SlideShare a Scribd company logo
1 of 9
Download to read offline
Application of Existing Technologies to
Reduce Arc-Flash Hazards
Jim Buff and Karl Zimmerman
Schweitzer Engineering Laboratories, Inc.
Presented at
NETA PowerTest
New Orleans, Louisiana
March 17–20, 2008
Previously presented at the
Pulp and Paper Industry Technical Conference, June 2007,
60th Annual Conference for Protective Relay Engineers, March 2007,
and 6th Annual Clemson University Power Systems Conference, March 2007
Originally presented at the
33rd Annual Western Protective Relay Conference, October 2006
1
Application of Existing Technologies to
Reduce Arc-Flash Hazards
Jim Buff and Karl Zimmerman, Schweitzer Engineering Laboratories, Inc.
I. INTRODUCTION
Protective relay engineers have long been concerned with
protecting power systems and all of the equipment associated
with those systems. We routinely apply relays to limit damage
to apparatus (e.g., transmission and distribution lines, power
transformers, buses, generators, motors, etc.) and protect
against, or reduce, the impact of electrical disturbances on the
larger power system (e.g., shedding load for frequency or
voltage variations).
Safety for personnel has always been a concern, but in the
past several years there is a heightened awareness of the
importance of safety around electrical apparatus, as reflected
in recent regulations and standards [1] [2].
In particular, industry and utilities alike recognize that arc-
flash events can cause dangerous and potentially fatal levels of
heat, ultraviolet radiation, blast pressure, flying shrapnel, and
deafening sound waves. The existing standards mainly deal
with the heat energy from the arc flash.
The energy produced by an arc-flash event is proportional to
voltage, current, and the duration of the event (V•I•t). Design
engineers have a few options to reduce system voltage or fault
currents (e.g., grounding practices and application of current-
limiting fuses), but the best and most direct ways to reduce arc-
flash hazards are to reduce fault-clearing times and use wireless
communications to reduce the need for technicians to be in
harms way. In most cases, clearing times are reduced via more
complete use of microprocessor relays features and other
technologies already available. Similarly, digital relay
communications and secure wireless communications devices
allow engineers and technicians to converse with relays from a
safe distance.
In this paper, we include some important industry
definitions of arc flash and ways of measuring arc-flash
hazards. We then examine the use of existing technologies,
including digital relays and communications capabilities, to
implement reduced trip times using instantaneous overcurrent
relays, a fast bus-trip scheme, and differential schemes. We
use a typical industrial switchgear lineup as an example of
how to implement these schemes. Finally, we quantify the
levels to which we can reduce arc-flash energy and its impact
on safety.
II. DEFINITIONS
What is an arc flash? How do we measure the energy so as
to quantify improvement? Some important definitions of arc
flash and related issues can be found in IEEE 1584-2002,
“IEEE Guide for Performing Arc-Flash Hazard Calculations.”
Similar definitions are found in NFPA 70E, “Standard for
Electrical Safety in the Workplace, 2004 Edition.”
Arc-Flash Hazard. A dangerous condition
associated with the release of energy caused by an
electric arc.
Flash Hazard Analysis. A method to determine the
risk of personal injury as a result of exposure to
incident energy from an electrical arc flash.
Flash-Protection Boundary. An approach limit at
a distance from live parts that are insulated or
exposed within which a person could receive a
second-degree burn.
Working Distance. The dimension between the
possible arc point and the head and the body of the
worker positioned in place to perform the assigned
task [1].
III. MEASURING ARC FLASH AND THE EFFECTS OF ARC FLASH
There are several methods for calculating incident energy
due to an arc-flash event. These include a table-based method
in NFPA 70E-2004, a theory-based model for applications
over 15 kV (Lee method), empirically derived models based
on a curve-fitting program, and a physical model-based
method with some verification testing.
Within the last few years, IEEE 1584 was published, and
an empirically derived model based on statistical analysis was
developed as part of this effort [1]. IEEE 1584 includes
several spreadsheets to assist the engineer in arc-flash studies.
We will use this method for our analysis in this paper.
Incident energy is typically quantified in cal/cm2
or
Joules/cm2
. The incident energy determines the personal
protective equipment (PPE) required to provide adequate
protection based on recommendations in NFPA 70E. Incident
energy calculations also provide the basis for the flash-
protection boundary.
A. Protection Considerations for Arc Flash
IEEE 1584-2002 concluded that arc time has a linear effect
on incident energy, i.e., reducing fault-clearing times
proportionately reduces arc flash.
Also, IEEE 1584-2002 states that the system X/R ratio had
“little or no effect” on arc current and incident energy and
was, thus, neglected. All of the formulas for arc current and
incident energy calculations assume a 200 ms arc duration and
use symmetrical fault current.
For the analysis in this paper, no “weight” factor was added
due to asymmetrical current, but it seems possible that faster
clearing times (< 100 ms) might increase incident energy due
2
to higher dc offset currents. Further study, beyond the scope
of this paper, would be required to analyze this issue.
B. Steps in Calculating Arc-Flash Energy and Its Effects
1) Collect the System Data and Modes of Operation
In short, we need an accurate one-line diagram including
system source, line, and transformer impedances. We also
need to know the modes of operation, if additional feeders and
generators may be in service, and how this impacts fault
currents and trip times. The goal is to establish the conditions
that produce the maximum fault currents.
2) Determine the Bolted Fault Currents
Next, we calculate the maximum three-phase fault current
based on short-circuit programs, fault studies, or the method
shown in Section IV.
3) Determine the Arc-Fault Currents
The arc-fault current is typically slightly less than bolted-
fault current due to arc impedance.
4) Determine the Protective Relay/Device Operate Times
One subtle aspect of calculating arc-flash incident energy is
that a lower fault current (e.g., further downstream fault) may
not decrease the energy if the protection used is an inverse
time-current characteristic (fuse or 51 device). The lower fault
current could (and often does) result in increased energy
because of the increased trip times. So, the incident energy
analysis is typically performed at 100% and 85% of maximum
arcing current.
Also, if no intentional time delay is used, the operate time
for “instantaneous” relaying is still taken into account. Thus
we must always consider breaker operate times.
5) Document System Voltages, Equipment Class, and
Working Distances
IEEE 1584-2002 includes tables that provide the typical
bus gaps and working distances for 15 kV, 5 kV, and low-
voltage switchgear, low-voltage motor control centers, panel
boards, and cable.
6) Determine the Incident Energy
Use one of the methods discussed earlier to calculate
incident energy. IEEE 1584-2002 includes the equations and
reference spreadsheets that can be used for this task.
7) Determine the Flash-Protection Boundary
Based on the incident energy, a flash boundary can be
calculated.
C. How Arc-Flash Energy Affects Personal Protective
Equipment (PPE)
NFPA 70E defines five levels of arc hazard. Table I shows
the hazard/risk category levels and the calculated incident
energy at the working distance. The table lists typical clothing
and layer counts for the torso. In short, this is the level of
clothing that should be worn to limit incident energy damage
to a second-degree burn. Put another way, this guide is
designed to protect the worker from heat to prevent a second-
degree burn.
TABLE I
PERSONAL PROTECTIVE EQUIPMENT (PPE) TO LIMIT BURNS
Hazard/Risk
Category
Clothing Description
(Typical clothing layers in
parentheses)
Requiring
Minimum Arc
Rating of PPE
cal/cm2
0 N/A
1
Fire retardant (FR) shirt and pants
or FR coverall (1)
4
2
Cotton undergarments plus FR
shirt and pants (1 or 2)
8
3
Cotton undergarments plus FR
shirt and pants, plus FR coverall,
or plus two FR coveralls (2 or 3)
25
4
Cotton undergarments plus FR
shirt and pants plus multilayer
flash suit (3 or more)
40
[3]
IV. EXAMPLE SYSTEM TO ANALYZE ARC FLASH
A. Steps to Calculate Arc Flash on an Example System
The system shown in Fig. 1 is used to help analyze these
issues.
Utility Utility
MTR
2000/5
2000/5
600/5
600/5
3500 HP
XFMR
4160/480
1.5/2.0 MVA
Z = 8.7%
583 MVA
X/R = 15
583 MVA
X/R = 15
13.8/4.16 kV
10.5/12.5 MVA
Z = 4.1%
4.16 kV
Bus A
4.16 kV
Bus B
2000/5
2400/120
24.7 kA
29 cal/cm2
24 Meter Boundary
Category 4 Protection
Required
2.4 ohms 2.4 ohms
NC NC
NO
Fig. 1. Example System
1) Determine the Bolted Fault Currents
The first step in calculating an arc-flash number is to
calculate the maximum available three-phase fault current.
The utility may give a number based on fault MVA and an
X/R ratio. As shown in (2), the utility has given the available
source fault MVA as 583 and the X/R ratio as 15.
3
To convert this to a percent impedance based on the
transformer MVA and kV, we use (1):
⎟
⎠
⎞
⎜
⎝
⎛
∠
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
= −
•
•
•
R
X
Tan
MVAkV
MVAkV
100Z% 1
u
2
t
t
2
u
(1)
Where:
%Z = Utility impedance in percent based on
transformer base
kVu = Utility voltage base
kVt = Transformer voltage base
MVAu = Utility fault MVA
MVAt = Transformer MVA base
X/R = Utility X/R ratio
The conversion gives the following result:
( )
%8.1j13.0
86@%8.1
15Tan
583•8.13
5.10•8.13
•100Z% 1
2
2
+=
°=
∠⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
= −
(2)
The example shows switchgear and has no cable
impedance to add to the total impedance to the bus. We must
add the transformer impedance, which is listed as 4.1%. If we
assume that the transformer impedance is all inductive, then
the total impedance to the bus is:
%Ztotal = 0.13 + j1.8 + j4.1
= 0.13 + j5.9
= 5.9% @ 89°
To calculate the fault current, we use (3):
totalt
t
f
Z%kV
57735MVA
I
•
•
= (3)
Where:
If = Maximum bus fault current
kVt = Transformer voltage base
MVAt = Transformer MVA base
%Ztotal = Total impedance on transformer base to bus
in percent
The fault current for this example is as follows:
kA7.24
9.516.4
577355.10
If ==
•
•
2) Determine the Arc-Fault Currents
After calculating the maximum three-phase fault current,
we calculate arcing current. The arc-fault current is typically
lower than the bolted-fault current due to the arc impedance.
In this example, the arcing fault current is 23.6 kA.
Equation (4) is used to calculate the arcing current:
bfa LogI983.000402.0LogI •+= (4)
aLogI
a 10I =
Where:
Ibf = Maximum bus fault current in kA
Ia = Maximum arcing current in kA
The arcing current for this example is as follows:
( ) 373.17.24Log983.000402.0LogIa =+= •
kA6.2310I 373.1
a ==
We also want 85% of this value to see how the lower fault
current impacts trip times (which may in fact increase energy).
The 85% value is 20 kA.
3) Determine the Protective Relay/Device Operate Times
The relay coordination for this system is shown in Fig. 2.
The breaker time of five cycles was added to obtain the total
trip time. For the 23.6 kA current, the bus relay trip time is:
0.69 + 5/60 = 0.77 s
For the 20.0 kA current, the bus relay trip time is:
0.88 + 5/60 = 0.96 s
4) Document the System Voltages, Equipment Class, and
Working Distances
IEEE 1584-2002 includes tables that provide typical bus
gaps and working distances for 15 kV, 5 kV, and low-voltage
switchgear, low-voltage motor control centers, panel boards,
and cable. Also included are spreadsheets, which perform
calculations based on selected parameters.
For 5 kV switchgear, the gap between conductors is
assumed to be 102 mm and the working distance is assumed to
be 910 mm. Other factors, like the configuration of the
switchgear, cable, or box, and the system grounding, are taken
into account.
5) Determine the Incident Energy
The empirically-derived model presented in IEEE 1584
provides two equations to calculate the incident arc-flash
energy. The first is the normalized incident energy. The
second is the incident energy with specific parameters.
The normalized incident energy assumes a “typical
working distance” of 610 mm and an arc duration of 0.2 s. The
equation for this example is:
G0011.0LogI081.1KKLogE a21n •• +++= (5)
nLogE
n 10E =
Where:
En = Normalized incident energy in J/cm2
K1 = –0.555 for a box configuration
K2 = 0.0 for a resistance-grounded system
Ia = Maximum arcing current in kA
G = Gap between conductors = 102 mm
Thus the normalized incident energy for the 23.6 kA arc
current in this example is as follows:
( ) 0413.11020011.06.23Log081.1555.0LogEn =++−= ••
20413.1
n cm/J1110E ==
4
Time Current Curves
0.10
1.00
10.00
100.00
1000.00
10000.00
100 1000 10000 100000
Current (Amps Primary)
Time(Seconds)
MTR
RELAY
TIE RELAY
START
CURVE
BUS
RELAY
Fig. 2. Example System Relay Coordination
The normalized incident energy for the 20 kA arc current in
this example is as follows:
( ) 9636.01020011.020Log081.1555.0LogEn =++−= ••
29636.0
n cm/J2.910E ==
Next, we vary the parameters to calculate incident energy
for our specific example system. For 5 kV switchgear, we use
a working distance of 910 mm and then we calculate incident
energy for different operate times (0.77 s and 0.96 s):
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= •••• x
x
nf
D
610
2.0
t
EC184.4E (6)
Where:
E = Incident energy in J/cm2
En = Normalized incident energy in J/cm2
Cf = 1.0 for voltages above 1.0 kV
t = Arcing time in seconds
D = Distance from the possible arc point = 910 mm
x = Distance exponent = 0.973 for 5.0 kV switchgear
For this system, the incident energy is:
kA6.23@cm/J120
910
610
2.0
77.0
110.1184.4E 2
973.0
973.0
=⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= ••••
kA0.20@cm/J125
910
610
2.0
96.0
2.90.1184.4E 2
973.0
973.0
=⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= ••••
Note the 85% current actually has more incident energy
due to the longer trip time delay from the bus relay.
Next, we convert the arc energy into cal/cm2
using the
conversion:
5.0 J/cm2
= 1.2 cal/cm2
Thus the arc-flash energy at the bus is:
kA6.23@cm/cal29
5
2.1
120E 2
== •
6) Determine the Flash-Protection Boundary
The flash boundary is calculated from (7):
x
1
b
x
nfb
E
610
2.0
t
EC184.4D
⎥
⎥
⎦
⎤
⎢
⎢
⎣
⎡
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= •••• (7)
Where:
Eb = Incident energy at the boundary in J/cm2
= 5.0
for bare skin
Cf = 1.0 for voltages above 1.0 kV
t = Arcing time in s
Db = Distance of the boundary from the arcing point in
mm
x = Distance exponent = 0.973 for 5.0 kV switchgear
En = Normalized incident energy in J/cm2
For this system, the flash boundary is:
meters24mm23867
5
610
2.0
77.0
110.1184.4D
973.0
1
973.0
b ==
⎥
⎥
⎦
⎤
⎢
⎢
⎣
⎡
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
•⎟
⎠
⎞
⎜
⎝
⎛
•••=
This indicates that within 24 meters of the arc flash, any
unprotected person could sustain second-degree burns from
the fault incident energy. From this we also see that a worker
must use Level 4 PPE to perform live work on this switchgear.
5
V. WHAT CAN BE DONE TO REDUCE ARC FLASH
Nearly all distribution, utility or industrial, uses fuse and/or
time-overcurrent protection. Using common practices and
coordination techniques, trip times are higher closest to the
source transformer or switchgear. In short, the hazard is the
greatest where personnel are most likely to be in or near the
switchgear.
As discussed earlier, the energy produced by an arc-flash
event is proportional to Energy = V•I•t. By performing arc-
flash analysis on each system, it is often possible to reduce
time-coordination intervals to achieve lower trip times and
thus, lower incident energy.
A. Nonrelaying Approaches
On low-voltage systems (<600 V), some users apply
current-limiting fuses. Current-limiting fuses are designed to
operate rapidly so that the current never reaches its bolted
short-circuit level. As a result, it is more difficult to calculate
incident energy, but significant testing has been performed to
obtain arc-flash data [1] [5].
Other ways to reduce arc flash include applying faster
breakers or designing “arc-resistant” switchgear such that arc
blast goes upward or away from personnel should a fault
occur. In addition, research and development is being
performed to use light-sensing technology to detect arcs.
B. Relaying Approaches
1) Reduce Coordination Intervals of Existing Time-
Overcurrent Relays
Fig. 3 shows a typical coordination of feeder relays. Most
engineers and many software programs use a 0.3-s minimum
coordination interval (CI) between tripping characteristics of
series-overcurrent devices. If coordination intervals are longer
than 0.3 s, tightening up these settings is a direct and simple
way of reducing tripping times. We do not recommend a margin
less than 0.3 s, unless very specific testing and analysis is
performed.
Note that setting an instantaneous overcurrent at B is
desired (80% reach or 125% of maximum fault current at A),
but coordination is not possible if there is no difference in the
fault current at A and B.
Fig. 4 shows fault current and relay-operate times based on
fault location. We can see that fault current is highest at the
source. If the distance between coordinating devices is low,
the effect is that the “delta Ts” continue to add. Thus, we end
up with the highest fault currents and longest trip times closest
to the source, where personnel are most likely to be working.
T
T
Distance
Distance
T
I
T T
Fig. 4. Fault Current and Operate Time as a Function of Electrical Distance
From Source
Thus, we can attempt to improve coordination, which has
the advantages of using existing relays and no electrical
design changes. The disadvantages are the cost of the
coordination study and only a small decrease in trip time may
be achieved.
2) High-Impedance Bus Differential Protection
Dedicated CTs are required for this scheme because all of
the CT inputs are paralleled and then connected to a high-
impedance input in the relay. The relay measures the voltage
across its internal impedance—typically about 2000 ohms.
80%
50
51
50
51
B
A
t
I(B)
(A)
t(B)
t(A)
CI
t
I
B
A
(B)
(A)
t(B)
t(A)
CI
Ipui (A)
t(B)
t(A)
CI
Ipui
Transformer Damage
Select Relay B
Instantaneous Pickup,
if possible
Use this current for coordination
“A” is the downstream
relay having longest time
delay and instantaneous
element
Fig. 3. Time Current Coordination
6
The relay is set such that, for the external fault, the voltage
measured across the impedance is less than the pickup, and the
internal fault is above the pickup.
This scheme is fast and secure but very costly because of
the need for the dedicated CTs and the additional wiring and
testing required to validate the scheme.
87Z
0 V
80 V
400 V
2000 V
Pickup
Fig. 5. High-Impedance Bus Differential Scheme
3) Low-Impedance Bus Differential
A low-impedance bus differential scheme is fast and secure
and does not require dedicated CTs (i.e., additional relays,
meters, transducers, etc., can be connected to the same set of
CTs).
Relay settings are typically slightly more complex than a
high-impedance differential scheme because each input has an
independent CT ratio and connection. Like the high-
impedance scheme, this scheme requires some additional
commissioning testing.
87
Fig. 6. Low-Impedance Bus Differential
4) Fast Bus Trip Schemes Using Overcurrent Relays and
Communications
Scheme operation:
• Feeder relays send “block” signal to low-side main
breaker for feeder faults.
• Main breaker set to trip with short (2- to 3-cycle)
delay to allow time to receive block signal.
• Maintains sensitivity and security even when CTs
approach saturation.
• Can be applied with nondirectional or directional
overcurrent elements.
Prot. Logic
Processor
Digital Communications
50
50
50
50
50
50/62
Fig. 7. Fast Bus Trip Scheme
One consideration is that if a fault occurs in one of the
feeder breakers, the feeder relay on the faulted line would
block the fast-tripping element. Thus the scheme would
perceive this as a feeder fault and block the fast-trip scheme. If
we take no other measures, time-delayed tripping would
occur.
5) Enable Instantaneous Element During Maintenance
Perhaps the best and simplest solution is to apply a control
solution, whereby, operators enable an instantaneous element
whenever live work is being performed. It would require
adding a control switch or pushbutton, cabling, and associated
logic. This could be added to new or old installations for a
relatively low cost.
Like any lock-out tag-out procedure, this could be added to
operations and maintenance plans for switchgear or electrical
equipment. Just as workers are expected to wear hard-hats and
safety goggles, they would be required to enable fast tripping
on the bus relays.
During maintenance periods, there is a risk of over-tripping,
but statistically, it is a small risk. For example, if we assume
that 80 hours per year of live work is performed, the probability
of overtripping during maintenance is 80/(24•365) = 0.91% per
year. This seems to be a small risk when considering the safety
of personnel.
On many systems, especially at industrial facilities, high-
fault currents, low-ratio CTs, and high-system X/R ratios con-
spire to CT saturation during faults with dc offset current.
Microprocessor relays typically use analog and digital
filtering to obtain phasors that eliminate dc and harmonic
components. This is superior for most applications, but the
ideal filter for an instantaneous overcurrent element must also
detect bipolar peaks for high current faults during extreme CT
saturation. Thus it is important to apply overcurrent elements
that respond to the fundamental in the absence of saturation
but respond to peak currents during saturation [4].
7
TABLE II
SUMMARY OF SCHEME ADVANTAGES AND DISADVANTAGES
TO REDUCE ARC-FLASH HAZARD
Scheme
Number
Protection
Scheme
Description
Advantages Disadvantages
1
Reduce
coordination
intervals of
existing time-
overcurrent
relays
Existing hardware,
existing technology.
Cost of coordination
study, trip times are
still likely to be high
(0.5–2 s, depending
on coordination
issues), only marginal
improvement can be
achieved.
2
High-
impedance
bus
differential
Fast (less than 1.5
cycles) and secure for
any fault type, easy to
set.
Requires additional
relay, dedicated CTs,
$$$$$ to purchase
CTs, wiring
installation. Testing
more complex.
3
Low-
impedance
bus
differential
Fast (less than 1.5
cycles) and secure for
any fault type.
Requires additional
relays, $$$$ to wire
CTs. Settings, testing
more complex.
4 Fast bus trip
Use of existing main
and feeder overcurrent
relays. Faster than
TOC (typically 3–5
cycles), secure,
communications
channel monitors
integrity of scheme.
Relatively low cost to
install fiber and
transceivers.
Settings more
complex. CTs on bus
side of breaker would
result in delayed
tripping for faults in
the feeder breaker.
5
Enable
instantaneous
overcurrent
protection
during
maintenance
Use of existing main
and feeder overcurrent
relays. Fast (less than
1.5 cycles). Low cost
to install control
switch, wiring.
Lose selectivity
during maintenance
periods, could over
trip. Introduces
change in
maintenance
procedures.
C. Arc-Flash Recalculation
When Schemes 4 and 5 from Table II are implemented,
significant reduction in arc-flash energy is observed.
1) Incident Energy Recalculation for Fast Bus Trip
(Scheme 4)
For the 23.6 kA current, the bus relay trip time is:
5/60 + 5/60 = 0.17 s
The breaker time of five cycles was added to obtain the
total trip time.
For this system, the new incident energy is:
kA6.23@cm/J5.26
910
610
2.0
17.0
110.1184.4E 2
973.0
973.0
=⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= ••••
It is desired to convert the arc energy into cal/cm2
using the
conversion:
22
cm/cal2.1cm/J0.5 =
Thus the new arc-flash energy at the bus is:
kA6.23@cm/cal4.6
5
2.1
5.26E 2
== •
For this system, the new flash boundary is:
meters1.5mm5053
5
610
2.0
17.0
110.1184.4D
973.0
1
973.0
b ==
⎥
⎥
⎦
⎤
⎢
⎢
⎣
⎡
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
•⎟
⎠
⎞
⎜
⎝
⎛
•••=
2) Incident Energy Recalculation With Instantaneous Trip
Element (Scheme 5) Enabled
For the 23.6 kA current, the feeder relay trip time is:
2/60 + 5/60 = 0.12 s
The breaker time of five cycles was added to obtain the
total trip time.
For this system, the new incident energy is:
kA6.23@cm/J7.18
910
610
2.0
12.0
110.1184.4E 2
973.0
973.0
=⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= ••••
It is desired to convert the arc energy into cal/cm2
using the
conversion:
22
cm/cal2.1cm/J0.5 =
Thus the new arc-flash energy at the bus is:
kA6.23@cm/cal5.4
5
2.1
7.18E 2
=•=
For this system, the new flash boundary is:
meters5.3mm3532
5
610
2.0
12.0
110.1184.4D
973.0
1
973.0
b ==
⎥
⎥
⎦
⎤
⎢
⎢
⎣
⎡
⎟
⎟
⎠
⎞
⎜
⎜
⎝
⎛
⎟
⎠
⎞
⎜
⎝
⎛
= ••••
3) Benefits of Reducing Trip Times on Example System
We can see from the data that applying faster tripping has
reduced the arc-flash incident energy significantly. For either
a fast bus trip scheme, adding instantaneous elements, or
combining schemes, we now require Level 2 PPE (compared
to Level 4), and flash boundary distances are about 5 meters or
less (compared to 24).
VI. CONCLUSIONS
An arc-flash event occurs whenever a fault occurs. The
attention given to the safety of personnel continues to
increase. Conducting arc-flash studies allows engineers to
determine personal protective equipment required and flash
boundaries.
Implementing protection schemes to reduce trip times
increases safety and could reduce injuries or even save lives.
Differential schemes can be, and often are, applied on
distribution buses. However, they are much more expensive to
install and test.
Protective systems already require overcurrent protection
on feeder and bus breakers. The incremental cost of adding
communications equipment and relay logic is small and
benefits are great. On new installations and protection
upgrades, always apply fast-tripping solutions.
On new and existing systems, consider adding controls to
enable instantaneous tripping when personnel are in close
8
proximity to energized equipment. The cost of implementation
is small compared to the benefits of reduced trip times and
reduced arc-flash hazards.
If a maintenance procedure can require a worker to wear
safety goggles and a hard hat, or to place a warning tag on
energized equipment, then it seems logical that a pushbutton
or control switch to enable instantaneous tripping can be
added as well.
Finally, whenever possible, use secure wireless
communications to operate devices from a safe distance.
VII. REFERENCES
[1] IEEE Standard 1584-2002, IEEE Guide for Performing Arc-Flash
Hazard Calculations.
[2] NFPA 70E, Standard for Electrical Safety in the Workplace, 2004
Edition.
[3] NFPA 70E, Standard for Electrical Safety in the Workplace, Table
130.7(C)(11), 2004 Edition.
[4] G. Benmouyal and S.E. Zocholl, “The Impact of High Fault Current and
CT Rating Limits on Overcurrent Protection,” 29th Annual Western
Protective Relay Conference, Spokane, WA, October 22–24, 2002.
[5] W. A. Brown and R. Shapiro, “A Comparison of Arc-Flash Incident
Energy Reduction Techniques Using Low-Voltage Power Circuit
Breakers,” 1-4244-0336-7/06, ©2006 IEEE.
VIII. BIOGRAPHIES
Jim Buff received a B.S. degree in Electrical Engineering from the University
of Missouri-Rolla in 1986. He currently holds a registered PE license in the
state of Missouri. Before joining Schweitzer Engineering Laboratories, Inc.,
in 1999, Jim worked in the utility industry for 13 years setting and testing
power plant and substation protective relays. Jim has experience with
generator and motor protective relaying. Jim is a field application engineer
located in Valparaiso, Indiana.
Karl Zimmerman is a Senior Application Engineer with Schweitzer Engi-
neering Laboratories, Inc., in Belleville, Illinois. His work includes providing
application support and technical training for protective relay users.
He is an active member of the IEEE Power System Relaying Committee and
is the Chairman of the Working Group on Arc-Flash Protection. Karl received
his BSEE degree at the University of Illinois at Urbana-Champaign and has
over 20 years of experience in the area of system protection. He is a past
speaker at many technical conferences and has authored over 20 papers and
application guides on protective relaying.
Previously presented at the 2007 Texas A&M Conference for Protective
Relay Engineers and 2007 Pulp and Paper Industry Technical Conference.
© 2007 IEEE – All rights reserved.
20070214 • TP6250-01

More Related Content

What's hot

IRJET- VHF Antenna for Fire Station
IRJET- VHF Antenna for Fire StationIRJET- VHF Antenna for Fire Station
IRJET- VHF Antenna for Fire StationIRJET Journal
 
Genetic algorithm approach into relay co ordination
Genetic algorithm approach into relay co ordinationGenetic algorithm approach into relay co ordination
Genetic algorithm approach into relay co ordinationIAEME Publication
 
Fpga versus dsp for wavelet transform based voltage sags detection
Fpga versus dsp for wavelet transform based voltage sags detectionFpga versus dsp for wavelet transform based voltage sags detection
Fpga versus dsp for wavelet transform based voltage sags detectionCecilio Martins
 
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...IRJET Journal
 
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...Power System Operation
 
Power quality improvement techniques
Power quality improvement techniquesPower quality improvement techniques
Power quality improvement techniquessahid raja khan
 
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...John Bickel
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...IRJET Journal
 
Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonGilberto Mejía
 
Safety in non-residential electrical installations
Safety in non-residential electrical installationsSafety in non-residential electrical installations
Safety in non-residential electrical installationsBruno De Wachter
 
Application of crowbar protection on dfig based wind turbine connected to grid-2
Application of crowbar protection on dfig based wind turbine connected to grid-2Application of crowbar protection on dfig based wind turbine connected to grid-2
Application of crowbar protection on dfig based wind turbine connected to grid-2IAEME Publication
 
Transient overvoltages and currents: lightning surges
Transient overvoltages and currents: lightning surgesTransient overvoltages and currents: lightning surges
Transient overvoltages and currents: lightning surgesBruno De Wachter
 
Nuisance tripping of circuit breakers
Nuisance tripping of circuit breakersNuisance tripping of circuit breakers
Nuisance tripping of circuit breakersLeonardo ENERGY
 

What's hot (20)

RAMS Tech Paper
RAMS Tech PaperRAMS Tech Paper
RAMS Tech Paper
 
IRJET- VHF Antenna for Fire Station
IRJET- VHF Antenna for Fire StationIRJET- VHF Antenna for Fire Station
IRJET- VHF Antenna for Fire Station
 
Genetic algorithm approach into relay co ordination
Genetic algorithm approach into relay co ordinationGenetic algorithm approach into relay co ordination
Genetic algorithm approach into relay co ordination
 
Fpga versus dsp for wavelet transform based voltage sags detection
Fpga versus dsp for wavelet transform based voltage sags detectionFpga versus dsp for wavelet transform based voltage sags detection
Fpga versus dsp for wavelet transform based voltage sags detection
 
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...
Optimal Overcurrent Relay Coordination using GA, FFA, CSA Techniques and Comp...
 
Hv sytem overvolatge
Hv sytem overvolatge Hv sytem overvolatge
Hv sytem overvolatge
 
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...
A Novel Back Up Wide Area Protection Technique for Power Transmission Grids U...
 
Power quality improvement techniques
Power quality improvement techniquesPower quality improvement techniques
Power quality improvement techniques
 
2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removi...
2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removi...2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removi...
2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removi...
 
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...Defense In Depth Of Electrical Systems   Preliminary Findings And Recommendat...
Defense In Depth Of Electrical Systems Preliminary Findings And Recommendat...
 
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
Double Circuit Transmission Line Protection using Line Trap & Artificial Neur...
 
Modeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenonModeling and analysis of power transformers under ferroresonance phenomenon
Modeling and analysis of power transformers under ferroresonance phenomenon
 
FPGA IMPLEMENTATION OF APPROXIMATE SOFTMAX FUNCTION FOR EFFICIENT CNN INFERENCE
FPGA IMPLEMENTATION OF APPROXIMATE SOFTMAX FUNCTION FOR EFFICIENT CNN INFERENCEFPGA IMPLEMENTATION OF APPROXIMATE SOFTMAX FUNCTION FOR EFFICIENT CNN INFERENCE
FPGA IMPLEMENTATION OF APPROXIMATE SOFTMAX FUNCTION FOR EFFICIENT CNN INFERENCE
 
Safety in non-residential electrical installations
Safety in non-residential electrical installationsSafety in non-residential electrical installations
Safety in non-residential electrical installations
 
Very-Short Term Wind Power Forecasting through Wavelet Based ANFIS
Very-Short Term Wind Power Forecasting through Wavelet Based ANFISVery-Short Term Wind Power Forecasting through Wavelet Based ANFIS
Very-Short Term Wind Power Forecasting through Wavelet Based ANFIS
 
Application of crowbar protection on dfig based wind turbine connected to grid-2
Application of crowbar protection on dfig based wind turbine connected to grid-2Application of crowbar protection on dfig based wind turbine connected to grid-2
Application of crowbar protection on dfig based wind turbine connected to grid-2
 
fault
faultfault
fault
 
Transient overvoltages and currents: lightning surges
Transient overvoltages and currents: lightning surgesTransient overvoltages and currents: lightning surges
Transient overvoltages and currents: lightning surges
 
Nuisance tripping of circuit breakers
Nuisance tripping of circuit breakersNuisance tripping of circuit breakers
Nuisance tripping of circuit breakers
 
IJET-V3I2P17
IJET-V3I2P17IJET-V3I2P17
IJET-V3I2P17
 

Similar to 6250 application existing_jb-kz_20070214_web

IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...
IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...
IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...IRJET Journal
 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectioAminu Bugaje
 
Arc flash application guide
Arc flash application guideArc flash application guide
Arc flash application guideSouvik Dutta
 
Review on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power TransformerReview on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power TransformerIRJET Journal
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardIJAPEJOURNAL
 
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...iosrjce
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsPower System Operation
 
Transfguide transformer protection application guide
Transfguide transformer protection application guideTransfguide transformer protection application guide
Transfguide transformer protection application guidePrasad RVS
 
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...IRJET Journal
 
Recent Trends InDigital Differential Protection of Power Transformer
Recent Trends InDigital Differential Protection of Power TransformerRecent Trends InDigital Differential Protection of Power Transformer
Recent Trends InDigital Differential Protection of Power Transformerijiert bestjournal
 
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfAzizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfSultanAlSaiari1
 
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...IRJET Journal
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET Journal
 
Fuzzy Logic-Based Fault Classification for Transmission Line Analysis
Fuzzy Logic-Based Fault Classification for Transmission Line AnalysisFuzzy Logic-Based Fault Classification for Transmission Line Analysis
Fuzzy Logic-Based Fault Classification for Transmission Line AnalysisIRJET Journal
 
Area of vulnerabilty
Area of vulnerabiltyArea of vulnerabilty
Area of vulnerabiltyPrasadVJ
 

Similar to 6250 application existing_jb-kz_20070214_web (20)

IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...
IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...
IRJET- Review: Different Techniques for ARC Flash and Fault Analysis and Clas...
 
Microcontroller based transformer protectio
Microcontroller based transformer protectioMicrocontroller based transformer protectio
Microcontroller based transformer protectio
 
Pe3426652670
Pe3426652670Pe3426652670
Pe3426652670
 
Arc flash application guide
Arc flash application guideArc flash application guide
Arc flash application guide
 
Review on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power TransformerReview on Different Techniques for Differential Protection of Power Transformer
Review on Different Techniques for Differential Protection of Power Transformer
 
Remediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazardRemediation of Old Substations for Arc Flash hazard
Remediation of Old Substations for Arc Flash hazard
 
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...
An adaptive protection scheme to prevent recloser-fuse miscoordination in dis...
 
D010622334
D010622334D010622334
D010622334
 
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service SystemsLessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
Lessons Learned of AC Arc Flash Studies for Station Auxiliary Service Systems
 
Transformer guide
Transformer guideTransformer guide
Transformer guide
 
Transfguide transformer protection application guide
Transfguide transformer protection application guideTransfguide transformer protection application guide
Transfguide transformer protection application guide
 
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...
IRJET- Power Quality Improvement by using Three Phase Adaptive Filter Control...
 
Recent Trends InDigital Differential Protection of Power Transformer
Recent Trends InDigital Differential Protection of Power TransformerRecent Trends InDigital Differential Protection of Power Transformer
Recent Trends InDigital Differential Protection of Power Transformer
 
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdfAzizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
Azizan_2020_IOP_Conf._Ser.__Mater._Sci._Eng._767_012004.pdf
 
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
Arc Fault and Flash Signal Analysis and Detection in DC Distribution Systems ...
 
H044023944
H044023944H044023944
H044023944
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
 
Fuzzy Logic-Based Fault Classification for Transmission Line Analysis
Fuzzy Logic-Based Fault Classification for Transmission Line AnalysisFuzzy Logic-Based Fault Classification for Transmission Line Analysis
Fuzzy Logic-Based Fault Classification for Transmission Line Analysis
 
PQ_surveys_FFF.pdf
PQ_surveys_FFF.pdfPQ_surveys_FFF.pdf
PQ_surveys_FFF.pdf
 
Area of vulnerabilty
Area of vulnerabiltyArea of vulnerabilty
Area of vulnerabilty
 

Recently uploaded

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 

Recently uploaded (20)

247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 

6250 application existing_jb-kz_20070214_web

  • 1. Application of Existing Technologies to Reduce Arc-Flash Hazards Jim Buff and Karl Zimmerman Schweitzer Engineering Laboratories, Inc. Presented at NETA PowerTest New Orleans, Louisiana March 17–20, 2008 Previously presented at the Pulp and Paper Industry Technical Conference, June 2007, 60th Annual Conference for Protective Relay Engineers, March 2007, and 6th Annual Clemson University Power Systems Conference, March 2007 Originally presented at the 33rd Annual Western Protective Relay Conference, October 2006
  • 2. 1 Application of Existing Technologies to Reduce Arc-Flash Hazards Jim Buff and Karl Zimmerman, Schweitzer Engineering Laboratories, Inc. I. INTRODUCTION Protective relay engineers have long been concerned with protecting power systems and all of the equipment associated with those systems. We routinely apply relays to limit damage to apparatus (e.g., transmission and distribution lines, power transformers, buses, generators, motors, etc.) and protect against, or reduce, the impact of electrical disturbances on the larger power system (e.g., shedding load for frequency or voltage variations). Safety for personnel has always been a concern, but in the past several years there is a heightened awareness of the importance of safety around electrical apparatus, as reflected in recent regulations and standards [1] [2]. In particular, industry and utilities alike recognize that arc- flash events can cause dangerous and potentially fatal levels of heat, ultraviolet radiation, blast pressure, flying shrapnel, and deafening sound waves. The existing standards mainly deal with the heat energy from the arc flash. The energy produced by an arc-flash event is proportional to voltage, current, and the duration of the event (V•I•t). Design engineers have a few options to reduce system voltage or fault currents (e.g., grounding practices and application of current- limiting fuses), but the best and most direct ways to reduce arc- flash hazards are to reduce fault-clearing times and use wireless communications to reduce the need for technicians to be in harms way. In most cases, clearing times are reduced via more complete use of microprocessor relays features and other technologies already available. Similarly, digital relay communications and secure wireless communications devices allow engineers and technicians to converse with relays from a safe distance. In this paper, we include some important industry definitions of arc flash and ways of measuring arc-flash hazards. We then examine the use of existing technologies, including digital relays and communications capabilities, to implement reduced trip times using instantaneous overcurrent relays, a fast bus-trip scheme, and differential schemes. We use a typical industrial switchgear lineup as an example of how to implement these schemes. Finally, we quantify the levels to which we can reduce arc-flash energy and its impact on safety. II. DEFINITIONS What is an arc flash? How do we measure the energy so as to quantify improvement? Some important definitions of arc flash and related issues can be found in IEEE 1584-2002, “IEEE Guide for Performing Arc-Flash Hazard Calculations.” Similar definitions are found in NFPA 70E, “Standard for Electrical Safety in the Workplace, 2004 Edition.” Arc-Flash Hazard. A dangerous condition associated with the release of energy caused by an electric arc. Flash Hazard Analysis. A method to determine the risk of personal injury as a result of exposure to incident energy from an electrical arc flash. Flash-Protection Boundary. An approach limit at a distance from live parts that are insulated or exposed within which a person could receive a second-degree burn. Working Distance. The dimension between the possible arc point and the head and the body of the worker positioned in place to perform the assigned task [1]. III. MEASURING ARC FLASH AND THE EFFECTS OF ARC FLASH There are several methods for calculating incident energy due to an arc-flash event. These include a table-based method in NFPA 70E-2004, a theory-based model for applications over 15 kV (Lee method), empirically derived models based on a curve-fitting program, and a physical model-based method with some verification testing. Within the last few years, IEEE 1584 was published, and an empirically derived model based on statistical analysis was developed as part of this effort [1]. IEEE 1584 includes several spreadsheets to assist the engineer in arc-flash studies. We will use this method for our analysis in this paper. Incident energy is typically quantified in cal/cm2 or Joules/cm2 . The incident energy determines the personal protective equipment (PPE) required to provide adequate protection based on recommendations in NFPA 70E. Incident energy calculations also provide the basis for the flash- protection boundary. A. Protection Considerations for Arc Flash IEEE 1584-2002 concluded that arc time has a linear effect on incident energy, i.e., reducing fault-clearing times proportionately reduces arc flash. Also, IEEE 1584-2002 states that the system X/R ratio had “little or no effect” on arc current and incident energy and was, thus, neglected. All of the formulas for arc current and incident energy calculations assume a 200 ms arc duration and use symmetrical fault current. For the analysis in this paper, no “weight” factor was added due to asymmetrical current, but it seems possible that faster clearing times (< 100 ms) might increase incident energy due
  • 3. 2 to higher dc offset currents. Further study, beyond the scope of this paper, would be required to analyze this issue. B. Steps in Calculating Arc-Flash Energy and Its Effects 1) Collect the System Data and Modes of Operation In short, we need an accurate one-line diagram including system source, line, and transformer impedances. We also need to know the modes of operation, if additional feeders and generators may be in service, and how this impacts fault currents and trip times. The goal is to establish the conditions that produce the maximum fault currents. 2) Determine the Bolted Fault Currents Next, we calculate the maximum three-phase fault current based on short-circuit programs, fault studies, or the method shown in Section IV. 3) Determine the Arc-Fault Currents The arc-fault current is typically slightly less than bolted- fault current due to arc impedance. 4) Determine the Protective Relay/Device Operate Times One subtle aspect of calculating arc-flash incident energy is that a lower fault current (e.g., further downstream fault) may not decrease the energy if the protection used is an inverse time-current characteristic (fuse or 51 device). The lower fault current could (and often does) result in increased energy because of the increased trip times. So, the incident energy analysis is typically performed at 100% and 85% of maximum arcing current. Also, if no intentional time delay is used, the operate time for “instantaneous” relaying is still taken into account. Thus we must always consider breaker operate times. 5) Document System Voltages, Equipment Class, and Working Distances IEEE 1584-2002 includes tables that provide the typical bus gaps and working distances for 15 kV, 5 kV, and low- voltage switchgear, low-voltage motor control centers, panel boards, and cable. 6) Determine the Incident Energy Use one of the methods discussed earlier to calculate incident energy. IEEE 1584-2002 includes the equations and reference spreadsheets that can be used for this task. 7) Determine the Flash-Protection Boundary Based on the incident energy, a flash boundary can be calculated. C. How Arc-Flash Energy Affects Personal Protective Equipment (PPE) NFPA 70E defines five levels of arc hazard. Table I shows the hazard/risk category levels and the calculated incident energy at the working distance. The table lists typical clothing and layer counts for the torso. In short, this is the level of clothing that should be worn to limit incident energy damage to a second-degree burn. Put another way, this guide is designed to protect the worker from heat to prevent a second- degree burn. TABLE I PERSONAL PROTECTIVE EQUIPMENT (PPE) TO LIMIT BURNS Hazard/Risk Category Clothing Description (Typical clothing layers in parentheses) Requiring Minimum Arc Rating of PPE cal/cm2 0 N/A 1 Fire retardant (FR) shirt and pants or FR coverall (1) 4 2 Cotton undergarments plus FR shirt and pants (1 or 2) 8 3 Cotton undergarments plus FR shirt and pants, plus FR coverall, or plus two FR coveralls (2 or 3) 25 4 Cotton undergarments plus FR shirt and pants plus multilayer flash suit (3 or more) 40 [3] IV. EXAMPLE SYSTEM TO ANALYZE ARC FLASH A. Steps to Calculate Arc Flash on an Example System The system shown in Fig. 1 is used to help analyze these issues. Utility Utility MTR 2000/5 2000/5 600/5 600/5 3500 HP XFMR 4160/480 1.5/2.0 MVA Z = 8.7% 583 MVA X/R = 15 583 MVA X/R = 15 13.8/4.16 kV 10.5/12.5 MVA Z = 4.1% 4.16 kV Bus A 4.16 kV Bus B 2000/5 2400/120 24.7 kA 29 cal/cm2 24 Meter Boundary Category 4 Protection Required 2.4 ohms 2.4 ohms NC NC NO Fig. 1. Example System 1) Determine the Bolted Fault Currents The first step in calculating an arc-flash number is to calculate the maximum available three-phase fault current. The utility may give a number based on fault MVA and an X/R ratio. As shown in (2), the utility has given the available source fault MVA as 583 and the X/R ratio as 15.
  • 4. 3 To convert this to a percent impedance based on the transformer MVA and kV, we use (1): ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ ∠ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ = − • • • R X Tan MVAkV MVAkV 100Z% 1 u 2 t t 2 u (1) Where: %Z = Utility impedance in percent based on transformer base kVu = Utility voltage base kVt = Transformer voltage base MVAu = Utility fault MVA MVAt = Transformer MVA base X/R = Utility X/R ratio The conversion gives the following result: ( ) %8.1j13.0 86@%8.1 15Tan 583•8.13 5.10•8.13 •100Z% 1 2 2 += °= ∠⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ = − (2) The example shows switchgear and has no cable impedance to add to the total impedance to the bus. We must add the transformer impedance, which is listed as 4.1%. If we assume that the transformer impedance is all inductive, then the total impedance to the bus is: %Ztotal = 0.13 + j1.8 + j4.1 = 0.13 + j5.9 = 5.9% @ 89° To calculate the fault current, we use (3): totalt t f Z%kV 57735MVA I • • = (3) Where: If = Maximum bus fault current kVt = Transformer voltage base MVAt = Transformer MVA base %Ztotal = Total impedance on transformer base to bus in percent The fault current for this example is as follows: kA7.24 9.516.4 577355.10 If == • • 2) Determine the Arc-Fault Currents After calculating the maximum three-phase fault current, we calculate arcing current. The arc-fault current is typically lower than the bolted-fault current due to the arc impedance. In this example, the arcing fault current is 23.6 kA. Equation (4) is used to calculate the arcing current: bfa LogI983.000402.0LogI •+= (4) aLogI a 10I = Where: Ibf = Maximum bus fault current in kA Ia = Maximum arcing current in kA The arcing current for this example is as follows: ( ) 373.17.24Log983.000402.0LogIa =+= • kA6.2310I 373.1 a == We also want 85% of this value to see how the lower fault current impacts trip times (which may in fact increase energy). The 85% value is 20 kA. 3) Determine the Protective Relay/Device Operate Times The relay coordination for this system is shown in Fig. 2. The breaker time of five cycles was added to obtain the total trip time. For the 23.6 kA current, the bus relay trip time is: 0.69 + 5/60 = 0.77 s For the 20.0 kA current, the bus relay trip time is: 0.88 + 5/60 = 0.96 s 4) Document the System Voltages, Equipment Class, and Working Distances IEEE 1584-2002 includes tables that provide typical bus gaps and working distances for 15 kV, 5 kV, and low-voltage switchgear, low-voltage motor control centers, panel boards, and cable. Also included are spreadsheets, which perform calculations based on selected parameters. For 5 kV switchgear, the gap between conductors is assumed to be 102 mm and the working distance is assumed to be 910 mm. Other factors, like the configuration of the switchgear, cable, or box, and the system grounding, are taken into account. 5) Determine the Incident Energy The empirically-derived model presented in IEEE 1584 provides two equations to calculate the incident arc-flash energy. The first is the normalized incident energy. The second is the incident energy with specific parameters. The normalized incident energy assumes a “typical working distance” of 610 mm and an arc duration of 0.2 s. The equation for this example is: G0011.0LogI081.1KKLogE a21n •• +++= (5) nLogE n 10E = Where: En = Normalized incident energy in J/cm2 K1 = –0.555 for a box configuration K2 = 0.0 for a resistance-grounded system Ia = Maximum arcing current in kA G = Gap between conductors = 102 mm Thus the normalized incident energy for the 23.6 kA arc current in this example is as follows: ( ) 0413.11020011.06.23Log081.1555.0LogEn =++−= •• 20413.1 n cm/J1110E ==
  • 5. 4 Time Current Curves 0.10 1.00 10.00 100.00 1000.00 10000.00 100 1000 10000 100000 Current (Amps Primary) Time(Seconds) MTR RELAY TIE RELAY START CURVE BUS RELAY Fig. 2. Example System Relay Coordination The normalized incident energy for the 20 kA arc current in this example is as follows: ( ) 9636.01020011.020Log081.1555.0LogEn =++−= •• 29636.0 n cm/J2.910E == Next, we vary the parameters to calculate incident energy for our specific example system. For 5 kV switchgear, we use a working distance of 910 mm and then we calculate incident energy for different operate times (0.77 s and 0.96 s): ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• x x nf D 610 2.0 t EC184.4E (6) Where: E = Incident energy in J/cm2 En = Normalized incident energy in J/cm2 Cf = 1.0 for voltages above 1.0 kV t = Arcing time in seconds D = Distance from the possible arc point = 910 mm x = Distance exponent = 0.973 for 5.0 kV switchgear For this system, the incident energy is: kA6.23@cm/J120 910 610 2.0 77.0 110.1184.4E 2 973.0 973.0 =⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• kA0.20@cm/J125 910 610 2.0 96.0 2.90.1184.4E 2 973.0 973.0 =⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• Note the 85% current actually has more incident energy due to the longer trip time delay from the bus relay. Next, we convert the arc energy into cal/cm2 using the conversion: 5.0 J/cm2 = 1.2 cal/cm2 Thus the arc-flash energy at the bus is: kA6.23@cm/cal29 5 2.1 120E 2 == • 6) Determine the Flash-Protection Boundary The flash boundary is calculated from (7): x 1 b x nfb E 610 2.0 t EC184.4D ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎣ ⎡ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• (7) Where: Eb = Incident energy at the boundary in J/cm2 = 5.0 for bare skin Cf = 1.0 for voltages above 1.0 kV t = Arcing time in s Db = Distance of the boundary from the arcing point in mm x = Distance exponent = 0.973 for 5.0 kV switchgear En = Normalized incident energy in J/cm2 For this system, the flash boundary is: meters24mm23867 5 610 2.0 77.0 110.1184.4D 973.0 1 973.0 b == ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎣ ⎡ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ •⎟ ⎠ ⎞ ⎜ ⎝ ⎛ •••= This indicates that within 24 meters of the arc flash, any unprotected person could sustain second-degree burns from the fault incident energy. From this we also see that a worker must use Level 4 PPE to perform live work on this switchgear.
  • 6. 5 V. WHAT CAN BE DONE TO REDUCE ARC FLASH Nearly all distribution, utility or industrial, uses fuse and/or time-overcurrent protection. Using common practices and coordination techniques, trip times are higher closest to the source transformer or switchgear. In short, the hazard is the greatest where personnel are most likely to be in or near the switchgear. As discussed earlier, the energy produced by an arc-flash event is proportional to Energy = V•I•t. By performing arc- flash analysis on each system, it is often possible to reduce time-coordination intervals to achieve lower trip times and thus, lower incident energy. A. Nonrelaying Approaches On low-voltage systems (<600 V), some users apply current-limiting fuses. Current-limiting fuses are designed to operate rapidly so that the current never reaches its bolted short-circuit level. As a result, it is more difficult to calculate incident energy, but significant testing has been performed to obtain arc-flash data [1] [5]. Other ways to reduce arc flash include applying faster breakers or designing “arc-resistant” switchgear such that arc blast goes upward or away from personnel should a fault occur. In addition, research and development is being performed to use light-sensing technology to detect arcs. B. Relaying Approaches 1) Reduce Coordination Intervals of Existing Time- Overcurrent Relays Fig. 3 shows a typical coordination of feeder relays. Most engineers and many software programs use a 0.3-s minimum coordination interval (CI) between tripping characteristics of series-overcurrent devices. If coordination intervals are longer than 0.3 s, tightening up these settings is a direct and simple way of reducing tripping times. We do not recommend a margin less than 0.3 s, unless very specific testing and analysis is performed. Note that setting an instantaneous overcurrent at B is desired (80% reach or 125% of maximum fault current at A), but coordination is not possible if there is no difference in the fault current at A and B. Fig. 4 shows fault current and relay-operate times based on fault location. We can see that fault current is highest at the source. If the distance between coordinating devices is low, the effect is that the “delta Ts” continue to add. Thus, we end up with the highest fault currents and longest trip times closest to the source, where personnel are most likely to be working. T T Distance Distance T I T T Fig. 4. Fault Current and Operate Time as a Function of Electrical Distance From Source Thus, we can attempt to improve coordination, which has the advantages of using existing relays and no electrical design changes. The disadvantages are the cost of the coordination study and only a small decrease in trip time may be achieved. 2) High-Impedance Bus Differential Protection Dedicated CTs are required for this scheme because all of the CT inputs are paralleled and then connected to a high- impedance input in the relay. The relay measures the voltage across its internal impedance—typically about 2000 ohms. 80% 50 51 50 51 B A t I(B) (A) t(B) t(A) CI t I B A (B) (A) t(B) t(A) CI Ipui (A) t(B) t(A) CI Ipui Transformer Damage Select Relay B Instantaneous Pickup, if possible Use this current for coordination “A” is the downstream relay having longest time delay and instantaneous element Fig. 3. Time Current Coordination
  • 7. 6 The relay is set such that, for the external fault, the voltage measured across the impedance is less than the pickup, and the internal fault is above the pickup. This scheme is fast and secure but very costly because of the need for the dedicated CTs and the additional wiring and testing required to validate the scheme. 87Z 0 V 80 V 400 V 2000 V Pickup Fig. 5. High-Impedance Bus Differential Scheme 3) Low-Impedance Bus Differential A low-impedance bus differential scheme is fast and secure and does not require dedicated CTs (i.e., additional relays, meters, transducers, etc., can be connected to the same set of CTs). Relay settings are typically slightly more complex than a high-impedance differential scheme because each input has an independent CT ratio and connection. Like the high- impedance scheme, this scheme requires some additional commissioning testing. 87 Fig. 6. Low-Impedance Bus Differential 4) Fast Bus Trip Schemes Using Overcurrent Relays and Communications Scheme operation: • Feeder relays send “block” signal to low-side main breaker for feeder faults. • Main breaker set to trip with short (2- to 3-cycle) delay to allow time to receive block signal. • Maintains sensitivity and security even when CTs approach saturation. • Can be applied with nondirectional or directional overcurrent elements. Prot. Logic Processor Digital Communications 50 50 50 50 50 50/62 Fig. 7. Fast Bus Trip Scheme One consideration is that if a fault occurs in one of the feeder breakers, the feeder relay on the faulted line would block the fast-tripping element. Thus the scheme would perceive this as a feeder fault and block the fast-trip scheme. If we take no other measures, time-delayed tripping would occur. 5) Enable Instantaneous Element During Maintenance Perhaps the best and simplest solution is to apply a control solution, whereby, operators enable an instantaneous element whenever live work is being performed. It would require adding a control switch or pushbutton, cabling, and associated logic. This could be added to new or old installations for a relatively low cost. Like any lock-out tag-out procedure, this could be added to operations and maintenance plans for switchgear or electrical equipment. Just as workers are expected to wear hard-hats and safety goggles, they would be required to enable fast tripping on the bus relays. During maintenance periods, there is a risk of over-tripping, but statistically, it is a small risk. For example, if we assume that 80 hours per year of live work is performed, the probability of overtripping during maintenance is 80/(24•365) = 0.91% per year. This seems to be a small risk when considering the safety of personnel. On many systems, especially at industrial facilities, high- fault currents, low-ratio CTs, and high-system X/R ratios con- spire to CT saturation during faults with dc offset current. Microprocessor relays typically use analog and digital filtering to obtain phasors that eliminate dc and harmonic components. This is superior for most applications, but the ideal filter for an instantaneous overcurrent element must also detect bipolar peaks for high current faults during extreme CT saturation. Thus it is important to apply overcurrent elements that respond to the fundamental in the absence of saturation but respond to peak currents during saturation [4].
  • 8. 7 TABLE II SUMMARY OF SCHEME ADVANTAGES AND DISADVANTAGES TO REDUCE ARC-FLASH HAZARD Scheme Number Protection Scheme Description Advantages Disadvantages 1 Reduce coordination intervals of existing time- overcurrent relays Existing hardware, existing technology. Cost of coordination study, trip times are still likely to be high (0.5–2 s, depending on coordination issues), only marginal improvement can be achieved. 2 High- impedance bus differential Fast (less than 1.5 cycles) and secure for any fault type, easy to set. Requires additional relay, dedicated CTs, $$$$$ to purchase CTs, wiring installation. Testing more complex. 3 Low- impedance bus differential Fast (less than 1.5 cycles) and secure for any fault type. Requires additional relays, $$$$ to wire CTs. Settings, testing more complex. 4 Fast bus trip Use of existing main and feeder overcurrent relays. Faster than TOC (typically 3–5 cycles), secure, communications channel monitors integrity of scheme. Relatively low cost to install fiber and transceivers. Settings more complex. CTs on bus side of breaker would result in delayed tripping for faults in the feeder breaker. 5 Enable instantaneous overcurrent protection during maintenance Use of existing main and feeder overcurrent relays. Fast (less than 1.5 cycles). Low cost to install control switch, wiring. Lose selectivity during maintenance periods, could over trip. Introduces change in maintenance procedures. C. Arc-Flash Recalculation When Schemes 4 and 5 from Table II are implemented, significant reduction in arc-flash energy is observed. 1) Incident Energy Recalculation for Fast Bus Trip (Scheme 4) For the 23.6 kA current, the bus relay trip time is: 5/60 + 5/60 = 0.17 s The breaker time of five cycles was added to obtain the total trip time. For this system, the new incident energy is: kA6.23@cm/J5.26 910 610 2.0 17.0 110.1184.4E 2 973.0 973.0 =⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• It is desired to convert the arc energy into cal/cm2 using the conversion: 22 cm/cal2.1cm/J0.5 = Thus the new arc-flash energy at the bus is: kA6.23@cm/cal4.6 5 2.1 5.26E 2 == • For this system, the new flash boundary is: meters1.5mm5053 5 610 2.0 17.0 110.1184.4D 973.0 1 973.0 b == ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎣ ⎡ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ •⎟ ⎠ ⎞ ⎜ ⎝ ⎛ •••= 2) Incident Energy Recalculation With Instantaneous Trip Element (Scheme 5) Enabled For the 23.6 kA current, the feeder relay trip time is: 2/60 + 5/60 = 0.12 s The breaker time of five cycles was added to obtain the total trip time. For this system, the new incident energy is: kA6.23@cm/J7.18 910 610 2.0 12.0 110.1184.4E 2 973.0 973.0 =⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• It is desired to convert the arc energy into cal/cm2 using the conversion: 22 cm/cal2.1cm/J0.5 = Thus the new arc-flash energy at the bus is: kA6.23@cm/cal5.4 5 2.1 7.18E 2 =•= For this system, the new flash boundary is: meters5.3mm3532 5 610 2.0 12.0 110.1184.4D 973.0 1 973.0 b == ⎥ ⎥ ⎦ ⎤ ⎢ ⎢ ⎣ ⎡ ⎟ ⎟ ⎠ ⎞ ⎜ ⎜ ⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ = •••• 3) Benefits of Reducing Trip Times on Example System We can see from the data that applying faster tripping has reduced the arc-flash incident energy significantly. For either a fast bus trip scheme, adding instantaneous elements, or combining schemes, we now require Level 2 PPE (compared to Level 4), and flash boundary distances are about 5 meters or less (compared to 24). VI. CONCLUSIONS An arc-flash event occurs whenever a fault occurs. The attention given to the safety of personnel continues to increase. Conducting arc-flash studies allows engineers to determine personal protective equipment required and flash boundaries. Implementing protection schemes to reduce trip times increases safety and could reduce injuries or even save lives. Differential schemes can be, and often are, applied on distribution buses. However, they are much more expensive to install and test. Protective systems already require overcurrent protection on feeder and bus breakers. The incremental cost of adding communications equipment and relay logic is small and benefits are great. On new installations and protection upgrades, always apply fast-tripping solutions. On new and existing systems, consider adding controls to enable instantaneous tripping when personnel are in close
  • 9. 8 proximity to energized equipment. The cost of implementation is small compared to the benefits of reduced trip times and reduced arc-flash hazards. If a maintenance procedure can require a worker to wear safety goggles and a hard hat, or to place a warning tag on energized equipment, then it seems logical that a pushbutton or control switch to enable instantaneous tripping can be added as well. Finally, whenever possible, use secure wireless communications to operate devices from a safe distance. VII. REFERENCES [1] IEEE Standard 1584-2002, IEEE Guide for Performing Arc-Flash Hazard Calculations. [2] NFPA 70E, Standard for Electrical Safety in the Workplace, 2004 Edition. [3] NFPA 70E, Standard for Electrical Safety in the Workplace, Table 130.7(C)(11), 2004 Edition. [4] G. Benmouyal and S.E. Zocholl, “The Impact of High Fault Current and CT Rating Limits on Overcurrent Protection,” 29th Annual Western Protective Relay Conference, Spokane, WA, October 22–24, 2002. [5] W. A. Brown and R. Shapiro, “A Comparison of Arc-Flash Incident Energy Reduction Techniques Using Low-Voltage Power Circuit Breakers,” 1-4244-0336-7/06, ©2006 IEEE. VIII. BIOGRAPHIES Jim Buff received a B.S. degree in Electrical Engineering from the University of Missouri-Rolla in 1986. He currently holds a registered PE license in the state of Missouri. Before joining Schweitzer Engineering Laboratories, Inc., in 1999, Jim worked in the utility industry for 13 years setting and testing power plant and substation protective relays. Jim has experience with generator and motor protective relaying. Jim is a field application engineer located in Valparaiso, Indiana. Karl Zimmerman is a Senior Application Engineer with Schweitzer Engi- neering Laboratories, Inc., in Belleville, Illinois. His work includes providing application support and technical training for protective relay users. He is an active member of the IEEE Power System Relaying Committee and is the Chairman of the Working Group on Arc-Flash Protection. Karl received his BSEE degree at the University of Illinois at Urbana-Champaign and has over 20 years of experience in the area of system protection. He is a past speaker at many technical conferences and has authored over 20 papers and application guides on protective relaying. Previously presented at the 2007 Texas A&M Conference for Protective Relay Engineers and 2007 Pulp and Paper Industry Technical Conference. © 2007 IEEE – All rights reserved. 20070214 • TP6250-01