SlideShare a Scribd company logo
Email: jeff.johnson@todo-solar.com-mx Tele: (+52) 871 722 9522 www.todo-solar.com.mx
Electrical Installation of a PV System
Making the Right Connections…
Dr. Jeffery Lee Johnson
CTO Todo-Solar
Coahuila, Mexico
Agenda
• Resources
• Assumptions and Background
• The DC side of things
– Choosing and Connecting the Panels in Series
– Proper grounding
– String combiners
• Meeting in the Middle
– DC connection to the Inverter
– DC Disconnects, fusing and loading
• The AC side of things
– AC Connection to the Inverter
– AC Disconnects, fusing and safety
– Connecting to the grid
• Summary and questions
Resources
Doc Solstice’s Seasoned Sentiments
Facts about Global PV installations
http://www.pv-tech.org/news/global_pv_installations_reached_27.7gw_in_2011_industry_at_crossroads_says
Global PV installations reached 27.7GW in 2011
That comes to 0.87 KW per second or 3 to 4 panels every
second of the year
Global PV Installations to Grow by up to 21 Percent in
2012 Predicts IMS Research
http://www.pvmarketresearch.com/press-release/Global_PV_Installations_to_Grow_by_up_to_21_Percent_in_2012_Predicts_IMS_Research/5
For comparison , the entire grid capacity
of the country of Mexico is 53 GW
INTRODUCTION, BACKGROUND AND
ASSUMPTIONS ABOUT THE SYSTEM
Key Concepts and Assumptions
• Follow the typical systematic Installation Procedures
– Assemble and place racks
– Mount and connect panels (DC)
– Install combiner box (DC)
– Connect DC disconnect (may be integrated) (DC)
– Connect DC to inverter (DC)
– Mount and configure inverter (AC/DC)
– Install AC Disconnect (AC)
– Connect inverter to grid via electrical center (AC)
– Commission and test (AC/DC
– Install or activate Monitoring system
• You have an approved wiring diagram meeting specifications and
needs of Locations
– Routing, cable lengths, junction locations, fusing etc a
• You have a complete parts list with prepared components
Electrical diagram: Generic System
General Schematic
One-line diagram
Sample SMA Wiring Diagram with
external DC Disconnect
Combiner Box
Sample SMA Wiring Diagram with
integrated DC Disconnect
Combiner Box
Sample System
3 strings of 10 panels
250W Siliken
SMA sunny Boy SB7000US
THE DC SIDE OF THINGS
Always use components rate for UL 1703 and
IEC standards
Panel Characteristics
Must know VOC, ISC, Vmp Imp Pmp, tolerances under STC and NOTC (preferably)
Characteristics of Panels in Series
String is a series of panels with predetermined current and voltage output
V = V1 + V2 + …Vn = ∑ Vi
I = I1 = I2 = …In
Choosing Panels for Series layout
Issue
 Voltages for Panels in Series add linearly
 Ideally, every series has the same voltage output – but
generally not true
 When combining series into Parallel Arrays at a
combination node (such as a combiner box or Inverter
input), the voltage at that node is the weighted average of
the series voltages favoring the lowest voltage present
Important to balance your strings by equalizing the
string voltages as best as possible !
Balancing String Voltage
Layout your panels in a similar environment of illumination & temperature
Measure and Record VOC for each panel – assign a numbering system
WHY measure VOC? Safer and varies
little with changes in illumination
WHEN? Measure during peak hours
near solar noon when solar radiation
is changing slowly
With knowledge of panel characteristics, group them as best you can so
each series will have equal or similar voltage – mix and match high /low
performers
Installing panels – measure as you go!
RETURN LINE
Using return line measure VOC
as you connect panels
Why? To ensure each connection is secure and voltage sums as you
go! Panel interconnect issues are difficult to find after the fact
Make Sure panel connectors and cables are secured to rack
Physical Ground
All panels must have common physical ground and be grounded to racks
Aluminum frames are anodized (resistive)
Most panels provide a ground connection hole
Other technique is to use WEEBs or lugs – electrically connect
panel frames to rack and then ground rack
Combiner boxes – adding the current of strings
PV COMBINER BOXES ARE CURRENT ADDERS FOR STRINGS IN PARALLEL
Common buss bar
• DC positive inputs
• DC Negative inputs
• Ground
•Single outputs for
Positive, Negative &
ground
Each DC positive input
(string) is fused before
common output
Fuse: 600 VDC with amp
rating > 1.45 operating amps
Acts as string switch
Recommendation:
Pre-wire the box with
negative/ positive cables
with mated connectors
DC routing
• Have a DC cable routing plan
– DC is on the roof or remote from inverter
• Best solar cables do not need conduit but
bundle them nicely using UV resistant cable ties
• For esthetics and some codes, use metal
conduit to distribute DC cables
MEETING IN THE MIDDLE
CONNECTING DC TO THE INVERTER
DC Disconnects
Integrated DC Disconnect Switch
(Typically fused inside the inverter)
Stand-alone DC Disconnect Switch
• Fuse: 600 VDC with
Amp rating > 1.45 x operating
amps for each positive lead
Connecting DC to Inverter
 Disconnect all DC power
 Follow Inverter manual to
connect positive, negative
and ground cables*
*Note: some panels are
positively grounded … so pay
attention
 Turn on DC and measure
voltage at all outputs and
inputs
 Turn off DC
THE AC SIDE OF THINGS
Know your Grid
Know which type of grid you are connecting to
Most inverters are reconfigurable by dip
switches or programming
Line voltages vary so choose the operating
output range that fits your grid conditions
Inverter must be equipped with anti-islanding
and must shutdown upon loss of grid power
(grid connected systems)
The AC connection
AC Disconnect
Main Panel
connection
AC Outputs
AC Disconnect
• Locate AC disconnect near the inverter
-- must be accessible
• Fuses or Breakers must be compatible
with grid voltage (240 VAC)
• Amp repeating should be 1.45 x the
output current under operating
conditions
Fused style
Breaker Style
Connecting to the Grid
L1
Phase 2
L2
Phase 1
Typical 240 VAC Connection
Outputs from Inverter are:
L1, L2 are positive feed lines
Neutral
Physical Ground
Shut off AC power at main switch
Shut off all DC inputs to inverter
Connect Neutral and Physical Ground
Connect L1 to Phase 1 using breaker
Connect L2 to Phase 2 using breaker
or use two pole breakers
** Phase numbering is for convenience
Commissioning
• Check all connections
• Follow manual for startup
• Usual procedure is
– For Startup: Turn on AC First then DC
– For Shutdown: Turn off DC first then AC
• After shutdown, ALWAYS wait 5 to 10 minutes
before opening or working on inverter !!!
• Capacitive load needs to discharge
SYSTEM MONITORING
30
Monitoreo de Bluetooth para Internet o iPhone, iPad
(Solar Energy made available to Everyone)
http://www.todo-solar.com.mx
Twitter: @TodoSolarKids
Twitter: @TodoSolar

More Related Content

What's hot

Building Utilities 2
Building Utilities 2Building Utilities 2
Building Utilities 2
Jay Gonzales
 
Integrated circuit
Integrated circuitIntegrated circuit
Integrated circuit
ddsshukla
 
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
Mahesh Chandra Manav
 
automatic light control at night ppt by Shubhan raj
automatic light control at night ppt by Shubhan rajautomatic light control at night ppt by Shubhan raj
automatic light control at night ppt by Shubhan raj
Shubham Raj
 
Automatic night lamp
Automatic night lampAutomatic night lamp
Automatic night lamp
ABUBAKKAR SIDDIKI
 
Home automation relays
Home automation relaysHome automation relays
Home automation relays
Meena Tanwar
 
Grid connected
Grid connectedGrid connected
Grid connected
Gomathy Sengottaiyan
 
What is electronics
What is electronicsWhat is electronics
What is electronicsMrinal Pal
 
30.led .projects
30.led .projects30.led .projects
30.led .projects
Toz Koparan
 
Report on inverters
Report on invertersReport on inverters
Report on inverters
Urvashi Khandelwal
 
Automatic Emergency Light
Automatic Emergency LightAutomatic Emergency Light
Automatic Emergency Light
Mridul Rawat
 
Electron Tube Afs Epri R5
Electron Tube   Afs Epri R5Electron Tube   Afs Epri R5
Electron Tube Afs Epri R5
John Kappenman
 
Electrical q
Electrical qElectrical q
Photovoltaic IV Curve Analysis
Photovoltaic IV Curve AnalysisPhotovoltaic IV Curve Analysis
Photovoltaic IV Curve Analysis
Dimas Kaharudin
 

What's hot (19)

Building Utilities 2
Building Utilities 2Building Utilities 2
Building Utilities 2
 
How to build a Inverters
How to build a InvertersHow to build a Inverters
How to build a Inverters
 
Integrated circuit
Integrated circuitIntegrated circuit
Integrated circuit
 
Electronics 01
Electronics 01Electronics 01
Electronics 01
 
Solar junction boxes jmv lps ltd
Solar junction boxes   jmv lps ltdSolar junction boxes   jmv lps ltd
Solar junction boxes jmv lps ltd
 
automatic light control at night ppt by Shubhan raj
automatic light control at night ppt by Shubhan rajautomatic light control at night ppt by Shubhan raj
automatic light control at night ppt by Shubhan raj
 
Presentation1
Presentation1Presentation1
Presentation1
 
Automatic night lamp
Automatic night lampAutomatic night lamp
Automatic night lamp
 
Home automation relays
Home automation relaysHome automation relays
Home automation relays
 
Grid connected
Grid connectedGrid connected
Grid connected
 
What is electronics
What is electronicsWhat is electronics
What is electronics
 
30.led .projects
30.led .projects30.led .projects
30.led .projects
 
Report on inverters
Report on invertersReport on inverters
Report on inverters
 
Solar shading and its effects
Solar shading and its effectsSolar shading and its effects
Solar shading and its effects
 
Automatic Emergency Light
Automatic Emergency LightAutomatic Emergency Light
Automatic Emergency Light
 
Electron Tube Afs Epri R5
Electron Tube   Afs Epri R5Electron Tube   Afs Epri R5
Electron Tube Afs Epri R5
 
Electrical q
Electrical qElectrical q
Electrical q
 
Report
ReportReport
Report
 
Photovoltaic IV Curve Analysis
Photovoltaic IV Curve AnalysisPhotovoltaic IV Curve Analysis
Photovoltaic IV Curve Analysis
 

Viewers also liked

Getting Solar PV off the ground - some practical feedback from the Worthy Far...
Getting Solar PV off the ground - some practical feedback from the Worthy Far...Getting Solar PV off the ground - some practical feedback from the Worthy Far...
Getting Solar PV off the ground - some practical feedback from the Worthy Far...Farming Futures
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
JLanka Technologies (Pvt) Limited
 
Presentation On Solar Installation Project
Presentation On Solar Installation ProjectPresentation On Solar Installation Project
Presentation On Solar Installation ProjectDHiraj Bohara
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
Rajesh Pindoriya
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
Leonardo ENERGY
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)solpowerpeople
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpoint
William Wallace
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systems
anish_hercules
 
Presentation on solar cell
Presentation on solar cellPresentation on solar cell
Presentation on solar cellOmar SYED
 
Solar energy ppt
Solar energy pptSolar energy ppt
Solar energy pptshubhajit_b
 
Electrical and Solar PV Systems (www.solartraining.ca)
Electrical and Solar PV Systems (www.solartraining.ca)Electrical and Solar PV Systems (www.solartraining.ca)
Electrical and Solar PV Systems (www.solartraining.ca)
Irtaza M. Syed
 
Simon Watson | SunEdison
Simon Watson | SunEdisonSimon Watson | SunEdison
Simon Watson | SunEdison
GW Solar Institute
 
Bs solar energy presentation
Bs solar energy presentationBs solar energy presentation
Bs solar energy presentation
Sheng Zhe
 
Solar Energy Panel Installation Process
Solar Energy Panel Installation ProcessSolar Energy Panel Installation Process
Solar Energy Panel Installation Process
NW Electric and Solar
 
Solar electric installation check list
Solar electric installation check listSolar electric installation check list
Solar electric installation check list
Digital Consummate
 

Viewers also liked (18)

Getting Solar PV off the ground - some practical feedback from the Worthy Far...
Getting Solar PV off the ground - some practical feedback from the Worthy Far...Getting Solar PV off the ground - some practical feedback from the Worthy Far...
Getting Solar PV off the ground - some practical feedback from the Worthy Far...
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
Presentation On Solar Installation Project
Presentation On Solar Installation ProjectPresentation On Solar Installation Project
Presentation On Solar Installation Project
 
Design off grid solar PV system
Design off grid solar PV systemDesign off grid solar PV system
Design off grid solar PV system
 
Photovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - DesignPhotovoltaic Training - Session 1 - Design
Photovoltaic Training - Session 1 - Design
 
Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013Solar O&M Presentation Intersolar 2013
Solar O&M Presentation Intersolar 2013
 
053013 pv system site assessment (1)
053013 pv system site assessment (1)053013 pv system site assessment (1)
053013 pv system site assessment (1)
 
Solar photovoltaic powerpoint
Solar photovoltaic powerpointSolar photovoltaic powerpoint
Solar photovoltaic powerpoint
 
Solar photovoltaic systems
Solar photovoltaic systemsSolar photovoltaic systems
Solar photovoltaic systems
 
Presentation on solar cell
Presentation on solar cellPresentation on solar cell
Presentation on solar cell
 
Solar energy ppt
Solar energy pptSolar energy ppt
Solar energy ppt
 
Electrical and Solar PV Systems (www.solartraining.ca)
Electrical and Solar PV Systems (www.solartraining.ca)Electrical and Solar PV Systems (www.solartraining.ca)
Electrical and Solar PV Systems (www.solartraining.ca)
 
Simon Watson | SunEdison
Simon Watson | SunEdisonSimon Watson | SunEdison
Simon Watson | SunEdison
 
hs_solar_brochure
hs_solar_brochurehs_solar_brochure
hs_solar_brochure
 
Bs solar energy presentation
Bs solar energy presentationBs solar energy presentation
Bs solar energy presentation
 
Solar Energy Panel Installation Process
Solar Energy Panel Installation ProcessSolar Energy Panel Installation Process
Solar Energy Panel Installation Process
 
Solar structure
Solar structureSolar structure
Solar structure
 
Solar electric installation check list
Solar electric installation check listSolar electric installation check list
Solar electric installation check list
 

Similar to Webinar 03 electrical installation of pv system

Introduction_Power_Supply-6-9-10.pptx
Introduction_Power_Supply-6-9-10.pptxIntroduction_Power_Supply-6-9-10.pptx
Introduction_Power_Supply-6-9-10.pptx
JagrutiParmar20
 
Introduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.pptIntroduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.ppt
DharaMilanPatel
 
Introduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.pptIntroduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.ppt
Lyka Gumatay
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
TESCO - The Eastern Specialty Company
 
Applied Electronics - Power Supply
Applied Electronics - Power SupplyApplied Electronics - Power Supply
Applied Electronics - Power Supply
Swapnil Agrawal
 
Grounding and Bonding
Grounding and BondingGrounding and Bonding
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
LiewChiaPing
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsx
MohanakumarMP3
 
SOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptxSOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptx
MohanakumarMP3
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
Dr. Catherine T J
 
Pre Final Year project/ mini project for Electronics and communication engine...
Pre Final Year project/ mini project for Electronics and communication engine...Pre Final Year project/ mini project for Electronics and communication engine...
Pre Final Year project/ mini project for Electronics and communication engine...
Shirshendu Das
 
Solar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdfSolar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdf
ssuserfd91eb
 
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter ModuleeIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
xmeteorite
 
powersupply.pptx
powersupply.pptxpowersupply.pptx
powersupply.pptx
RoelTabuyo2
 
Intro to Electronics design
Intro to Electronics designIntro to Electronics design
Intro to Electronics design
mark_nabil
 
Apollo Solar TSW Inverter Training
Apollo Solar TSW Inverter TrainingApollo Solar TSW Inverter Training
Apollo Solar TSW Inverter Training
jen_seder
 
Basic Electronic UNIT-IV PPT
Basic Electronic UNIT-IV PPTBasic Electronic UNIT-IV PPT
Basic Electronic UNIT-IV PPT
Praveen Kunda
 
Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020
RekaNext Capital
 
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
Power Spikes Isolation to avoid corruption within sensitive ICs SolutionsPower Spikes Isolation to avoid corruption within sensitive ICs Solutions
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
Mistral Solutions
 
Transistor cb cc ce power point transistor
Transistor cb cc ce power point transistorTransistor cb cc ce power point transistor
Transistor cb cc ce power point transistor
2004akkuu
 

Similar to Webinar 03 electrical installation of pv system (20)

Introduction_Power_Supply-6-9-10.pptx
Introduction_Power_Supply-6-9-10.pptxIntroduction_Power_Supply-6-9-10.pptx
Introduction_Power_Supply-6-9-10.pptx
 
Introduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.pptIntroduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.ppt
 
Introduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.pptIntroduction_Power_Supply-6-9-10.ppt
Introduction_Power_Supply-6-9-10.ppt
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 
Applied Electronics - Power Supply
Applied Electronics - Power SupplyApplied Electronics - Power Supply
Applied Electronics - Power Supply
 
Grounding and Bonding
Grounding and BondingGrounding and Bonding
Grounding and Bonding
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsx
 
SOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptxSOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptx
 
Distribution systems
Distribution systemsDistribution systems
Distribution systems
 
Pre Final Year project/ mini project for Electronics and communication engine...
Pre Final Year project/ mini project for Electronics and communication engine...Pre Final Year project/ mini project for Electronics and communication engine...
Pre Final Year project/ mini project for Electronics and communication engine...
 
Solar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdfSolar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdf
 
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter ModuleeIQ Datasheet - 350-WATT DC-TO-DC Converter Module
eIQ Datasheet - 350-WATT DC-TO-DC Converter Module
 
powersupply.pptx
powersupply.pptxpowersupply.pptx
powersupply.pptx
 
Intro to Electronics design
Intro to Electronics designIntro to Electronics design
Intro to Electronics design
 
Apollo Solar TSW Inverter Training
Apollo Solar TSW Inverter TrainingApollo Solar TSW Inverter Training
Apollo Solar TSW Inverter Training
 
Basic Electronic UNIT-IV PPT
Basic Electronic UNIT-IV PPTBasic Electronic UNIT-IV PPT
Basic Electronic UNIT-IV PPT
 
Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020Surge and Lightning Protection Oct 2020
Surge and Lightning Protection Oct 2020
 
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
Power Spikes Isolation to avoid corruption within sensitive ICs SolutionsPower Spikes Isolation to avoid corruption within sensitive ICs Solutions
Power Spikes Isolation to avoid corruption within sensitive ICs Solutions
 
Transistor cb cc ce power point transistor
Transistor cb cc ce power point transistorTransistor cb cc ce power point transistor
Transistor cb cc ce power point transistor
 

More from solpowerpeople

NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
solpowerpeople
 
Changes to 2014 NEC Interconnection Rule 705.12
Changes to 2014 NEC Interconnection Rule 705.12Changes to 2014 NEC Interconnection Rule 705.12
Changes to 2014 NEC Interconnection Rule 705.12
solpowerpeople
 
012413 passive solar design
012413 passive solar design012413 passive solar design
012413 passive solar designsolpowerpeople
 
Inter row shading 4-19-12
Inter row shading 4-19-12Inter row shading 4-19-12
Inter row shading 4-19-12
solpowerpeople
 
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...
"Grid-Interactive Systems- A Matter of Energy Storage" w/  Dr Jeffery Lee Joh..."Grid-Interactive Systems- A Matter of Energy Storage" w/  Dr Jeffery Lee Joh...
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...solpowerpeople
 
PV Monitoring Systems w/Arturo Zarate
PV Monitoring Systems w/Arturo ZaratePV Monitoring Systems w/Arturo Zarate
PV Monitoring Systems w/Arturo Zarate
solpowerpeople
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
solpowerpeople
 
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...solpowerpeople
 
Using sohcahtoa
Using sohcahtoaUsing sohcahtoa
Using sohcahtoa
solpowerpeople
 
What is a triangle
What is a triangleWhat is a triangle
What is a triangle
solpowerpeople
 
#Solar mooc voltage drop calculations
#Solar mooc voltage drop calculations#Solar mooc voltage drop calculations
#Solar mooc voltage drop calculations
solpowerpeople
 
Final trig problem solution
Final trig problem solutionFinal trig problem solution
Final trig problem solution
solpowerpeople
 
#Solarmooc Arctan Solution
#Solarmooc Arctan Solution#Solarmooc Arctan Solution
#Solarmooc Arctan Solution
solpowerpeople
 
#Solar mooc problem set 1 alternate exercise 1 solution.
#Solar mooc problem set 1 alternate exercise 1 solution.#Solar mooc problem set 1 alternate exercise 1 solution.
#Solar mooc problem set 1 alternate exercise 1 solution.
solpowerpeople
 

More from solpowerpeople (15)

NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
 
Changes to 2014 NEC Interconnection Rule 705.12
Changes to 2014 NEC Interconnection Rule 705.12Changes to 2014 NEC Interconnection Rule 705.12
Changes to 2014 NEC Interconnection Rule 705.12
 
012413 passive solar design
012413 passive solar design012413 passive solar design
012413 passive solar design
 
Metering Solutions
Metering SolutionsMetering Solutions
Metering Solutions
 
Inter row shading 4-19-12
Inter row shading 4-19-12Inter row shading 4-19-12
Inter row shading 4-19-12
 
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...
"Grid-Interactive Systems- A Matter of Energy Storage" w/  Dr Jeffery Lee Joh..."Grid-Interactive Systems- A Matter of Energy Storage" w/  Dr Jeffery Lee Joh...
"Grid-Interactive Systems- A Matter of Energy Storage" w/ Dr Jeffery Lee Joh...
 
PV Monitoring Systems w/Arturo Zarate
PV Monitoring Systems w/Arturo ZaratePV Monitoring Systems w/Arturo Zarate
PV Monitoring Systems w/Arturo Zarate
 
Webinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsystWebinar 02 demonstration of pv system design pvsyst
Webinar 02 demonstration of pv system design pvsyst
 
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
#SolarMOOC: Webinar on Project Management of Solar PV with Jeffery Lee Johnso...
 
Using sohcahtoa
Using sohcahtoaUsing sohcahtoa
Using sohcahtoa
 
What is a triangle
What is a triangleWhat is a triangle
What is a triangle
 
#Solar mooc voltage drop calculations
#Solar mooc voltage drop calculations#Solar mooc voltage drop calculations
#Solar mooc voltage drop calculations
 
Final trig problem solution
Final trig problem solutionFinal trig problem solution
Final trig problem solution
 
#Solarmooc Arctan Solution
#Solarmooc Arctan Solution#Solarmooc Arctan Solution
#Solarmooc Arctan Solution
 
#Solar mooc problem set 1 alternate exercise 1 solution.
#Solar mooc problem set 1 alternate exercise 1 solution.#Solar mooc problem set 1 alternate exercise 1 solution.
#Solar mooc problem set 1 alternate exercise 1 solution.
 

Recently uploaded

Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Akanksha trivedi rama nursing college kanpur.
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
Wasim Ak
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
Mohammed Sikander
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
goswamiyash170123
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 

Recently uploaded (20)

Natural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama UniversityNatural birth techniques - Mrs.Akanksha Trivedi Rama University
Natural birth techniques - Mrs.Akanksha Trivedi Rama University
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Normal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of LabourNormal Labour/ Stages of Labour/ Mechanism of Labour
Normal Labour/ Stages of Labour/ Mechanism of Labour
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Multithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race conditionMultithreading_in_C++ - std::thread, race condition
Multithreading_in_C++ - std::thread, race condition
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdfMASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
MASS MEDIA STUDIES-835-CLASS XI Resource Material.pdf
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 

Webinar 03 electrical installation of pv system

  • 1. Email: jeff.johnson@todo-solar.com-mx Tele: (+52) 871 722 9522 www.todo-solar.com.mx Electrical Installation of a PV System Making the Right Connections… Dr. Jeffery Lee Johnson CTO Todo-Solar Coahuila, Mexico
  • 2. Agenda • Resources • Assumptions and Background • The DC side of things – Choosing and Connecting the Panels in Series – Proper grounding – String combiners • Meeting in the Middle – DC connection to the Inverter – DC Disconnects, fusing and loading • The AC side of things – AC Connection to the Inverter – AC Disconnects, fusing and safety – Connecting to the grid • Summary and questions
  • 3. Resources Doc Solstice’s Seasoned Sentiments Facts about Global PV installations http://www.pv-tech.org/news/global_pv_installations_reached_27.7gw_in_2011_industry_at_crossroads_says Global PV installations reached 27.7GW in 2011 That comes to 0.87 KW per second or 3 to 4 panels every second of the year Global PV Installations to Grow by up to 21 Percent in 2012 Predicts IMS Research http://www.pvmarketresearch.com/press-release/Global_PV_Installations_to_Grow_by_up_to_21_Percent_in_2012_Predicts_IMS_Research/5 For comparison , the entire grid capacity of the country of Mexico is 53 GW
  • 5. Key Concepts and Assumptions • Follow the typical systematic Installation Procedures – Assemble and place racks – Mount and connect panels (DC) – Install combiner box (DC) – Connect DC disconnect (may be integrated) (DC) – Connect DC to inverter (DC) – Mount and configure inverter (AC/DC) – Install AC Disconnect (AC) – Connect inverter to grid via electrical center (AC) – Commission and test (AC/DC – Install or activate Monitoring system • You have an approved wiring diagram meeting specifications and needs of Locations – Routing, cable lengths, junction locations, fusing etc a • You have a complete parts list with prepared components
  • 6. Electrical diagram: Generic System General Schematic One-line diagram
  • 7. Sample SMA Wiring Diagram with external DC Disconnect Combiner Box
  • 8. Sample SMA Wiring Diagram with integrated DC Disconnect Combiner Box
  • 9. Sample System 3 strings of 10 panels 250W Siliken SMA sunny Boy SB7000US
  • 10. THE DC SIDE OF THINGS
  • 11. Always use components rate for UL 1703 and IEC standards
  • 12. Panel Characteristics Must know VOC, ISC, Vmp Imp Pmp, tolerances under STC and NOTC (preferably)
  • 13. Characteristics of Panels in Series String is a series of panels with predetermined current and voltage output V = V1 + V2 + …Vn = ∑ Vi I = I1 = I2 = …In
  • 14. Choosing Panels for Series layout Issue  Voltages for Panels in Series add linearly  Ideally, every series has the same voltage output – but generally not true  When combining series into Parallel Arrays at a combination node (such as a combiner box or Inverter input), the voltage at that node is the weighted average of the series voltages favoring the lowest voltage present Important to balance your strings by equalizing the string voltages as best as possible !
  • 15. Balancing String Voltage Layout your panels in a similar environment of illumination & temperature Measure and Record VOC for each panel – assign a numbering system WHY measure VOC? Safer and varies little with changes in illumination WHEN? Measure during peak hours near solar noon when solar radiation is changing slowly With knowledge of panel characteristics, group them as best you can so each series will have equal or similar voltage – mix and match high /low performers
  • 16. Installing panels – measure as you go! RETURN LINE Using return line measure VOC as you connect panels Why? To ensure each connection is secure and voltage sums as you go! Panel interconnect issues are difficult to find after the fact Make Sure panel connectors and cables are secured to rack
  • 17. Physical Ground All panels must have common physical ground and be grounded to racks Aluminum frames are anodized (resistive) Most panels provide a ground connection hole Other technique is to use WEEBs or lugs – electrically connect panel frames to rack and then ground rack
  • 18. Combiner boxes – adding the current of strings PV COMBINER BOXES ARE CURRENT ADDERS FOR STRINGS IN PARALLEL Common buss bar • DC positive inputs • DC Negative inputs • Ground •Single outputs for Positive, Negative & ground Each DC positive input (string) is fused before common output Fuse: 600 VDC with amp rating > 1.45 operating amps Acts as string switch Recommendation: Pre-wire the box with negative/ positive cables with mated connectors
  • 19. DC routing • Have a DC cable routing plan – DC is on the roof or remote from inverter • Best solar cables do not need conduit but bundle them nicely using UV resistant cable ties • For esthetics and some codes, use metal conduit to distribute DC cables
  • 20. MEETING IN THE MIDDLE CONNECTING DC TO THE INVERTER
  • 21. DC Disconnects Integrated DC Disconnect Switch (Typically fused inside the inverter) Stand-alone DC Disconnect Switch • Fuse: 600 VDC with Amp rating > 1.45 x operating amps for each positive lead
  • 22. Connecting DC to Inverter  Disconnect all DC power  Follow Inverter manual to connect positive, negative and ground cables* *Note: some panels are positively grounded … so pay attention  Turn on DC and measure voltage at all outputs and inputs  Turn off DC
  • 23. THE AC SIDE OF THINGS
  • 24. Know your Grid Know which type of grid you are connecting to Most inverters are reconfigurable by dip switches or programming Line voltages vary so choose the operating output range that fits your grid conditions Inverter must be equipped with anti-islanding and must shutdown upon loss of grid power (grid connected systems)
  • 25. The AC connection AC Disconnect Main Panel connection AC Outputs
  • 26. AC Disconnect • Locate AC disconnect near the inverter -- must be accessible • Fuses or Breakers must be compatible with grid voltage (240 VAC) • Amp repeating should be 1.45 x the output current under operating conditions Fused style Breaker Style
  • 27. Connecting to the Grid L1 Phase 2 L2 Phase 1 Typical 240 VAC Connection Outputs from Inverter are: L1, L2 are positive feed lines Neutral Physical Ground Shut off AC power at main switch Shut off all DC inputs to inverter Connect Neutral and Physical Ground Connect L1 to Phase 1 using breaker Connect L2 to Phase 2 using breaker or use two pole breakers ** Phase numbering is for convenience
  • 28. Commissioning • Check all connections • Follow manual for startup • Usual procedure is – For Startup: Turn on AC First then DC – For Shutdown: Turn off DC first then AC • After shutdown, ALWAYS wait 5 to 10 minutes before opening or working on inverter !!! • Capacitive load needs to discharge
  • 30. 30 Monitoreo de Bluetooth para Internet o iPhone, iPad
  • 31. (Solar Energy made available to Everyone) http://www.todo-solar.com.mx Twitter: @TodoSolarKids Twitter: @TodoSolar