2. You are working with a team to estimate how much time is required for each activity. You are using
a document that contains information on the categories of labor, material, and equipment
required to complete the project. You are also interested in the skill levels, required certifications,
and the grade levels for supplies.
Which of the following documents would you primarily refer to for this purpose?
A. Resource breakdown structure
B. Organizational breakdown structure
C. Work breakdown structure
D. Risk breakdown structure
HINT: The correct answer is one of the inputs to the Estimate Activity Duration process.
Question
3. The correct answer is A.
Based on the scenario described, the project team is performing the Estimate Activity Durations
process.
An input to this process is the resource breakdown structure (RBS), which is a hierarchical list of
team and physical resources related by category and resource type that is used for planning,
managing, and controlling project work.
Each descending level represents an increasingly detailed description of the resource until the
information is small enough to be used in conjunction with the WBS to allow the work to be
planned, monitored, and controlled.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.