A project manager is in the process of identifying stakeholders for a software development project that is
just getting underway. The organization has a project management office (PMO) that ensures all relevant
project documents are created, and all project management processes are followed according to
established best practices. In order to identify stakeholders for the newly started project, what should the
project manager do first?
A. Review the business documents as a source of information about the project's stakeholders
B. Review the communications management plan for knowledge about the project's stakeholders
C. Review the stakeholder management plan to identify the management strategies and actions required
to engage stakeholders effectively
D. Review the requirements documentation for information on potential stakeholders
HINT: Which of the documents mentioned in the answer choices is available during the first iteration of
the Identify Stakeholders process?
Question
The correct answer is A.
The business documents include the business case and the benefits management plan. Both of
these documents are created during pre-project work and are available as sources of information
about the project's stakeholders during the first iteration of the Identify Stakeholders process. The
business case identifies an initial list of stakeholders affected by the project. The benefits
management plan may identify the individuals and groups that will benefit from the delivery of
the outcomes of the project and are thus considered as stakeholders. Of the available options,
only the business documents are available as sources of relevant information during the first
iteration of the Identify Stakeholders process.
Answer
All our questions are updated to the latest 
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.


Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.


We are a trusted and experienced education provider.

Free PMP Sample Q & A

  • 1.
  • 2.
    A project manageris in the process of identifying stakeholders for a software development project that is just getting underway. The organization has a project management office (PMO) that ensures all relevant project documents are created, and all project management processes are followed according to established best practices. In order to identify stakeholders for the newly started project, what should the project manager do first? A. Review the business documents as a source of information about the project's stakeholders B. Review the communications management plan for knowledge about the project's stakeholders C. Review the stakeholder management plan to identify the management strategies and actions required to engage stakeholders effectively D. Review the requirements documentation for information on potential stakeholders HINT: Which of the documents mentioned in the answer choices is available during the first iteration of the Identify Stakeholders process? Question
  • 3.
    The correct answeris A. The business documents include the business case and the benefits management plan. Both of these documents are created during pre-project work and are available as sources of information about the project's stakeholders during the first iteration of the Identify Stakeholders process. The business case identifies an initial list of stakeholders affected by the project. The benefits management plan may identify the individuals and groups that will benefit from the delivery of the outcomes of the project and are thus considered as stakeholders. Of the available options, only the business documents are available as sources of relevant information during the first iteration of the Identify Stakeholders process. Answer
  • 4.
    All our questionsare updated to the latest  A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days. We are a trusted and experienced education provider.