Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. A project manager meets with a customer for initial discussions about an upcoming project. At
the end of the meeting, the customer asks the project manager for a rough estimate of the
project duration. Based on her experience with three similar projects, the project manager
provides an estimate of 8-10 months.
What estimation technique does the project manager use?
A. Expert judgment
B. Three-point estimating
C. Analogous estimating
D. Bottom-up estimating
HINT: Identify the estimating technique that compares a project to a previous, similar project.
Question
3. The correct answer is C
The project manager is using historical duration information from comparable projects to
estimate the duration of a future project. This gross value estimating approach is called
analogous estimating and is frequently used to provide a ballpark figure when there is a limited
amount of detailed information available about the project.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.