2. All of the following processes fall under the Executing Process Group except:
A. Direct and Manage Project Work
B. Manage Quality
C. Perform Integrated Change Control
D. Manage Team
HINT: Think of what is done in each process, which should help you identify the process
that is not part of the Executing Process Group.
QUESTION:
3. The correct answer is C.
IThe Executing Process Group includes processes that are performed to complete the work required to
meet the project requirements, while Perform Integrated Change Control process focuses on managing
changes to the project, which is performed as a part of the Monitoring and Controlling Process Group.
ANSWER:
4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.