a critical distance. It is important to focus on significant disturbances. 4. DURATION AND FREQUENCY The duration and frequency of a disturbance can often determine its effect on an environmental resource. For example, short term intermittent flows of fresh water from dry season irrigation runoff have been found to produce beneficial impacts on the biological resources in esturine wetlands, whereas long term and frequent flows produce negative impacts on these resources. 5. RISK Risk refers to the probability of an unplanned incident caused by the project with major impacts on the environmental resources, for example a large uncontained chemical spill at a petrochemical plant. 6. REVERSIBILITY For impacts that are short term, for example many construction impacts, can the environmental resources recover? If the impact is reversible, what is the rate of recovery? If the impact is not reversible, is there another beneficial use for the area?
  12. GRADING A PROJECT'S ANTICIPATED ENVIRONMENTAL ISSUES 1. OVERVIEW This slide shows a grading scale for anticipated environmental issues that may be used to determine which course of action to take to resolve them. The general matrix methodology is used to review each project activity against the list of environmental resources. Evaluation criteria are employed to assign a rating to each effect of an environmental resource by each project activity. The rating scale is described below. 2. NO EFFECT It is usually very obvious when an activity is definitely not expected to have an effect on an area of the environment. For example, if a project site is in an area lacking surface water, environmental resource categories such as surface water quality, aquatic ecology, and water related aesthetics will obviously be rated - "no effect." 3. INSIGNIFICANT EFFECTS If a potential adverse environmental effect is known, but is not considered significant, it is rated as "insignificant." An example would be an industry that uses very small amounts of cooling water which it discharges into a sewer to be treated at a centralized wastewater treatment plant. It is obvious that the discharge will have some impact on the local receiving water body, but this impact can be considered as insignificant. 4. UNKNOWN SIGNIFICANCE If there is a lack of knowledge concerning the possible environmental effects of an activity, it should be rated as having unknown significance. For example, the introduction of a large irrigation system into an area with many different types of farmers will probably have a profound socioeconomic impact, benefiting some farmers and hurting others. Without a detailed socioeconomic review, it may be difficult to anticipate what will happen. More information must be collected and this should be assigned to the EIA stage. 5. SIGNIFICANT EFFECTS BUT ENVIRONMENTAL PROTECTION MEASURES EASILY IMPLEMENTED Many environmental problems have standard solutions which can be easily implemented; for example pollution control for industries. If an industry burns fuel for its boiler, some air pollution will result. If a large amount of fuel is used but the industry is located in a suitable industrial area, then only standard air quality modeling needs to be performed to determine the height of the stack. This can occur as part of a follow-up study and does not need a full-scale EIA by itself. 6. SIGNIFICANT EFFECTS WITHOUT EASILY IDENTIFIABLE ENVIRONMENTAL PROTECTION MEASURES These include environmental effects which are very large and need special or unique solutions for their resolution.
  13. SLIDE 3.7 NOTES TREATMENT OF ENVIRONMENTAL ISSUES BASED ON THEIR SIGNIFICANT GRADING 1. OVERVIEW This slide shows the action to be taken on differently rated environmental issues contained in a single project. The example shows the most complex project and possible includes each of the five grades. Many projects contain issues with no significant effect, or no effect at all, and can be resolved with no further examination. 2. ISSUES WITH "NO EFFECT" OR "INSIGNIFICANT EFFECT" These issues require no further examination. The findings of the examination and the justification for the rating must be included in the appropriate section of the IEE. 3. ISSUES WITH "UNKNOWN SIGNIFICANT EFFECT" OR "SIGNIFICANT EFFECT OUTSIDE THE SCOPE OF THE "IEE" These issues require additional study, which in most cases means full scale EIA. For projects with special circumstances, additional specialized reports may be needed. The social design study, which focuses on socioeconomic issues, is one of these. A social design study report may be required for a project involving major resettlement issues. In this case, the EIA and social design study would be separate interactive reports. The IEE develops the tasks and scope for these studies. This information is the foundation for the terms of reference for future studies. All of the findings on these issues as well as the requirements for additional studies, must be included in the IEE report. 4. ISSUES WITH "SIGNIFICANT EFFECT WITHIN THE SCOPE OF THE IEE" These issues may be resolved by the IEE, but environmental protection measures (EPM) and an environmental management plan must be produced. This can only be accomplished in the IEE stage if the EPMs are obvious and simply developed. For these issues, the IEE report will serve as a final EIA report. For projects whose only SEIs are of this grade, no additional reports will be required. 5. CONCLUSION The issues resolved in the IEE will undergo a similar regulatory critiquing and final approval process as that required for the EIA. This ensures that the justifications for grading the significance of environmental issues was sound and agreeable to responsible agencies. If an international assistance agency is involved in the project, it will also pursue a thorough critiquing.
  14. SLIDE 3.8 NOTES IEE REPORT TABLE OF CONTENTS 1. OVERVIEW The IEE report is similar in content to the EIA report. It covers the description of project, the environment of the study area, and the significant environmental issues (SEIs). It also contains a development of the environmental protection measures and environmental monitoring required to resolve simple, yet significant environmental issues. Recommendations must be included for additional studies when SEIs remain unresolved due to their complex nature, or a lack of necessary information. 2. INTRODUCTION This section should include background information for the IEE study. The following subject areas are relevant: 2.1 Identification of project and project proponent 2.2 A brief description of the nature, size and location of the project 2.3 A description of the project's importance 2.4 A description of the IEE study 2.4.1 Scope 2.4.2 Staffing requirements 2.4.3 Identification of the lead agency overseeing the study 3. DESCRIPTION OF THE PROJECT The description of the project must be sufficiently detailed so that reviewers of the study can understand the cause of the anticipated environmental impacts. The amount of detailed information available is necessarily limited by the stage of the project (ideally it should be at the pre-feasibility stage at the time of the IEE). The important subjects to be covered in this section are: 3.1 Project Type 3.2 Need for the project 3.3 Location (including maps detailing project site and the IEE study area) 3.4 Size and magnitude of project operations 3.5 Proposed schedule for implementation
  15. SLIDE 1.1 NOTES FLOW CHART OF TERMS OF REFERENCE, INITIAL ENVIRONMENTAL EXAMINATION, AND FULL-SCALE EIA 1. OVERVIEW This slide shows the inter-relation between the Initial Environmental Examination, the Terms of Reference, and the Environmental Impact Assessment. Through this process, the significant environmental issues which remain unresolved in the IEE are linked to the study area resources which may be impacted. The research and analysis of resource impacts are the tasks to be performed in the EIA. THE TOR: 1) Delineates the study area; 2) Lists the significant issues and the related resources to be investigated and describes how the findings will be presented; 3) Details a work plan for the EIA so that the process will run smoothly, on time and within budget.
  16. SLIDE 2.1 NOTES ANNEX A DETAILED BREAKDOWN OF TERMS OF REFERENCE BACKGROUND INFORMATION SECTION 1. BACKGROUND INFORMATION 1) Project Description The project information available during the initial engineering examination is likely to be preliminary. The project type (dam/hydroelectric, wastewater treatment, etc.) will be known, as well as its magnitude, proposed location, project status and project proponent. The additional project information layout, material mass balance and design criteria - represent aspects which will be dealt with in the EIA report. 2) Environmental Setting The focus of this section is the delineation of the geographical area of study, as well as description of the area in terms of environmental resources and locations of special value. The information provided by the initial examination of potentially significant issues is often insufficient to evaluate them. Extensive surveys of "at risk" environmental resources may be required. Base maps showing resource distribution are valuable for orienting these resources with respect to the proposed project location. 2. BACKGROUND REPORTS These include any reports which may be of value to the EIA team in their detailed study of the project's significant impacts on the environmental resources. The following examples relate to the environmental classification grouping on slide 2.1.1: 1)streamflow surveys, geophysical surveys, soil surveys; 2)timber inventories, ecosystem inventories; 3)agricultural production summaries, fisheries catch statistics, livestock production reports; 4)census data, public works department reports, industrial production reports, reports from the national tourism board; 5)national or regional energy board reports, United Nations ESCAP reports, reports from governmental and non-governmental agencies involved with the protection of endangered species.
  17. SLIDE 2.1 NOTES ANNEX A DETAILED BREAKDOWN OF TERMS OF REFERENCE BACKGROUND INFORMATION SECTION 1. BACKGROUND INFORMATION 1) Project Description The project information available during the initial engineering examination is likely to be preliminary. The project type (dam/hydroelectric, wastewater treatment, etc.) will be known, as well as its magnitude, proposed location, project status and project proponent. The additional project information layout, material mass balance and design criteria - represent aspects which will be dealt with in the EIA report. 2) Environmental Setting The focus of this section is the delineation of the geographical area of study, as well as description of the area in terms of environmental resources and locations of special value. The information provided by the initial examination of potentially significant issues is often insufficient to evaluate them. Extensive surveys of "at risk" environmental resources may be required. Base maps showing resource distribution are valuable for orienting these resources with respect to the proposed project location. 2. BACKGROUND REPORTS These include any reports which may be of value to the EIA team in their detailed study of the project's significant impacts on the environmental resources. The following examples relate to the environmental classification grouping on slide 2.1.1: 1)streamflow surveys, geophysical surveys, soil surveys; 2)timber inventories, ecosystem inventories; 3)agricultural production summaries, fisheries catch statistics, livestock production reports; 4)census data, public works department reports, industrial production reports, reports from the national tourism board; 5)national or regional energy board reports, United Nations ESCAP reports, reports from governmental and non-governmental agencies involved with the protection of endangered species.
  18. SLIDE 2.3.2 NOTES ANNEX A WORK PLAN TASK SCHEDULE EXAMPLE IRRIGATION PROJECT 1. OVERVIEW The scheduling of EIA tasks in the TOR is important to: a) facilitate the resolution of any task conflicts, b) properly manage the various tasks, and c) plan the budget for the tasks. Each task must be scheduled by action item (sub-task) and compared with the schedule for interdependent tasks. 2. TASK CONFLICT AND TASK MANAGEMENT Due to the interdependent nature of tasks in environmental impact assessment, the evaluation of a Task (A) often requires completion of a separate task (Task B) in another scientific discipline. If Task A and Task B are scheduled for completion at the same time, a conflict arises. Task B must be completed first. The independence of tasks and action items within tasks must be taken into account by the entire EIA team. Task interdependencies should be noted in the work plan task schedules and monitored during the production of the EIA by the planner and management staff. 3. BUDGETING Task level budgeting is facilitated by the scheduling process. Once time requirements for action items and tasks are determined, a man-hour or man-month budget can be constructed. The monetary task budget may be computed by applying the overhead rate and expected salaries to the time requirement budget. An example of a task budget developed from the work plan task schedule slide is provided in Annex B (Selected References).
  19. SLIDE 5.2 NOTESANNEX A FLOW CHART OF THE PRIMARY ANALYSIS AND DESIGN STEPS IN THE EIA Each significant environmental issue undergoes a similar process in assessing its environmental impact. The first step is to evaluate the treatment of the issue in the IEE. This determines: (1) the adequacy of the data available on the issue, the casual aspects of the project and the baseline data on the resources affected; and (2) the adequacy of the impact prediction that was made, i.e. do the impact pathways include all of the probable higher order effects to the resources in the study area? The second step is to conduct field research to fill in the information gaps and confirm that all of the environmental resources in the study area have been taken into consideration. The information collected by the feasibility study teams helps to fill in the information gaps. Detailed descriptions of project activities are required for impact prediction. In this context, public participation is essentially field data collection from the study area and often the surround communities as well. Impact prediction is the step in which specialists determine a project's probable impacts to environmental resources. This step is divided into socioeconomic and other resources categories because socioeconomic resources are so important that they are often treated separately. An entire module is devoted to socioeconomics. Risk assessment is a specific type of impact prediction used for assessing the risks of a major project-related accident. It applies predominantly to industrial and large structure projects, but can also be applied to other projects with the potential for large impacts from unplanned occurrences. A review of standards follows the impact predictions in order to ascertain whether there are any existing standards regarding the impacts or disturbances the project may cause. Finally, an economic evaluation of the issue is performed to determine what kinds of actions are justified, based on the severity of the impacts in the issue. Environmental protection measures (EPM) are designed to address the impacts to environmental resources. They either: (1) limit the impacts to resources by reducing the disturbance that creates the impacts; or (2) replace the lost value of the resource by creating a new resource or enhancing an existing one. The monitoring plan measures the effectiveness of the EPMs in achieving their objective of maintaining levels of environmental parameters. The results of the monitoring program may suggest a change in the EPM or conclude that the EPMs are not being implemented. The environmental management plan is the terms of reference for the monitoring plan. The management plan also incorporates implementation strategies for such monitoring related activities as strengthening regulations for environmental resource protection and developing local or regional environmental protection agencies to continue ambient monitoring beyond the time frame of the EIA related monitoring.