Analysis of Contractual Communication among parties to the contract
with respect to disputes in construction
Aniruddha A Patil1 and Dr. Sunil S Pimlikar2
1PG Student, Dr. Vishwanath Karad MIT World Peace University, Kothrud, Pune.
2Professor and Head, Civil Dept. Maharashtra Institute of Technology, Kothrud, Pune.
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Construction industry have a very vital role in financial condition of any country. Disputes are the very important
factors which affects the project. Communication plays crucial role in progress of all projects. Astheprojectunfoldsand thedesign
is realized, information in the form of drawings, specifications and construction methods must be communicated from one expert
to another. Therefore, using an appropriate communication method and communication medium to resolve construction and
design problems is essential. This researchpapercontainsvariousreasonsof dispute, importanceofcommunicationin construction
projects, various reasons behind lack of communication and their impact on performance of the project.
Key Words: : Construction disputes, Communication gap, Impact.
1.INTRODUCTION
Construction industry is the biggest asset to the financial status of any country. Construction industry has very strong impact
on economy of different countries. Disputes are the tumor to the construction industry. This tumour is unavoidable due to
various reasons. Construction disputes affects cost and time of completion, which results into time overrun and cost overrun.
Communication is the very important factor for the functions like planning, designing, production,organizingand managingof
any project. Poor or insufficient communication is one of the many factors behind disputes in construction projects. A
successful project demand that professionals involved are experienced, appropriate, have the same mindset,areteamplayers
with complimentary skill sets and are managed to bring out their best work to meet the vision and goals of the project.
Furthermore, communication between these professionals is an integral part of the construction process in any successful
project. During a project, communication can occur in variousdirectionsdependingonwhoiscommunicating. Thereisupward
communication to management from ones organization and the customer’s organization. Lateral communication takes place
with customers and within project teams. Machinery needs to be put in place for further communication to take place, either
downward communication (from superior to sub-ordinate), horizontal communication (between colleagues) or upward
communication (from sub-ordinates to superior). There are various reasons for disputes in construction industry. People
involved in the construction project are the key to successfully completing the project. Therefore it is necessary to invent
techniques for encouraging people to communicate, cooperate, face the problems at their occurrence, and try to resolve the
disputes as soon as possible. The key factor of solving disputes is how the organization approaches them.
1.1 PURPOSE OF WORK
Communication gap is the important reason for the disputes occurring on construction projects. Purpose of this researchisto
suggest methods to minimize the various disputes occurring due to lack of communication among different stakeholders of
construction site.
2. LITERATURE REVIEW
From the existing literature reviewed, some following observations were noted:
1. It is the people involved in project who make the construction process work successfully, the only way to change the
adversarial climate on project is to develop techniques for encouraging people to communicate, cooperate, deal
realistically with problems at the time they occur, and resolve disputes as early as possible [1].
2. To avoid construction disputes implementing good management technique with regard to people policy and
communication is more effective than attempting to shift risk to other parties by narrowing scope of services [2].
3. The success of project depends upon how the organization approaches problems and conflicts..
4. Majority of disputes have occurred due to lack of communication and misunderstanding between various stake
holders.[4].
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1122
5. There are four types of relationships between client and contractors: Adversarial, Guarded adversarial, Informal
partners, Project partners.
3. RESEARCH METHODOLOGY
The disputes always made negative impact on progress of construction projects. Therefore disputesshouldbesettledasearly
as possible. The researches believed that by usingproper methodsthesedisputescanbeavoidedorminimized.Thereforemain
objectives of the research were
1. To examine different causes of disputes in construction industry.
2. To find out the reasons behind lack of communication among different stakeholders.
3. To analyse the impact of lack of communication between the parties to the contract on the project performance.
To achieve the targets as mentioned above following methodology was adopted: For completing the first objective of the
research various previously published papers are studied.Actual interaction withconstructionprofessionalsisdone.Anonline
questionnaire was formed and circulated to the various stakeholders involved in constructionindustry.Qualitativeanalysisof
the responses from stakeholders was done. By analyzing questionnaire survey various reasons behind lack ofcommunication
were identified. Impact of disputes on project performance was identified by doing analysis of dispute cases.
4. DATA COLLECTION, ANALYSIS AND INTERPRETATION
In order to complete research objectives various data collection wasdone.Thisdata collectioninvolvedcollectionofminutesof
meetings, actual written letters between client and contractor, contract documents, various dispute case studies, online
questionnaire survey.
By studying the literature and case studies various reasonsofdisputeoccurringinconstructionindustrywereidentified. These
various reasons are as follows:
1. Contract errors or omissions
2. Different site conditions
3. Non-compliance of contractual obligations
4. Failing to correctly administrate the contract
5. Claims error
6. Failure to account the cost
7. Communication gap
8. The design deficiency
9. Defective plans
10. Methods and specification performance
11. Construction processes
12. Owner satisfaction
13. Quality of work
14. Warranties
15. Time
For finding out importance of communicationinorganizationandvariousreasonsbehindlack ofcommunication questionnaire
survey was done. The survey wasfloatedtovariousstakeholdersbelongingtoconstructionindustry. Thestakeholdersinvolved
in this survey was project managers, architects, engineers, rcc consultant, material supplier, board of directors etc.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1123
From the following Pie-chart, we can conclude that majority of the stakeholders do agree that there isa lack ofcommunication
among various stakeholders in their respective organizations. Approximately 64% of the respondents have experienced
improper communication in their organizations.
Almost 94% of the respondent have agreed to the hypothesis considered in this situation (Lack of communication is a
significant factor affecting the disputes in the construction industry). The results obtained from the questionnaire states the
hypothesis assumed is true.
Considering the major reasons stated by the respondents, following are significant reasons responsible for lack of
communication:
1. Difference in the Skill levels
2. Weak organization structure
3. Improper Communication Channels
4. Lack of an effective platform
5. Casual attitude of the stakeholders
For completing the third objective detailed analysis of different cases of disputes was done. By analysing 20 case studies
relationships between client and contractors were classified into four types. Case studies also helped to find out impact of
communication gap on the project performance.
Table No. 1
Case
No
Name and type
of work
Parties involved Assessmentof
relationship
Classificatio
n of types of
relationship
Effects on parties
Party
no.
Name Role
1 Agreement
regarding land
for five star hotel
including hotel
shopping arcade
1 Airport
Authority of
India (AAI)
Client In this case
both client and
contractor
were pursuing
their own
Adversarial Client had to extend
lease as contractor was
ready and willing to
perform its part of the
agreement
2 Grover
International
Contractor
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1124
(Construction of
hotel)
limited (GIL) interest at the
other parties
expense
2 Four laning and
strengthening of
the existing two
lane section
(Widening of
existing road)
1 National
Highway
Authority of
India (NHAI)
Client Both parties
refused to hear
each others
problems and
pushed for
their own
interests
Adversarial The client is restrained
from en-cashing the
bank guarantees and
contractor should keep
the same alive2 Sew
Infrastructure
Ltd
Contractor
3 The national
thermal power
station (NTPS),
construction of
port used for
coal import
(construction of
port)
1 National
thermal power
station (NTPS)
Client Client was not
accepting any
problems
showed by
contractor
Adversarial Client had to payback
extra made money from
contractor
2 XYZ Contractor
4 Construction of
Veer Baji
Palsakar
masonary dam
(construction of
dam)
1 State
Government of
Maharashtra
Client Client and
contractor
was only
seeing their
own benefit at
the expense of
other party
Adversarial The owner had to pay
contractor as
mentioned in contract
2 M/S Atur India
Pvt. Ltd.
Contractor
5 Florida
department of
transportation
(road
construction)
1 Tampa-
Hillsborough
County
Expressway
Authority
Client Client made
changes in the
contract
without
notifying
contractor
Adversarial Client was responsible
for the expended cost
and had to pay the extra
amount
2 Hubbard
Construction
Company
Contractor
6 Construction of
girls hostel at
NID, Gujarat
1 National
institute of
design
Client Client hired
his own
professionals
without telling
contractorand
demanded
changes in
construction
Adversarial Client was responsible
for dispute and had to
give compensation to
contracting firm.2 Xyz project
management
consultancy
Contractor
7 Widening and
upgrading
existing road
(widening of the
road)
1 National
Highway
Authority of
India (NHAI)
Client Parties
cooperate
within
boundaries of
the contract
Guarded
adversarial
All claims made by
NHAI were rejected by
arbitrator and by the
court.
2 Sew
Infrastructure
Ltd
Contractor
8 Four laning of
NS-26 project
(widening of
existing road)
1 National
Highway
Authority of
India (NHAI)
Client In this case
involved
parties gave
importance to
each other but
see them as
suspicious
allies
Guarded
adversarial
Claims of contractor
were dismissed by the
arbitrator
2 Bhageeratha
Engineering
Ltd.
Contractor
9 Widening of 1 National Client All the claims Guarded Client had to pay the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1125
four lanes and
rehabilitation of
existing
carriageway of
Pune – Satara
highway
(widening of
existing road)
Highways
Authority of
India
done by
contractor
was by
referring
contract
conditions
adversarial money to contractor.
2 ITD
Cementation
India, LTD
Contractor
Like this total 20 cases were analyzed. From this data impactoflack ofcommunication amongpartiesonprojectperformanceis
identified. Following are the impacts on project performance:
1. Cost overrun
2. Time overrun
3. Litigation cases
4. Damaged reputation of company
5. Loss of profitability
6. Deterioration of relationships among stakeholders
7. Extension in award procedures
8. Rework
9. Loss of professional reputation.
5. CONCLUSION
From the all above analysis we can conclude that relationships amongstakeholdersaffectsthe project.Communicationgapcan
result into delaying of project, overbudgeting of the project, need of rework etc. Communication gap is the root cause of
majority disputes occurring in the construction industry. A method could be suggested that will help the construction
organization to minimize communication gap among stakeholders.
REFERENCES
1. Luka Goji Tipili (2014) Evaluating the effects of communication in construction project delivery in Nigeria, Global
Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5)
2. Rui Cunha Marques (2017) Is arbitration right way to settle conflicts
3. Charles T. Jahren (1990) Investigation of construction disputes Journal of Management in Engineering, Vol. 6, No. 1
4. Foley J, Macmillan S (2005). Patterns of Interaction in Construction ream meeting
5. Project management handbook (2007). Communication management
6. http://www.scribd.com/doc/7875707/Project-CommunicationSummary-by-Sachitn-Mehra.

More Related Content

What's hot

AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAM Publications
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...Alexander Decker
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...Alexander Decker
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Rizwan Khurram
 
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...IAEME Publication
 
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...IRJET Journal
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewA Makwana
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Contract review
Contract reviewContract review
Contract reviewnethisip13
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...A Makwana
 

What's hot (20)

AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTE
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.Exploring the risk factors associated with peb projects in lahore.
Exploring the risk factors associated with peb projects in lahore.
 
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...
BRAND IMAGE, SERVICE QUALITY AND HOUSEHOLDER’S SATISFACTION AND LOYALTY TOWAR...
 
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
Y4408131137
Y4408131137Y4408131137
Y4408131137
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Contract review
Contract reviewContract review
Contract review
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
ANALYSIS OF RISK CATEGORIES AND FACTORS FOR PPP PROJECTS USING ANALYTIC HIERA...
 

Similar to IRJET- Analysis of Contractual Communication among Parties to the Contract with Respect to Disputes in Construction

Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...IRJET Journal
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...IJMREMJournal
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET Journal
 
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRY
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRYTHE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRY
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRYIRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxsaeedahmed433704
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...IRJET Journal
 
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsAM Publications
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction ProjectDr. Amarjeet Singh
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...IRJET Journal
 

Similar to IRJET- Analysis of Contractual Communication among Parties to the Contract with Respect to Disputes in Construction (20)

Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
Disputes Impact in Pakistan Construction Industry: A Comprehensive Study of R...
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure Projects
 
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRY
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRYTHE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRY
THE VALUE OF EFFECTIVE COMMUNICATION IN THE CONSTRUCTION INDUSTRY
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
PAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptxPAPER ID 109 Presentation.pptx
PAPER ID 109 Presentation.pptx
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
 
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects i...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Master's project viva zam
Master's project viva   zamMaster's project viva   zam
Master's project viva zam
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
Contractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure ProjectsContractual Steps for Smooth Delivery of Infrastructure Projects
Contractual Steps for Smooth Delivery of Infrastructure Projects
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...Critical Success Factors and Strategies for Sub-contractor Management in Infr...
Critical Success Factors and Strategies for Sub-contractor Management in Infr...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

IRJET- Analysis of Contractual Communication among Parties to the Contract with Respect to Disputes in Construction

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1121 Analysis of Contractual Communication among parties to the contract with respect to disputes in construction Aniruddha A Patil1 and Dr. Sunil S Pimlikar2 1PG Student, Dr. Vishwanath Karad MIT World Peace University, Kothrud, Pune. 2Professor and Head, Civil Dept. Maharashtra Institute of Technology, Kothrud, Pune. ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Construction industry have a very vital role in financial condition of any country. Disputes are the very important factors which affects the project. Communication plays crucial role in progress of all projects. Astheprojectunfoldsand thedesign is realized, information in the form of drawings, specifications and construction methods must be communicated from one expert to another. Therefore, using an appropriate communication method and communication medium to resolve construction and design problems is essential. This researchpapercontainsvariousreasonsof dispute, importanceofcommunicationin construction projects, various reasons behind lack of communication and their impact on performance of the project. Key Words: : Construction disputes, Communication gap, Impact. 1.INTRODUCTION Construction industry is the biggest asset to the financial status of any country. Construction industry has very strong impact on economy of different countries. Disputes are the tumor to the construction industry. This tumour is unavoidable due to various reasons. Construction disputes affects cost and time of completion, which results into time overrun and cost overrun. Communication is the very important factor for the functions like planning, designing, production,organizingand managingof any project. Poor or insufficient communication is one of the many factors behind disputes in construction projects. A successful project demand that professionals involved are experienced, appropriate, have the same mindset,areteamplayers with complimentary skill sets and are managed to bring out their best work to meet the vision and goals of the project. Furthermore, communication between these professionals is an integral part of the construction process in any successful project. During a project, communication can occur in variousdirectionsdependingonwhoiscommunicating. Thereisupward communication to management from ones organization and the customer’s organization. Lateral communication takes place with customers and within project teams. Machinery needs to be put in place for further communication to take place, either downward communication (from superior to sub-ordinate), horizontal communication (between colleagues) or upward communication (from sub-ordinates to superior). There are various reasons for disputes in construction industry. People involved in the construction project are the key to successfully completing the project. Therefore it is necessary to invent techniques for encouraging people to communicate, cooperate, face the problems at their occurrence, and try to resolve the disputes as soon as possible. The key factor of solving disputes is how the organization approaches them. 1.1 PURPOSE OF WORK Communication gap is the important reason for the disputes occurring on construction projects. Purpose of this researchisto suggest methods to minimize the various disputes occurring due to lack of communication among different stakeholders of construction site. 2. LITERATURE REVIEW From the existing literature reviewed, some following observations were noted: 1. It is the people involved in project who make the construction process work successfully, the only way to change the adversarial climate on project is to develop techniques for encouraging people to communicate, cooperate, deal realistically with problems at the time they occur, and resolve disputes as early as possible [1]. 2. To avoid construction disputes implementing good management technique with regard to people policy and communication is more effective than attempting to shift risk to other parties by narrowing scope of services [2]. 3. The success of project depends upon how the organization approaches problems and conflicts.. 4. Majority of disputes have occurred due to lack of communication and misunderstanding between various stake holders.[4].
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1122 5. There are four types of relationships between client and contractors: Adversarial, Guarded adversarial, Informal partners, Project partners. 3. RESEARCH METHODOLOGY The disputes always made negative impact on progress of construction projects. Therefore disputesshouldbesettledasearly as possible. The researches believed that by usingproper methodsthesedisputescanbeavoidedorminimized.Thereforemain objectives of the research were 1. To examine different causes of disputes in construction industry. 2. To find out the reasons behind lack of communication among different stakeholders. 3. To analyse the impact of lack of communication between the parties to the contract on the project performance. To achieve the targets as mentioned above following methodology was adopted: For completing the first objective of the research various previously published papers are studied.Actual interaction withconstructionprofessionalsisdone.Anonline questionnaire was formed and circulated to the various stakeholders involved in constructionindustry.Qualitativeanalysisof the responses from stakeholders was done. By analyzing questionnaire survey various reasons behind lack ofcommunication were identified. Impact of disputes on project performance was identified by doing analysis of dispute cases. 4. DATA COLLECTION, ANALYSIS AND INTERPRETATION In order to complete research objectives various data collection wasdone.Thisdata collectioninvolvedcollectionofminutesof meetings, actual written letters between client and contractor, contract documents, various dispute case studies, online questionnaire survey. By studying the literature and case studies various reasonsofdisputeoccurringinconstructionindustrywereidentified. These various reasons are as follows: 1. Contract errors or omissions 2. Different site conditions 3. Non-compliance of contractual obligations 4. Failing to correctly administrate the contract 5. Claims error 6. Failure to account the cost 7. Communication gap 8. The design deficiency 9. Defective plans 10. Methods and specification performance 11. Construction processes 12. Owner satisfaction 13. Quality of work 14. Warranties 15. Time For finding out importance of communicationinorganizationandvariousreasonsbehindlack ofcommunication questionnaire survey was done. The survey wasfloatedtovariousstakeholdersbelongingtoconstructionindustry. Thestakeholdersinvolved in this survey was project managers, architects, engineers, rcc consultant, material supplier, board of directors etc.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1123 From the following Pie-chart, we can conclude that majority of the stakeholders do agree that there isa lack ofcommunication among various stakeholders in their respective organizations. Approximately 64% of the respondents have experienced improper communication in their organizations. Almost 94% of the respondent have agreed to the hypothesis considered in this situation (Lack of communication is a significant factor affecting the disputes in the construction industry). The results obtained from the questionnaire states the hypothesis assumed is true. Considering the major reasons stated by the respondents, following are significant reasons responsible for lack of communication: 1. Difference in the Skill levels 2. Weak organization structure 3. Improper Communication Channels 4. Lack of an effective platform 5. Casual attitude of the stakeholders For completing the third objective detailed analysis of different cases of disputes was done. By analysing 20 case studies relationships between client and contractors were classified into four types. Case studies also helped to find out impact of communication gap on the project performance. Table No. 1 Case No Name and type of work Parties involved Assessmentof relationship Classificatio n of types of relationship Effects on parties Party no. Name Role 1 Agreement regarding land for five star hotel including hotel shopping arcade 1 Airport Authority of India (AAI) Client In this case both client and contractor were pursuing their own Adversarial Client had to extend lease as contractor was ready and willing to perform its part of the agreement 2 Grover International Contractor
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1124 (Construction of hotel) limited (GIL) interest at the other parties expense 2 Four laning and strengthening of the existing two lane section (Widening of existing road) 1 National Highway Authority of India (NHAI) Client Both parties refused to hear each others problems and pushed for their own interests Adversarial The client is restrained from en-cashing the bank guarantees and contractor should keep the same alive2 Sew Infrastructure Ltd Contractor 3 The national thermal power station (NTPS), construction of port used for coal import (construction of port) 1 National thermal power station (NTPS) Client Client was not accepting any problems showed by contractor Adversarial Client had to payback extra made money from contractor 2 XYZ Contractor 4 Construction of Veer Baji Palsakar masonary dam (construction of dam) 1 State Government of Maharashtra Client Client and contractor was only seeing their own benefit at the expense of other party Adversarial The owner had to pay contractor as mentioned in contract 2 M/S Atur India Pvt. Ltd. Contractor 5 Florida department of transportation (road construction) 1 Tampa- Hillsborough County Expressway Authority Client Client made changes in the contract without notifying contractor Adversarial Client was responsible for the expended cost and had to pay the extra amount 2 Hubbard Construction Company Contractor 6 Construction of girls hostel at NID, Gujarat 1 National institute of design Client Client hired his own professionals without telling contractorand demanded changes in construction Adversarial Client was responsible for dispute and had to give compensation to contracting firm.2 Xyz project management consultancy Contractor 7 Widening and upgrading existing road (widening of the road) 1 National Highway Authority of India (NHAI) Client Parties cooperate within boundaries of the contract Guarded adversarial All claims made by NHAI were rejected by arbitrator and by the court. 2 Sew Infrastructure Ltd Contractor 8 Four laning of NS-26 project (widening of existing road) 1 National Highway Authority of India (NHAI) Client In this case involved parties gave importance to each other but see them as suspicious allies Guarded adversarial Claims of contractor were dismissed by the arbitrator 2 Bhageeratha Engineering Ltd. Contractor 9 Widening of 1 National Client All the claims Guarded Client had to pay the
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1125 four lanes and rehabilitation of existing carriageway of Pune – Satara highway (widening of existing road) Highways Authority of India done by contractor was by referring contract conditions adversarial money to contractor. 2 ITD Cementation India, LTD Contractor Like this total 20 cases were analyzed. From this data impactoflack ofcommunication amongpartiesonprojectperformanceis identified. Following are the impacts on project performance: 1. Cost overrun 2. Time overrun 3. Litigation cases 4. Damaged reputation of company 5. Loss of profitability 6. Deterioration of relationships among stakeholders 7. Extension in award procedures 8. Rework 9. Loss of professional reputation. 5. CONCLUSION From the all above analysis we can conclude that relationships amongstakeholdersaffectsthe project.Communicationgapcan result into delaying of project, overbudgeting of the project, need of rework etc. Communication gap is the root cause of majority disputes occurring in the construction industry. A method could be suggested that will help the construction organization to minimize communication gap among stakeholders. REFERENCES 1. Luka Goji Tipili (2014) Evaluating the effects of communication in construction project delivery in Nigeria, Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5) 2. Rui Cunha Marques (2017) Is arbitration right way to settle conflicts 3. Charles T. Jahren (1990) Investigation of construction disputes Journal of Management in Engineering, Vol. 6, No. 1 4. Foley J, Macmillan S (2005). Patterns of Interaction in Construction ream meeting 5. Project management handbook (2007). Communication management 6. http://www.scribd.com/doc/7875707/Project-CommunicationSummary-by-Sachitn-Mehra.