Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are employed by a software development company as a project manager. Your company has a policy
that a change control board (CCB) reviews all of the change requests for every project in your organization,
and the CCB follows all the recommended activities outlined in A Guide to the Project Management Body
of Knowledge (PMBOK® Guide). You and your project team do not serve as members of the CCB. Based on
this scenario, which of the following activities might be performed by members of the CCB?
A. Creating a change request
B. Implementing approved change requests
C. Initiating and closing a project
D. Monitoring implementation of approved changes
HINT: Which answer choices are the responsibilities of the project manager and the project team?
Question
3. The correct answer is A.
The change control board (CCB) is a formally chartered group responsible for reviewing,
evaluating, approving, deferring, or rejecting change requests. The CCB can include project
stakeholders, and a change may be requested by any stakeholder involved with the project.
Therefore, it is possible for a member of the CCB to create and submit a change request.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.