Integrating Innovative and Sustainable Developments in Civil Engineering
PAPER ID: 109
An Expert System for Disputes Avoidance in Highways,
Public Sector Projects of Pakistan Construction Industry
Authors
Saeed Ahmeda*, Nafees Ahmed Memona, Tauha Hussain Alia Aftab Hameed Memonb Ali Raza
Khosoa
Integrating Innovative and Sustainable Developments in Civil Engineering
Contents
Introduction
Literature Review
Research methodology
Results and discussion
Conclusion
References
Integrating Innovative and Sustainable Developments in Civil Engineering
Introduction.
 The construction sector, defined as "activities involved with the
construction of physical infrastructure and related activities," plays a crucial
part in the nation's economy. It was anticipated that this sector's
production would contribute significantly to gross constant capital
creation. In addition, research investigations have suggested that the
expansion of the construction industry is linked to the growth of other
businesses. As an important modern business, the construction sector has
a substantial impact on the economy and labor force of any nation [1].
 The construction industry is regarded as being crucial to the development
of any nation's economy, and investments made in this industry have a
significant impact on all other economic sectors[2].
Integrating Innovative and Sustainable Developments in Civil Engineering
While this industry is engaged in the preparation of lands and building of real estate
throughout the nation, the participants in the construction industry have a variety of
perspectives, talents, and high levels of knowledge in the construction sector. In addition to
developing an expert system for dispute avoidance in public sector road construction
projects, this research study is focused on identifying important issues that are,
contributing to disputes connected to road projects in Pakistan's construction industry [3].
Conflict.
Conflicts are simply described as opposing participant interests in the execution of a
project contract. Conflict was defined by Edmonds and Kennedy as disagreements over a
project's execution, frequently the consequence of discussions concerning how differently
two or more people perceive the circumstances. Conflicts arise when one person's actions
obstruct or interfere with those of another [4].
Introduction.
Claim.
The Canadian Law Dictionary says. The claim is described as a "statement to the right to
remedy, comfort, or property" or a "failure to meet obligations under the agreement" [6].
Additionally, the definition of "claim" in the Oxford English Dictionary is "a demand for
something as due, an action of right to something," which is derived from the old French
word "clima" [7].
Disputes.
A dispute is defined as a specific disagreement over a matter of fact, law, or policy in which
a claim or assertion is rejected and that rejection is not accepted [9]. Any contract question
or argument that needs to be resolved outside of the jobsite control group of workers is a
dispute, according to Baloch, SA et al, (2018) definition [10]. Due to the complexity of the
construction industry, some difficulties will occasionally arise for the stakeholders. The
different perspectives of the stakeholders, including the sponsor, function Object and
engineer, on the development issues. As a result, whenever there are issues and
disagreements, a confrontation over that something is unavoidable [12].
Introduction.
Elziny, A. et al. (2016) noted that the construction business has developed into one of the most
unfavourable and trouble-prone, with claims and disputes on projects and construction jobs being the
norm rather than the exception. Because of the enormous risk that disagreements present, rational
decision-making is necessary [13].
Literature Review.
Fig. 1 shows the flow diagram of dispute occurrence
Mrs. Arcadies (2016), Construction disputes in Asia continue to rank highly according to
studies. Customers and sponsors are the primary suppliers of resources in the construction
development industry. All problems, their causes, and their effects are interconnected with
customers[16]. Planning, design, drawings, conduct, building technique, significances, and
order exchange are a few examples of the various types of conflicts that can result in claims
and disputes in the construction industry. The primary reasons of arguments among
members of the creation enterprise are issues from the outside world, delays in delivering
drawings, billing, design errors, procurement, and handing over the website to the client
[17].
Irlayc akmak, P. (2016) also looked at the disputes in the Turkish construction sector. This
study examined the issues and root causes of disagreements in building projects. This
study came to the conclusion that the risk to participants, the time constraints, the
intended cost, and the proper quality are the main sources of conflicts. If they are not
managed effectively, projects won't be completed successfully [21].
Literature Review.
A professional-level intellectual computer software programmer application to a few
particular areas for coding the facts is called a "knowledge-based expert system" (KBES).
The purpose of using this precise method is to solve issues at the level of human
capabilities [19].
Muhammad Akram (2016) recognized the important factor that contributes to time and
cost overruns in building projects for the Pakistani construction sector and created a
professional guide for managing measures for the major component time and cost overrun
[24]. Failures to perform have become a notable element of the building construction
industry. This wide range of failures, from little fractures to complete collapse, are linked to
a number of negative outcomes. Abbas Muhammad Burhan (2016) additionally created an
"expert system for investigation of failure in the construction business" [25].
And El-Adaway, Ogburn (2013). Conducted a study to look into the cause-and-effect chain
of disputes. The investigation concluded that risks, conflicts, and claims are the main
causes. These issues eventually result in disagreements, and if they are not appropriately
handled, they have a severe impact on the project's completion [26].
Literature Review.
Research Methodology
Fig 2. Shows Research Methodology Flow chart
Data Analysis and Results
National Highway
Authority
46%
Works and Services
31%
Pakistan Works
Department
23%
Range of Respondents from public Sector Road Construction
Department
National Highway Authority Works and Services Pakistan Works Department
Fig. 3 shows the statistics of questionnaire
75 questionnaires from public sector road construction departments, 46% from the national
highway authority (NHA), 31% from works and services, and 23% from Pakistan Works
Department (PWD) of the country's construction industry were successfully collected from
the respondents after 106 questionnaires were distributed to them. The problems were
identified which are leading to disputes in road construction projects are:
Data Analysis and Results
4.8
4.72
4.24
4.21
4.05
3.89
3.75
0 1 2 3 4 5 6
ERROR IN PROJECT DESIGN
POOR QUALITY PERFORMANCE OF CONTRACTOR
POOR COMMUNICATION
UNAVAILABILITY OF RIGHT OF WAY (ROW)
EXTERNAL FACTOR INFLUENCES
POOR SELECTION OF DIVERSION FOR TRAFFIC FLOW
ABSENCE OF PRE-QUALIFICATION PROCESS FOR CONTRACTOR SELECTION
Most significant problem which are leading to disputes
Most significant problem which are leading to disputes
Causes and controlling measures related to the significant problems
S.
No
Causes of the problem Controlling Measure
I. During survey activities,
uncalibrated devices were
employed
The consultant makes sure that every device seems
faultless.
conducting instrument error testing prior to the start
of the survey
II. Incorrect design data Before beginning design, the design data should be
thoroughly analyzed.
to confirm that all info is correct according to the site
Table. 1 shows causes and controlling measure related to problem Error in project design
Causes and controlling measures related to the significant problems
S. No Causes of the problem Controlling Measure
I.
Defects during the construction
stage that become apparent during
liability period
Before handing over the site, create a list of defects.
The contractor is bounded to resolve all defects
II.
Insufficient quality standard
operating procedures by the
contracting company
To make sure that the quality control mechanism is
followed
To appoint a quality assurance manager
III. Unsatisfactory labor productivity
Setting a self-imposed timeframe procedure
Begin workshops, seminars, seminars and put the two
mints rules into action.
Table. 2 shows causes and controlling measure related to problem Poor quality performance of contractor
Causes and controlling measures related to the significant problems
S. No Causes of the problem Controlling Measure
I.
Ineffective collaboration with
other departments
To establish a committee to co - ordinate with multiple
departments
To cultivate effective leadership abilities and
qualities within the organisation in order to achieve co –
ordination
II.
Intentionally delaying the flow of
information
Create an efficient information process flow.
Workshops and training should be held on a regular
basis.
Table. 3 shows causes and controlling measure related to problem Poor communication
Causes and controlling measures related to the significant problems
S. No Causes of the problem Controlling Measure
I. Land acquisition
The right to receive just compensation when land is
acquired
Disclosure of all relevant information regarding the
acquisition of land under the rehabilitation or resettlement
act.
II. Ethical/Holy places
Alteration to the blueprint for the motorways, highways and
road construction.
to reroute the road as much as possible in order to save the
sacred places
III.
land acquisition rewards are not
given to the incentives
Establish a procedure for equitable compensation in the
process of land acquisition.
In order to acquire land through the adoption of a
rehabilitation and resettlement act
Table. 4 shows causes and controlling measure related to Unavailability of Right of Way (ROW)
Causes and controlling measures related to the significant problems
S. No Causes of the problem Controlling Measure
I.
Interference of political processes in
construction
Dependencies on external parties
Getting a response that can be considered
reasonable
II.
Delay in the process of obtaining a
certificate of no objection (NOC)
management that works well with various
stakeholders
Obtain the NOC before placing any bids.
Table. 5 shows causes and controlling measure related to problem external factor influences
Causes and controlling measures related to the significant problems
S. No Causes of the problem Controlling Measure
I.
Inadequate preparation in ahead of
time
Carry out a pre-construction planning of the
necessary activities and resources for the project.
It is important to involve the project manager along
with the rest of the team during the initial stages of
planning.
II.
Disruptions in the neighboring
areas
Taking preventative measures to redirect high
volumes of traffic away from construction/residential
areas
Plan for the Regulation of Traffic
Table. 6 shows causes and controlling measure related to problem poor selection of diversion for traffic flow
Developing an Expert System for Disputes Avoidance in highways Construction Projects.
The Purposes of developing of Expert System (DES) is to provide a user interface approachable system
for defining the various causes of disputes performances in road construction sector. It will also able to
suggest appropriate and controlling measure to avoid disputes during road construction project. The
following tasks are involved in the development of an Expert system to overcome from disputes.
1. Identifying the issues that are causing the road construction project to be delayed and contentious.
2. Determining the significant level of causative factor which are leading to disputes through (SPSS).
3. Determining appropriate controlling remedial measure to overcome from disputes.
4. Establishing an Expert System for the Purpose of Suggesting Appropriate and Governing Measures to
Prevent Disputes
Focus of this paper is the determination of the factors that contribute to disputes in highways construction
projects, and it uses both qualitative and quantitative methods. SPSS is used to perform the analysis on the
data. The primary contribution made by this study is the integration of expert systems (ES) with experience-
based recommendations from the construction industry regarding appropriate and controlling dispute
prevention measures for use during road construction projects.
The Conceptual Frame Work of Expert System for Disputes Avoidance in road
construction project.
Expert system will provide a user interface approachable system for the determination of
problems that lead to disputes in the road construction sector. This ES will also support the users in
suggesting and appropriate controlling measures to avoid disputes during road construction
projects.
Working Mechanism of Expert System
KBES for road construction dispute avoidance helps users step-by-step.
In the first step of evaluating knowledge-based expert system input from users, when the
user starts the program, a new window will open on screen where the user will enter user
name and password to get access and select the disputes-causing problems. Start
Programming
Working Mechanism of Expert System
After starting the program, than Enter the problem
Fig. 5 Shows Screen shot of displayed Problem which is leading to disputes
The user will choose the most important problem causes
as usual in roadway projects. To avoid construction
disputes, the expert system will present control measures
for each of the following causes.
Fig. 6 Screen shot of displayed significant causes of the problem
Working Mechanism of Expert System
Fig. 7 Shows Screen shot of displayed controlling measures of causes to avoid
dispute
1. Conclusion:
This research paper proposes a conceptual framework for developing intellectual computer software (ES)
to suggest and control construction industry disputes. As mentioned, most construction projects worldwide
experience disputes. Significant issues and their causes are causing construction disputes that will delay
project completion. The ESDA&SCM framework can identify major issues that cause disputes and suggest
ways to avoid them in road construction projects to improve performance. This study also shows the most
effective dispute avoidance methods. The knowledge-based expert system developed using structured query
language (MYSQL) database, hypertext preprocessor (PHP) server site scripting, and HTML/Java Script
user interface achieved the research's main goal. To avoid conflict, the system controls problems, causes,
and their controls. If applied to road construction, the suggested controlling remedial measures will prevent
disputes and finish the project on time and within budget.
6. Reference
1. Saad, A., “Development the A Dispute Resolution Framework to Improve the Efficiency of Dispute Resolution
in Saudi Construction Projects”, Ph.D. Thesis, university of Salford collage of Science and Technology School
of the Built Environment. (2017)
2. Edmonds, W.A. and Kennedy, T. D., “An Applied Reference Guide to Research Designs: Quantitative,
Qualitative, and Mixed Methods. London” SAGE, (2012).
3. Femi, O.T., “Causes and effects of conflict in the Nigerian Construction Industry,” International journal of
Technology Enhancements and Emerging Engineering Research journal V. 2(6), pp.7-16, (2014)
4. Chan, H., “Innovations in construction disputology” In A half day professional workshop on international
construction contract management. V.1, (pp. 5-17), (2008, October).
5. Agwu, M. O., “Total Safety Management: A Strategy for Improving Organisational Performance in Chosen
Construction Companies in Nigeria”. International Journal of Business and Social Science, 3(20), (2012).
6. Cheung, S. O., & Yiu, T. W., “Are construction disputes inevitable”, IEEE Transactions on Engineering
Management, 53(3), 456-470, (2006).
7. Goldberg, D. M., “As the world burns: negotiating the framework convention on climate change”, Geo. Int'l
Envtl. L. Rev., 5, 239 (1992).
8. Baloch, S.A., Memon, N.A. and Khoso, A.R., “Developing Conceptual Framework to Improve the Efficiency
of Disputes Avoidance in Public Sector Road Projects in Pakistan Construction Industry”, 2nd international
conference on sustainable development in civil engineering, 5th to 7th December, 2019.
9. Baloch, S.A., Memon, N.A. and Khoso, A.R. “Disputes impact in Pakistan construction industry: A
Comprehensive study of road development projects”, IJMREM Vol. 1, Issue 10, Issn No. 2581-4540,
November 2018.
10. Cheung SO, Yiu TW. “A study of construction mediator tactics Part I: taxonomies of dispute sources, mediator
tactics and mediation outcomes”, J Build Environ 2007:752–61.
6. Reference
11. Hashmi, S.A.S.; Memon, N.A.; Ali, T.H.; Ahmed, S.; and Leghari, M.A., “Problems Caused Due to Low Bid
Award System: A Case Study of Public Sector Construction Projects in Pakistan”. Proceeding of the
International Conference on Sustainable Development in Civil Engineering MUET, Jamshoro Sindh Pakistan,
(2017).
12. Elzing, A.A.; Mohamadien, A.M.; And Ibrahim, M.H.; & Fatha A.K.M., “An Expert system to Manage disputes
resolution in construction projects in Egypt,” Ain Shams Engineering Journal, V. 7, Issue 1, pp. 57-71, (2016).
13. Morqan, C., “Failure to properly administer contract, errors and omission in the contract, and properly drafted
claims are the main causes of disputes,” Research presented in international conference 28 June 2016.
14. Erdis, E.; Ozdenir, A.S., “Analysis of Technical Specification based on disputes in construction industry,”
KSEC journal of civil engineering 2013.
15. Cakmak, E.; Cakmak, I.P., “An analysis of causes of disputes in the construction industries of Pakistan using an
analytical network process,” Okan university, Istanbul, (2014), 34959, Turkey
16. Bolloju, N.; Schneider, C.; and Sugumaran, V., “A Knowledge-Based System for improving the Consistency
between Object Model and Use Case Narrative,” Expert system with application, V. 39, 9398-9410. 2012.
17. Irlayıcı, Ç. P., “Causes of disputes in the Turkish construction industry: Case of public sector projects”. A Z ITU
Journal of the Faculty of Architecture, 13(3), 109-118, (2016).
18. Demirkesen, S.; and Ozoehon, B. (2017), “Impect of Integration Management on Construction Project
Management Performance,” International Journal of Project Management. Vol. 35, Pages 1639-1654 Issue on
08 Nov: 2017.
19. Akram, M., “Developing Knowledge Based Expert System for Controlling Time Overrun And Cost Overrun In
Construction Industry Of Pakistan.” M.E Thesis, MUET Jamshoro. 2016.
PAPER ID 109 Presentation.pptx

More Related Content

Similar to PAPER ID 109 Presentation.pptx

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...IRJET Journal
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodIRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewIRJET Journal
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...IRJET Journal
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET Journal
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET Journal
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSIAEME Publication
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268HASHIM HANIF
 

Similar to PAPER ID 109 Presentation.pptx (20)

IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
D012261521
D012261521D012261521
D012261521
 
Ijciet 10 01_088
Ijciet 10 01_088Ijciet 10 01_088
Ijciet 10 01_088
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Documentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- ReviewDocumentation and Process Challenges Faced at Works Department- Review
Documentation and Process Challenges Faced at Works Department- Review
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
20320140503023
2032014050302320320140503023
20320140503023
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 

More from saeedahmed433704

STONE as engineering materials in buildings
STONE as engineering materials in buildingsSTONE as engineering materials in buildings
STONE as engineering materials in buildingssaeedahmed433704
 
Communication Skills for engineers1 (3).pptx
Communication Skills for engineers1 (3).pptxCommunication Skills for engineers1 (3).pptx
Communication Skills for engineers1 (3).pptxsaeedahmed433704
 
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptx
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptxy_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptx
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptxsaeedahmed433704
 
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptx
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptxMarketing-Management-Unit-2-Dr-Neha-Vashistha.pptx
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptxsaeedahmed433704
 
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdf
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdfA-configurational-explanation-for-performance-mana_2019_International-Journa.pdf
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdfsaeedahmed433704
 
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdf
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdfWomen-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdf
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdfsaeedahmed433704
 
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdf
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdfWhy-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdf
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdfsaeedahmed433704
 
RECYCLE ANR REUSE OF SOLID WASTE.pptx
RECYCLE ANR REUSE OF SOLID WASTE.pptxRECYCLE ANR REUSE OF SOLID WASTE.pptx
RECYCLE ANR REUSE OF SOLID WASTE.pptxsaeedahmed433704
 
lecture 01 Materials and methods of construction.pptx
lecture 01 Materials and methods of construction.pptxlecture 01 Materials and methods of construction.pptx
lecture 01 Materials and methods of construction.pptxsaeedahmed433704
 

More from saeedahmed433704 (11)

STONE as engineering materials in buildings
STONE as engineering materials in buildingsSTONE as engineering materials in buildings
STONE as engineering materials in buildings
 
Communication Skills for engineers1 (3).pptx
Communication Skills for engineers1 (3).pptxCommunication Skills for engineers1 (3).pptx
Communication Skills for engineers1 (3).pptx
 
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptx
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptxy_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptx
y_chapter_1_intro_to_consumer_behaviour_ahmad_yamin.pptx
 
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptx
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptxMarketing-Management-Unit-2-Dr-Neha-Vashistha.pptx
Marketing-Management-Unit-2-Dr-Neha-Vashistha.pptx
 
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdf
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdfA-configurational-explanation-for-performance-mana_2019_International-Journa.pdf
A-configurational-explanation-for-performance-mana_2019_International-Journa.pdf
 
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdf
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdfWomen-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdf
Women-directors-contribution-to-organizational-inn_2018_Scandinavian-Journal.pdf
 
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdf
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdfWhy-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdf
Why-do-millennials-stay-in-their-jobs--The-roles-of-prote_2020_Journal-of-Vo.pdf
 
RECYCLE ANR REUSE OF SOLID WASTE.pptx
RECYCLE ANR REUSE OF SOLID WASTE.pptxRECYCLE ANR REUSE OF SOLID WASTE.pptx
RECYCLE ANR REUSE OF SOLID WASTE.pptx
 
lecture 01 Materials and methods of construction.pptx
lecture 01 Materials and methods of construction.pptxlecture 01 Materials and methods of construction.pptx
lecture 01 Materials and methods of construction.pptx
 
cOST eSTIMATION.pptx
cOST eSTIMATION.pptxcOST eSTIMATION.pptx
cOST eSTIMATION.pptx
 
Concrete Technology.pptx
Concrete Technology.pptxConcrete Technology.pptx
Concrete Technology.pptx
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

PAPER ID 109 Presentation.pptx

  • 1. Integrating Innovative and Sustainable Developments in Civil Engineering
  • 2. PAPER ID: 109 An Expert System for Disputes Avoidance in Highways, Public Sector Projects of Pakistan Construction Industry Authors Saeed Ahmeda*, Nafees Ahmed Memona, Tauha Hussain Alia Aftab Hameed Memonb Ali Raza Khosoa Integrating Innovative and Sustainable Developments in Civil Engineering
  • 3. Contents Introduction Literature Review Research methodology Results and discussion Conclusion References Integrating Innovative and Sustainable Developments in Civil Engineering
  • 4. Introduction.  The construction sector, defined as "activities involved with the construction of physical infrastructure and related activities," plays a crucial part in the nation's economy. It was anticipated that this sector's production would contribute significantly to gross constant capital creation. In addition, research investigations have suggested that the expansion of the construction industry is linked to the growth of other businesses. As an important modern business, the construction sector has a substantial impact on the economy and labor force of any nation [1].  The construction industry is regarded as being crucial to the development of any nation's economy, and investments made in this industry have a significant impact on all other economic sectors[2]. Integrating Innovative and Sustainable Developments in Civil Engineering
  • 5. While this industry is engaged in the preparation of lands and building of real estate throughout the nation, the participants in the construction industry have a variety of perspectives, talents, and high levels of knowledge in the construction sector. In addition to developing an expert system for dispute avoidance in public sector road construction projects, this research study is focused on identifying important issues that are, contributing to disputes connected to road projects in Pakistan's construction industry [3]. Conflict. Conflicts are simply described as opposing participant interests in the execution of a project contract. Conflict was defined by Edmonds and Kennedy as disagreements over a project's execution, frequently the consequence of discussions concerning how differently two or more people perceive the circumstances. Conflicts arise when one person's actions obstruct or interfere with those of another [4]. Introduction.
  • 6. Claim. The Canadian Law Dictionary says. The claim is described as a "statement to the right to remedy, comfort, or property" or a "failure to meet obligations under the agreement" [6]. Additionally, the definition of "claim" in the Oxford English Dictionary is "a demand for something as due, an action of right to something," which is derived from the old French word "clima" [7]. Disputes. A dispute is defined as a specific disagreement over a matter of fact, law, or policy in which a claim or assertion is rejected and that rejection is not accepted [9]. Any contract question or argument that needs to be resolved outside of the jobsite control group of workers is a dispute, according to Baloch, SA et al, (2018) definition [10]. Due to the complexity of the construction industry, some difficulties will occasionally arise for the stakeholders. The different perspectives of the stakeholders, including the sponsor, function Object and engineer, on the development issues. As a result, whenever there are issues and disagreements, a confrontation over that something is unavoidable [12]. Introduction.
  • 7. Elziny, A. et al. (2016) noted that the construction business has developed into one of the most unfavourable and trouble-prone, with claims and disputes on projects and construction jobs being the norm rather than the exception. Because of the enormous risk that disagreements present, rational decision-making is necessary [13]. Literature Review. Fig. 1 shows the flow diagram of dispute occurrence
  • 8. Mrs. Arcadies (2016), Construction disputes in Asia continue to rank highly according to studies. Customers and sponsors are the primary suppliers of resources in the construction development industry. All problems, their causes, and their effects are interconnected with customers[16]. Planning, design, drawings, conduct, building technique, significances, and order exchange are a few examples of the various types of conflicts that can result in claims and disputes in the construction industry. The primary reasons of arguments among members of the creation enterprise are issues from the outside world, delays in delivering drawings, billing, design errors, procurement, and handing over the website to the client [17]. Irlayc akmak, P. (2016) also looked at the disputes in the Turkish construction sector. This study examined the issues and root causes of disagreements in building projects. This study came to the conclusion that the risk to participants, the time constraints, the intended cost, and the proper quality are the main sources of conflicts. If they are not managed effectively, projects won't be completed successfully [21]. Literature Review.
  • 9. A professional-level intellectual computer software programmer application to a few particular areas for coding the facts is called a "knowledge-based expert system" (KBES). The purpose of using this precise method is to solve issues at the level of human capabilities [19]. Muhammad Akram (2016) recognized the important factor that contributes to time and cost overruns in building projects for the Pakistani construction sector and created a professional guide for managing measures for the major component time and cost overrun [24]. Failures to perform have become a notable element of the building construction industry. This wide range of failures, from little fractures to complete collapse, are linked to a number of negative outcomes. Abbas Muhammad Burhan (2016) additionally created an "expert system for investigation of failure in the construction business" [25]. And El-Adaway, Ogburn (2013). Conducted a study to look into the cause-and-effect chain of disputes. The investigation concluded that risks, conflicts, and claims are the main causes. These issues eventually result in disagreements, and if they are not appropriately handled, they have a severe impact on the project's completion [26]. Literature Review.
  • 10. Research Methodology Fig 2. Shows Research Methodology Flow chart
  • 11. Data Analysis and Results National Highway Authority 46% Works and Services 31% Pakistan Works Department 23% Range of Respondents from public Sector Road Construction Department National Highway Authority Works and Services Pakistan Works Department Fig. 3 shows the statistics of questionnaire 75 questionnaires from public sector road construction departments, 46% from the national highway authority (NHA), 31% from works and services, and 23% from Pakistan Works Department (PWD) of the country's construction industry were successfully collected from the respondents after 106 questionnaires were distributed to them. The problems were identified which are leading to disputes in road construction projects are:
  • 12. Data Analysis and Results 4.8 4.72 4.24 4.21 4.05 3.89 3.75 0 1 2 3 4 5 6 ERROR IN PROJECT DESIGN POOR QUALITY PERFORMANCE OF CONTRACTOR POOR COMMUNICATION UNAVAILABILITY OF RIGHT OF WAY (ROW) EXTERNAL FACTOR INFLUENCES POOR SELECTION OF DIVERSION FOR TRAFFIC FLOW ABSENCE OF PRE-QUALIFICATION PROCESS FOR CONTRACTOR SELECTION Most significant problem which are leading to disputes Most significant problem which are leading to disputes
  • 13. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. During survey activities, uncalibrated devices were employed The consultant makes sure that every device seems faultless. conducting instrument error testing prior to the start of the survey II. Incorrect design data Before beginning design, the design data should be thoroughly analyzed. to confirm that all info is correct according to the site Table. 1 shows causes and controlling measure related to problem Error in project design
  • 14. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. Defects during the construction stage that become apparent during liability period Before handing over the site, create a list of defects. The contractor is bounded to resolve all defects II. Insufficient quality standard operating procedures by the contracting company To make sure that the quality control mechanism is followed To appoint a quality assurance manager III. Unsatisfactory labor productivity Setting a self-imposed timeframe procedure Begin workshops, seminars, seminars and put the two mints rules into action. Table. 2 shows causes and controlling measure related to problem Poor quality performance of contractor
  • 15. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. Ineffective collaboration with other departments To establish a committee to co - ordinate with multiple departments To cultivate effective leadership abilities and qualities within the organisation in order to achieve co – ordination II. Intentionally delaying the flow of information Create an efficient information process flow. Workshops and training should be held on a regular basis. Table. 3 shows causes and controlling measure related to problem Poor communication
  • 16. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. Land acquisition The right to receive just compensation when land is acquired Disclosure of all relevant information regarding the acquisition of land under the rehabilitation or resettlement act. II. Ethical/Holy places Alteration to the blueprint for the motorways, highways and road construction. to reroute the road as much as possible in order to save the sacred places III. land acquisition rewards are not given to the incentives Establish a procedure for equitable compensation in the process of land acquisition. In order to acquire land through the adoption of a rehabilitation and resettlement act Table. 4 shows causes and controlling measure related to Unavailability of Right of Way (ROW)
  • 17. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. Interference of political processes in construction Dependencies on external parties Getting a response that can be considered reasonable II. Delay in the process of obtaining a certificate of no objection (NOC) management that works well with various stakeholders Obtain the NOC before placing any bids. Table. 5 shows causes and controlling measure related to problem external factor influences
  • 18. Causes and controlling measures related to the significant problems S. No Causes of the problem Controlling Measure I. Inadequate preparation in ahead of time Carry out a pre-construction planning of the necessary activities and resources for the project. It is important to involve the project manager along with the rest of the team during the initial stages of planning. II. Disruptions in the neighboring areas Taking preventative measures to redirect high volumes of traffic away from construction/residential areas Plan for the Regulation of Traffic Table. 6 shows causes and controlling measure related to problem poor selection of diversion for traffic flow
  • 19. Developing an Expert System for Disputes Avoidance in highways Construction Projects. The Purposes of developing of Expert System (DES) is to provide a user interface approachable system for defining the various causes of disputes performances in road construction sector. It will also able to suggest appropriate and controlling measure to avoid disputes during road construction project. The following tasks are involved in the development of an Expert system to overcome from disputes. 1. Identifying the issues that are causing the road construction project to be delayed and contentious. 2. Determining the significant level of causative factor which are leading to disputes through (SPSS). 3. Determining appropriate controlling remedial measure to overcome from disputes. 4. Establishing an Expert System for the Purpose of Suggesting Appropriate and Governing Measures to Prevent Disputes Focus of this paper is the determination of the factors that contribute to disputes in highways construction projects, and it uses both qualitative and quantitative methods. SPSS is used to perform the analysis on the data. The primary contribution made by this study is the integration of expert systems (ES) with experience- based recommendations from the construction industry regarding appropriate and controlling dispute prevention measures for use during road construction projects.
  • 20. The Conceptual Frame Work of Expert System for Disputes Avoidance in road construction project. Expert system will provide a user interface approachable system for the determination of problems that lead to disputes in the road construction sector. This ES will also support the users in suggesting and appropriate controlling measures to avoid disputes during road construction projects.
  • 21. Working Mechanism of Expert System KBES for road construction dispute avoidance helps users step-by-step. In the first step of evaluating knowledge-based expert system input from users, when the user starts the program, a new window will open on screen where the user will enter user name and password to get access and select the disputes-causing problems. Start Programming
  • 22. Working Mechanism of Expert System After starting the program, than Enter the problem Fig. 5 Shows Screen shot of displayed Problem which is leading to disputes The user will choose the most important problem causes as usual in roadway projects. To avoid construction disputes, the expert system will present control measures for each of the following causes. Fig. 6 Screen shot of displayed significant causes of the problem
  • 23. Working Mechanism of Expert System Fig. 7 Shows Screen shot of displayed controlling measures of causes to avoid dispute 1. Conclusion: This research paper proposes a conceptual framework for developing intellectual computer software (ES) to suggest and control construction industry disputes. As mentioned, most construction projects worldwide experience disputes. Significant issues and their causes are causing construction disputes that will delay project completion. The ESDA&SCM framework can identify major issues that cause disputes and suggest ways to avoid them in road construction projects to improve performance. This study also shows the most effective dispute avoidance methods. The knowledge-based expert system developed using structured query language (MYSQL) database, hypertext preprocessor (PHP) server site scripting, and HTML/Java Script user interface achieved the research's main goal. To avoid conflict, the system controls problems, causes, and their controls. If applied to road construction, the suggested controlling remedial measures will prevent disputes and finish the project on time and within budget.
  • 24. 6. Reference 1. Saad, A., “Development the A Dispute Resolution Framework to Improve the Efficiency of Dispute Resolution in Saudi Construction Projects”, Ph.D. Thesis, university of Salford collage of Science and Technology School of the Built Environment. (2017) 2. Edmonds, W.A. and Kennedy, T. D., “An Applied Reference Guide to Research Designs: Quantitative, Qualitative, and Mixed Methods. London” SAGE, (2012). 3. Femi, O.T., “Causes and effects of conflict in the Nigerian Construction Industry,” International journal of Technology Enhancements and Emerging Engineering Research journal V. 2(6), pp.7-16, (2014) 4. Chan, H., “Innovations in construction disputology” In A half day professional workshop on international construction contract management. V.1, (pp. 5-17), (2008, October). 5. Agwu, M. O., “Total Safety Management: A Strategy for Improving Organisational Performance in Chosen Construction Companies in Nigeria”. International Journal of Business and Social Science, 3(20), (2012). 6. Cheung, S. O., & Yiu, T. W., “Are construction disputes inevitable”, IEEE Transactions on Engineering Management, 53(3), 456-470, (2006). 7. Goldberg, D. M., “As the world burns: negotiating the framework convention on climate change”, Geo. Int'l Envtl. L. Rev., 5, 239 (1992). 8. Baloch, S.A., Memon, N.A. and Khoso, A.R., “Developing Conceptual Framework to Improve the Efficiency of Disputes Avoidance in Public Sector Road Projects in Pakistan Construction Industry”, 2nd international conference on sustainable development in civil engineering, 5th to 7th December, 2019. 9. Baloch, S.A., Memon, N.A. and Khoso, A.R. “Disputes impact in Pakistan construction industry: A Comprehensive study of road development projects”, IJMREM Vol. 1, Issue 10, Issn No. 2581-4540, November 2018. 10. Cheung SO, Yiu TW. “A study of construction mediator tactics Part I: taxonomies of dispute sources, mediator tactics and mediation outcomes”, J Build Environ 2007:752–61.
  • 25. 6. Reference 11. Hashmi, S.A.S.; Memon, N.A.; Ali, T.H.; Ahmed, S.; and Leghari, M.A., “Problems Caused Due to Low Bid Award System: A Case Study of Public Sector Construction Projects in Pakistan”. Proceeding of the International Conference on Sustainable Development in Civil Engineering MUET, Jamshoro Sindh Pakistan, (2017). 12. Elzing, A.A.; Mohamadien, A.M.; And Ibrahim, M.H.; & Fatha A.K.M., “An Expert system to Manage disputes resolution in construction projects in Egypt,” Ain Shams Engineering Journal, V. 7, Issue 1, pp. 57-71, (2016). 13. Morqan, C., “Failure to properly administer contract, errors and omission in the contract, and properly drafted claims are the main causes of disputes,” Research presented in international conference 28 June 2016. 14. Erdis, E.; Ozdenir, A.S., “Analysis of Technical Specification based on disputes in construction industry,” KSEC journal of civil engineering 2013. 15. Cakmak, E.; Cakmak, I.P., “An analysis of causes of disputes in the construction industries of Pakistan using an analytical network process,” Okan university, Istanbul, (2014), 34959, Turkey 16. Bolloju, N.; Schneider, C.; and Sugumaran, V., “A Knowledge-Based System for improving the Consistency between Object Model and Use Case Narrative,” Expert system with application, V. 39, 9398-9410. 2012. 17. Irlayıcı, Ç. P., “Causes of disputes in the Turkish construction industry: Case of public sector projects”. A Z ITU Journal of the Faculty of Architecture, 13(3), 109-118, (2016). 18. Demirkesen, S.; and Ozoehon, B. (2017), “Impect of Integration Management on Construction Project Management Performance,” International Journal of Project Management. Vol. 35, Pages 1639-1654 Issue on 08 Nov: 2017. 19. Akram, M., “Developing Knowledge Based Expert System for Controlling Time Overrun And Cost Overrun In Construction Industry Of Pakistan.” M.E Thesis, MUET Jamshoro. 2016.