GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES NEC REQUIREMENTS FOR
GENERATORS
(Based on NEC 2005 with limited 2008 commentary)
AIA certified Continuing EducationUnits(CEU) Available
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
The Presenters
Mike Kirchner
• EE
• MBA – University of Wisconsin
• Application Engineer - Marathon
• Sales Training Manager - Generac
Scott Collins
• EE
• Sales & Product Manager – CAT
• Consulting Sales Engineer - Generac
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Where will you find generators?
Q1) Where will you find generators?
– Healthcare (NEC 517)
– Fire Pumps (NEC 695)
– Emergency Life Safety (NEC 700)
– Legally Required Standby (NEC 701)
– Optional Standby (NEC 702)
– Interconnected Power (NEC 705)
– Critical Power Systems (NEC 708 – 2008)
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
What are the key codes and standards for generators?
Q2) What are the key codes and standards for generators?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• National Fire Protection Association (NFPA)
– Mission is to reduce fire risks
– Standards typically adopted into state statutes
– Require compliance for AHJ approval
• Generator related NFPA standards
– 20 Installation of Fire Pumps
– 37 Installation & Use of Stationary Engines
– 54 National Fuel Gas Code
– 58 LP Gas Code
– 70 National Electric Code
– 99 Health Care Facilities
– 110 Standard for Emergency & Standby Power Systems
What are the key codes and standardsfor generators?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Underwriters Laboratories (UL)
– Focused on product safety and usability
– UL does not “approve”
– AHJoften use UL listing as “approved for use”
• Power Generation related UL standards
– 2200 Stationary Engine Generators
– 1008 Automatic Transfer Switches
– 891 Dead Front Panel Board
– 142 Liquid Storage Tanks
What are the key codes and standardsfor generators?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Generator related NEC articles
– NEC 100 Definitions
– NEC 215 & 225 Feeders
– NEC 240 Overcurrent Protection
– NEC 250 Grounding
– NEC 445 Generators
– NEC 517 Healthcare
– NEC 695 Fire Pumps
– NEC 700 Emergency Systems
– NEC 701 Legally Required Standby
– NEC 702 Optional Standby
– NEC 705 Interconnected Electric Power Sources
– NEC 708 “2008” Critical Power Systems
What are the key codes and standardsfor generators?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q3) What is a generator?
– Prime mover (engine) & alternator
What is a generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Generator Cabling - Feeder or Service?
• Generator cabling is considered a feeder
• It does not matter if the generator is separately derived or not
• Reference the feeder articles (NEC 215 & 225) when installing generators
Feeder (NEC 100)
“All circuit conductors between the service equipment, the source of a
separately derived system, or other power supply source and the final
branch-circuit overcurrent device.”
What is a generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Service (NEC 100)
“The conductors and equipment for delivering electric energy from the
serving utility to the wiring system of the premises served.”
Handbook:
“If electric energy is supplied by other than the serving utility, the supplied
conductors and equipment are considered feeders, not a service.”
Generator Cabling - Feeder or Service?
• The generator cabling is not a service
• Only the utility can be a service
What is a generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q4) What is the required generator size (capacity)?
– Emergency System (NEC 700.5)
 “Carry the entire load connected to the emergency system at one time”
– Legally Required Standby (NEC 701.6) & Optional Standby (NEC 702.5)
 “Supply of all equipment intended to be operated at one time”
 Sizing based on NEC 220 or AHJ approved method (NEC 702.5 (2008))
– Health Care Facilities (NEC 517.30 D)
 “Meet the demand of the essential load at any given time.”
What is the required generator size?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q5) How quickly must a generator startup and transfer?
– 10 sec start-up time
 Emergency Systems (NEC 700.12)
 Fire Pumps (NFPA 20, 9.6.2.1)
 Health Care Facilities (NEC 517.31, & NFPA 99 3-4.3.1)
– 60 sec start-up time
 Legally Required Standby (NEC 701.11)
– No defined start-up time
 Optional Standby (NEC 702)
How quickly must the generatorstartup?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
General Points Summary
• NFPA & UL are key codes & standards
• Generator is considered a feeder – not service
• Generator sizing & start time based on load classification
GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES
DISCONNECT
REQUIREMENTS
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
What are the requirements for disconnect?
Q6) What are the requirements for disconnect?
Q6a) Does the NEC require a generator disconnect (breaker)?
Q6b) Is a disconnect required at the point of building entry (additional disconnect)?
Q6c) Are there any exceptions to adding an additional disconnect?
This is an area of the code that is not overly clear. The following
slides will explore the codes verbiage on this topic.
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q6a) Does the NEC require a generator disconnect (breaker)?
– NEC preference & market norm includes a generator output breaker
– Disconnect at the generator may be optional
Disconnecting MeansRequired for Generators (NEC 445.18)
“Generators shall be equipped with a disconnect(s) by means of which the generator and
all protective devices and control apparatus are able to be disconnected entirely from the
circuits supplied by the generator except where:
(1) The driving means for the generator can be readily shut down; and
(2) The generator is not arranged to operate in parallel with another generator or other
source of voltage.”
What are the requirements for disconnect?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q6b) Is a disconnect required at the point of building entry?
– A disconnect is required at the point of building entrance (NEC 225.32)
OutsideFeeders (NEC 225)
– Requires a disconnect (NEC 225.31)
– Location (NEC 225.32)
“... The disconnecting means shall be at a readily accessible location nearest
the pointof entrance of the conductors. For the purposes of this section, the
requirements in 230.6 shall be permitted to be utilized.”
Thisseems to imply:
– An additional disconnect is required in addition to the generator breaker
– Unless exempted in another part of the code
What are the requirements for disconnect?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q6c) Are there any exceptions to adding an additional disconnect?
– Yes, chapter 7 allows the disconnect to be relocated
– Thismay allow the generator breaker to function as the required disconnect
Outdoor Generator Sets
– NEC 700.12(B)(6), NEC 701.11(B)(5), NEC 702.11
“Where an outdoor housed generator set is equipped with a readily accessible
disconnecting means located within sight of the building or structure supplied, an
additionaldisconnecting meansshall not be required where ungrounded
conductors pass through the building or structure.”
Is it the generator or the generator disconnectthat must be visible from the building?
– Thisis an area of local interpretation (what needs to be visible)
What are the requirements for disconnect?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Disconnect Summary
• Generator disconnect may be optional
• Building disconnect is required
• A generator disconnect may meet the
building disconnect requirements
In the market, we see significant variations on the use of an additional
disconnect at the point of entry of the generator cabling. Ultimately this is an
issue that is largely affected by local normsand AHJ interpretation and
preferences.
GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES
CABLING &
COORDINATION
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q7) What are the requirements for generator cabling?
– Size to the generator breaker (or)
– Size to 445.13
 Size to 115% of the generator rating
Generator - Ampacity of Conductors (NEC 445.13)
“The ampacity of the conductors from the generator terminals to the first distribution
device(s) containing overcurrent protection shall not be less than 115 percent of the
nameplate current rating of the generator…”
What are the requirements for generator cabling?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
What are the requirements for separationof circuits?
Q8) What are the requirements for separation of circuits?
– The emergency system wiring must be separated
– Emergency system breaker may be in a separate vertical section (NEC 2008) (or)
– Emergency system breaker may be located in the generator connection box
EmergencySystems – Wiring (NEC 700.9)
“… Wiring from an emergency source or emergency source distribution overcurrent
protection to emergency loads shall be kept entirely independent of all other wiring and
equipment, unless otherwise permitted.”
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Emergency system breaker at generator
• Emergency system breaker in separate vertical section
• Emergency system breaker in same section (interpretation)
Emergency System
Gen
Other Loads
NEC 2005 & 2008
Emergency SystemGen
Other Loads
NEC 2005 Single Section
(Interpretation)
Emergency SystemGen
Other Loads
NEC 2008 Separate Sections
What are the requirements for separationof circuits?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
What are the requirements for coordination?
Q9) What are the requirements for coordination?
– A fault in the optional standby circuit shall not trip the other circuits
– Goal is to maintain continuity of power to emergency and legally required loads
– Not required for optional standby applications
EmergencySystem – Coordination (NEC 700.27)
LegallyRequired Standby – Coordination (NEC 701.18)
“… over-current devices shall be selectively coordinated with all supply side over-current
protective devices”
X
Branch
Device Opens Fault
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Cabling & Coordination Summary
• Generator cabling can be sized at 115% of output
• Emergency circuits need to be separated
• Emergency and legally required circuits need
selective coordination
GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES
GROUNDING &
GROUND FAULT
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q10) What are the grounding requirements for the generator?
– Generator systems can be separately derived (4 pole ATS)
– Generator systems can be non-separately derived (3 pole ATS)
Grounding&Bonding - Separately Derived Systems (NEC 250.20 (D))
“FPN 1: An alternate ac power source such as an on-site generator is not a separately
derived system if the neutral is solidly interconnected to a service-supplied system
neutral.”
What are the grounding requirements for the generator?
3-Pole, Neutral Not Switched 4-Pole, Switched Neutral
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Bonding - Neutral conductor to Grounding conductor
– Single point of neutral bonding per system
 Main bonding jumper
 Connects the facility’s neutral system to the facility’s ground system
What are the grounding requirements for the generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Non-separatelyderived system (3 pole ATS)
– Generator neutral bonded to system ground at the service
– Generator frame requires equipment grounding conductor
 Ground rod at generator is not adequate
What are the grounding requirements for the generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• Separatelyderived system (4 Pole ATS)
– Generator neutral bonded to system ground at the generator
– Generator frame requires equipment grounding connection to ATS
 Grounding electrode(s) needs to be “nearby”
What are the grounding requirements for the generator?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q11) Are generators required to have GFI or GFP?
– Emergency generators (480v, 1000amps) require GFI
– Legally required generators do not require GFI or GFP
EmergencySystems – Ground Fault (NEC 700.7 (D))
“To indicate a ground fault in solidly grounded wye emergency systems of more than 150
volts to ground and circuit-protective devices rated 1000 amperes or more.”
LegallyRequired Standby -- Ground-FaultProtection ofEquipment (NEC 701.17)
“The alternate source for legally required standby systems shall not be required to have
ground-fault protection of equipment.”
Are Generators required to have GFI or GFP?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q11) Are generators required to have GFI or GFP?
– Optional standby generators typically don’t include GFP
– Optional standby (480v, 1000 amps) could be required to include GFP (interpretation)
• NEC 702 (Optional Standby)
– No comment on GFP or GFI
– Feeder Ground-Fault Protection of Equipment (NEC 215.10)
 “Each feeder disconnect rated 1000 amperes or more and installed on solidly
grounded wye electrical systems of more than 150 volts to ground, but not exceeding
600 volts phase-to-phase, shall be provided with ground-fault protection of
equipment in accordance with the provisions of 230.95.”
Are Generators required to have GFI or GFP?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Grounding and Ground Fault Summary
• Generators can be separately or non-separatelyderived
• Generator neutral should only be bonded at a single point
• Generator requires a grounding conductor
• Ground fault protection is not common on generator feeders
GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES
FIRE PUMPS
(NEC 695 and NFPA 20)
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q12) What size is the generator breaker for a fire pump?
– We have seen multiple requests for magnetic only breakers
– We have seen multiple requests for breakers at 6x running amps
– We feel this is a misinterpretation of NEC 695 requirements
• Code is confusing, resulting in this behavior
– Fire Pumps - Overcurrent Device Selection (NEC 695.4(B)(1))
“set to indefinitely carry the sum of locked rotor current”
 This section only applies to “remote power sources”
What is being confused is the utility versus the generator feeder.
What size is the generator breaker for a fire pump?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• NEC 695 is also confusing on the issue of overload
– NEC defines overload protection very specifically
– Overload protection is defined in 430.32 (limited to 125% of rated)
– If overcurrent protection is larger than 125% of rated amps
 The circuit has no protection against overload (based on the NEC definition)
 The circuit has short circuit protection only
• Example of verbiage that causes misinterpretation
– Fire Pump - Power Wiring - Overload Protection (NEC 695.6(D))
“Power circuits shall not have automatic protection against overloads. Branch
circuits and feeder conductors shall be protected against short circuit only.”
What size is the generator breaker for a fire pump?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• NEC 695 specifies the requirements for the generator
– Sized for normal starting & running
– Not sized for locked rotor amps
Fire Pumps – Generator Capacity (NEC 695.3(B)(1))
“Generator Capacity. An on-site generator(s) used to comply with this section shall be of
sufficient capacity to allownormal starting and running of the motor(s) …. A tap ahead of the
on-site generator disconnecting means shall not be required…”
Handbook:
“…alternative source overcurrent protective device(s) for the electric-drive fire pump are not
required to be sized for locked-rotor current of the fire pump motor(s). Rather, the circuit
components of the alternative source are permitted to be sized according to Article 430...”
What size is the generator breaker for a fire pump?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
• NEC 695 defines the size of the generator’s fire pump breaker
– Generator’s fire pump breaker is between 125% to 250% of rated amps
– Thisprovides no overload protection (>125%)
– NEC430 limits the maximum size to 250%
• Fire Pumps – Continuity of Power (NEC 695.4(B))
“... Overcurrent protective devices between an on-site standby generator and a fire pump
controller shall be selected and sized according to 430.62 to provide short-circuit
protection only.”
What size is the generator breaker for a fire pump?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Q13) What are other requirements for fire pumps?
– Voltage dip limited to 15% for normal starting
– ATS must be fire pump rated
– Generator must meet requirements for NFPA 110 Level 1
 Reliable fuel (AHJ may require on-site fuel)
 Remote audible alarm
 NFPA 110 testing, maintenance and recording requirements
What size is the generator breaker for a fire pump?
Professional Development Seminar Series – GPS-140 National Electric Code (NEC)
Portions hereof © 2004 National Fire Protection Association.
Fire Pump Summary
• Locked rotor amp sizing applies to the utility source
• Generator’s fire pump breaker needs to be 125 to 250% of pump rating
• Limit voltage dips to 15%
GPS-140
National Electric Code
(NEC)
PROFESSIONAL
DEVELOPMENT
SEMINAR
SERIES
Thank you!
Please complete the exit survey.
And thank you for your live questions!
Go to www.csemag.com to take the CEU test if you want
AIA learning units for attending this Webcast.
Thisevent will be archived at www.csemag.com for 12
monthsbeginningon or beforeDec. 15, 2007.

More Related Content

What's hot

Ejercicios resueltos matriz de admitancias
Ejercicios resueltos matriz de admitanciasEjercicios resueltos matriz de admitancias
Ejercicios resueltos matriz de admitanciasJOe Torres Palomino
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLPreet_patel
 
Lecture 6 BATTERIES 2023.pptx
Lecture 6 BATTERIES 2023.pptxLecture 6 BATTERIES 2023.pptx
Lecture 6 BATTERIES 2023.pptxAdityaVashist12
 
M25 installation et dipanage de moteur a courant continu
M25 installation et dipanage de moteur a courant continuM25 installation et dipanage de moteur a courant continu
M25 installation et dipanage de moteur a courant continuMOUHSSINE BEN HAMMOU
 
Diapositivas transformadores-de-medición-y-protección
Diapositivas transformadores-de-medición-y-protecciónDiapositivas transformadores-de-medición-y-protección
Diapositivas transformadores-de-medición-y-protecciónAlexander Moreno Matinez
 
Cours master phys sc chap 4 2015
Cours master phys sc chap 4 2015Cours master phys sc chap 4 2015
Cours master phys sc chap 4 2015omar bllaouhamou
 
Single phase grid connected fuel system based on boost inverter
Single phase grid connected fuel system based on boost inverterSingle phase grid connected fuel system based on boost inverter
Single phase grid connected fuel system based on boost inverterRohithasangaraju
 
Informe 1 - Laboratorio de electrónica B
Informe 1 - Laboratorio de electrónica BInforme 1 - Laboratorio de electrónica B
Informe 1 - Laboratorio de electrónica BJuan Lucin
 
Alimentations statiques ininterrompues - Guide européen
Alimentations statiques ininterrompues - Guide européenAlimentations statiques ininterrompues - Guide européen
Alimentations statiques ininterrompues - Guide européenGimélec
 
DigSILENT PF - 04 ejercicios de estabilidad
DigSILENT PF - 04 ejercicios de estabilidadDigSILENT PF - 04 ejercicios de estabilidad
DigSILENT PF - 04 ejercicios de estabilidadHimmelstern
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principlesAmmar Al Hakeim
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Living Online
 
3 identification des systèmes
3 identification des systèmes3 identification des systèmes
3 identification des systèmesRachid Lajouad
 

What's hot (20)

Ejercicios resueltos matriz de admitancias
Ejercicios resueltos matriz de admitanciasEjercicios resueltos matriz de admitancias
Ejercicios resueltos matriz de admitancias
 
9 system-sizing
9 system-sizing9 system-sizing
9 system-sizing
 
Transformadores
TransformadoresTransformadores
Transformadores
 
Power system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter fivePower system planing and operation (pce5312) chapter five
Power system planing and operation (pce5312) chapter five
 
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROLLOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
LOAD FREQUENCY AND VOLTAGE GENERATION CONTROL
 
Lecture 6 BATTERIES 2023.pptx
Lecture 6 BATTERIES 2023.pptxLecture 6 BATTERIES 2023.pptx
Lecture 6 BATTERIES 2023.pptx
 
M25 installation et dipanage de moteur a courant continu
M25 installation et dipanage de moteur a courant continuM25 installation et dipanage de moteur a courant continu
M25 installation et dipanage de moteur a courant continu
 
Diapositivas transformadores-de-medición-y-protección
Diapositivas transformadores-de-medición-y-protecciónDiapositivas transformadores-de-medición-y-protección
Diapositivas transformadores-de-medición-y-protección
 
Cours master phys sc chap 4 2015
Cours master phys sc chap 4 2015Cours master phys sc chap 4 2015
Cours master phys sc chap 4 2015
 
Trafos romagñole
Trafos romagñoleTrafos romagñole
Trafos romagñole
 
chapter-2 Breakdown in Gases (part-1)
chapter-2 Breakdown  in Gases (part-1)chapter-2 Breakdown  in Gases (part-1)
chapter-2 Breakdown in Gases (part-1)
 
Single phase grid connected fuel system based on boost inverter
Single phase grid connected fuel system based on boost inverterSingle phase grid connected fuel system based on boost inverter
Single phase grid connected fuel system based on boost inverter
 
Informe 1 - Laboratorio de electrónica B
Informe 1 - Laboratorio de electrónica BInforme 1 - Laboratorio de electrónica B
Informe 1 - Laboratorio de electrónica B
 
Alimentations statiques ininterrompues - Guide européen
Alimentations statiques ininterrompues - Guide européenAlimentations statiques ininterrompues - Guide européen
Alimentations statiques ininterrompues - Guide européen
 
Redresseurs
RedresseursRedresseurs
Redresseurs
 
DigSILENT PF - 04 ejercicios de estabilidad
DigSILENT PF - 04 ejercicios de estabilidadDigSILENT PF - 04 ejercicios de estabilidad
DigSILENT PF - 04 ejercicios de estabilidad
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principles
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
 
3 identification des systèmes
3 identification des systèmes3 identification des systèmes
3 identification des systèmes
 

Similar to Nec emergency requirements

Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignConsultingSpecifyingEngineer
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolarReference
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and groundingmichaeljmack
 
Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - finalRon Henderson
 
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceAnkit Saxena
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterPaul Plavicheanu
 
Nidec asi capability overview for lng and oil&gas applications
Nidec asi capability overview for lng and oil&gas applicationsNidec asi capability overview for lng and oil&gas applications
Nidec asi capability overview for lng and oil&gas applicationsNidec Corporation
 
Weg with aegis_brochure
Weg with aegis_brochureWeg with aegis_brochure
Weg with aegis_brochureDaniel García
 
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.com
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.comCatalog Inverter FR-E700 Mitsubishi Electric-Beeteco.com
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.comBeeteco
 
Session 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxSession 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxTaashish
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...kevinfok
 
Classification of electric motors
Classification of electric motors Classification of electric motors
Classification of electric motors Sudhanshu Tripathi
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2fboshell
 
Tb08104003e
Tb08104003eTb08104003e
Tb08104003emrepol02
 

Similar to Nec emergency requirements (20)

Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Upgrading gen protect and grounding
Upgrading gen protect and groundingUpgrading gen protect and grounding
Upgrading gen protect and grounding
 
Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - final
 
Inspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_complianceInspecting pv systems_for_code_compliance
Inspecting pv systems_for_code_compliance
 
Inspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code ComplianceInspecting Photovoltaic (PV) Systems for Code Compliance
Inspecting Photovoltaic (PV) Systems for Code Compliance
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
 
Nidec asi capability overview for lng and oil&gas applications
Nidec asi capability overview for lng and oil&gas applicationsNidec asi capability overview for lng and oil&gas applications
Nidec asi capability overview for lng and oil&gas applications
 
11.docx
11.docx11.docx
11.docx
 
Weg with aegis_brochure
Weg with aegis_brochureWeg with aegis_brochure
Weg with aegis_brochure
 
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.com
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.comCatalog Inverter FR-E700 Mitsubishi Electric-Beeteco.com
Catalog Inverter FR-E700 Mitsubishi Electric-Beeteco.com
 
Session 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptxSession 5 - Grid Connected Inverter.pptx
Session 5 - Grid Connected Inverter.pptx
 
E lne technical document
E lne technical documentE lne technical document
E lne technical document
 
Schneider plc
Schneider plcSchneider plc
Schneider plc
 
ABB in Bulgaria
ABB in BulgariaABB in Bulgaria
ABB in Bulgaria
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
Classification of electric motors
Classification of electric motors Classification of electric motors
Classification of electric motors
 
IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2IRENA_The Role of Grid Codes v2
IRENA_The Role of Grid Codes v2
 
Tb08104003e
Tb08104003eTb08104003e
Tb08104003e
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodinationmichaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 
Arc Flash
Arc FlashArc Flash
Arc Flash
 
Selectivity and Coodination
Selectivity and CoodinationSelectivity and Coodination
Selectivity and Coodination
 

Recently uploaded

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 

Recently uploaded (20)

Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 

Nec emergency requirements

  • 1. GPS-140 National Electric Code (NEC) PROFESSIONAL DEVELOPMENT SEMINAR SERIES NEC REQUIREMENTS FOR GENERATORS (Based on NEC 2005 with limited 2008 commentary) AIA certified Continuing EducationUnits(CEU) Available
  • 2. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. The Presenters Mike Kirchner • EE • MBA – University of Wisconsin • Application Engineer - Marathon • Sales Training Manager - Generac Scott Collins • EE • Sales & Product Manager – CAT • Consulting Sales Engineer - Generac
  • 3. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Where will you find generators? Q1) Where will you find generators? – Healthcare (NEC 517) – Fire Pumps (NEC 695) – Emergency Life Safety (NEC 700) – Legally Required Standby (NEC 701) – Optional Standby (NEC 702) – Interconnected Power (NEC 705) – Critical Power Systems (NEC 708 – 2008)
  • 4. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. What are the key codes and standards for generators? Q2) What are the key codes and standards for generators?
  • 5. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • National Fire Protection Association (NFPA) – Mission is to reduce fire risks – Standards typically adopted into state statutes – Require compliance for AHJ approval • Generator related NFPA standards – 20 Installation of Fire Pumps – 37 Installation & Use of Stationary Engines – 54 National Fuel Gas Code – 58 LP Gas Code – 70 National Electric Code – 99 Health Care Facilities – 110 Standard for Emergency & Standby Power Systems What are the key codes and standardsfor generators?
  • 6. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Underwriters Laboratories (UL) – Focused on product safety and usability – UL does not “approve” – AHJoften use UL listing as “approved for use” • Power Generation related UL standards – 2200 Stationary Engine Generators – 1008 Automatic Transfer Switches – 891 Dead Front Panel Board – 142 Liquid Storage Tanks What are the key codes and standardsfor generators?
  • 7. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Generator related NEC articles – NEC 100 Definitions – NEC 215 & 225 Feeders – NEC 240 Overcurrent Protection – NEC 250 Grounding – NEC 445 Generators – NEC 517 Healthcare – NEC 695 Fire Pumps – NEC 700 Emergency Systems – NEC 701 Legally Required Standby – NEC 702 Optional Standby – NEC 705 Interconnected Electric Power Sources – NEC 708 “2008” Critical Power Systems What are the key codes and standardsfor generators?
  • 8. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q3) What is a generator? – Prime mover (engine) & alternator What is a generator?
  • 9. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Generator Cabling - Feeder or Service? • Generator cabling is considered a feeder • It does not matter if the generator is separately derived or not • Reference the feeder articles (NEC 215 & 225) when installing generators Feeder (NEC 100) “All circuit conductors between the service equipment, the source of a separately derived system, or other power supply source and the final branch-circuit overcurrent device.” What is a generator?
  • 10. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Service (NEC 100) “The conductors and equipment for delivering electric energy from the serving utility to the wiring system of the premises served.” Handbook: “If electric energy is supplied by other than the serving utility, the supplied conductors and equipment are considered feeders, not a service.” Generator Cabling - Feeder or Service? • The generator cabling is not a service • Only the utility can be a service What is a generator?
  • 11. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q4) What is the required generator size (capacity)? – Emergency System (NEC 700.5)  “Carry the entire load connected to the emergency system at one time” – Legally Required Standby (NEC 701.6) & Optional Standby (NEC 702.5)  “Supply of all equipment intended to be operated at one time”  Sizing based on NEC 220 or AHJ approved method (NEC 702.5 (2008)) – Health Care Facilities (NEC 517.30 D)  “Meet the demand of the essential load at any given time.” What is the required generator size?
  • 12. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q5) How quickly must a generator startup and transfer? – 10 sec start-up time  Emergency Systems (NEC 700.12)  Fire Pumps (NFPA 20, 9.6.2.1)  Health Care Facilities (NEC 517.31, & NFPA 99 3-4.3.1) – 60 sec start-up time  Legally Required Standby (NEC 701.11) – No defined start-up time  Optional Standby (NEC 702) How quickly must the generatorstartup?
  • 13. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. General Points Summary • NFPA & UL are key codes & standards • Generator is considered a feeder – not service • Generator sizing & start time based on load classification
  • 15. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. What are the requirements for disconnect? Q6) What are the requirements for disconnect? Q6a) Does the NEC require a generator disconnect (breaker)? Q6b) Is a disconnect required at the point of building entry (additional disconnect)? Q6c) Are there any exceptions to adding an additional disconnect? This is an area of the code that is not overly clear. The following slides will explore the codes verbiage on this topic.
  • 16. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q6a) Does the NEC require a generator disconnect (breaker)? – NEC preference & market norm includes a generator output breaker – Disconnect at the generator may be optional Disconnecting MeansRequired for Generators (NEC 445.18) “Generators shall be equipped with a disconnect(s) by means of which the generator and all protective devices and control apparatus are able to be disconnected entirely from the circuits supplied by the generator except where: (1) The driving means for the generator can be readily shut down; and (2) The generator is not arranged to operate in parallel with another generator or other source of voltage.” What are the requirements for disconnect?
  • 17. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q6b) Is a disconnect required at the point of building entry? – A disconnect is required at the point of building entrance (NEC 225.32) OutsideFeeders (NEC 225) – Requires a disconnect (NEC 225.31) – Location (NEC 225.32) “... The disconnecting means shall be at a readily accessible location nearest the pointof entrance of the conductors. For the purposes of this section, the requirements in 230.6 shall be permitted to be utilized.” Thisseems to imply: – An additional disconnect is required in addition to the generator breaker – Unless exempted in another part of the code What are the requirements for disconnect?
  • 18. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q6c) Are there any exceptions to adding an additional disconnect? – Yes, chapter 7 allows the disconnect to be relocated – Thismay allow the generator breaker to function as the required disconnect Outdoor Generator Sets – NEC 700.12(B)(6), NEC 701.11(B)(5), NEC 702.11 “Where an outdoor housed generator set is equipped with a readily accessible disconnecting means located within sight of the building or structure supplied, an additionaldisconnecting meansshall not be required where ungrounded conductors pass through the building or structure.” Is it the generator or the generator disconnectthat must be visible from the building? – Thisis an area of local interpretation (what needs to be visible) What are the requirements for disconnect?
  • 19. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Disconnect Summary • Generator disconnect may be optional • Building disconnect is required • A generator disconnect may meet the building disconnect requirements In the market, we see significant variations on the use of an additional disconnect at the point of entry of the generator cabling. Ultimately this is an issue that is largely affected by local normsand AHJ interpretation and preferences.
  • 21. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q7) What are the requirements for generator cabling? – Size to the generator breaker (or) – Size to 445.13  Size to 115% of the generator rating Generator - Ampacity of Conductors (NEC 445.13) “The ampacity of the conductors from the generator terminals to the first distribution device(s) containing overcurrent protection shall not be less than 115 percent of the nameplate current rating of the generator…” What are the requirements for generator cabling?
  • 22. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. What are the requirements for separationof circuits? Q8) What are the requirements for separation of circuits? – The emergency system wiring must be separated – Emergency system breaker may be in a separate vertical section (NEC 2008) (or) – Emergency system breaker may be located in the generator connection box EmergencySystems – Wiring (NEC 700.9) “… Wiring from an emergency source or emergency source distribution overcurrent protection to emergency loads shall be kept entirely independent of all other wiring and equipment, unless otherwise permitted.”
  • 23. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Emergency system breaker at generator • Emergency system breaker in separate vertical section • Emergency system breaker in same section (interpretation) Emergency System Gen Other Loads NEC 2005 & 2008 Emergency SystemGen Other Loads NEC 2005 Single Section (Interpretation) Emergency SystemGen Other Loads NEC 2008 Separate Sections What are the requirements for separationof circuits?
  • 24. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. What are the requirements for coordination? Q9) What are the requirements for coordination? – A fault in the optional standby circuit shall not trip the other circuits – Goal is to maintain continuity of power to emergency and legally required loads – Not required for optional standby applications EmergencySystem – Coordination (NEC 700.27) LegallyRequired Standby – Coordination (NEC 701.18) “… over-current devices shall be selectively coordinated with all supply side over-current protective devices” X Branch Device Opens Fault
  • 25. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Cabling & Coordination Summary • Generator cabling can be sized at 115% of output • Emergency circuits need to be separated • Emergency and legally required circuits need selective coordination
  • 27. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q10) What are the grounding requirements for the generator? – Generator systems can be separately derived (4 pole ATS) – Generator systems can be non-separately derived (3 pole ATS) Grounding&Bonding - Separately Derived Systems (NEC 250.20 (D)) “FPN 1: An alternate ac power source such as an on-site generator is not a separately derived system if the neutral is solidly interconnected to a service-supplied system neutral.” What are the grounding requirements for the generator? 3-Pole, Neutral Not Switched 4-Pole, Switched Neutral
  • 28. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Bonding - Neutral conductor to Grounding conductor – Single point of neutral bonding per system  Main bonding jumper  Connects the facility’s neutral system to the facility’s ground system What are the grounding requirements for the generator?
  • 29. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Non-separatelyderived system (3 pole ATS) – Generator neutral bonded to system ground at the service – Generator frame requires equipment grounding conductor  Ground rod at generator is not adequate What are the grounding requirements for the generator?
  • 30. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • Separatelyderived system (4 Pole ATS) – Generator neutral bonded to system ground at the generator – Generator frame requires equipment grounding connection to ATS  Grounding electrode(s) needs to be “nearby” What are the grounding requirements for the generator?
  • 31. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q11) Are generators required to have GFI or GFP? – Emergency generators (480v, 1000amps) require GFI – Legally required generators do not require GFI or GFP EmergencySystems – Ground Fault (NEC 700.7 (D)) “To indicate a ground fault in solidly grounded wye emergency systems of more than 150 volts to ground and circuit-protective devices rated 1000 amperes or more.” LegallyRequired Standby -- Ground-FaultProtection ofEquipment (NEC 701.17) “The alternate source for legally required standby systems shall not be required to have ground-fault protection of equipment.” Are Generators required to have GFI or GFP?
  • 32. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q11) Are generators required to have GFI or GFP? – Optional standby generators typically don’t include GFP – Optional standby (480v, 1000 amps) could be required to include GFP (interpretation) • NEC 702 (Optional Standby) – No comment on GFP or GFI – Feeder Ground-Fault Protection of Equipment (NEC 215.10)  “Each feeder disconnect rated 1000 amperes or more and installed on solidly grounded wye electrical systems of more than 150 volts to ground, but not exceeding 600 volts phase-to-phase, shall be provided with ground-fault protection of equipment in accordance with the provisions of 230.95.” Are Generators required to have GFI or GFP?
  • 33. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Grounding and Ground Fault Summary • Generators can be separately or non-separatelyderived • Generator neutral should only be bonded at a single point • Generator requires a grounding conductor • Ground fault protection is not common on generator feeders
  • 35. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q12) What size is the generator breaker for a fire pump? – We have seen multiple requests for magnetic only breakers – We have seen multiple requests for breakers at 6x running amps – We feel this is a misinterpretation of NEC 695 requirements • Code is confusing, resulting in this behavior – Fire Pumps - Overcurrent Device Selection (NEC 695.4(B)(1)) “set to indefinitely carry the sum of locked rotor current”  This section only applies to “remote power sources” What is being confused is the utility versus the generator feeder. What size is the generator breaker for a fire pump?
  • 36. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • NEC 695 is also confusing on the issue of overload – NEC defines overload protection very specifically – Overload protection is defined in 430.32 (limited to 125% of rated) – If overcurrent protection is larger than 125% of rated amps  The circuit has no protection against overload (based on the NEC definition)  The circuit has short circuit protection only • Example of verbiage that causes misinterpretation – Fire Pump - Power Wiring - Overload Protection (NEC 695.6(D)) “Power circuits shall not have automatic protection against overloads. Branch circuits and feeder conductors shall be protected against short circuit only.” What size is the generator breaker for a fire pump?
  • 37. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • NEC 695 specifies the requirements for the generator – Sized for normal starting & running – Not sized for locked rotor amps Fire Pumps – Generator Capacity (NEC 695.3(B)(1)) “Generator Capacity. An on-site generator(s) used to comply with this section shall be of sufficient capacity to allownormal starting and running of the motor(s) …. A tap ahead of the on-site generator disconnecting means shall not be required…” Handbook: “…alternative source overcurrent protective device(s) for the electric-drive fire pump are not required to be sized for locked-rotor current of the fire pump motor(s). Rather, the circuit components of the alternative source are permitted to be sized according to Article 430...” What size is the generator breaker for a fire pump?
  • 38. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. • NEC 695 defines the size of the generator’s fire pump breaker – Generator’s fire pump breaker is between 125% to 250% of rated amps – Thisprovides no overload protection (>125%) – NEC430 limits the maximum size to 250% • Fire Pumps – Continuity of Power (NEC 695.4(B)) “... Overcurrent protective devices between an on-site standby generator and a fire pump controller shall be selected and sized according to 430.62 to provide short-circuit protection only.” What size is the generator breaker for a fire pump?
  • 39. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Q13) What are other requirements for fire pumps? – Voltage dip limited to 15% for normal starting – ATS must be fire pump rated – Generator must meet requirements for NFPA 110 Level 1  Reliable fuel (AHJ may require on-site fuel)  Remote audible alarm  NFPA 110 testing, maintenance and recording requirements What size is the generator breaker for a fire pump?
  • 40. Professional Development Seminar Series – GPS-140 National Electric Code (NEC) Portions hereof © 2004 National Fire Protection Association. Fire Pump Summary • Locked rotor amp sizing applies to the utility source • Generator’s fire pump breaker needs to be 125 to 250% of pump rating • Limit voltage dips to 15%
  • 41. GPS-140 National Electric Code (NEC) PROFESSIONAL DEVELOPMENT SEMINAR SERIES Thank you! Please complete the exit survey. And thank you for your live questions! Go to www.csemag.com to take the CEU test if you want AIA learning units for attending this Webcast. Thisevent will be archived at www.csemag.com for 12 monthsbeginningon or beforeDec. 15, 2007.