2. Which document describes how to create the WBS?
A. Project scope statement
B. Requirements traceability matrix
C. Scope management plan
D. Requirements management plan
HINT: Notice that only the project management plan provides such guidelines.
QUESTION:
3. The correct answer is C.
The scope management plan specifies how to create the work breakdown structure (WBS)
from the detailed project scope statement and how the WBS will be maintained and
approved.
ANSWER: