2. An organization has a project management office (PMO) that ensures all relevant project
documents are created, and all project management processes are followed according to
established best practices.
What should the project manager review first to identify stakeholders for a newly started project?
A. The business documents as a source of information about the project's stakeholders
B. The communications management plan to learn about the project's stakeholders
C. The stakeholder engagement plan to identify the management strategies and actions required
to engage stakeholders effectively
D. The requirements documentation for information on potential stakeholders
HINT: Which of the documents mentioned in the answer choices is available during the first
iteration of the Identify Stakeholders process?
Question
3. The correct answer is A.
The business documents include the business case and the benefits management plan. Both of
these documents are created during pre-project work and are available as sources of information
about the project's stakeholders during the first iteration of the Identify Stakeholders process.
The business case identifies an initial list of stakeholders affected by the project. The benefits
management plan may identify the individuals and groups that will benefit from the delivery of the
outcomes of the project and are thus considered as stakeholders.
Among the available options, only the business documents are available as sources of relevant
information during the first iteration of the Identify Stakeholders process.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.