Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are managing a project to develop a new robot for a mining rescue company. You are currently
performing a monitoring and controlling project activity, and you have discovered that some of the project
work has not been performed according to the plan. If these issues are not fixed before the next customer
inspection, your project might be canceled. You have analyzed the situation, and the corrective action will
only require a minor adjustment to a configuration element. What should you do first?
A. Implement the corrective actions
B. Submit a change request
C. Consult the project sponsor
D.Delay the scheduled customer inspection
HINT: What is the proper change control procedure when an adjustment to a configuration element is
required?
Question
3. The correct answer B
All of the available answers seem like possible options in this scenario, but the question is
specifically asking what you should do 'first'. Although you have already analyzed the situation
and you know what corrective actions are required, you must follow the proper change control
procedure. A configuration element is a project artifact that has been placed under configuration
control. Any change to a configuration element should be formally controlled and will require a
change request. Since the question describes a situation requiring a change to a configuration
element, the first thing you should do is submit a change request and have it approved before
you can implement the changes.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.