Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. An organization has a policy that a change control board (CCB) must review all change requests
for every project in the organization, and that the CCB follows the recommended activities
outlined in the A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Project
managers and the project team do not serve as members of the CCB.
Based on this scenario, which of the following activities might be performed by members of the
CCB?
A. Submitting a change request
B. Implementing approved change requests
C. Initiating and closing a project
D. Monitoring implementation of approved changes
HINT: Which option includes the responsibilities of the project manager and the project team?
Question
3. The correct answer is A
The change control board (CCB) is a formally chartered group responsible for reviewing,
evaluating, approving, deferring, or rejecting change requests. The CCB can include project
stakeholders, and a change may be requested by any stakeholder involved with the project.
Therefore, it is possible for a member of the CCB to submit a change request.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.