NABCEP PV Installer™ Exam
  120 Rule & Test-taking
        Strategies
          Richard Stovall
        SolPowerPeople, Inc.
            Austin, TX

           April 18, 2013
Today’s Topics

 120-Rule

 Last Minute Articles &
  Resources
 Test-taking Strategies

 Time Management

 What to Expect
120-Rule: Question from
NABCEP 2009 Study Guide
Problem 64

 NEC 705.12 (D) (2)
Problem 64



 Rating of the buss bar = 225 amps

 225 A x 1.20 = 270 amps

 Rating of the breaker serving the utility = 200 amps

 270 amps - 200 amps = 70 amps is the maximum breaker size for the PV system

 Divide by 1.25 from NEC 690.8

 70 amps / 1.25 = 56 amps is the maximum inverter output Answer (c)
Problem 64

 NEC 690.8(B)(1)(a)
70A * .8 = 56A
inverter output max!
70A * .8 = 56A
56A * 240V = 13,440 Watts max!
NEC 705.12 (D)(7)
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??

 What would your OCPD max be?
   (200A Buss x 1.2) – 200A Breaker = ?
   240A – 200A = 40A


   40A OCPD maximum!!!
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??

 What would the most current allowable from your inverter?
   40A OCPD/ 1.25 =


   32A current from inverter MAXIMUM!!!
What if you had a 200A Main
 Breaker and a 225A Main
           Buss??

 …AND you needed to put in a 20A OCPD, but the opposite
  end of the panel was already filled up?
 Could you do it?
Yes!! Total supply to
the BUSS (220A) is
less than the BUSS is
rated for (225A)!!
Side note on Fastener
     Requirement for OCPD

 NEC 408.36(D):
Side note on Fastener
      Requirement for OCPD

 Exception to this provided by 705.12(D)(6)
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??
 …AND you really wanted to use that 13KW inverter that
  requires a 70A OCPD?
 Could you do it?
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??
 …AND you really wanted to use that 13KW inverter that
  requires a 70A OCPD?
 Could you do it? Maybe… There are two ways it can be
  achieved.
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??
 …AND you really wanted to use that 13KW inverter that
  requires a 70A OCPD?
 Could you do it? Maybe…

 1. Do a load analysis on the facility and if you determine
  that you can reduce your Main Breaker down to 150A, then
  that gives you 90A of PV supply OCPD head room:
 (200A Main Buss * 1.2) – 150A Main Breaker = ?A

 240A – 150A = 90A
What if you had a 200A Main
 Breaker and a 200A Main
           Buss??
 …AND you really wanted to use that 13KW inverter that
  requires a 70A OCPD?
 Could you do it? Maybe…

 OR,      2. Do a line-side tap.
Various ways to do Supply-Side Tap
How big can I go with a supply-
          side tap?
In this example with the
service size being 200A,
then the maximum size
line-side tap OCPD would
be 200A.

Maximum current from PV
array? 200A/1.25= 160A
PV Supply!!!

Wattage?? 160A x 240V =
38,400 Watts!!
705.12 (D)(2) Exception

 Now hold on there!!!… The specifications of my 6KW
  240V bimodal inverter (grid-tied with battery backup) is
  asking for a 60A OCPD in the main panel. I’ve got a 200A
  Main Breaker and a 200A which gives me just 40A PV
  supply OCPD headroom… I sure don’t want to downsize
  my main. Is there any hope for me??
 YES… there is.. It is the exception listed in 705.12(D)(2).
705.12 (D)(2) Exception
705.12 (D)(2) Exception
            (rationale)

 Because the charging current required from the grid for the
  batteries can be greater than the current supplied by the
  inverter and PV array, the size of the backfed breaker must
  be larger.
 However, the 120-rule is concerned with the supply currents
  to the main buss, not the load currents leaving the buss.
  They therefore allow 125% of the inverter’s supply current
  to be used instead of OCPD size to determine the buss
  loading as it pertains to the 120-rule.
Sooo… In our example…

 6000W 240V inverter will produce a maximum of 25A.

 1.25 (per the 705.12(D)(2) exception) x 25A= 31.25A

 (200A Main Buss x 1.2) – 200A Main Breaker = 40A
  allowable.
 31.25A< 40A so it is GOOD!!!
Charging
currents




           Actual currents with
           exception factor = 32.5A
                                      32.5A < 40A so we are good!
Last Minute Resources

 Home Power Magazine: Code Corner Articles, Mehalic Article
  on Load Side Connections, and the one on Line-Side
  Connections
 Solar Pro Articles
   Hren/Mehalic – Issue 4.3 “Code Red: Notable Changes to 2011 NEC”
   Leblanc/Yates – Issue 2.4 “Can We Land?” load vs. supply side
     interconnection
   Q & A Sections – All issues

 SolarABCs.org – Expedited Permit Process Workbook

 Cross – reference to the Code Book as you prepare
Drilling Down

 Web Reader iPhone App – reads
  articles to you!
   Listen passively to article voice-
     overs. Good for driving, chores,
     etc.

 NEC Code Book – Know where
  things are and where related
  information is!!!
   Tables
   Index
   Definitions, Article 100
Test-Taking Strategies


 Core Dump upon arrival
   Write out formulas you know
   I-V Curve, PIE chart, write it down before you get going

 CIRCLE what the question is asking you to figure out!

 Multiple Choice – the right answer is there!!!

 Look for clues in other questions
How to Attack the Questions
 For a question requiring no calculations that you have
   complete confidence in the answer you’ve provided put a
   star next to it.

 For a question that you are not sure about the answer
   you’ve provided, or involves a calculation that you want
   to double-check later, put a circle.

 For a question with a circle that gets revisited later and
   you are confident of the answer, put a check in the circle.
   If you don’t think you need to visit again, put a star.

 For a question that you skip, put a circle.

 BE CAREFUL: When filling out the answer sheet that
   you don’t mix up your answers or put them where they
   shouldn’t be.
Time Management


 4 hours, 70 questions (60 count, 10 are pilot questions)

 First time through – Recommend NOT to spend more than
  3 minutes on each question!
 Need to be able to get through the test at least one time and
  have time to go back
Next Test Insurance


 Do your best! BUT, no matter what, this is a window into
  the NEXT test!
 Stay the FULL 4 hours, NO MATTER WHEN YOU
  FINISH!
 Do you best to memorize as many questions as possible so
  that if you fail this time, you can use those questions as a
  study aide for the next test!! (just keep them to yourself).
NABCEP Code of Ethics
Be sure to buy the Casio fx260


 Buy the Calculator:
  Casio fx260 – about $5-
  10.00
 Get familiar with the
  function keys
  (especially trig and
  arctan)
Why arctan??


 Arctan is the function you use to convert a rise over run
  value to an actual value of pitch of the roof in degrees.



 For example: What if you had a roof with a 2/12 pitch?
First we must understand what
         2/12 means?
It refers to the rise over the run



    2”


              12”
For every 2” of rise, there is 12”
             of run


    2”


              12”
So how do we solve for the
         angle?


 2”
                ?°
          12”
We know that the tangent of the
 angle is equal to the opposite
       over the adjacent
Opposite


           2”
                          ?°
                12”


                      Adjacent
Therefore, 2 divided by 12 is the
  tangent of the angle which is
              0.1666
Opposite


           2”
                          ?°
                12”


                      Adjacent
How to solve
                 In order to convert from the tangent of an angle to
Opposite         the actual angle value use the arctan function


           2”
                                   ?°
                     12”


                              Adjacent
Arctan function

Press shift
or 2nd key
Arctan function


Arctan is the
tan-1 key
What to Expect


 Scratch paper is either the exam cover sheet – limited

 They supply pencils, you can ask for more sharpened

 They supply a copy of the NEC 2011

 Tight Security – varies by location, but you can be sure you
  will not be able to bring anything into the exam
 A lot of page turning, distractions: FOCUS!!!
“You Got This!!!”

        Yes, this is a difficult test.
              26% pass rate (rumor has it)
              Experience helps, but don’t
                count on it (solely)
              Code, Code, Code

        49/70 = 70%

041813 rs 120 rule and test taking strat

  • 1.
    NABCEP PV Installer™Exam 120 Rule & Test-taking Strategies Richard Stovall SolPowerPeople, Inc. Austin, TX April 18, 2013
  • 2.
    Today’s Topics  120-Rule Last Minute Articles & Resources  Test-taking Strategies  Time Management  What to Expect
  • 3.
  • 4.
    Problem 64  NEC705.12 (D) (2)
  • 5.
    Problem 64  Ratingof the buss bar = 225 amps  225 A x 1.20 = 270 amps  Rating of the breaker serving the utility = 200 amps  270 amps - 200 amps = 70 amps is the maximum breaker size for the PV system  Divide by 1.25 from NEC 690.8  70 amps / 1.25 = 56 amps is the maximum inverter output Answer (c)
  • 6.
    Problem 64  NEC690.8(B)(1)(a)
  • 8.
    70A * .8= 56A inverter output max!
  • 9.
    70A * .8= 56A 56A * 240V = 13,440 Watts max!
  • 10.
  • 14.
    What if youhad a 200A Main Breaker and a 200A Main Buss??
  • 15.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  What would your OCPD max be?  (200A Buss x 1.2) – 200A Breaker = ?  240A – 200A = 40A  40A OCPD maximum!!!
  • 16.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  What would the most current allowable from your inverter?  40A OCPD/ 1.25 =  32A current from inverter MAXIMUM!!!
  • 17.
    What if youhad a 200A Main Breaker and a 225A Main Buss??  …AND you needed to put in a 20A OCPD, but the opposite end of the panel was already filled up?  Could you do it?
  • 19.
    Yes!! Total supplyto the BUSS (220A) is less than the BUSS is rated for (225A)!!
  • 20.
    Side note onFastener Requirement for OCPD  NEC 408.36(D):
  • 21.
    Side note onFastener Requirement for OCPD  Exception to this provided by 705.12(D)(6)
  • 22.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  …AND you really wanted to use that 13KW inverter that requires a 70A OCPD?  Could you do it?
  • 23.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  …AND you really wanted to use that 13KW inverter that requires a 70A OCPD?  Could you do it? Maybe… There are two ways it can be achieved.
  • 24.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  …AND you really wanted to use that 13KW inverter that requires a 70A OCPD?  Could you do it? Maybe…  1. Do a load analysis on the facility and if you determine that you can reduce your Main Breaker down to 150A, then that gives you 90A of PV supply OCPD head room:  (200A Main Buss * 1.2) – 150A Main Breaker = ?A  240A – 150A = 90A
  • 26.
    What if youhad a 200A Main Breaker and a 200A Main Buss??  …AND you really wanted to use that 13KW inverter that requires a 70A OCPD?  Could you do it? Maybe…  OR, 2. Do a line-side tap.
  • 29.
    Various ways todo Supply-Side Tap
  • 30.
    How big canI go with a supply- side tap?
  • 31.
    In this examplewith the service size being 200A, then the maximum size line-side tap OCPD would be 200A. Maximum current from PV array? 200A/1.25= 160A PV Supply!!! Wattage?? 160A x 240V = 38,400 Watts!!
  • 32.
    705.12 (D)(2) Exception Now hold on there!!!… The specifications of my 6KW 240V bimodal inverter (grid-tied with battery backup) is asking for a 60A OCPD in the main panel. I’ve got a 200A Main Breaker and a 200A which gives me just 40A PV supply OCPD headroom… I sure don’t want to downsize my main. Is there any hope for me??  YES… there is.. It is the exception listed in 705.12(D)(2).
  • 33.
  • 34.
    705.12 (D)(2) Exception (rationale)  Because the charging current required from the grid for the batteries can be greater than the current supplied by the inverter and PV array, the size of the backfed breaker must be larger.  However, the 120-rule is concerned with the supply currents to the main buss, not the load currents leaving the buss. They therefore allow 125% of the inverter’s supply current to be used instead of OCPD size to determine the buss loading as it pertains to the 120-rule.
  • 35.
    Sooo… In ourexample…  6000W 240V inverter will produce a maximum of 25A.  1.25 (per the 705.12(D)(2) exception) x 25A= 31.25A  (200A Main Buss x 1.2) – 200A Main Breaker = 40A allowable.  31.25A< 40A so it is GOOD!!!
  • 36.
    Charging currents Actual currents with exception factor = 32.5A 32.5A < 40A so we are good!
  • 37.
    Last Minute Resources Home Power Magazine: Code Corner Articles, Mehalic Article on Load Side Connections, and the one on Line-Side Connections  Solar Pro Articles  Hren/Mehalic – Issue 4.3 “Code Red: Notable Changes to 2011 NEC”  Leblanc/Yates – Issue 2.4 “Can We Land?” load vs. supply side interconnection  Q & A Sections – All issues  SolarABCs.org – Expedited Permit Process Workbook  Cross – reference to the Code Book as you prepare
  • 38.
    Drilling Down  WebReader iPhone App – reads articles to you!  Listen passively to article voice- overs. Good for driving, chores, etc.  NEC Code Book – Know where things are and where related information is!!!  Tables  Index  Definitions, Article 100
  • 39.
    Test-Taking Strategies  CoreDump upon arrival  Write out formulas you know  I-V Curve, PIE chart, write it down before you get going  CIRCLE what the question is asking you to figure out!  Multiple Choice – the right answer is there!!!  Look for clues in other questions
  • 40.
    How to Attackthe Questions  For a question requiring no calculations that you have complete confidence in the answer you’ve provided put a star next to it.  For a question that you are not sure about the answer you’ve provided, or involves a calculation that you want to double-check later, put a circle.  For a question with a circle that gets revisited later and you are confident of the answer, put a check in the circle. If you don’t think you need to visit again, put a star.  For a question that you skip, put a circle.  BE CAREFUL: When filling out the answer sheet that you don’t mix up your answers or put them where they shouldn’t be.
  • 41.
    Time Management  4hours, 70 questions (60 count, 10 are pilot questions)  First time through – Recommend NOT to spend more than 3 minutes on each question!  Need to be able to get through the test at least one time and have time to go back
  • 42.
    Next Test Insurance Do your best! BUT, no matter what, this is a window into the NEXT test!  Stay the FULL 4 hours, NO MATTER WHEN YOU FINISH!  Do you best to memorize as many questions as possible so that if you fail this time, you can use those questions as a study aide for the next test!! (just keep them to yourself).
  • 43.
  • 44.
    Be sure tobuy the Casio fx260  Buy the Calculator: Casio fx260 – about $5- 10.00  Get familiar with the function keys (especially trig and arctan)
  • 45.
    Why arctan??  Arctanis the function you use to convert a rise over run value to an actual value of pitch of the roof in degrees.  For example: What if you had a roof with a 2/12 pitch?
  • 46.
    First we mustunderstand what 2/12 means?
  • 47.
    It refers tothe rise over the run 2” 12”
  • 48.
    For every 2”of rise, there is 12” of run 2” 12”
  • 49.
    So how dowe solve for the angle? 2” ?° 12”
  • 50.
    We know thatthe tangent of the angle is equal to the opposite over the adjacent Opposite 2” ?° 12” Adjacent
  • 51.
    Therefore, 2 dividedby 12 is the tangent of the angle which is 0.1666 Opposite 2” ?° 12” Adjacent
  • 52.
    How to solve In order to convert from the tangent of an angle to Opposite the actual angle value use the arctan function 2” ?° 12” Adjacent
  • 53.
  • 54.
  • 56.
    What to Expect Scratch paper is either the exam cover sheet – limited  They supply pencils, you can ask for more sharpened  They supply a copy of the NEC 2011  Tight Security – varies by location, but you can be sure you will not be able to bring anything into the exam  A lot of page turning, distractions: FOCUS!!!
  • 57.
    “You Got This!!!”  Yes, this is a difficult test.  26% pass rate (rumor has it)  Experience helps, but don’t count on it (solely)  Code, Code, Code  49/70 = 70%