International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 99
“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing
Projects in Kolhapur”
Neha V. Jadhav1, Prof. Amit B. Patil2, Prof. G.N. Kanade3
1M. Tech Scholar, Department of Civil Engineering, Tatyasaheb Kore Institute of Technology, Kolhapur,
Maharashtra, India.
2,3Professor, Department of Civil Engineering, Tatyasaheb Kore Institute of Technology, Kolhapur, Maharashtra,
India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - For Indian real estate sector has been facing a
slump since 2012. In this research project, the study's focus is
restricted to the Kolhapur City. We will investigate the impact
of RERA on India's building constructions industries in this
project. To check the impact of RERA we are dealing with 25
factors for seller and 23 factors for buyer. For the analysis
purpose we have made the questionnairesurvey. Fromthatwe
have calculated RII from collected data by usingLikert’sScale.
A study is conducted to determine the immediate impact of
this act on the Builders and the consumer.
Key Words: RERA, RII, real Estate, Likert’sScale,Construction
1. INTRODUCTION
In the Indian Real Estate Industry's History, The Real Estate
Regulation and Development Act (RERA) of 2016 is a game-
changing piece of legislation. It was enacted to encourage
real estate investment while simultaneously safeguarding
the interests of home buyers. The Act promotes ethical
behavior in the real estate industry and attempts toincrease
openness. The Act covers both new and ongoing projects
(which had to be registered by July 31, 2017). This statute
covers both commercial and residential construction
projects. Agents or brokers in the real estate industry are
also covered under the umbrella.
Furthermore, the developers must report the project
designs, government approvals, and the status of the land
ownership to the regulatory authorities. Failuretodoso will
result in a fine, jail, or both, depending on the gravity of the
offence. The Real Estate Industry was in critical need ofsuch
a transparent system in order to promote market mood and
protect customers' interests. The bill also requiresbuyers to
pay developers within a certain amount of time, failing
which appropriate action can be taken against them. One of
the most typical challenges in the construction sector is
building project delays. Delays havea negativeimpacton the
project's performance, timeliness, and cost. As a result, it's
critical to understand the different sorts of delays that can
arise in a project. Delays can occur for a varietyofcauses(or,
in other words, have diverse origins); they can be
compensated or not; and they can occur concurrently or
afterwards. In addition, the impact on project performance
can be direct or indirect. Their presence results in increased
costs, conflicts among project partners, and, in the worst-
case scenario, litigation, which may result in more costs.
When dealing with delays, it's necessary to not only detect
them and quantify their effects on project performance, but
also to identify and quantify the implications of previous
delays on future project progress. The key causes and
sources of delays should also be identified in order to
regulate accountability and allow for learning from these
unfavorable events.
1.1 RERA Act 2016
The Real Estate (Regulation & Development) Act of 2016
proposes to create a Real Estate Regulatory Authority to
govern and promote the real estate industry.
The physical body will –
 Ensure that land, buildings, or projects are sold in a
timely and transparent manner.
 Consumers' interests must be protected.
 Create a method to ensure that conflicts are resolved
quickly.
 Createan AppellateTribunal to overseebothresidential
and commercial construction projects.
2. Literature Review
Shubhangi Salunkhe, R Mahadeva Swamy – In this paper,
author explains carpet area term in detail and explains its
impact on RERA. Also explains with the examples. For the
analysis, author uses relative importance index method. For
that they donequestionnairesurveyandcollectresponsesfor
the analysis. They also make comparative analysis of RERA
approach and traditional approach for one site in Pune for
the time andcost analysis. Author conclude that, builders are
not allowed fake commitment to buyer for possession date.
Somdutta P. Patil, Prof. Ashish P. Waghmare – The author
analyses the effect of RERA on the real estate business,
including the impact on ongoing and new projects, as well as
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 100
the impact on builders, purchasers, and agents and brokers.
Additionally, they examined the economicimpactofRERAon
the real estate business. They spend the most of their time
studying MahaRERA. They learn about the benefits and
drawbacks of the RERA real estate legislation. Prompt
possession of apartments, project clearance, and after-sales
services are someof the benefits of RERA listedinthisarticle.
Additionally, this report discusses historical challenges,
project delays, and other negatives. Additionally, they said
that this legislation is a step forward in terms of boosting
openness in the real estate industry, increasing promoters'
and developers' responsibility, and enabling efficient
channels for grievance resolution.
Akshaykumar P. Udasi, Milind M. Darade– This study is
divided into two stages. To begin, a survey of the literature
was conducted to ascertain the elements that contribute to
building project delays.101sourcesofdelayswereidentified
by a literaturestudyand dividedintoninedistinctcategories:
owner-related,contractor-related,consultant-related,design-
related, labor-related, material-related, equipment-related,
and external factors- related,andRERA-related.Additionally,
determine their various impacts/effects on the building
project. Following that, a questionnaire survey is
administered using Google forms. This Google form issent to
numerous stakeholders in the building business by email,
whatsApp, and text messaging. There are a total of ten
replies. Graphs in paper illustrate the relationship between
RERA characteristics and the number of respondents.
Suhas G. Awari, Raju Narwade and Manisha Jamgade –
The research is divided into two stages: a literature review
and interviews. The first step entails doing a literature
review. As a result of this evaluation, 51 delay factors
appropriate for the current investigation were found. These
causes were then classified into eight distinct categories
based on their nature and mode of occurrence: project-
related, client-related, contractor- related, RCC consultant-
related, construction design-related, construction material-
related, machinery-related, labor-related factors, and
external factors. The second step is the creation of a
questionnaire based ontherelativeimportanceindexandthe
calculation of the Spearman rank correlation coefficient for
the importance index. The questionnaire was split into three
sections, which included reasonsofconstructiondelays,their
effects, and ways forreducingconstructiondelays.Thisstudy
to identify the effective methods to reduce delays in
construction projects.
Thorat Sourabh, Khandare Manish, A.K. Kanase – The
empirical association between the causes and consequences
of delay is also examined in this study utilizing Pearson's
correlation coefficient in SPSS 23. Additionally,prescriptions
for reducing delays were made in this research to clients,
consultants, and contractors. The purpose of this study is to
determine the causes and effects of delay in residential
construction projects in India and to investigate the
relationship between specificcausesandspecificeffects.This
study employs an integrated approach to ascertain the
impact of specific causes on specific effects in residential
construction projects in the Indian context. There are a total
of 41 causes classified into seven main categories, as well as
seven significant impacts of delay. A questionnaire survey
was used to elicit information on the causes and impacts of
delay from clients, consultants, and contractors, with 67
respondents. The study's findings were satisfactory. This
research will assist practitioners and scholars in better
understanding project management and making attempts to
eliminate delays in residential construction.
Tibin Joy, B.Selvam - This article discussed the RERA act in
depth. The author defines carpet area concept in detail. The
author created identical questionnaires for builders and
purchasers and conductedsurveystoascertainthereplies.As
a result of this regulation, each project must be registered
with RERA, which will serve as the regulatory authority. It
will increase openness, as the client/allottedwillhaveaccess
to further information about the project, promoter,
promoter's historical experience, and agent, among other
things.
3. Methodology
3.1 Objectives:
1. To study the present status & collect the
information about chronological event from
development of RERA to till date.
2. Identification of ongoing problems in construction
industry & to analyses them.
3. To prepare questionnaire survey obtained through
builders.
4. To carry out analysis of various responses obtained
through live construction project in Kolhapur.
5. To recommend best suggestive measures for
reducing costs and delay.
3.2 Research Methodology:
1) Collection of preliminary information through
literature review.
2) Descriptive analysis by collection of data by
questionnaire survey & interviews.
3) Assessing the current situation of construction
industry pertaining RERA effects by questionnaire
survey.
4) Defining problems in constructionindustrythrough
survey conducted.
5) Giving suggestive measures for reducing problems
through RERA.
6) Giving results & conclusions from data analyzed.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 101
Considered factors:
The questionnaire designed by consideration of factors
affecting the RERA act on constructionindustrythroughpre-
existing literature and studied model. The following factors
are considered in the design of the questionnaire.
Sr.No. BUYER’S FACTORS SELLER’S FACTORS
1 Restrictions to
diversion of money
Restrictions to
diversion of money
2 Property sold on carpet
area
Punctuality
3 Punctuality Security of money
4 Dispute resolution Quality of work
5 Penalties More profitable to
buyer
6 More profitable to
buyer
Transparency
7 Transparency Quality is improved
8 Security of money Penalties on delay
9 Responsibility of
defects
Professionalism
10 Professionalism Dispute resolution
11 Quality of work Structural warranty
12 Use of ICT No misleading claims
13 Balanced agreement
and treatment
Use of ICT
14 No misleading claims Property sold on carpet
area
15 Structural warranty Advertising only after
RERA
16 Value of money Easy problem solution
17 Easy problem solution Value of money
18 Hike in property prices Value of money
19 Easy problem solution Authorization
20 Hike in property prices Real advertisement
21 Investment rate Responsibility of
defects
22 Quality is improved Harsh penalties for
seller
23 Penalties on delay Hike in property prices
24 Investment rates
25 Supply demand
imbalance
2. Data Analysis by using Likert’s Scale
Adopted scale is Five-point scale ranging from 1 (Strongly
Not Effective) to 5 (Strongly Effective) and it is transformed
to relative importance indices (RII) for each factor as
follows; Where,
N1 = number of respondents who voted for Strongly Not
Effective
N2= number of respondents who voted for Least
Effective
N3= number of respondents who voted for Neutral
N4= number of respondents who voted for Effective
N5= number of respondents who voted for Strongly
Effective
N is the weighting given to each factor by the respondents
(ranging from 1 to 5). The RII value had a range from 1 to 5,
the higher the value of RII, the more important was the
factor affecting RERA.
2.3 Results:
Table -1: Result for Buyer:
RANK BUYER’S FACTORS RII%
1 Restrictions to diversion of money 82%
2 Property sold on carpet area 80%
2 Punctuality 80%
2 Dispute resolution 80%
3 Penalties 79%
4 More profitable to buyer 77%
5 Transparency 76%
6 Security of money 75%
6 Responsibility of defects 75%
7 Professionalism 72%
7 Quality of work 72%
8 Use of ICT 70%
9 Balanced agreement and treatment 69%
9 No misleading claims 69%
9 Structural warranty 69%
10 Value of money 68%
11 Easy problem solution 66%
12 Hike in property prices 65%
13 Investment rate 61%
14 Quality is improved 60%
14 Penalties on delay 60%
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 102
Table -2: Result for seller
RANK SELLER’S FACTORS RII%
1 Restrictions to diversion of money 94%
2 Punctuality 90%
3 Security of money 88%
3 Quality of work 88%
3 More profitable to buyer 88%
4 Transparency 86%
5 Quality is improved 84%
5 Penalties on delay 84%
5 Professionalism 84%
5 Dispute resolution 84%
6 Structural warranty 78%
7 No misleading claims 76%
7 Use of ICT 76%
8 Property sold on carpet area 74%
8 Advertising only after RERA 74%
8 Easy problem solution 74%
9 Value of money 72%
9 Authorization 72%
10 Real advertisement 70%
10 Responsibility of defects 70%
11 Harsh penalties for seller 68%
12 Hike in property prices 64%
13 Investment rates 58%
13 Supply demand imbalance 58%
3. CONCLUSIONS
A. Positive Impact
1. Sellers cannot make any false commitment regarding
possession date. If it is not happened then seller should
face the harsh penalties.
2. Sellers need to mention all the details which they are
going to provide in the project accurately.
3. The sellers became more specific about the carpet area
so that the buyers can get the idea about for what they
are paying.
4. The land should be free from any type of litigation
before the beginning of the project. The sellers should
provide all clearance documents to the RERA.
5. For the transparency purpose and restriction for the
money diversion, every project has to make separate
bank account for transactions.
6. After selling the flat, thesellershouldprovidestructural
warranty for 5 years span.
B. Negative Impact:
1. Registration became mandatory only for projects which
are more than 500 Sq m area. But it should be bound to
every seller.
2. Old projects with some litigations are supposed to be
delayed because of the rules of the RERA
3. For every quarterly period government approval became
mandatory for project which may be delayed because of late
work of government agencies.
4. Registration fees increased that's why project values are
rising.
REFERENCES
[1] Aditya V Kadam, Rushikesh R Jangam, Rushikesh R
Pawar, Ashwini A Sagavekar, Prof. G. D. Parulekar, Prof.
S. S. Patil, ‘ Detailed Study and Analysis of RERA Act’,
[2] www.irjet.net, Volume: 05 Issue: 04 Apr-2018.
Akshaykumar P. Udasi, Milind M. Darade, ‘Delays in
construction projects : causes, effects and impacts of
RERA’, 2018 IJRTI | Volume 3, Issue 7.
[3] Thorat, Manish Khandare, A.K.Kanase, ‘Exploratory
Study Of Causes And Effects Of Delay In Indian
Residential Projects’, Volume: 04 Issue: 06 | June -2017
[4] Dr. Ashish B. Joshi, Nisha Singh, ‘Real Estate Regulation
Act (RERA), 2016: Implementation and Issues’,
International Journal of Management Studies, Vol.–V,
Issue –4(8), October 2018.
[5] Meghwant Singh Thakur, ‘Effect of RERAonprofitability
of Indian real estate developers’,International Journal of
Management and Applied Science, ISSN: 2394- 7926
Volume-4, Issue-9, Sep.-2018.
[6] Prof. S. G. Rodgi, ‘An Overview of „RERA‟ in India: A
Regulatory Shift’, www.rrjournals.com, Volume 4, Issue
01, January 2019.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 103
[7] 7) S. Radhakrishnan, Dr. K. G. Selvan, ‘ImpactofRERAon
Construction of Multi Storied Buildings’, International
Research Journal of Advanced Engineering and Science,
Volume 4, Issue 1.
[8] Somdutta P. Patil, Prof. Ashish P. Waghmare, ‘ Impact of
Real Estate Regulation and Development Act (RERA) on
India’s Real Estate Sector’, 2017 IJSRST | Volume3Issue
8.
[9] Suhas G. Awari, Raju Narwade and Manisha Jamgade,
‘Analysis for cause identification for delay in building
construction industry’, International Journal of Modern
Trends in Engineering and Research (IJMTER) Volume
03, Issue 10, October 2016.
[10] Tibin Joy, B.Selvam, ‘Impact of Real estate regulation
authority (RERA) on residential project’,IRJET,Volume:
05 Issue: 11 | Nov 2018.

More Related Content

Similar to “Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects in Kolhapur”

IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsIRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET Journal
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET Journal
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET Journal
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET Journal
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectseSAT Journals
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportationeSAT Publishing House
 

Similar to “Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects in Kolhapur” (20)

IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
 
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
IRJET- Analysis of Contractual Communication among Parties to the Contract wi...
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure Projects
 
IRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure ProjectsIRJET- Management of Stakeholder in Infrastructure Projects
IRJET- Management of Stakeholder in Infrastructure Projects
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 
Causes of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projectsCauses of delay in indian transportation infrastructure projects
Causes of delay in indian transportation infrastructure projects
 
Causes of delay in indian transportation
Causes of delay in indian transportationCauses of delay in indian transportation
Causes of delay in indian transportation
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 

“Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects in Kolhapur”

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 99 “Analysis & Critical study of Impacts of RERA Act, 2016 on Housing Projects in Kolhapur” Neha V. Jadhav1, Prof. Amit B. Patil2, Prof. G.N. Kanade3 1M. Tech Scholar, Department of Civil Engineering, Tatyasaheb Kore Institute of Technology, Kolhapur, Maharashtra, India. 2,3Professor, Department of Civil Engineering, Tatyasaheb Kore Institute of Technology, Kolhapur, Maharashtra, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - For Indian real estate sector has been facing a slump since 2012. In this research project, the study's focus is restricted to the Kolhapur City. We will investigate the impact of RERA on India's building constructions industries in this project. To check the impact of RERA we are dealing with 25 factors for seller and 23 factors for buyer. For the analysis purpose we have made the questionnairesurvey. Fromthatwe have calculated RII from collected data by usingLikert’sScale. A study is conducted to determine the immediate impact of this act on the Builders and the consumer. Key Words: RERA, RII, real Estate, Likert’sScale,Construction 1. INTRODUCTION In the Indian Real Estate Industry's History, The Real Estate Regulation and Development Act (RERA) of 2016 is a game- changing piece of legislation. It was enacted to encourage real estate investment while simultaneously safeguarding the interests of home buyers. The Act promotes ethical behavior in the real estate industry and attempts toincrease openness. The Act covers both new and ongoing projects (which had to be registered by July 31, 2017). This statute covers both commercial and residential construction projects. Agents or brokers in the real estate industry are also covered under the umbrella. Furthermore, the developers must report the project designs, government approvals, and the status of the land ownership to the regulatory authorities. Failuretodoso will result in a fine, jail, or both, depending on the gravity of the offence. The Real Estate Industry was in critical need ofsuch a transparent system in order to promote market mood and protect customers' interests. The bill also requiresbuyers to pay developers within a certain amount of time, failing which appropriate action can be taken against them. One of the most typical challenges in the construction sector is building project delays. Delays havea negativeimpacton the project's performance, timeliness, and cost. As a result, it's critical to understand the different sorts of delays that can arise in a project. Delays can occur for a varietyofcauses(or, in other words, have diverse origins); they can be compensated or not; and they can occur concurrently or afterwards. In addition, the impact on project performance can be direct or indirect. Their presence results in increased costs, conflicts among project partners, and, in the worst- case scenario, litigation, which may result in more costs. When dealing with delays, it's necessary to not only detect them and quantify their effects on project performance, but also to identify and quantify the implications of previous delays on future project progress. The key causes and sources of delays should also be identified in order to regulate accountability and allow for learning from these unfavorable events. 1.1 RERA Act 2016 The Real Estate (Regulation & Development) Act of 2016 proposes to create a Real Estate Regulatory Authority to govern and promote the real estate industry. The physical body will –  Ensure that land, buildings, or projects are sold in a timely and transparent manner.  Consumers' interests must be protected.  Create a method to ensure that conflicts are resolved quickly.  Createan AppellateTribunal to overseebothresidential and commercial construction projects. 2. Literature Review Shubhangi Salunkhe, R Mahadeva Swamy – In this paper, author explains carpet area term in detail and explains its impact on RERA. Also explains with the examples. For the analysis, author uses relative importance index method. For that they donequestionnairesurveyandcollectresponsesfor the analysis. They also make comparative analysis of RERA approach and traditional approach for one site in Pune for the time andcost analysis. Author conclude that, builders are not allowed fake commitment to buyer for possession date. Somdutta P. Patil, Prof. Ashish P. Waghmare – The author analyses the effect of RERA on the real estate business, including the impact on ongoing and new projects, as well as
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 100 the impact on builders, purchasers, and agents and brokers. Additionally, they examined the economicimpactofRERAon the real estate business. They spend the most of their time studying MahaRERA. They learn about the benefits and drawbacks of the RERA real estate legislation. Prompt possession of apartments, project clearance, and after-sales services are someof the benefits of RERA listedinthisarticle. Additionally, this report discusses historical challenges, project delays, and other negatives. Additionally, they said that this legislation is a step forward in terms of boosting openness in the real estate industry, increasing promoters' and developers' responsibility, and enabling efficient channels for grievance resolution. Akshaykumar P. Udasi, Milind M. Darade– This study is divided into two stages. To begin, a survey of the literature was conducted to ascertain the elements that contribute to building project delays.101sourcesofdelayswereidentified by a literaturestudyand dividedintoninedistinctcategories: owner-related,contractor-related,consultant-related,design- related, labor-related, material-related, equipment-related, and external factors- related,andRERA-related.Additionally, determine their various impacts/effects on the building project. Following that, a questionnaire survey is administered using Google forms. This Google form issent to numerous stakeholders in the building business by email, whatsApp, and text messaging. There are a total of ten replies. Graphs in paper illustrate the relationship between RERA characteristics and the number of respondents. Suhas G. Awari, Raju Narwade and Manisha Jamgade – The research is divided into two stages: a literature review and interviews. The first step entails doing a literature review. As a result of this evaluation, 51 delay factors appropriate for the current investigation were found. These causes were then classified into eight distinct categories based on their nature and mode of occurrence: project- related, client-related, contractor- related, RCC consultant- related, construction design-related, construction material- related, machinery-related, labor-related factors, and external factors. The second step is the creation of a questionnaire based ontherelativeimportanceindexandthe calculation of the Spearman rank correlation coefficient for the importance index. The questionnaire was split into three sections, which included reasonsofconstructiondelays,their effects, and ways forreducingconstructiondelays.Thisstudy to identify the effective methods to reduce delays in construction projects. Thorat Sourabh, Khandare Manish, A.K. Kanase – The empirical association between the causes and consequences of delay is also examined in this study utilizing Pearson's correlation coefficient in SPSS 23. Additionally,prescriptions for reducing delays were made in this research to clients, consultants, and contractors. The purpose of this study is to determine the causes and effects of delay in residential construction projects in India and to investigate the relationship between specificcausesandspecificeffects.This study employs an integrated approach to ascertain the impact of specific causes on specific effects in residential construction projects in the Indian context. There are a total of 41 causes classified into seven main categories, as well as seven significant impacts of delay. A questionnaire survey was used to elicit information on the causes and impacts of delay from clients, consultants, and contractors, with 67 respondents. The study's findings were satisfactory. This research will assist practitioners and scholars in better understanding project management and making attempts to eliminate delays in residential construction. Tibin Joy, B.Selvam - This article discussed the RERA act in depth. The author defines carpet area concept in detail. The author created identical questionnaires for builders and purchasers and conductedsurveystoascertainthereplies.As a result of this regulation, each project must be registered with RERA, which will serve as the regulatory authority. It will increase openness, as the client/allottedwillhaveaccess to further information about the project, promoter, promoter's historical experience, and agent, among other things. 3. Methodology 3.1 Objectives: 1. To study the present status & collect the information about chronological event from development of RERA to till date. 2. Identification of ongoing problems in construction industry & to analyses them. 3. To prepare questionnaire survey obtained through builders. 4. To carry out analysis of various responses obtained through live construction project in Kolhapur. 5. To recommend best suggestive measures for reducing costs and delay. 3.2 Research Methodology: 1) Collection of preliminary information through literature review. 2) Descriptive analysis by collection of data by questionnaire survey & interviews. 3) Assessing the current situation of construction industry pertaining RERA effects by questionnaire survey. 4) Defining problems in constructionindustrythrough survey conducted. 5) Giving suggestive measures for reducing problems through RERA. 6) Giving results & conclusions from data analyzed.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 101 Considered factors: The questionnaire designed by consideration of factors affecting the RERA act on constructionindustrythroughpre- existing literature and studied model. The following factors are considered in the design of the questionnaire. Sr.No. BUYER’S FACTORS SELLER’S FACTORS 1 Restrictions to diversion of money Restrictions to diversion of money 2 Property sold on carpet area Punctuality 3 Punctuality Security of money 4 Dispute resolution Quality of work 5 Penalties More profitable to buyer 6 More profitable to buyer Transparency 7 Transparency Quality is improved 8 Security of money Penalties on delay 9 Responsibility of defects Professionalism 10 Professionalism Dispute resolution 11 Quality of work Structural warranty 12 Use of ICT No misleading claims 13 Balanced agreement and treatment Use of ICT 14 No misleading claims Property sold on carpet area 15 Structural warranty Advertising only after RERA 16 Value of money Easy problem solution 17 Easy problem solution Value of money 18 Hike in property prices Value of money 19 Easy problem solution Authorization 20 Hike in property prices Real advertisement 21 Investment rate Responsibility of defects 22 Quality is improved Harsh penalties for seller 23 Penalties on delay Hike in property prices 24 Investment rates 25 Supply demand imbalance 2. Data Analysis by using Likert’s Scale Adopted scale is Five-point scale ranging from 1 (Strongly Not Effective) to 5 (Strongly Effective) and it is transformed to relative importance indices (RII) for each factor as follows; Where, N1 = number of respondents who voted for Strongly Not Effective N2= number of respondents who voted for Least Effective N3= number of respondents who voted for Neutral N4= number of respondents who voted for Effective N5= number of respondents who voted for Strongly Effective N is the weighting given to each factor by the respondents (ranging from 1 to 5). The RII value had a range from 1 to 5, the higher the value of RII, the more important was the factor affecting RERA. 2.3 Results: Table -1: Result for Buyer: RANK BUYER’S FACTORS RII% 1 Restrictions to diversion of money 82% 2 Property sold on carpet area 80% 2 Punctuality 80% 2 Dispute resolution 80% 3 Penalties 79% 4 More profitable to buyer 77% 5 Transparency 76% 6 Security of money 75% 6 Responsibility of defects 75% 7 Professionalism 72% 7 Quality of work 72% 8 Use of ICT 70% 9 Balanced agreement and treatment 69% 9 No misleading claims 69% 9 Structural warranty 69% 10 Value of money 68% 11 Easy problem solution 66% 12 Hike in property prices 65% 13 Investment rate 61% 14 Quality is improved 60% 14 Penalties on delay 60%
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 102 Table -2: Result for seller RANK SELLER’S FACTORS RII% 1 Restrictions to diversion of money 94% 2 Punctuality 90% 3 Security of money 88% 3 Quality of work 88% 3 More profitable to buyer 88% 4 Transparency 86% 5 Quality is improved 84% 5 Penalties on delay 84% 5 Professionalism 84% 5 Dispute resolution 84% 6 Structural warranty 78% 7 No misleading claims 76% 7 Use of ICT 76% 8 Property sold on carpet area 74% 8 Advertising only after RERA 74% 8 Easy problem solution 74% 9 Value of money 72% 9 Authorization 72% 10 Real advertisement 70% 10 Responsibility of defects 70% 11 Harsh penalties for seller 68% 12 Hike in property prices 64% 13 Investment rates 58% 13 Supply demand imbalance 58% 3. CONCLUSIONS A. Positive Impact 1. Sellers cannot make any false commitment regarding possession date. If it is not happened then seller should face the harsh penalties. 2. Sellers need to mention all the details which they are going to provide in the project accurately. 3. The sellers became more specific about the carpet area so that the buyers can get the idea about for what they are paying. 4. The land should be free from any type of litigation before the beginning of the project. The sellers should provide all clearance documents to the RERA. 5. For the transparency purpose and restriction for the money diversion, every project has to make separate bank account for transactions. 6. After selling the flat, thesellershouldprovidestructural warranty for 5 years span. B. Negative Impact: 1. Registration became mandatory only for projects which are more than 500 Sq m area. But it should be bound to every seller. 2. Old projects with some litigations are supposed to be delayed because of the rules of the RERA 3. For every quarterly period government approval became mandatory for project which may be delayed because of late work of government agencies. 4. Registration fees increased that's why project values are rising. REFERENCES [1] Aditya V Kadam, Rushikesh R Jangam, Rushikesh R Pawar, Ashwini A Sagavekar, Prof. G. D. Parulekar, Prof. S. S. Patil, ‘ Detailed Study and Analysis of RERA Act’, [2] www.irjet.net, Volume: 05 Issue: 04 Apr-2018. Akshaykumar P. Udasi, Milind M. Darade, ‘Delays in construction projects : causes, effects and impacts of RERA’, 2018 IJRTI | Volume 3, Issue 7. [3] Thorat, Manish Khandare, A.K.Kanase, ‘Exploratory Study Of Causes And Effects Of Delay In Indian Residential Projects’, Volume: 04 Issue: 06 | June -2017 [4] Dr. Ashish B. Joshi, Nisha Singh, ‘Real Estate Regulation Act (RERA), 2016: Implementation and Issues’, International Journal of Management Studies, Vol.–V, Issue –4(8), October 2018. [5] Meghwant Singh Thakur, ‘Effect of RERAonprofitability of Indian real estate developers’,International Journal of Management and Applied Science, ISSN: 2394- 7926 Volume-4, Issue-9, Sep.-2018. [6] Prof. S. G. Rodgi, ‘An Overview of „RERA‟ in India: A Regulatory Shift’, www.rrjournals.com, Volume 4, Issue 01, January 2019.
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 03 | Mar 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 103 [7] 7) S. Radhakrishnan, Dr. K. G. Selvan, ‘ImpactofRERAon Construction of Multi Storied Buildings’, International Research Journal of Advanced Engineering and Science, Volume 4, Issue 1. [8] Somdutta P. Patil, Prof. Ashish P. Waghmare, ‘ Impact of Real Estate Regulation and Development Act (RERA) on India’s Real Estate Sector’, 2017 IJSRST | Volume3Issue 8. [9] Suhas G. Awari, Raju Narwade and Manisha Jamgade, ‘Analysis for cause identification for delay in building construction industry’, International Journal of Modern Trends in Engineering and Research (IJMTER) Volume 03, Issue 10, October 2016. [10] Tibin Joy, B.Selvam, ‘Impact of Real estate regulation authority (RERA) on residential project’,IRJET,Volume: 05 Issue: 11 | Nov 2018.