SlideShare a Scribd company logo
1 of 8
Download to read offline
GE Industrial
Systems
UPS and Generator
Compatibility Issues
GE Proprietary Information
Typical Electrical One line
GE Proprietary Information
Need to Know Interface Data
• Rectifier Power
– Remember the input power of a UPS is different than the output power, due to its efficiency,
losses and battery re-charge. For example a 150KVA Signature UPS has an input power rating
of 162KVA.
– Some UPS do not have a soft start feature. In this case the generator will have to be sized to
accept all the inrush current of the UPS during energization.
• Input Harmonics
– A standard 6 pulse rectifier generates input current harmonics on the order of 25%-30% these
are reflected back to the source and can generate voltage harmonics, which can make it difficult
for the generator to regulate voltage properly. These current harmonics can also overheat the
alternator windings in the generator.
• Sub-transient Reactance “Xd”
– It is best for a generator to have as low a sub-transient reactance as possible. This figure directly
relates to the voltage distortion that the generator will have to cope with. It is usually given as a
percentage. A good Xd is something around 8%-12%
• Total Load on Generator
– Be sure to take into account other loads that may be on the generator apart from the UPS, such
as air conditioning and lighting. Also if there are any pf correction capacitors in the system these
can intensify voltage distortion and need to taken into account. The line impedance of the input
cabling can also be a factor in the amount of voltage distortion seen by the generator.
GE Proprietary Information
Basic Generator Sizing
• Quick rule of thumb
– Generator size = 2.5 times UPS rating with no filter
– Generator size = 1.5 times UPS rating with input filter
• Generator sizing calculation
PG = PR x C x Xd / d
– PG is the Generator power;
– PR is Rectifier input power;
– Xd is the Sub transient Reactance of the generator;
– d is the acceptable THD voltage distortion;
– C is a constant value which is calculated by the number of Rectifier pulses and the total input line Impedance of
the electrical system.
– Typical values: for 6 pulse Rectifier C= 1.3 to 1.6
– for 6 pulse rectifier with input filter C= 0.8 to 1
– for 12 pulse Rectifier C= 0.8 to 1
Example: UPS 100 kVA; Acceptable voltage distortion 6%; Sub transient Reactance Xd=12%
– With 6 pulse Rectifier; PG= (110 x 1.3 x 0.12)/0.06 = 260 kVA
– With 6 pulse Rectifier and filter; PG= (110 x 0.8 x 0.12)/0.06 = 176 kVA
GE Proprietary Information
• In a system where a generator is already in place and a UPS size
has been determined it is possible to calculate the need for an
input filter based on the Voltage Distortion allowed by the
generator.
d = ( PR x C x Xd ) / PG
Example: UPS 300 kVA; EG 450 kVA; Xd = 0.12
d = (330 x 1.3 x 0.12) / 450 = 11% with 6 pulse Rectifier
d = (330 x 0.8 x 0.12) / 450 = 7% with 12 pulse Rectifier.
If a smaller voltage distortion is required it is necessary to install
filters.
It is generally good practice to include a 5th harmonic filter with
all generator applications.
Deciding if you need a 5th Harmonic Filter
GE Proprietary Information
The GE Advantage
• Soft Start
– The GE UPS has a soft start feature which slowly ramps the rectifier into its performance band.
This limits inrush currents that can cause problems with generator regulation, and also reduces
the need to over size the generator. The time window that the ramp up takes place is adjustable
through the UPS parameters up to 30 seconds.
• Adjustable frequency window and phase angle detection.
– The GE UPS can be fine tuned for the generator it will be interfacing with through its parameters.
If the generator has particularly poor frequency regulation the window can be widened to allow
the UPS to accept larger frequency fluctuations. If loads other than the UPS affect the utility
phase angle that the UPS is trying to track then the tracking window can also be adjusted to
allow the UPS and generator to stay in sync.
• Battery recharge disconnect
– If the utility fails and the UPS is forced to go on battery for a time before the generator is started,
the UPS can be set through its parameters to inhibit battery recharge once the generator comes
on line. This is advantageous because generator power is expensive and it would be useful to
recharge large battery systems with the electrical mains and not the generator.
• Programmable parameters
– There are other parameters that can be programmed from the front display that will reduce
UPS/Generator compatibility issues. Most of these serve to adjust the way that the UPS
interprets the generator signals and avoid erroneous alarms.
GE Proprietary Information
Active Filter
• 5th Harmonic Cancellation
– The optional filter is designed to cancel the current
distortion that is most present on the 5th harmonic.
• Power Factor Correction
– The input filter also raises the input pf to approximately 0.93
with addition of capacitors. This will allow the generator to
operate more efficiently delivering more real power.
• Automatic Delay and Disconnect
– If the UPS is energized while a generator is supplying the
source voltage the filter can be automatically taken out of
the circuit for a time to allow the generator and the UPS to
more easily sync together. Also, if the load drops below the
30% the filter is automatically removed from the circuit for
more efficient operation.
THD without filter
THD after filter
GE Proprietary Information
Summary
• The interfacing of a generator with a UPS is complex and requires special consideration of
many factors. When problems arise it is difficult to assign responsibility. The generator
manufacture may say it is a problem with the UPS load and the UPS manufacturer may say
that the system is working perfectly and that it is the generator which is unstable.
• Many customers will use generators to reduce the investment required for large battery
systems. In this case the required battery backup time needs only to be long enough to get the
generator on line. 5-10 minutes should compensate for the difference in generator starting
systems.
• The adjustable features available through the parameters allow the GE UPS to be fine tuned to
specific generator characteristics reducing possible interface issues and the time it takes for
the UPS and generator to couple together, this in turn reduces the battery runtime that is
required.
• The design of the GE UPS with adjustable Soft Start reduces the need for extensive generator
over sizing.
• The optional input filter does more than just reduce harmonics. Its programmable features
allow it to more easily interface with a generator further reducing UPS/Generator compatibility
issues and increasing efficiency.

More Related Content

What's hot

harmonic analysis of 6 phase converter
harmonic analysis of 6 phase converterharmonic analysis of 6 phase converter
harmonic analysis of 6 phase converter
Rahul Kumar
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
Dinesh Sarda
 
Automatic Generation Control of Two Equal Areas with Traditional Controllers
Automatic Generation Control of Two Equal Areas with Traditional ControllersAutomatic Generation Control of Two Equal Areas with Traditional Controllers
Automatic Generation Control of Two Equal Areas with Traditional Controllers
IJPEDS-IAES
 

What's hot (20)

Auto synch considerations methods
Auto synch considerations methodsAuto synch considerations methods
Auto synch considerations methods
 
Static kramer system
Static kramer systemStatic kramer system
Static kramer system
 
transient stability analysis
transient stability analysistransient stability analysis
transient stability analysis
 
voltage stability by compensating reactive power
voltage stability by compensating reactive powervoltage stability by compensating reactive power
voltage stability by compensating reactive power
 
Concepts of Reactive Power Control and Voltage Stability Methods in Power Sys...
Concepts of Reactive Power Control and Voltage Stability Methods in Power Sys...Concepts of Reactive Power Control and Voltage Stability Methods in Power Sys...
Concepts of Reactive Power Control and Voltage Stability Methods in Power Sys...
 
Unit 2 Reactive Power Management
Unit 2 Reactive Power ManagementUnit 2 Reactive Power Management
Unit 2 Reactive Power Management
 
Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier Three phase power factor improvement using Vienna Rectifier
Three phase power factor improvement using Vienna Rectifier
 
Power System Control And Line Compensation
Power System Control And Line CompensationPower System Control And Line Compensation
Power System Control And Line Compensation
 
Automatic voltaer regulator and it's modelling
Automatic voltaer regulator and it's modellingAutomatic voltaer regulator and it's modelling
Automatic voltaer regulator and it's modelling
 
voltage stability
voltage stabilityvoltage stability
voltage stability
 
Unit 3 FACTS Technology
Unit 3 FACTS TechnologyUnit 3 FACTS Technology
Unit 3 FACTS Technology
 
harmonic analysis of 6 phase converter
harmonic analysis of 6 phase converterharmonic analysis of 6 phase converter
harmonic analysis of 6 phase converter
 
Under voltage load shedding
Under voltage load sheddingUnder voltage load shedding
Under voltage load shedding
 
Synchronous condensers
Synchronous condensersSynchronous condensers
Synchronous condensers
 
Method of voltage control
Method of voltage controlMethod of voltage control
Method of voltage control
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
importance of reactive power in power system
importance of reactive power in power systemimportance of reactive power in power system
importance of reactive power in power system
 
Protecting Power Plants from SSR
Protecting Power Plants from SSRProtecting Power Plants from SSR
Protecting Power Plants from SSR
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
Automatic Generation Control of Two Equal Areas with Traditional Controllers
Automatic Generation Control of Two Equal Areas with Traditional ControllersAutomatic Generation Control of Two Equal Areas with Traditional Controllers
Automatic Generation Control of Two Equal Areas with Traditional Controllers
 

Viewers also liked

Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
michaeljmack
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
michaeljmack
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lcca
michaeljmack
 
2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty
michaeljmack
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
michaeljmack
 
X472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leedX472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leed
michaeljmack
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
michaeljmack
 
Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guideliness
michaeljmack
 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
michaeljmack
 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building types
michaeljmack
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
michaeljmack
 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class
michaeljmack
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
michaeljmack
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
michaeljmack
 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl
michaeljmack
 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview
michaeljmack
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
michaeljmack
 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems
michaeljmack
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
michaeljmack
 

Viewers also liked (20)

Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lcca
 
2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
 
X472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leedX472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leed
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
 
Nfpa 110 review
Nfpa 110 reviewNfpa 110 review
Nfpa 110 review
 
Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guideliness
 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building types
 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl
 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems
 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
 

Similar to Ge generator and ups problems

Report BQPS II- Saad Janjua
Report BQPS II- Saad JanjuaReport BQPS II- Saad Janjua
Report BQPS II- Saad Janjua
Saad Janjua
 

Similar to Ge generator and ups problems (20)

2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...
2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...
2014 PV Distribution System Modeling Workshop: Interaction and Coordination w...
 
StartOff ACCL [Automatic Source Changeover cum Current Limiter
StartOff ACCL [Automatic Source Changeover cum Current LimiterStartOff ACCL [Automatic Source Changeover cum Current Limiter
StartOff ACCL [Automatic Source Changeover cum Current Limiter
 
4.5 assessment of motors n
4.5 assessment of  motors n4.5 assessment of  motors n
4.5 assessment of motors n
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
Report BQPS II- Saad Janjua
Report BQPS II- Saad JanjuaReport BQPS II- Saad Janjua
Report BQPS II- Saad Janjua
 
253 user benjmin
253 user benjmin253 user benjmin
253 user benjmin
 
Automatic power factor correction and its advantage
Automatic power factor correction and its advantageAutomatic power factor correction and its advantage
Automatic power factor correction and its advantage
 
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUESpower factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
power factor and power factor correction schneider EMERSON EDUARDO RODRIGUES
 
gas turbine generator set operation and maintenance
gas turbine generator set operation and maintenancegas turbine generator set operation and maintenance
gas turbine generator set operation and maintenance
 
Dc rda-rdat-low
Dc rda-rdat-lowDc rda-rdat-low
Dc rda-rdat-low
 
Two-Phase Interleaved CCM PFC Controller
Two-Phase Interleaved CCM PFC ControllerTwo-Phase Interleaved CCM PFC Controller
Two-Phase Interleaved CCM PFC Controller
 
Automatic Power Factor Corrector
Automatic Power Factor CorrectorAutomatic Power Factor Corrector
Automatic Power Factor Corrector
 
Regeneration in Variable Frequency Drives and Energy Saving Methods
Regeneration in Variable Frequency Drives and Energy Saving MethodsRegeneration in Variable Frequency Drives and Energy Saving Methods
Regeneration in Variable Frequency Drives and Energy Saving Methods
 
Energy conservation in electric drives
Energy conservation in electric drives Energy conservation in electric drives
Energy conservation in electric drives
 
Sme apfc panel catalogue
Sme apfc panel catalogueSme apfc panel catalogue
Sme apfc panel catalogue
 
Power electronic converter in wind turbine.1.
Power electronic converter in wind turbine.1.Power electronic converter in wind turbine.1.
Power electronic converter in wind turbine.1.
 
Active Harmonic Filter vs Passive | Installation Catalogue
Active Harmonic Filter vs Passive | Installation CatalogueActive Harmonic Filter vs Passive | Installation Catalogue
Active Harmonic Filter vs Passive | Installation Catalogue
 
Ac drive
Ac driveAc drive
Ac drive
 
Power Factors
Power FactorsPower Factors
Power Factors
 
Module2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.pptModule2-Automatic-Generation-control.ppt
Module2-Automatic-Generation-control.ppt
 

More from michaeljmack

Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
michaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
michaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
michaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
michaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
michaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
michaeljmack
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
michaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 
Arc Flash
Arc FlashArc Flash
Arc Flash
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
pritamlangde
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Digital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptxDigital Communication Essentials: DPCM, DM, and ADM .pptx
Digital Communication Essentials: DPCM, DM, and ADM .pptx
 
Post office management system project ..pdf
Post office management system project ..pdfPost office management system project ..pdf
Post office management system project ..pdf
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 

Ge generator and ups problems

  • 1. GE Industrial Systems UPS and Generator Compatibility Issues
  • 3. GE Proprietary Information Need to Know Interface Data • Rectifier Power – Remember the input power of a UPS is different than the output power, due to its efficiency, losses and battery re-charge. For example a 150KVA Signature UPS has an input power rating of 162KVA. – Some UPS do not have a soft start feature. In this case the generator will have to be sized to accept all the inrush current of the UPS during energization. • Input Harmonics – A standard 6 pulse rectifier generates input current harmonics on the order of 25%-30% these are reflected back to the source and can generate voltage harmonics, which can make it difficult for the generator to regulate voltage properly. These current harmonics can also overheat the alternator windings in the generator. • Sub-transient Reactance “Xd” – It is best for a generator to have as low a sub-transient reactance as possible. This figure directly relates to the voltage distortion that the generator will have to cope with. It is usually given as a percentage. A good Xd is something around 8%-12% • Total Load on Generator – Be sure to take into account other loads that may be on the generator apart from the UPS, such as air conditioning and lighting. Also if there are any pf correction capacitors in the system these can intensify voltage distortion and need to taken into account. The line impedance of the input cabling can also be a factor in the amount of voltage distortion seen by the generator.
  • 4. GE Proprietary Information Basic Generator Sizing • Quick rule of thumb – Generator size = 2.5 times UPS rating with no filter – Generator size = 1.5 times UPS rating with input filter • Generator sizing calculation PG = PR x C x Xd / d – PG is the Generator power; – PR is Rectifier input power; – Xd is the Sub transient Reactance of the generator; – d is the acceptable THD voltage distortion; – C is a constant value which is calculated by the number of Rectifier pulses and the total input line Impedance of the electrical system. – Typical values: for 6 pulse Rectifier C= 1.3 to 1.6 – for 6 pulse rectifier with input filter C= 0.8 to 1 – for 12 pulse Rectifier C= 0.8 to 1 Example: UPS 100 kVA; Acceptable voltage distortion 6%; Sub transient Reactance Xd=12% – With 6 pulse Rectifier; PG= (110 x 1.3 x 0.12)/0.06 = 260 kVA – With 6 pulse Rectifier and filter; PG= (110 x 0.8 x 0.12)/0.06 = 176 kVA
  • 5. GE Proprietary Information • In a system where a generator is already in place and a UPS size has been determined it is possible to calculate the need for an input filter based on the Voltage Distortion allowed by the generator. d = ( PR x C x Xd ) / PG Example: UPS 300 kVA; EG 450 kVA; Xd = 0.12 d = (330 x 1.3 x 0.12) / 450 = 11% with 6 pulse Rectifier d = (330 x 0.8 x 0.12) / 450 = 7% with 12 pulse Rectifier. If a smaller voltage distortion is required it is necessary to install filters. It is generally good practice to include a 5th harmonic filter with all generator applications. Deciding if you need a 5th Harmonic Filter
  • 6. GE Proprietary Information The GE Advantage • Soft Start – The GE UPS has a soft start feature which slowly ramps the rectifier into its performance band. This limits inrush currents that can cause problems with generator regulation, and also reduces the need to over size the generator. The time window that the ramp up takes place is adjustable through the UPS parameters up to 30 seconds. • Adjustable frequency window and phase angle detection. – The GE UPS can be fine tuned for the generator it will be interfacing with through its parameters. If the generator has particularly poor frequency regulation the window can be widened to allow the UPS to accept larger frequency fluctuations. If loads other than the UPS affect the utility phase angle that the UPS is trying to track then the tracking window can also be adjusted to allow the UPS and generator to stay in sync. • Battery recharge disconnect – If the utility fails and the UPS is forced to go on battery for a time before the generator is started, the UPS can be set through its parameters to inhibit battery recharge once the generator comes on line. This is advantageous because generator power is expensive and it would be useful to recharge large battery systems with the electrical mains and not the generator. • Programmable parameters – There are other parameters that can be programmed from the front display that will reduce UPS/Generator compatibility issues. Most of these serve to adjust the way that the UPS interprets the generator signals and avoid erroneous alarms.
  • 7. GE Proprietary Information Active Filter • 5th Harmonic Cancellation – The optional filter is designed to cancel the current distortion that is most present on the 5th harmonic. • Power Factor Correction – The input filter also raises the input pf to approximately 0.93 with addition of capacitors. This will allow the generator to operate more efficiently delivering more real power. • Automatic Delay and Disconnect – If the UPS is energized while a generator is supplying the source voltage the filter can be automatically taken out of the circuit for a time to allow the generator and the UPS to more easily sync together. Also, if the load drops below the 30% the filter is automatically removed from the circuit for more efficient operation. THD without filter THD after filter
  • 8. GE Proprietary Information Summary • The interfacing of a generator with a UPS is complex and requires special consideration of many factors. When problems arise it is difficult to assign responsibility. The generator manufacture may say it is a problem with the UPS load and the UPS manufacturer may say that the system is working perfectly and that it is the generator which is unstable. • Many customers will use generators to reduce the investment required for large battery systems. In this case the required battery backup time needs only to be long enough to get the generator on line. 5-10 minutes should compensate for the difference in generator starting systems. • The adjustable features available through the parameters allow the GE UPS to be fine tuned to specific generator characteristics reducing possible interface issues and the time it takes for the UPS and generator to couple together, this in turn reduces the battery runtime that is required. • The design of the GE UPS with adjustable Soft Start reduces the need for extensive generator over sizing. • The optional input filter does more than just reduce harmonics. Its programmable features allow it to more easily interface with a generator further reducing UPS/Generator compatibility issues and increasing efficiency.