SlideShare a Scribd company logo
1 of 11
Download to read offline
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -11
Contractual Steps for Smooth Delivery of Infrastructure
Projects
Manish Gandhi
Civil Engineering, NMIMS University
Abstract — Governments and public entities spend huge public money for purchase of goods, services and
construction of works. Therefore, it is vital that procurement system shall not only be efficient but also be transparent,
fair & just without compromising the quality of output. Various stakeholders have different interests in influencing
the decision-making. This paper elaborates various possible alternative strategies available for procurement.
Depending upon environment and various challenges, one can choose the best mode, method & process of
procurement. The procurement could be for goods, work, services, consultancy etc. Consultancy contracts are
different game altogether, because they have more emphasis on intellectual inputs rather than mere physical outcome.
The scope of this paper is limited to works procurement.
Keywords— Procurement steps, contracting, Infrastructure contracting.
I. INTRODUCTION
Public contracting or public procurement is an important economic activity of any government, which has direct impact
on economy of the nation. It is not only that awarding a contract or finalization of procurement would suffice but most
important aspect in current scenario is that the whole process shall be inclusive, transparent, fair, equitable & just. The
process shall also comply with international obligations, which has been signed in different treaties such as WTO. The
most important factor is image and efficiency of the procurement. Robust image of procurement, not only encourages
entrepreneurship but also attracts investment from private and from off shore, helping in building economy of the
countries.
This paper has identified various issues related with public procurement in order to get optimal procurement strategy
under different circumstances.
II. OBJECTIVES
At the early stage of a project and once a project manager is selected, the main issue that faces the owner is to decide on
the contract strategy that best suits the project objectives. Contract strategy means selecting organizational and
contractual policies required for the execution of a specific project. The development of the contract strategy comprises a
complete assessment of the choices available for the management of design and construction to maximize the likelihood
of achieving project objectives. The scope of such contracts is very wide, from a simple purchase of standard article to
multi-million Rupees projects. The size and complexity of the contract matter vary accordingly.
A proper contract strategy for a project involves four key decisions:
- Setting the project objectives and constraints
- Selecting a proper project delivery method
- Selecting a proper contract form / type
-Contract administration practices
Objectives of project delivery and objectives of procurement strategy shall normally align. However, these may be at
variance and at conflict creating a challenging situation for managers.
A. Project Objectives/Constraint
The client will have a number of overall objectives. These objectives may be of primary and/or secondary importance.
Primary objectives include functional performance, time objectives, and cost objectives.
a. Project Scope (performance): The project scope defines the extent or the area that the contract covers. Any additions
or omissions during the life of the project will increase or decrease the quantity of work involved. Likewise, any changes
in design must be discussed carefully to establish whether or not they are likely to affect the scope of the project.
b. Time: The scope and time are closely interrelated. Decisions must often be made on the effect of increasing or
decreasing scope on time. If the completion date of a project is critical, then increasing scope will call for an accelerated
program. The extra cost associated with this acceleration must be quantified.
c. Price: The cost of a project is closely related to scope and time. The effect of the contract on price, and the various
incentives and penalties that can help to keep price steady must be discussed and clearly defined.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -12
On the other hand, secondary objectives could arise on a construction project and would exert a major influence over
contract strategy decisions Examples of secondary objectives are:
 Allocation and payment for risk.
 Training of the client's staff.
 Transfer of technology.
 Involvement of contractor in design.
 Involvement of client in contract management.
 Choice of labour-incentive construction.
 Use of local material and resources.
 Protection of the environment.
Generic project objectives could be enumerated as
 Minimize project cost
 Maximize the project scope and improvements within the project budget.
 Minimize project delivery time
 Complete the project on time
 Provide high quality design
 Select best team
 Minimize inconvenience to traffic during construction
 Maximize safety during construction etc…
B. Project constraints
All construction projects have constraints that influence the achievement of the project objectives. These constraints
should therefore, be considered when choosing an appropriate contract strategy. There are varieties of constraints and
these are examples:
 Availability of funds.
 Availability of contractual incentives.
 Method of tendering.
 Project location.
 Target dates of the project.
 Possibility of design changes.
 Availability of resources.
 Seasonal working.
 Number of contractors willing or able to tender.
 Inflation.
C. Procurement objectives and challenges
Procurement requirements normally include timelines, cost-minimizing competition, maintaining transparency &
integrity, minimizing financial & technical risks. There are also conflicting economic goals related with social,
environment, and international trade agreements. Therefore, in complex projects/requirements, the public procurement
cannot be considered just a clerical exercise. Whereas, it requires strategic planning consistent with goals/objectives
surrounded by internal & external challenges.
D. What is a Contract:
A contract is defined as: "an agreement made between two or more parties which is enforceable by law to provide
something in return for something else from a second party". Contracts can be very simple or they may be very long and
complicated legal documents. When a contract is properly set-up, it is legally binding upon. The two parties are expected
to perform the various obligations they have undertaken, as expressed in a mutually agreed set of contract documents. A
contract therefore, is necessary to protect both client and contractor. According to its simple definition, a contract is an
agreement enforceable at law, but not all agreements are contracts. Some elements must be present before an agreement
becomes a contract. These elements are:
Competent Parties: For an agreement to be a contract, there must be two or more competent parties. In order to be
considered competent, a part must have a certain legal standing.
Proper Subject Matter: For the subject matter of a contract to be proper, the first requirement is that it was be clearly
defined as to the rights and obligations of each party. Second, the purpose of the contract must not violate the law.
Consideration: There must be a lawful and valuable consideration given to both parties. A Consideration often called
"Something for something."
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -13
Agreement: For valid contract, there must be a mutual agreement. An agreement is considered to have been reached
when an offer made by one party is accepted by the second party. Both parties must wish and intend their bargain to be
enforceable by law.
Proper Form: The terms of a contract must be written so that both parties are very sure of what their rights and
responsibilities are.
Consent of the Parties: The agreement must be free from Misrepresentation, Duress Undue influence, etc.
Procurement objectives have been defined by various agencies as under:
E. World Bank
In general, following, generally, guide the procurement process: -
a) The need for economy and efficiency in the implementation of the project, including the procurement of the goods and
works involved.
b) The Bank’s interest in giving all eligible bidders from developed and developing countries the same information and
equal opportunity to compete in providing goods and works financed by the Bank;
c) The Bank’s interest in encouraging the development of domestic contracting and manufacturing industries in the
borrowing country; and
d) The importance of transparency in the procurement process.
F. Public Procurement Bill
The objectives of the public procurement bill 2012 are “to regulate public procurement with the objectives of ensuring
transparency, accountability and probity in the procurement process, fair and equitable treatment of bidders, promoting
competition, enhancing efficiency and economy, maintaining integrity and public confidence in the public procurement
process and for matters connected therewith or incidental thereto.”
G. Factors influencing contract choice
Three main factors influence the choice of a given contract including: the incentive, risk sharing and the flexibility.
H. Internal Challenges
Procurement policy takes challenges from within depending upon type of goods, services, capital assets etc. are required.
Interaction between various arms of department, executing agency influence the procurement decision. Process, methods,
organizational structure, professionalism of staff also impact the procurement strategy. Internal policies make it a tight
rope walk, which may be in conflict with the objectives.
I. External Challenges
External factors such as market, political environment, legal environment and other socio-economic factors impose
challenges to public procurement.
(i) Legal
Here it is referred to general /broad legal frame work prevailing in the society e.g. various regulations dealing with safety
and health at work place, pollution control, finance regulations, right to information, dispute resolution mechanism,
contract law, dealing with equal opportunities for women and minorities etc. However, if laws regarding such issues are
not comprehensive, the contract may need detailed provisions.
(ii) Political
In democratic setup, various interest groups play an important role to influence public procurement strategy. These
interest groups include trade organizations, professional associations, business firms or companies etc. Types of
influence vary from influencing procurement guidelines, procurement process, technical specifications, budget
authorization etc. Eventually, a compromise view emerges for adoption. In certain cases, coalition of policy makers,
bureaucrats and interest group exist to push forward their agenda. Public procurement strategy has choices, one side it is
faced with political pressure and on other side maintaining sound economic decision.
(iii) Social
Policies on social issues such as affirmative action towards certain section of society e.g. tribal, backward groups etc.
play an important influence in procurement strategies. Environmental protection movements, activities of various groups
concerning to wild life, animals, monuments etc. also put pressure on procurement policies. Commitment on foreign
policy, trade agreements etc. also have bearing on decision making.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -14
(iv) Cultural
Public procurement system is also influenced by culture and technology. Knowledge & spread of information technology
have changed the procurement strategy and process. In certain cultures, giving gift is a common public relation activity
however; it is difficult to distinguish between gift and bribe.
(v) Market Environment
Market conditions influence competition and determine outcome of procurement process. Market conditions vary from
country to country and vary from sector to sector. Even under a perfect competition market, certain supplies/services may
have a monopoly. New challenges also arise in order to comply with governments procurement laws, international
treaties, custom regulations etc. There is tough choice to allow foreign firms along with domestic firms, putting pressure
on domestic players.
III. MODE OF PROCUREMENT
The project delivery method translates what project parties are involved in the project and how they interact with each
other and called also project organizational structure. The choice of an organizational structure should be related to
project objectives and constraints. It can be facilitated considering the following factors:
a. Size and nature of the work packages within the project.
b. Selection of the design team form in-house resources external consultants or contractors.
c. Process of supervision of construction.
d. Restrictions upon using combination of organizational structures within the project.
e. Expertise which the client wishes to commit to the project.
When plans are completed and the owner is interested in securing the low price, the use of competitive bids is suggested.
The competitive bidding results in the type of contract that many are familiar with.
A negotiated contract should be used when construction should start before plans are completed or when the many
unknown factors of the project make an accurate estimate impossible. When many changes are expected and when
inspection and supervision cannot be done efficiently, the negotiated type of contract should be used. The various project
delivery methods are summarized as follows:
A. Traditional approach
This is the most common approach in civil engineering projects in which the design has to be completed before
construction can start. Design and construction are usually performed by two different parties who interact directly and
separately with the owner.
The pros and cons of this approach are summarized as follow:
Advantages:
a. Price competition
b. Total cost is known before construction starts
c. Well documented approach used in most government projects. Disadvantages
Disadvantages:
a. Long time
b. Design does not benefit from construction expertise
c. Conflict between owner, contractor and A/E
Therefore, this method is fine in many cases where the project is clearly definable, design is completed, time need not be
shortened, and changes are unlikely to occur during construction.
B. Admeasurement contract
In this type of contracting, items of work are specified in Bills of Quantities or Schedule of Rates. The contractor then
specifies rates against each item. The rates include risk contingency. Payment is paid monthly for all work completed
during the month. The contract offers a facility for the client to introduce changes in the work defined in the tender
documents. The contractor can claim additional payment for any changes in the work content of the contract. Claims
resolution is very difficult because the client has no knowledge of actual cost or hidden contingency. Tender price is
usually increased by variations and claims. Two forms of admeasurement contract are usually used: bill of quantities and
schedule of rates.
Bill of Quantities Contract: Tenderers enter rates against each item of the estimated quantities of work. The quantities
are re-measured during the course of the contract, valued at the tendered rates and the contract price adjusted accordingly.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -15
Schedule of Rates Contract: It contains inaccurate quantities of work, possibly with upper and lower probable limits.
Therefore, it is common for separate rates to be quoted for labour, plant, and materials. The contract price is derived by
measuring the person-hours, plant-hours and the quantities of materials actually consumed, and then pricing them at the
tendered price. This contract is best suitable for repetitive works.
The admeasurement contract is well understood and widely used. It can be used when little or no changes are expected,
level of risk is low and quantifiable, and when design and construction need to be overlapped.
C. Direct labour
In this approach, owner organization performs both the design and construction using its in-house labour force.
a. Used by large authorities
b. The owner performs both the design and the construction
c. May use consultants for some specialized designs
d. Most suitable for small projects
e. Can be used when expertise is available
f. Low risk projects
g. Inadequate scope definition
D. Design-build
In this approach, a single organization is responsible for performing both design and construction and, in some cases,
providing certain “know-how” for the project. The pros and cons of this approach are summarized as follow:
Advantages:
a. One contract that may include know-how
b. Minimum owner involvement
c. Used for fast-track projects in order to reduce time
d. Co-ordination between design and construction and easier in implementing the changes
Disadvantages:
a. Cost may not be known until end of the construction
b. High risk to contractor and more cost to owner
c. Design-build company may reduce quality to save cost
The use of this approach, therefore, should be considered when contractors offer specialized design/construction/know-
how expertise or when design is strongly influenced by the method of construction.
E. Design and build lump sum contracts
In this mode contractor agrees to execute the complete work with all its contingencies. Such type of strategy is most
suitable in case of large projects where the aims are:
a) Innovation of private initiatives
b) Economy of scale (Contractor using standard designs, module, technology etc.)
c) Speed of construction
This method is also referred as turn-key contract with some variations.
F. Turnkey
This approach is similar to the design -build approach but with the organization being responsible for performing design,
construction, expertise (if any), and project financing. Owner payment is then made at the completion (when the
contractor turns over the “key”). An example is franchise projects in which a new branch of a restaurant chain needs to
maintain the same design, construction quality, and food service quality.
G. Cost-reimbursable contract (cost-plus contract)
The contractor is reimbursed for actual cost plus a special fee for head office overheads and profit, no special payment
for risk. Payment may be made monthly in advance. The contract involves a high level of flexibility for design changes.
Final price depends on changes and extent to which risks materialize. The contractor must make all his records and
accounts available for inspection by the client or by some agreed third party. The fee may be a fixed amount or a
percentage of actual costs. This contract has no direct financial incentives for the contractor to perform efficiently. It may
be used when it is desirable for design to proceed concurrently with construction and when the client wishes to be
involved in contract management.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -16
H. Target cost contract
Cost targets may be introduced into cost-reimbursable contracts. In addition to the reimbursement of actual cost plus
percentage fee, the contractor will be paid a share for any saving between target and actual cost, while the fee will be
reduced if actual cost exceeds the target. The target figure should be realistic and the incentive must be sufficient to
generate the desired motivation. Specified risk' can be excluded from the tendered target cost. When these occur, the
target cost is adjusted accordingly and the client pays the actual cost incurred by the contractor. The target may also b'
adjusted for major changes in work and cost inflation. This contract can be used in the same circumstances as the cost-
plus contract.
I. Time and material (T&M) contracts
T&M contracts are a hybrid type of contractual arrangement that contains aspects of both cost-reimbursable and fixed-
price-type arrangements. T&M contracts resemble cost-type arrangements in that they are open ended, because the full
value of the arrangement is not defined at the time of the award. Thus, T&M contracts can grow in contract value as if
they were cost-reimbursable-type arrangements. Conversely, T&M arrangements can also resemble fixed-unit
arrangements when, for example, the unit rates are pre-set by the buyer and seller, as when both parties agree on the rates
for the category of "senior engineers." Most appropriate when the buyer wants to be more in control. It is also used in an
emergency to begin work immediately when a scope of work has not yet been completed. Not possible at time of placing
contract to estimate extent or duration of the work, or anticipated cost, with any degree of confidence.
J. PPP (Public Private Partnership)
In this mode the private firms or consortium agrees to construct with its own cost in lieu of future revenues over a period
of time. Various models like BOT, BOLT, BOOT or BOO under PPP are available depending upon type of work,
preparedness of the project, future projections, funding arrangement, leverage, risk sharing arrangements etc. In this
approach, a business entity is responsible for performing the design, construction, long-term financing, and operation and
Maintenance of the project. At the end of the operation period, which can be many years, operation of the project is
transferred to the owner. This approach has been extensively used in recent years and is expected to continue. An
example of its use is in express routes and turnpikes. A consortium of companies shares the cost (design, construction,
financing, operation, and maintenance) and the profits gained from user fees, for a stipulated number of years.
Afterwards, the project returns to the government to become publicly owned. This approach has also been used
extensively in large infrastructure projects financed by the World Bank in parts of the world that cannot afford the high
investment cost of such projects.
IV. METHOD OF PROCUREMENT
Generally, competition is a basis of efficient contracting strategy. However, in selective cases requiring skilled and
specified work, procurement can be through limited competitive or through single source. Any of the following methods
could be resorted by following general principle of economy, efficiency and transparency.
A. International competitive bidding
In this method, notice of bid is advertised globally to invite eligible prospective bidders from eligible countries to
participate in the bidding process. This method brings not only overseas technology work culture but also overall
economy.
B. National competitive bidding
This method is normally used by open advertisement within country. This method is most suited for goods, works;
services that are available locally at prices below the international market and the works are limited intensive.
C. Limited bidding
Limited bidding is by direct invitation without open advertisement. This method may be appropriate where:
a. There are only limited nos. of suppliers
b. Value of contract is not very large
c. Emergency situations
d. Security reasons, which do not justify open competitive bidding.
D. Single source bidding
This strategy is adopted for special works or in emergent situations. Employer can select firms based on qualification and
experience. There is no competition in such bidding method.
V. PROCESS OF PROCUREMENT
Depending upon complexity and regulatory requirements, the bidding process can be very short or very elaborate and
exhaustive. Generally, following processes are used:
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -17
a. Single Packet without PQ (Prequalification)
b. Two Packet without PQ
c. Single stage two packets with PQ
d. Two stage with PQ
The above processes could be interactive with the bidders by way of pre-bid submission meetings. Depending upon the
complexity and size of the project, further stages can be added to meet the objectives.
VI. CONTRACT ADMINISTRATION
As it was discussed in the previous sections, there is variety of types of contracts used in civil engineering projects. Each
type has its specific characteristics. Contracts may be prepared under the heading of one type but could include
characteristics of more than a single type. Many professional societies and government agencies have done a great deal
toward the standardization of construction contracts such that the general form and content are well established for the
various types of construction that may arise.
A. Professional construction management (PCM)
In this approach, the owner appoints a PCM organization (also known as Construction Management organization) to
manage and coordinate the design and construction phases of a project using a Teamwork approach. The design may be
provided by specialist design firms and in some cases by the PCM organization. With high level of coordination between
the participants, innovative approaches of overlapping design and construction (i.e., fast tracking) can be adopted. The
PCM organization aims at holding a friendly position similar to that of the consultants in the traditional approach.
The services offered by the PCM organization overlap those traditionally performed by the architect, the engineer, and
the contractor. This may include: management and programming of design; cost forecasting and financial arrangements;
preparation of tender documents; tender analysis and selection of contractors; selection of methods of construction;
recommendations on construction economics; planning and scheduling construction works; materials procurement and
delivery expedition; provision for site security, cleanup, and temporary utilities; supervision of control of construction
contractors; construction quality assurance; cost control; costing of variations and assessment of claims; and certification
of interim and final payments to contractors. The use of PCM approach, therefore, should be considered when there is a
need for time saving, flexibility for design changes is required, and owner has insufficient management resources.
B. Contract documents
The contract is defined by the contract documents, which are developed from the tender documents. In a logical order,
these documents refer to the following subjects:
a. Input from the client (task description).
b. Output of the contract (specifications, results to be achieved).
c. Prices for the contractor's contribution.
d. Responsibilities and procedures (liability, resources provided, time schedule, payment conditions, change
procedures, etc.).
Contract documents are usually arranged according to the following sequence:
a. General (for any project).
b. Special (for a specialty area of the project).
c. Supplementary (unique to a given project).
d. Additional (during bidding or negotiation).
e. Agreement form (for singing very important and particular clauses).
f. Modifications (during contract fulfilment).
The complete contract agreement usually consists of the following documents:
a. Conditions (general, special, supplementary).
b. Drawing and specifications.
c. Addenda.
d. Agreement form.
e. Modifications.
The most important document from the legal point of view is the agreement. It is sometimes called the contract. Since so
many documents are included as contract documents, the agreement is the better term for this particular one. The form of
the agreement can be standardized and used for many projects, or a unique document can be prepared for each project.
The standard form of agreement prescribed by the American Institute of Architects has proved to be satisfactory and has
been used on many building projects with good results. The form followed for non- building projects is often more varied.
Man: agencies have own standard forms, which are used on all their projects. Information usually included in the
agreement are of three parts. The first part is a short introductory paragraph which defines the parties, gives the date of
the agreement, and state that each party agrees to what follows.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -18
The second part contains the elements of contract and defines the work to be undertaken. The final paragraph confirms
the agreement and provides space for signatures of the parties. Thus, the agreement usually composed of the following
articles:
a. A short introductory paragraph.
b. Scope of the work.
c. Time of completion.
d. Contract documents.
e. Performance bond.
f. Contractor's insurance.
g. Owner's insurance.
h. Laws, regulations and permits.
i. Payments.
j. Extensions of time.
k. Changes in the work.
l. Owner's right to terminate the work.
m. Contractor's right to terminate the work.
n. Confirmation and signatures.
C. Conditions of contract
The conditions of a contract are rules by which the execution of the contract is to be governed. They set-out the
responsibilities, rights, and liabilities of the two parties. They also set- out the actions to be taken by the parties if and
when certain eventualities should arise. No two civil engineering contracts are similar. Probably, no two construction
contracts are truly the same. Therefore, identical conditions of contracts are not likely to be required. However, for work
of a similar type, certain conditions will apply for the vast majority of cases. It follows that a standard form of conditions
for a given type of work will remove the necessity of thinking out and drafting new sets of conditions for every new
contract. By taking the standard form and modifying it to suit the requirements of a particular contract, time and effort
will be saved. The terms of a contract legally fall into two categories:
a. Conditions: They are terms expressing matters basic to the contract. A failure to perform the requirements of a
condition is a fundamental breach of an essential obligation giving the aggrieved party the right to:
1. End the contract and claim damages, or
2. Continue the contract and claim damages.
b. Warranties: They deal with matters not of the essence of the contract, being subsidiary to the main purposes for
which the parties contracted. An example of a warranty is where a nominated sub-contractor warrants that the work will
be carried-out to specific standards. The conditions of a contract usually comprise the following:
1. A standard form of general conditions of contract appropriate to the natures of the work involved.
2. A series of amendments to the forging in order to adjust them to the circumstances of the actual contract concerned.
3. A number of special conditions, which deal with matters peculiar to the contract and not dealt with by the standard.
D. Standard (general) forms of conditions of contract
Standard forms are prepared jointly by professional bodies and organizations representing contractors or by large
organizations and public bodies to suit their own circumstances. The intention is that a common approach by the parties
to all contracts will be achieved and standard interpretations of risks and responsibilities involved. There are a number of
standard forms of conditions of contract used in civil engineering. The most commonly used are:
Institute of Civil Engineering (ICE) Conditions of Contract: This document includes the forms of Tender, Agreement
and Bond. It is applicable to all civil engineering construction works. It is particularly suitable for general civil
engineering work which is predominantly either in the ground or in, or adjacent to, water, and carets for the attendant
risks and claims situations. It is also used, sometimes, for building works and for mechanical and electrical works where
such works are included in a civil engineering or building contract.
Federation Internationale Des Ingenieure-Conseils (FIDIC): These conditions are, in effect, international versions of
the ICE conditions to which they are closely related. The fourth edition (1987) of the conditions for works of civil
engineering construction comprises:
Part I: General conditions with forms of tender and agreement.
Part II: Conditions of particular application with guidelines for preparation of Part II clauses.
It is intended for general use for works where tenderers are invited on an international basis, but it also suitable to
domestic contracts. The objective is to provide a standardized document which is well-known, internationally recognized
and accepted, an adequately reflects the interests of the parties concerned.
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -19
The standard (general) forms of conditions of contract usually cover the general aspects in arranged clauses. For example,
FIDIC general conditions of contract comprise clauses that cover the following items:
a. Definitions and interpretations.
b. Engineer and Engineer's representative.
c. Assignment and sub-contracting.
d. Contract documents.
e. General obligations.
f. Labour, Materials, plant, and workmanship.
g. Suspension.
h. Commencement and delays.
i. Defects liability.
j. Alternations, Additions and Omissions.
k. Procedure of claims.
l. Contractors' equipment, temporary works and materials.
m. Provisional sums.
n. Certificates and payments.
o. Remedies.
p. Special risks.
q. Release for performance.
r. Settlement of disputes.
s. Notices.
t. Default of Employer.
u. Changes in cost and legislation.
v. Currency and rates of exchange.
Most of the standard forms of conditions of contract contain one or more clauses, which require completion by the
Client/Engineer before the conditions are issued.
E. Special conditions of contract
Special conditions are new clauses to augment the general conditions of a standard form.
Usually they deal with subjects not touched on by the standard form. It is often simpler to introduce a special condition
than to amend a standard form condition. After a new clause is written, it must be ensuring that no conflict or ambiguity
is being introduced. The range of possible subjects for special conditions is large. They normally deal with the
peculiarities of one contract and one site. There are varieties of choices in which a new subject may be written:
a. In the specification (if it is of technical matter). As special condition of contract.
b. In the site regulations (if it deals with site administration or discipline).
c. In separate correspondence (if it is not essential to incorporate it into the formal contract).
The decision to consider a special condition does not depend on importance. The following are typical examples of
subjects for special conditions:
a. Special terms of payments.
b. Patents and licenses.
c. Applicable law.
d. Official Language.
e. Obligatory use of local labour, plant and material.
f. Co-operation with contractor on site.
g. Fair wages to be paid.
h. Union membership of work force.
i. Protection and disposal of historic, valuable, archaeological, etc. finds on site.
j. Prohibition of access to named places.
k. Restrictions on noise levels, dust, fire hazards, etc.
l. Control of demolition work, explosives, etc.
m. Responsibility for damage to public services.
n. Responsibility for payment of local taxes.
F. Construction claims
A construction claim is a request for payment or time extension to which the contractor considers him/herself entitled.
There are three types under which claims are required:
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -20
a. Extension of time only.
b. Additional cost.
c. Both extensions of time and additional cost.
The main reasons for construction claims may include:
a. Late possession of site or late provision of working drawings.
b. Change of contract start or activities schedule.
c. Design change and variation.
d. Delays in approval and examining work.
e. Work acceleration by the client.
f. Late delivery of materials supplied by the client.
g. Different ground and/or site conditions.
h. Unforeseen events and disasters.
VII. SELECTION CRITERIA
Traditional selection of successful bidder is based on contract price of the project. The selection of the bidder can be
based on lowest price bid, qualification based, qualification cum cost based, cost plus time based, lowest life cycle cost,
period of contract, return from the project etc. Based on selection criteria the component of bidding i.e. mode, method
and process are suitably modified to reduce the risk of subjectivity at the time of evaluation.
VIII. PROCUREMENT STRATEGY SELECTION MATRIX
After the detailed analysis & evaluation of various pros and cons with respect to modes, methods & processes a formal
approach as suggested below (Figure-1) can be adopted for selection of optimal strategy. A suggestive
comparison/matrix with respect to various issues for different modes of procurement is listed in table -1; similar matrix
for method and process shall also be made as part of an iterative process to find final strategy.
Figure-1 Procurement Strategy Selection Matrix
a. Set Project Goal
b. Assess the resources and capacity of the organization
1. Technical
2. Infrastructure
3. Risk management capacity
4. Staff experience etc.
c. Project profile
1. Complexity of project
2. Schedule of completion
3. Availability of designs
4. Availability of supervision staff
5. Innovations
5. Availability of funds
7. Availability of land & other Statutory clearances
8. Major stake holders
9. Project specific constraints 1, 2, 3………
International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763
Issue 02, Volume 3 (February 2016) www.ijirae.com
_________________________________________________________________________________________________
IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57
© 2014- 16, IJIRAE- All Rights Reserved Page -21
d. Do risk assessment [w.r.t. different mode/ method/process of procurement strategy]
e. Can risk be shared/transferred/ allocated/ ignored
f. Re-work on procurement strategy considering complexities of the project
g. Final selection
IX.CONCLUSION
No single contracting strategy is suitable for every project. Each project should be critically analysed to determine the
most optimal delivery strategy. It is requisite to map all the factors, Project goals, Procurement goals and institutional
capacity available for a project.
TABLE 1- METHOD SELECTION CHECK LIST.
ISSUE BIDDING METHODS
ITEM RATE DESIGN BUILD LUMP SUM MANAGEMENT CONTRACT
PROJECT DELIVERY
SCHEDULE
If design is available, the time
required for this procurement
is short.
Design and construction ae
parallel activity, which
accelerate the project delivery
schedule, however procurement
time is lengthy
Project development, design,
procurement and construction, etc.
Are parallel activity. Project
delivery schedule can be slow due
to coordination issues.
COMPLEXITY OF PROJECT Complex design issues can be
sorted quantitatively before
hand
Contractor provides most
economical innovative solution
with alternate technical
proposals.
It allows qualitative design with
mutual consultations.
PREPAREDNESS OF DESIGN 100 percent in house design. Design risk is allocated to
bidder. Employee is to give
only precise performance
requirements.
In due course improvement in
design is possible. However it
may extend project schedule.
COST OF PROJECT Competitive bidding allows a
low cost. Cost accuracy is
expected.
It is cost efficient. However
poor risk allocation can result
higher contingencies and
improper risk loading.
It has flexibility of designing as
per budget limit
RISK ALLOCATION Quite Clear Proper allocation of risk to the
party best able to manage them.
These risks are to be well
defined to minimize
contractor’s contingencies on
cost price.
Risks are collectively shared and
minimizes loading of
contingencies on cost price. But
there is less competition
REQUIREMENT OF IN HOUSE
STAFF EXPERIENCE
AVAILABILITY.
Elaborate Technical design
team is necessary
Elaborate Technical design and
management team is necessary
to develop RFP and subsequent
monitoring.
Committed Technical design and
design team is necessary with
consultant
LEVEL OF AGENCY
CONTROL
Full Less Collaborative effort
MARKET COMPETITION High level Competition Medium level Competition Low level Competition
REFERENCES
[1] Guidelines procurement under IBRD loans and IDA credits, (2010).
[2] JICA guideline for procurement.
[3] Keith Molennar, Harpan Chris, Daniel Tran, “Guide book for Selecting Project Delivery Methods and alternative
contracting strategies”, University of Colorado, Colorado, (2012).
[4] Khi V. Thai,” Public Procurement re- examined, Journal of Public procurement, Vol- I, Issue 1, PP. 9-50, (2001).
[5] Procurement guidelines, Asian Development Bank, (2010).
[6] The public procurement bill (2012).
[7] Works Manual, Dedicated Freight Corridor Corporation of India Limited (2012).

More Related Content

What's hot

Construction economic
Construction economicConstruction economic
Construction economicfauziani
 
Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami Mikhail
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methodsNitin Kumar
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web readySumit Gupta
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...IRJET Journal
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghanaAlexander Decker
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED
 
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...IJORCS
 
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...inventionjournals
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal, sksbatish
 

What's hot (14)

Construction economic
Construction economicConstruction economic
Construction economic
 
Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015Rami A.docResumeFeb-2015
Rami A.docResumeFeb-2015
 
Construction project delivery methods
Construction project delivery methodsConstruction project delivery methods
Construction project delivery methods
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
Study of Different Public-Private Partnership (PPP) Model for the Road Infras...
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Management of government funded construction projects in ghana
Management of government funded construction projects in ghanaManagement of government funded construction projects in ghana
Management of government funded construction projects in ghana
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
IJSRED-V2I3P74
IJSRED-V2I3P74IJSRED-V2I3P74
IJSRED-V2I3P74
 
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
Study of Influencing Factors of Tender Evaluation: An Evidential Reasoning Ap...
 
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
Quantity Surveyor’s Impact: A Panacea to achieving Critical Success Factors i...
 
Bank project appraisal,
Bank  project appraisal, Bank  project appraisal,
Bank project appraisal,
 

Viewers also liked

Guia para el segundo examen de arquitectura
Guia para el segundo examen de arquitecturaGuia para el segundo examen de arquitectura
Guia para el segundo examen de arquitecturaBear23
 
PTCL internship letter
PTCL internship letterPTCL internship letter
PTCL internship letterWajahat Ali
 
Home repairbrochure
Home repairbrochureHome repairbrochure
Home repairbrochurepoconnor
 
What creates real Real Estate value?
What creates real Real Estate value?What creates real Real Estate value?
What creates real Real Estate value?Dan Kamminga
 
2016 budget fbcad
2016 budget fbcad2016 budget fbcad
2016 budget fbcadpoconnor
 
Fortbend reappraisal plan15 16
Fortbend reappraisal plan15 16Fortbend reappraisal plan15 16
Fortbend reappraisal plan15 16poconnor
 
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016John Anderson
 
Top 10 SharePoint Terms and Acronyms Explained
Top 10 SharePoint Terms and Acronyms ExplainedTop 10 SharePoint Terms and Acronyms Explained
Top 10 SharePoint Terms and Acronyms ExplainedGregory Zelfond
 
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross Layer
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross LayerDelay Sensitive Packet Scheduling Algorithm for MANETs by Cross Layer
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross LayerAM Publications
 
Implementation Secure Authentication Using Elliptic Curve Cryptography
Implementation Secure Authentication Using Elliptic Curve CryptographyImplementation Secure Authentication Using Elliptic Curve Cryptography
Implementation Secure Authentication Using Elliptic Curve CryptographyAM Publications
 
Tower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPSTower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPSAM Publications
 
Simulation of Contamination of Groundwater Using Environmental Quality Model
Simulation of Contamination of Groundwater Using Environmental Quality ModelSimulation of Contamination of Groundwater Using Environmental Quality Model
Simulation of Contamination of Groundwater Using Environmental Quality ModelAM Publications
 
Load Balancing for Achieving the Network Lifetime in WSN-A Survey
Load Balancing for Achieving the Network Lifetime in WSN-A SurveyLoad Balancing for Achieving the Network Lifetime in WSN-A Survey
Load Balancing for Achieving the Network Lifetime in WSN-A SurveyAM Publications
 

Viewers also liked (18)

Guia para el segundo examen de arquitectura
Guia para el segundo examen de arquitecturaGuia para el segundo examen de arquitectura
Guia para el segundo examen de arquitectura
 
PTCL internship letter
PTCL internship letterPTCL internship letter
PTCL internship letter
 
Home repairbrochure
Home repairbrochureHome repairbrochure
Home repairbrochure
 
What creates real Real Estate value?
What creates real Real Estate value?What creates real Real Estate value?
What creates real Real Estate value?
 
2016 budget fbcad
2016 budget fbcad2016 budget fbcad
2016 budget fbcad
 
Fortbend reappraisal plan15 16
Fortbend reappraisal plan15 16Fortbend reappraisal plan15 16
Fortbend reappraisal plan15 16
 
20160503_Resume
20160503_Resume20160503_Resume
20160503_Resume
 
Curriculum Vitae
Curriculum VitaeCurriculum Vitae
Curriculum Vitae
 
jobs_talentcheck
jobs_talentcheckjobs_talentcheck
jobs_talentcheck
 
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016
TCAD - Travis Central Appraisal District reappraisal plan 2015 - 2016
 
Top 10 SharePoint Terms and Acronyms Explained
Top 10 SharePoint Terms and Acronyms ExplainedTop 10 SharePoint Terms and Acronyms Explained
Top 10 SharePoint Terms and Acronyms Explained
 
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross Layer
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross LayerDelay Sensitive Packet Scheduling Algorithm for MANETs by Cross Layer
Delay Sensitive Packet Scheduling Algorithm for MANETs by Cross Layer
 
Implementation Secure Authentication Using Elliptic Curve Cryptography
Implementation Secure Authentication Using Elliptic Curve CryptographyImplementation Secure Authentication Using Elliptic Curve Cryptography
Implementation Secure Authentication Using Elliptic Curve Cryptography
 
Tower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPSTower verticality for Tall Building using DGPS
Tower verticality for Tall Building using DGPS
 
Simulation of Contamination of Groundwater Using Environmental Quality Model
Simulation of Contamination of Groundwater Using Environmental Quality ModelSimulation of Contamination of Groundwater Using Environmental Quality Model
Simulation of Contamination of Groundwater Using Environmental Quality Model
 
Ortho conf
Ortho confOrtho conf
Ortho conf
 
Load Balancing for Achieving the Network Lifetime in WSN-A Survey
Load Balancing for Achieving the Network Lifetime in WSN-A SurveyLoad Balancing for Achieving the Network Lifetime in WSN-A Survey
Load Balancing for Achieving the Network Lifetime in WSN-A Survey
 
Primum project presentation
Primum project presentationPrimum project presentation
Primum project presentation
 

Similar to Contractual Steps for Smooth Delivery of Infrastructure Projects

Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsIRJET Journal
 
Pm0012 project finance and budgeting
Pm0012   project finance and budgetingPm0012   project finance and budgeting
Pm0012 project finance and budgetingsmumbahelp
 
project implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptproject implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptselam49
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015SONU61709
 
AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAM Publications
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 
Deloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction SummitDeloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction Summitaakash malhotra
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
Pm0010 introduction to project management
Pm0010   introduction to project managementPm0010   introduction to project management
Pm0010 introduction to project managementStudy Stuff
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Dr. Zaid Mahayni
 
Pm0010 introduction to project management
Pm0010   introduction to project managementPm0010   introduction to project management
Pm0010 introduction to project managementsmumbahelp
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contractsidnobleg77
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction ProjectIRJET Journal
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docxSUBHI7
 
Navigating MOU Evaluation & A Manager's Guide.docx
Navigating MOU Evaluation & A Manager's Guide.docxNavigating MOU Evaluation & A Manager's Guide.docx
Navigating MOU Evaluation & A Manager's Guide.docxMD. ANOARUL HAQUE
 

Similar to Contractual Steps for Smooth Delivery of Infrastructure Projects (20)

Risk Mitigation In Construction Contracts
Risk Mitigation In Construction ContractsRisk Mitigation In Construction Contracts
Risk Mitigation In Construction Contracts
 
Pm0012 project finance and budgeting
Pm0012   project finance and budgetingPm0012   project finance and budgeting
Pm0012 project finance and budgeting
 
project implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.pptproject implimentation.-Three.Procurement.ppt
project implimentation.-Three.Procurement.ppt
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Internal audit
Internal audit Internal audit
Internal audit
 
Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015Contracting process paper cpmgt302september 21, 2015
Contracting process paper cpmgt302september 21, 2015
 
AVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTEAVOIDING AN ARBITRATION DISPUTE
AVOIDING AN ARBITRATION DISPUTE
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 
Deloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction SummitDeloitte India - Deloitte Construction Summit
Deloitte India - Deloitte Construction Summit
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Pm0010 introduction to project management
Pm0010   introduction to project managementPm0010   introduction to project management
Pm0010 introduction to project management
 
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
Zaid Mahayni - Bankability of BOT Arrangements - CEPMLP 2000-2001
 
Pm0010 introduction to project management
Pm0010   introduction to project managementPm0010   introduction to project management
Pm0010 introduction to project management
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
IRJET- Dispute Resolution Mechanism in Construction Project
IRJET-  	  Dispute Resolution Mechanism in Construction ProjectIRJET-  	  Dispute Resolution Mechanism in Construction Project
IRJET- Dispute Resolution Mechanism in Construction Project
 
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
Running head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docxRunning head  ACQUISITION STRATEGY  PIEZOELECTRIC EMBEDDED TRA.docx
Running head ACQUISITION STRATEGY PIEZOELECTRIC EMBEDDED TRA.docx
 
Navigating MOU Evaluation & A Manager's Guide.docx
Navigating MOU Evaluation & A Manager's Guide.docxNavigating MOU Evaluation & A Manager's Guide.docx
Navigating MOU Evaluation & A Manager's Guide.docx
 

More from AM Publications

DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...AM Publications
 
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...AM Publications
 
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGNTHE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGNAM Publications
 
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...AM Publications
 
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...AM Publications
 
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISESANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISESAM Publications
 
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS AM Publications
 
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...AM Publications
 
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITIONHMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITIONAM Publications
 
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...AM Publications
 
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...AM Publications
 
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...AM Publications
 
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...AM Publications
 
OPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNNOPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNNAM Publications
 
DETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECTDETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECTAM Publications
 
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENTSIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENTAM Publications
 
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...AM Publications
 
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...AM Publications
 
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY AM Publications
 

More from AM Publications (20)

DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
DEVELOPMENT OF TODDLER FAMILY CADRE TRAINING BASED ON ANDROID APPLICATIONS IN...
 
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
TESTING OF COMPOSITE ON DROP-WEIGHT IMPACT TESTING AND DAMAGE IDENTIFICATION ...
 
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGNTHE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
THE USE OF FRACTAL GEOMETRY IN TILING MOTIF DESIGN
 
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
TWO-DIMENSIONAL INVERSION FINITE ELEMENT MODELING OF MAGNETOTELLURIC DATA: CA...
 
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
USING THE GENETIC ALGORITHM TO OPTIMIZE LASER WELDING PARAMETERS FOR MARTENSI...
 
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISESANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
ANALYSIS AND DESIGN E-MARKETPLACE FOR MICRO, SMALL AND MEDIUM ENTERPRISES
 
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
REMOTE SENSING AND GEOGRAPHIC INFORMATION SYSTEMS
 
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
EVALUATE THE STRAIN ENERGY ERROR FOR THE LASER WELD BY THE H-REFINEMENT OF TH...
 
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITIONHMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
HMM APPLICATION IN ISOLATED WORD SPEECH RECOGNITION
 
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
PEDESTRIAN DETECTION IN LOW RESOLUTION VIDEOS USING A MULTI-FRAME HOG-BASED D...
 
INTELLIGENT BLIND STICK
INTELLIGENT BLIND STICKINTELLIGENT BLIND STICK
INTELLIGENT BLIND STICK
 
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
EFFECT OF SILICON - RUBBER (SR) SHEETS AS AN ALTERNATIVE FILTER ON HIGH AND L...
 
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
UTILIZATION OF IMMUNIZATION SERVICES AMONG CHILDREN UNDER FIVE YEARS OF AGE I...
 
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
REPRESENTATION OF THE BLOCK DATA ENCRYPTION ALGORITHM IN AN ANALYTICAL FORM F...
 
OPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNNOPTICAL CHARACTER RECOGNITION USING RBFNN
OPTICAL CHARACTER RECOGNITION USING RBFNN
 
DETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECTDETECTION OF MOVING OBJECT
DETECTION OF MOVING OBJECT
 
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENTSIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
SIMULATION OF ATMOSPHERIC POLLUTANTS DISPERSION IN AN URBAN ENVIRONMENT
 
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
PREPARATION AND EVALUATION OF WOOL KERATIN BASED CHITOSAN NANOFIBERS FOR AIR ...
 
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
ANALYSIS ON LOAD BALANCING ALGORITHMS IMPLEMENTATION ON CLOUD COMPUTING ENVIR...
 
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
A MODEL BASED APPROACH FOR IMPLEMENTING WLAN SECURITY
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Contractual Steps for Smooth Delivery of Infrastructure Projects

  • 1. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -11 Contractual Steps for Smooth Delivery of Infrastructure Projects Manish Gandhi Civil Engineering, NMIMS University Abstract — Governments and public entities spend huge public money for purchase of goods, services and construction of works. Therefore, it is vital that procurement system shall not only be efficient but also be transparent, fair & just without compromising the quality of output. Various stakeholders have different interests in influencing the decision-making. This paper elaborates various possible alternative strategies available for procurement. Depending upon environment and various challenges, one can choose the best mode, method & process of procurement. The procurement could be for goods, work, services, consultancy etc. Consultancy contracts are different game altogether, because they have more emphasis on intellectual inputs rather than mere physical outcome. The scope of this paper is limited to works procurement. Keywords— Procurement steps, contracting, Infrastructure contracting. I. INTRODUCTION Public contracting or public procurement is an important economic activity of any government, which has direct impact on economy of the nation. It is not only that awarding a contract or finalization of procurement would suffice but most important aspect in current scenario is that the whole process shall be inclusive, transparent, fair, equitable & just. The process shall also comply with international obligations, which has been signed in different treaties such as WTO. The most important factor is image and efficiency of the procurement. Robust image of procurement, not only encourages entrepreneurship but also attracts investment from private and from off shore, helping in building economy of the countries. This paper has identified various issues related with public procurement in order to get optimal procurement strategy under different circumstances. II. OBJECTIVES At the early stage of a project and once a project manager is selected, the main issue that faces the owner is to decide on the contract strategy that best suits the project objectives. Contract strategy means selecting organizational and contractual policies required for the execution of a specific project. The development of the contract strategy comprises a complete assessment of the choices available for the management of design and construction to maximize the likelihood of achieving project objectives. The scope of such contracts is very wide, from a simple purchase of standard article to multi-million Rupees projects. The size and complexity of the contract matter vary accordingly. A proper contract strategy for a project involves four key decisions: - Setting the project objectives and constraints - Selecting a proper project delivery method - Selecting a proper contract form / type -Contract administration practices Objectives of project delivery and objectives of procurement strategy shall normally align. However, these may be at variance and at conflict creating a challenging situation for managers. A. Project Objectives/Constraint The client will have a number of overall objectives. These objectives may be of primary and/or secondary importance. Primary objectives include functional performance, time objectives, and cost objectives. a. Project Scope (performance): The project scope defines the extent or the area that the contract covers. Any additions or omissions during the life of the project will increase or decrease the quantity of work involved. Likewise, any changes in design must be discussed carefully to establish whether or not they are likely to affect the scope of the project. b. Time: The scope and time are closely interrelated. Decisions must often be made on the effect of increasing or decreasing scope on time. If the completion date of a project is critical, then increasing scope will call for an accelerated program. The extra cost associated with this acceleration must be quantified. c. Price: The cost of a project is closely related to scope and time. The effect of the contract on price, and the various incentives and penalties that can help to keep price steady must be discussed and clearly defined.
  • 2. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -12 On the other hand, secondary objectives could arise on a construction project and would exert a major influence over contract strategy decisions Examples of secondary objectives are:  Allocation and payment for risk.  Training of the client's staff.  Transfer of technology.  Involvement of contractor in design.  Involvement of client in contract management.  Choice of labour-incentive construction.  Use of local material and resources.  Protection of the environment. Generic project objectives could be enumerated as  Minimize project cost  Maximize the project scope and improvements within the project budget.  Minimize project delivery time  Complete the project on time  Provide high quality design  Select best team  Minimize inconvenience to traffic during construction  Maximize safety during construction etc… B. Project constraints All construction projects have constraints that influence the achievement of the project objectives. These constraints should therefore, be considered when choosing an appropriate contract strategy. There are varieties of constraints and these are examples:  Availability of funds.  Availability of contractual incentives.  Method of tendering.  Project location.  Target dates of the project.  Possibility of design changes.  Availability of resources.  Seasonal working.  Number of contractors willing or able to tender.  Inflation. C. Procurement objectives and challenges Procurement requirements normally include timelines, cost-minimizing competition, maintaining transparency & integrity, minimizing financial & technical risks. There are also conflicting economic goals related with social, environment, and international trade agreements. Therefore, in complex projects/requirements, the public procurement cannot be considered just a clerical exercise. Whereas, it requires strategic planning consistent with goals/objectives surrounded by internal & external challenges. D. What is a Contract: A contract is defined as: "an agreement made between two or more parties which is enforceable by law to provide something in return for something else from a second party". Contracts can be very simple or they may be very long and complicated legal documents. When a contract is properly set-up, it is legally binding upon. The two parties are expected to perform the various obligations they have undertaken, as expressed in a mutually agreed set of contract documents. A contract therefore, is necessary to protect both client and contractor. According to its simple definition, a contract is an agreement enforceable at law, but not all agreements are contracts. Some elements must be present before an agreement becomes a contract. These elements are: Competent Parties: For an agreement to be a contract, there must be two or more competent parties. In order to be considered competent, a part must have a certain legal standing. Proper Subject Matter: For the subject matter of a contract to be proper, the first requirement is that it was be clearly defined as to the rights and obligations of each party. Second, the purpose of the contract must not violate the law. Consideration: There must be a lawful and valuable consideration given to both parties. A Consideration often called "Something for something."
  • 3. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -13 Agreement: For valid contract, there must be a mutual agreement. An agreement is considered to have been reached when an offer made by one party is accepted by the second party. Both parties must wish and intend their bargain to be enforceable by law. Proper Form: The terms of a contract must be written so that both parties are very sure of what their rights and responsibilities are. Consent of the Parties: The agreement must be free from Misrepresentation, Duress Undue influence, etc. Procurement objectives have been defined by various agencies as under: E. World Bank In general, following, generally, guide the procurement process: - a) The need for economy and efficiency in the implementation of the project, including the procurement of the goods and works involved. b) The Bank’s interest in giving all eligible bidders from developed and developing countries the same information and equal opportunity to compete in providing goods and works financed by the Bank; c) The Bank’s interest in encouraging the development of domestic contracting and manufacturing industries in the borrowing country; and d) The importance of transparency in the procurement process. F. Public Procurement Bill The objectives of the public procurement bill 2012 are “to regulate public procurement with the objectives of ensuring transparency, accountability and probity in the procurement process, fair and equitable treatment of bidders, promoting competition, enhancing efficiency and economy, maintaining integrity and public confidence in the public procurement process and for matters connected therewith or incidental thereto.” G. Factors influencing contract choice Three main factors influence the choice of a given contract including: the incentive, risk sharing and the flexibility. H. Internal Challenges Procurement policy takes challenges from within depending upon type of goods, services, capital assets etc. are required. Interaction between various arms of department, executing agency influence the procurement decision. Process, methods, organizational structure, professionalism of staff also impact the procurement strategy. Internal policies make it a tight rope walk, which may be in conflict with the objectives. I. External Challenges External factors such as market, political environment, legal environment and other socio-economic factors impose challenges to public procurement. (i) Legal Here it is referred to general /broad legal frame work prevailing in the society e.g. various regulations dealing with safety and health at work place, pollution control, finance regulations, right to information, dispute resolution mechanism, contract law, dealing with equal opportunities for women and minorities etc. However, if laws regarding such issues are not comprehensive, the contract may need detailed provisions. (ii) Political In democratic setup, various interest groups play an important role to influence public procurement strategy. These interest groups include trade organizations, professional associations, business firms or companies etc. Types of influence vary from influencing procurement guidelines, procurement process, technical specifications, budget authorization etc. Eventually, a compromise view emerges for adoption. In certain cases, coalition of policy makers, bureaucrats and interest group exist to push forward their agenda. Public procurement strategy has choices, one side it is faced with political pressure and on other side maintaining sound economic decision. (iii) Social Policies on social issues such as affirmative action towards certain section of society e.g. tribal, backward groups etc. play an important influence in procurement strategies. Environmental protection movements, activities of various groups concerning to wild life, animals, monuments etc. also put pressure on procurement policies. Commitment on foreign policy, trade agreements etc. also have bearing on decision making.
  • 4. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -14 (iv) Cultural Public procurement system is also influenced by culture and technology. Knowledge & spread of information technology have changed the procurement strategy and process. In certain cultures, giving gift is a common public relation activity however; it is difficult to distinguish between gift and bribe. (v) Market Environment Market conditions influence competition and determine outcome of procurement process. Market conditions vary from country to country and vary from sector to sector. Even under a perfect competition market, certain supplies/services may have a monopoly. New challenges also arise in order to comply with governments procurement laws, international treaties, custom regulations etc. There is tough choice to allow foreign firms along with domestic firms, putting pressure on domestic players. III. MODE OF PROCUREMENT The project delivery method translates what project parties are involved in the project and how they interact with each other and called also project organizational structure. The choice of an organizational structure should be related to project objectives and constraints. It can be facilitated considering the following factors: a. Size and nature of the work packages within the project. b. Selection of the design team form in-house resources external consultants or contractors. c. Process of supervision of construction. d. Restrictions upon using combination of organizational structures within the project. e. Expertise which the client wishes to commit to the project. When plans are completed and the owner is interested in securing the low price, the use of competitive bids is suggested. The competitive bidding results in the type of contract that many are familiar with. A negotiated contract should be used when construction should start before plans are completed or when the many unknown factors of the project make an accurate estimate impossible. When many changes are expected and when inspection and supervision cannot be done efficiently, the negotiated type of contract should be used. The various project delivery methods are summarized as follows: A. Traditional approach This is the most common approach in civil engineering projects in which the design has to be completed before construction can start. Design and construction are usually performed by two different parties who interact directly and separately with the owner. The pros and cons of this approach are summarized as follow: Advantages: a. Price competition b. Total cost is known before construction starts c. Well documented approach used in most government projects. Disadvantages Disadvantages: a. Long time b. Design does not benefit from construction expertise c. Conflict between owner, contractor and A/E Therefore, this method is fine in many cases where the project is clearly definable, design is completed, time need not be shortened, and changes are unlikely to occur during construction. B. Admeasurement contract In this type of contracting, items of work are specified in Bills of Quantities or Schedule of Rates. The contractor then specifies rates against each item. The rates include risk contingency. Payment is paid monthly for all work completed during the month. The contract offers a facility for the client to introduce changes in the work defined in the tender documents. The contractor can claim additional payment for any changes in the work content of the contract. Claims resolution is very difficult because the client has no knowledge of actual cost or hidden contingency. Tender price is usually increased by variations and claims. Two forms of admeasurement contract are usually used: bill of quantities and schedule of rates. Bill of Quantities Contract: Tenderers enter rates against each item of the estimated quantities of work. The quantities are re-measured during the course of the contract, valued at the tendered rates and the contract price adjusted accordingly.
  • 5. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -15 Schedule of Rates Contract: It contains inaccurate quantities of work, possibly with upper and lower probable limits. Therefore, it is common for separate rates to be quoted for labour, plant, and materials. The contract price is derived by measuring the person-hours, plant-hours and the quantities of materials actually consumed, and then pricing them at the tendered price. This contract is best suitable for repetitive works. The admeasurement contract is well understood and widely used. It can be used when little or no changes are expected, level of risk is low and quantifiable, and when design and construction need to be overlapped. C. Direct labour In this approach, owner organization performs both the design and construction using its in-house labour force. a. Used by large authorities b. The owner performs both the design and the construction c. May use consultants for some specialized designs d. Most suitable for small projects e. Can be used when expertise is available f. Low risk projects g. Inadequate scope definition D. Design-build In this approach, a single organization is responsible for performing both design and construction and, in some cases, providing certain “know-how” for the project. The pros and cons of this approach are summarized as follow: Advantages: a. One contract that may include know-how b. Minimum owner involvement c. Used for fast-track projects in order to reduce time d. Co-ordination between design and construction and easier in implementing the changes Disadvantages: a. Cost may not be known until end of the construction b. High risk to contractor and more cost to owner c. Design-build company may reduce quality to save cost The use of this approach, therefore, should be considered when contractors offer specialized design/construction/know- how expertise or when design is strongly influenced by the method of construction. E. Design and build lump sum contracts In this mode contractor agrees to execute the complete work with all its contingencies. Such type of strategy is most suitable in case of large projects where the aims are: a) Innovation of private initiatives b) Economy of scale (Contractor using standard designs, module, technology etc.) c) Speed of construction This method is also referred as turn-key contract with some variations. F. Turnkey This approach is similar to the design -build approach but with the organization being responsible for performing design, construction, expertise (if any), and project financing. Owner payment is then made at the completion (when the contractor turns over the “key”). An example is franchise projects in which a new branch of a restaurant chain needs to maintain the same design, construction quality, and food service quality. G. Cost-reimbursable contract (cost-plus contract) The contractor is reimbursed for actual cost plus a special fee for head office overheads and profit, no special payment for risk. Payment may be made monthly in advance. The contract involves a high level of flexibility for design changes. Final price depends on changes and extent to which risks materialize. The contractor must make all his records and accounts available for inspection by the client or by some agreed third party. The fee may be a fixed amount or a percentage of actual costs. This contract has no direct financial incentives for the contractor to perform efficiently. It may be used when it is desirable for design to proceed concurrently with construction and when the client wishes to be involved in contract management.
  • 6. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -16 H. Target cost contract Cost targets may be introduced into cost-reimbursable contracts. In addition to the reimbursement of actual cost plus percentage fee, the contractor will be paid a share for any saving between target and actual cost, while the fee will be reduced if actual cost exceeds the target. The target figure should be realistic and the incentive must be sufficient to generate the desired motivation. Specified risk' can be excluded from the tendered target cost. When these occur, the target cost is adjusted accordingly and the client pays the actual cost incurred by the contractor. The target may also b' adjusted for major changes in work and cost inflation. This contract can be used in the same circumstances as the cost- plus contract. I. Time and material (T&M) contracts T&M contracts are a hybrid type of contractual arrangement that contains aspects of both cost-reimbursable and fixed- price-type arrangements. T&M contracts resemble cost-type arrangements in that they are open ended, because the full value of the arrangement is not defined at the time of the award. Thus, T&M contracts can grow in contract value as if they were cost-reimbursable-type arrangements. Conversely, T&M arrangements can also resemble fixed-unit arrangements when, for example, the unit rates are pre-set by the buyer and seller, as when both parties agree on the rates for the category of "senior engineers." Most appropriate when the buyer wants to be more in control. It is also used in an emergency to begin work immediately when a scope of work has not yet been completed. Not possible at time of placing contract to estimate extent or duration of the work, or anticipated cost, with any degree of confidence. J. PPP (Public Private Partnership) In this mode the private firms or consortium agrees to construct with its own cost in lieu of future revenues over a period of time. Various models like BOT, BOLT, BOOT or BOO under PPP are available depending upon type of work, preparedness of the project, future projections, funding arrangement, leverage, risk sharing arrangements etc. In this approach, a business entity is responsible for performing the design, construction, long-term financing, and operation and Maintenance of the project. At the end of the operation period, which can be many years, operation of the project is transferred to the owner. This approach has been extensively used in recent years and is expected to continue. An example of its use is in express routes and turnpikes. A consortium of companies shares the cost (design, construction, financing, operation, and maintenance) and the profits gained from user fees, for a stipulated number of years. Afterwards, the project returns to the government to become publicly owned. This approach has also been used extensively in large infrastructure projects financed by the World Bank in parts of the world that cannot afford the high investment cost of such projects. IV. METHOD OF PROCUREMENT Generally, competition is a basis of efficient contracting strategy. However, in selective cases requiring skilled and specified work, procurement can be through limited competitive or through single source. Any of the following methods could be resorted by following general principle of economy, efficiency and transparency. A. International competitive bidding In this method, notice of bid is advertised globally to invite eligible prospective bidders from eligible countries to participate in the bidding process. This method brings not only overseas technology work culture but also overall economy. B. National competitive bidding This method is normally used by open advertisement within country. This method is most suited for goods, works; services that are available locally at prices below the international market and the works are limited intensive. C. Limited bidding Limited bidding is by direct invitation without open advertisement. This method may be appropriate where: a. There are only limited nos. of suppliers b. Value of contract is not very large c. Emergency situations d. Security reasons, which do not justify open competitive bidding. D. Single source bidding This strategy is adopted for special works or in emergent situations. Employer can select firms based on qualification and experience. There is no competition in such bidding method. V. PROCESS OF PROCUREMENT Depending upon complexity and regulatory requirements, the bidding process can be very short or very elaborate and exhaustive. Generally, following processes are used:
  • 7. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -17 a. Single Packet without PQ (Prequalification) b. Two Packet without PQ c. Single stage two packets with PQ d. Two stage with PQ The above processes could be interactive with the bidders by way of pre-bid submission meetings. Depending upon the complexity and size of the project, further stages can be added to meet the objectives. VI. CONTRACT ADMINISTRATION As it was discussed in the previous sections, there is variety of types of contracts used in civil engineering projects. Each type has its specific characteristics. Contracts may be prepared under the heading of one type but could include characteristics of more than a single type. Many professional societies and government agencies have done a great deal toward the standardization of construction contracts such that the general form and content are well established for the various types of construction that may arise. A. Professional construction management (PCM) In this approach, the owner appoints a PCM organization (also known as Construction Management organization) to manage and coordinate the design and construction phases of a project using a Teamwork approach. The design may be provided by specialist design firms and in some cases by the PCM organization. With high level of coordination between the participants, innovative approaches of overlapping design and construction (i.e., fast tracking) can be adopted. The PCM organization aims at holding a friendly position similar to that of the consultants in the traditional approach. The services offered by the PCM organization overlap those traditionally performed by the architect, the engineer, and the contractor. This may include: management and programming of design; cost forecasting and financial arrangements; preparation of tender documents; tender analysis and selection of contractors; selection of methods of construction; recommendations on construction economics; planning and scheduling construction works; materials procurement and delivery expedition; provision for site security, cleanup, and temporary utilities; supervision of control of construction contractors; construction quality assurance; cost control; costing of variations and assessment of claims; and certification of interim and final payments to contractors. The use of PCM approach, therefore, should be considered when there is a need for time saving, flexibility for design changes is required, and owner has insufficient management resources. B. Contract documents The contract is defined by the contract documents, which are developed from the tender documents. In a logical order, these documents refer to the following subjects: a. Input from the client (task description). b. Output of the contract (specifications, results to be achieved). c. Prices for the contractor's contribution. d. Responsibilities and procedures (liability, resources provided, time schedule, payment conditions, change procedures, etc.). Contract documents are usually arranged according to the following sequence: a. General (for any project). b. Special (for a specialty area of the project). c. Supplementary (unique to a given project). d. Additional (during bidding or negotiation). e. Agreement form (for singing very important and particular clauses). f. Modifications (during contract fulfilment). The complete contract agreement usually consists of the following documents: a. Conditions (general, special, supplementary). b. Drawing and specifications. c. Addenda. d. Agreement form. e. Modifications. The most important document from the legal point of view is the agreement. It is sometimes called the contract. Since so many documents are included as contract documents, the agreement is the better term for this particular one. The form of the agreement can be standardized and used for many projects, or a unique document can be prepared for each project. The standard form of agreement prescribed by the American Institute of Architects has proved to be satisfactory and has been used on many building projects with good results. The form followed for non- building projects is often more varied. Man: agencies have own standard forms, which are used on all their projects. Information usually included in the agreement are of three parts. The first part is a short introductory paragraph which defines the parties, gives the date of the agreement, and state that each party agrees to what follows.
  • 8. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -18 The second part contains the elements of contract and defines the work to be undertaken. The final paragraph confirms the agreement and provides space for signatures of the parties. Thus, the agreement usually composed of the following articles: a. A short introductory paragraph. b. Scope of the work. c. Time of completion. d. Contract documents. e. Performance bond. f. Contractor's insurance. g. Owner's insurance. h. Laws, regulations and permits. i. Payments. j. Extensions of time. k. Changes in the work. l. Owner's right to terminate the work. m. Contractor's right to terminate the work. n. Confirmation and signatures. C. Conditions of contract The conditions of a contract are rules by which the execution of the contract is to be governed. They set-out the responsibilities, rights, and liabilities of the two parties. They also set- out the actions to be taken by the parties if and when certain eventualities should arise. No two civil engineering contracts are similar. Probably, no two construction contracts are truly the same. Therefore, identical conditions of contracts are not likely to be required. However, for work of a similar type, certain conditions will apply for the vast majority of cases. It follows that a standard form of conditions for a given type of work will remove the necessity of thinking out and drafting new sets of conditions for every new contract. By taking the standard form and modifying it to suit the requirements of a particular contract, time and effort will be saved. The terms of a contract legally fall into two categories: a. Conditions: They are terms expressing matters basic to the contract. A failure to perform the requirements of a condition is a fundamental breach of an essential obligation giving the aggrieved party the right to: 1. End the contract and claim damages, or 2. Continue the contract and claim damages. b. Warranties: They deal with matters not of the essence of the contract, being subsidiary to the main purposes for which the parties contracted. An example of a warranty is where a nominated sub-contractor warrants that the work will be carried-out to specific standards. The conditions of a contract usually comprise the following: 1. A standard form of general conditions of contract appropriate to the natures of the work involved. 2. A series of amendments to the forging in order to adjust them to the circumstances of the actual contract concerned. 3. A number of special conditions, which deal with matters peculiar to the contract and not dealt with by the standard. D. Standard (general) forms of conditions of contract Standard forms are prepared jointly by professional bodies and organizations representing contractors or by large organizations and public bodies to suit their own circumstances. The intention is that a common approach by the parties to all contracts will be achieved and standard interpretations of risks and responsibilities involved. There are a number of standard forms of conditions of contract used in civil engineering. The most commonly used are: Institute of Civil Engineering (ICE) Conditions of Contract: This document includes the forms of Tender, Agreement and Bond. It is applicable to all civil engineering construction works. It is particularly suitable for general civil engineering work which is predominantly either in the ground or in, or adjacent to, water, and carets for the attendant risks and claims situations. It is also used, sometimes, for building works and for mechanical and electrical works where such works are included in a civil engineering or building contract. Federation Internationale Des Ingenieure-Conseils (FIDIC): These conditions are, in effect, international versions of the ICE conditions to which they are closely related. The fourth edition (1987) of the conditions for works of civil engineering construction comprises: Part I: General conditions with forms of tender and agreement. Part II: Conditions of particular application with guidelines for preparation of Part II clauses. It is intended for general use for works where tenderers are invited on an international basis, but it also suitable to domestic contracts. The objective is to provide a standardized document which is well-known, internationally recognized and accepted, an adequately reflects the interests of the parties concerned.
  • 9. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -19 The standard (general) forms of conditions of contract usually cover the general aspects in arranged clauses. For example, FIDIC general conditions of contract comprise clauses that cover the following items: a. Definitions and interpretations. b. Engineer and Engineer's representative. c. Assignment and sub-contracting. d. Contract documents. e. General obligations. f. Labour, Materials, plant, and workmanship. g. Suspension. h. Commencement and delays. i. Defects liability. j. Alternations, Additions and Omissions. k. Procedure of claims. l. Contractors' equipment, temporary works and materials. m. Provisional sums. n. Certificates and payments. o. Remedies. p. Special risks. q. Release for performance. r. Settlement of disputes. s. Notices. t. Default of Employer. u. Changes in cost and legislation. v. Currency and rates of exchange. Most of the standard forms of conditions of contract contain one or more clauses, which require completion by the Client/Engineer before the conditions are issued. E. Special conditions of contract Special conditions are new clauses to augment the general conditions of a standard form. Usually they deal with subjects not touched on by the standard form. It is often simpler to introduce a special condition than to amend a standard form condition. After a new clause is written, it must be ensuring that no conflict or ambiguity is being introduced. The range of possible subjects for special conditions is large. They normally deal with the peculiarities of one contract and one site. There are varieties of choices in which a new subject may be written: a. In the specification (if it is of technical matter). As special condition of contract. b. In the site regulations (if it deals with site administration or discipline). c. In separate correspondence (if it is not essential to incorporate it into the formal contract). The decision to consider a special condition does not depend on importance. The following are typical examples of subjects for special conditions: a. Special terms of payments. b. Patents and licenses. c. Applicable law. d. Official Language. e. Obligatory use of local labour, plant and material. f. Co-operation with contractor on site. g. Fair wages to be paid. h. Union membership of work force. i. Protection and disposal of historic, valuable, archaeological, etc. finds on site. j. Prohibition of access to named places. k. Restrictions on noise levels, dust, fire hazards, etc. l. Control of demolition work, explosives, etc. m. Responsibility for damage to public services. n. Responsibility for payment of local taxes. F. Construction claims A construction claim is a request for payment or time extension to which the contractor considers him/herself entitled. There are three types under which claims are required:
  • 10. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -20 a. Extension of time only. b. Additional cost. c. Both extensions of time and additional cost. The main reasons for construction claims may include: a. Late possession of site or late provision of working drawings. b. Change of contract start or activities schedule. c. Design change and variation. d. Delays in approval and examining work. e. Work acceleration by the client. f. Late delivery of materials supplied by the client. g. Different ground and/or site conditions. h. Unforeseen events and disasters. VII. SELECTION CRITERIA Traditional selection of successful bidder is based on contract price of the project. The selection of the bidder can be based on lowest price bid, qualification based, qualification cum cost based, cost plus time based, lowest life cycle cost, period of contract, return from the project etc. Based on selection criteria the component of bidding i.e. mode, method and process are suitably modified to reduce the risk of subjectivity at the time of evaluation. VIII. PROCUREMENT STRATEGY SELECTION MATRIX After the detailed analysis & evaluation of various pros and cons with respect to modes, methods & processes a formal approach as suggested below (Figure-1) can be adopted for selection of optimal strategy. A suggestive comparison/matrix with respect to various issues for different modes of procurement is listed in table -1; similar matrix for method and process shall also be made as part of an iterative process to find final strategy. Figure-1 Procurement Strategy Selection Matrix a. Set Project Goal b. Assess the resources and capacity of the organization 1. Technical 2. Infrastructure 3. Risk management capacity 4. Staff experience etc. c. Project profile 1. Complexity of project 2. Schedule of completion 3. Availability of designs 4. Availability of supervision staff 5. Innovations 5. Availability of funds 7. Availability of land & other Statutory clearances 8. Major stake holders 9. Project specific constraints 1, 2, 3………
  • 11. International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: 2349-2763 Issue 02, Volume 3 (February 2016) www.ijirae.com _________________________________________________________________________________________________ IJIRAE: Impact Factor Value - ISRAJIF: 1.857 | PIF: 2.469 | Jour Info: 4.085 | Index Copernicus 2014 = 6.57 © 2014- 16, IJIRAE- All Rights Reserved Page -21 d. Do risk assessment [w.r.t. different mode/ method/process of procurement strategy] e. Can risk be shared/transferred/ allocated/ ignored f. Re-work on procurement strategy considering complexities of the project g. Final selection IX.CONCLUSION No single contracting strategy is suitable for every project. Each project should be critically analysed to determine the most optimal delivery strategy. It is requisite to map all the factors, Project goals, Procurement goals and institutional capacity available for a project. TABLE 1- METHOD SELECTION CHECK LIST. ISSUE BIDDING METHODS ITEM RATE DESIGN BUILD LUMP SUM MANAGEMENT CONTRACT PROJECT DELIVERY SCHEDULE If design is available, the time required for this procurement is short. Design and construction ae parallel activity, which accelerate the project delivery schedule, however procurement time is lengthy Project development, design, procurement and construction, etc. Are parallel activity. Project delivery schedule can be slow due to coordination issues. COMPLEXITY OF PROJECT Complex design issues can be sorted quantitatively before hand Contractor provides most economical innovative solution with alternate technical proposals. It allows qualitative design with mutual consultations. PREPAREDNESS OF DESIGN 100 percent in house design. Design risk is allocated to bidder. Employee is to give only precise performance requirements. In due course improvement in design is possible. However it may extend project schedule. COST OF PROJECT Competitive bidding allows a low cost. Cost accuracy is expected. It is cost efficient. However poor risk allocation can result higher contingencies and improper risk loading. It has flexibility of designing as per budget limit RISK ALLOCATION Quite Clear Proper allocation of risk to the party best able to manage them. These risks are to be well defined to minimize contractor’s contingencies on cost price. Risks are collectively shared and minimizes loading of contingencies on cost price. But there is less competition REQUIREMENT OF IN HOUSE STAFF EXPERIENCE AVAILABILITY. Elaborate Technical design team is necessary Elaborate Technical design and management team is necessary to develop RFP and subsequent monitoring. Committed Technical design and design team is necessary with consultant LEVEL OF AGENCY CONTROL Full Less Collaborative effort MARKET COMPETITION High level Competition Medium level Competition Low level Competition REFERENCES [1] Guidelines procurement under IBRD loans and IDA credits, (2010). [2] JICA guideline for procurement. [3] Keith Molennar, Harpan Chris, Daniel Tran, “Guide book for Selecting Project Delivery Methods and alternative contracting strategies”, University of Colorado, Colorado, (2012). [4] Khi V. Thai,” Public Procurement re- examined, Journal of Public procurement, Vol- I, Issue 1, PP. 9-50, (2001). [5] Procurement guidelines, Asian Development Bank, (2010). [6] The public procurement bill (2012). [7] Works Manual, Dedicated Freight Corridor Corporation of India Limited (2012).