2. A project manager is planning an educational research project and is developing the components of the
project management plan. The project manager is nearly complete with the requirements management
plan using a template provided by the project management office (PMO). The project manager notices
that an element included in the template is misplaced and should not be part of the requirements
management plan. Which of the following elements did the project manager most likely notice and should
exclude from the requirements management plan?
A. The metrics that will be used and the rationale for using them
B. A requirements prioritization process
C. A process that specifies how formal acceptance of the completed project deliverables will be obtained
D. How requirement activities will be planned, tracked, and reported
Hint: Which element should be included in the scope management plan and not the requirements
management plan
Question
3. The correct answer C
The requirements management plan is a component of the project or program management
plan that describes how requirements will be analyzed, documented, and managed. A process
that specifies how formal acceptance of the completed project deliverables will be obtained is an
element of the scope management plan and should be excluded from the requirements
management plan. The incorrect answer choices represent components that should be included
in the requirements management plan
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.