You are employed by a software development company as a project manager. Your company has a policy
that a change control board (CCB) reviews all of the change requests for every project in your organization,
and the CCB follows all the recommended activities outlined in A Guide to the Project Management Body
of Knowledge (PMBOK® Guide). You and your project team do not serve as members of the CCB. Based on
this scenario, which of the following activities might be performed by members of the CCB?
A. Creating a change request
B. Implementing approved change requests
C. Initiating and closing a project
D. Monitoring implementation of approved changes
HINT: Which answer choices are the responsibilities of the project manager and the project team?
Question
The correct answer is A.
The change control board (CCB) is a formally chartered group responsible for reviewing,
evaluating, approving, deferring, or rejecting change requests. The CCB can include project
stakeholders, and a change may be requested by any stakeholder involved with the project.
Therefore, it is possible for a member of the CCB to create and submit a change request.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

Free PMP Sample Q & A

  • 1.
  • 2.
    You are employedby a software development company as a project manager. Your company has a policy that a change control board (CCB) reviews all of the change requests for every project in your organization, and the CCB follows all the recommended activities outlined in A Guide to the Project Management Body of Knowledge (PMBOK® Guide). You and your project team do not serve as members of the CCB. Based on this scenario, which of the following activities might be performed by members of the CCB? A. Creating a change request B. Implementing approved change requests C. Initiating and closing a project D. Monitoring implementation of approved changes HINT: Which answer choices are the responsibilities of the project manager and the project team? Question
  • 3.
    The correct answeris A. The change control board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting change requests. The CCB can include project stakeholders, and a change may be requested by any stakeholder involved with the project. Therefore, it is possible for a member of the CCB to create and submit a change request. Answer