Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You have finished estimating costs for your project. What is your next activity with regard to
managing the costs?
A. Develop Cost Performance Baseline
B. Develop Work Performance Measurements
C. Develop Budget Forecasts
D. Plan Quality Management
HINT: Determine Budget is the process after the Estimate Costs process.
Question
3. The correct answer is A.
The immediate activity following estimation of costs is determining the budget. The output of the
Determine Budget process is the development of a Cost Performance Baseline.
Answer