SlideShare a Scribd company logo
1 of 7
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
Critical Success Factors and Strategiesfor Sub-contractorManagementin
Infrastructure Projects
Akhilesh Gandhi
Assistant Professor, Jaypee University of Information Technology
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - With complexities involved in construction
projects continuously on a rise, the role of subcontractors
has become crucial for the successful execution of these
projects. This paper tries to examine the current
subcontractor management system adopted by general
contractors. A case study approach was adopted for the
same and 3 projects basedupon contract value are selected.
In the second phase, through literature review and expert
opinions, critical factors affecting the performance of
subcontractors were identified and ranked based on their
relative importance. Lastly, interviews with experts
working as industry leaders were conducted to understand
the various strategies which can be adopted to improve the
performance of subcontractors in a project.
Key Words: Vendor Management, Supply Chain
Management, Construction Management, Sub-
contractor Management.
1. INTRODUCTION
Each construction project possesses a unique
characteristic in terms of engineering and construction.To
deal with the arising complexities of projects, general
contractors must either develop in-house expertise for
each construction activity or sub-let the work to a sub-
contractor. The option of sub- contracting generally
emerges to be more profitable and sustainable in the
market. While the general contractor is responsible for
the overall success or failure, sub-contractors are
deployed to perform specific tasks under the supervision
of the general contractor without any obligation to the
client. In countries like Hong Kong, United Kingdom
researchers have arrived at a consensus that sub-
contracting of activities in a project helps the general
contractors toreduce the cost and resources required [1].
However,sub-contracting, in certain cases has also proved
to be fatal in the success of a project. According to [2] ,
poor subcontractor performance is a major reason for
delaysand poor quality of work in construction projects.
In Malaysia and UAE, poor subcontracting is found to be
among the top five reasons contributing to project delays
[3]. With global spending in the construction sector
projected to reach $17.5 Trillion by 2030, it becomes
important for the general contractors to maximize the
performance of sub-contractors in a project. In order to
achieve the same general contractors, need to focus on
factors or uncertainties that might impact the
performance of a sub-contractor. Along this line, the
objective of this study is to:-
a. To understand the sub-contractor management
system adopted by general contractors in construction
projects.
b. Identify the critical factors affecting performance ofsub-
contractors in construction projects.
c. To statically analyse the identified factors and rankthe
factors based upon their impact on sub- contractor
performance.
d. To identify the strategies which can be adopted inthe
industry to counter the challenges encountered in
management of sub-contractors.
2. RESEARCH METHODOLOGY
A mixed research methodology was adopted to conduct the
study. The study was conducted in four phases. Firstly, a
literature review was conducted to identify the factor’s
affecting performance of sub-contractors in construction
projects. Inthe second phase, a qualitativeresearch technique
was adopted to understand the applicability of identified
factors. In this direction, five infrastructure projects were
shortlisted. The criteria for selection of projects are
mentioned below:-
1. The Project has major amount of work being
carried out by sub-contractor
Value of the project is greater than 500 Cr. In the third
phase of the study, interviews were conducted with the
relevant professionals from the projects. The objective of
these interviews was to understand the sub-contractor
management system adopted by the stakeholders and
applicability of the identified factors in context of Indian
construction industry. (Patton, 2002) suggested that
sample size in qualitative research should be determined
by the concept of saturation and can be limited to between
five to fifty interviews depending upon the interview
content. In the present study to avoid biased results from
the interviews representatives from the side of General
contractor, Sub-contractor and Client were interviewed.
Saturation was observed in the Tenth interview, further
one more interview was carried out.4 General contractors,
4 Subcontractors, and 3 clients were interviewed. The
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1728
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1729
selection was made based on position in the
organization and experience of the individual in project
management. The interviews werecarried out personally
and the duration of each interview varied from 45
minutes to 1 hour.
Further to quantitatively assess the identified factors, a
questionnaire approach was adopted. The questionnaire
designedforthisstudyhad2sections.1st section included
questions related to demographic information of the
respondent. The 2nd section of the questionnaire
included questions related to identifiedfactors affecting
performance of subcontractors in a project. The experts
were asked to rate the impact of a factor on the
performance of sub-contractor on a scaleof 1-5. The scale
was defined as follows:
Table-1: Definition of rating scale adopted in the
study
In total 150 questionnaires were floated, and 88
responses were received from industry professionals.
Demographic information about respondents is
summarized below: -
Figure-1: Demographic information about
respondents
The data collected was analyzed in MS Excel and Python.
The RII (Relative Importance index) method was used to
rank the factors affecting the subcontractor’s
performance. The relationship for computing RII is
depicted below:-
∑W/(A*N)
∑W = The weighting given to each factor by the
respondent.
A= The highest weight N= Sample Number
Rating Meaning
1: Very Low The given factor has a negligible impact
on performance of the sub- contractor in
the project.
2: Low The given factor has a slightly
significant impact on performanceof the
sub-contractor in the project.
3: Moderate The given factor has a significant
impact on performance of the sub-
contractor in the project.
4: High The given factor has a remarkable
impact on performance of the sub-
contractor in the project.
5: Very High Thegiven factorhasaconsequential
impact on performance of the sub-
contractor in the project.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1730
To check the internal consistency of the data, the
Cronbach Alpha test was conducted. Alpha = 0.85 was
obtained. The relation between Coefficient of Cronbach
alpha and Reliability level of data is summarized below:
Table-2: Relation between Cronbach Alpha and
Reliability Levelofthe data
Coefficient of Cronbach
Alpha
Reliability Level
More than .90 Excellent
0.80- 0.89 Good
0.70- 0.79 Acceptable
0.60- 0.69 Questionable
0.50- 0.59 Poor
Less than 0.49 Unacceptable
Further, to understand the variation betweenresponses
received from Sub-Contractors and Main- Contractors,
two variance test was conducted. The hypothesis
assumed for Two variance tests arementioned below: -
Null Hypothesis: General contractor and Sub-
Contractor had same notion for a given factor.
Alternate Hypothesis: General contractor and Sub-
Contractor had a different notion for a given factor.
For all the factors shortlisted in the study, the f value
obtained in two variance tests was within permissible
limits to accept the null hypothesis with a 95%
confidence interval. In the last phase of the study,
structured interviews were conducted with
professionals from leading construction firms to identify
the strategies that can be adopted to nullify these
challenges.
2. LITERATURE REVIEW
to
achieve the same include open communication, top
management commitment, and proportionate risk
distribution. Further,[9] identified conflicts between
When a general contractor is awarded a project, the
first step is to decide the packages in the project which
must be outsourced. So as to support general
contractors in their selection of packages, [6] devised a
decision support system to identify the works that must
be subcontracted based upon the given constraints
(Maximum units of work that can be assigned to a sub-
contractor). Attempting to understand the existing
subcontractor management processes adopted by
general contractors to manage subcontractors working
is a project, [7] conducted a study, ultimately identifying
strategies for mitigating the issues encountered in sub-
contractors. Addressing the issue of
non-compliancetocontractual clauses by Subcontractors in
the United Kingdom [12] conducted thematic interviews
withsub-
Based on the literature review conducted, the factors
identified in the study are listed below:-
that competitive advantage in the market is a
major factor that promotes establishment of long terms
relations between the general contractor and
subcontractor. The key strategies that can be adopted
individual personalities as a major challenge for efficient
sub-contractor management in construction industry.
Extending the research on this line [10] developed a model
based upon social exchange theory,examining the relation
between justice perception of a subcontractor in previous
works with a particular general contractor and their
willingness to corporate in present job. [11] identified that
lack of integrity respectand fairness, and unwillingness to
negotiate the risk and price as the major factors for
prevalence of poor relationship between general
contractors and general
contractors. The findings of these interviews led to
the conclusion that subcontractors generally have limited
knowledge about the contractual clauses they are entering
into. Thus, in addition to understanding the pricing of
contract, the top management of subcontractors must also
focus upon the contractual clauses.
contractor management. The study concluded that
relevant pre-qualification criteria, warning systems for
sub-contractor performance can be viable solutions for
Factor Source
Sub-Contractor Selection
process
(Li, Weifang, 2018);
(Ashraf M. Elazouni and Fikry
G.Metwally, 2000)
Sub-Contractor Bid Price (Li, Weifang, 2018)
Distribution of Risk Between
General contractor and Sub-
Contractor
(Loosemore Martina, Lim
Benson, 2021); (Assbeihat
J.M, 2019)
Cash Flow Management of
Sub-
Contractor
(Loosemore Martina, Lim
Benson, 2021); (Jianga,
2014)
Impact of Regular
Performance Monitoring of
Sub-Contractor
(Temitope Seun Omotayo
et.al
,2022), (Arditi, 2005)
The ambiguous contractual
agreement between Sub-
contractor and General
contractor
(Temitope Seun Omotayo et.
al
,2022) ; (LIM, Patrick X.W.
ZOU ,
Benson T.H., 2014)
Table-3: Factors Identified from Literature Review
the same. [8] conducted research to understand the
perception of general contractors towards development
of long-termrelations with Sub-contractors. The research
concluded
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1731
3. Case Study
A detailed review of sub-contract documents and
interviews with multiple stakeholders involved in the
projects selected for case studies were conducted to
understand how sub-contractors are managed in a project.
The same has been summarized below in a phase-wise
manner.
issued.
to
track the progress of the work.
Pre-Award Phase : Detailed discussions are carried out
within various stakeholders of the general contractor to
understand the major benefits and consequences of
subletting a particular package and not doing the works
inhouse. In coordination with the project team a detailed
scope matrix, resource requirement and a pre-
qualification criterion for the works is prepared. Further
market research is carried out to identify the major
sub-contractors carrying the similar works.
most importantly the final price received,
work is awarded to the suitable sub-contractor and LOI is
Award phase: The identified sub-contractors are asked to
share their company profile, turnover information, and
relevant information for pre- qualification criteria
evaluation. Detailed drawings, BOQ, designs and site
related details are shared with sub-contractors. Multiple
rounds of negotiations and technical evaluation offers
received from sub- contractors in carried out. Based
upon the score in prequalification criteria, methodology of
the work and
Execution phase: In this phase, kick off meeting is
conducted between the site team of general contractor
and sub-contractor to ascertain the work plan and
mobilization schedule for the work. Bills for the works
certified by the general contractor are booked and
submitted to the clients for further certification and
invoicing. Regular review meetings between the top
management of both the stakeholders are carried out
Closure phase: In this phase, final certification of the
sub-contractor’s work is done, the sub-contractor is
issued completion certificate, maintenance of the
finished services as per the contract document is carried
out by the sub-contractor. All the retentions and other
withheld amounts are released as per the agreed
schedule.
was calculated to understand the relative importanceof the
factors.
4. RESULTS
5.1 Relative Importance Index Test:-
As per the responses received to the questionnaire, RII
Factor Rank RII Mean
Sub-contractor bid
price.
1 0.7106 3.55
Impact of regular
performance
monitoring of Sub-
contractor.
2 0.6988 3.49
Sub-contractor selection
process.
2 0.6988 3.49
Distribution of risk
between General
contractor and Sub-
contractor.
3 0.6541 3.27
Cash Flow management of
Sub-contractor.
4 0.6424 3.21
The ambiguous contractual
agreement between Sub-
contractor and General
contractor.
5 0.6400 3.20
Table-4: Result for RII value
5.2Two Variance Test
In addition to RII value, to understand the variance
between notions of subcontractor’s and general contractor
about a particular factor, two variance testwas conducted.
The results of the same are tabulated below:-
Factor Calculated
F Value F(5%) F(95%)
Sub-Contractor Bid Price 0.84 1.81 0.54
Impact of Regular
Performance Monitoring of
Sub-Contractor
1.39 1.81 0.54
Sub-Contractor Selection
process
1.09 1.81 0.54
Distribution of Risk
Between General
contractor and Sub-
Contractor
0.93 1.81 0.54
Cash Flow Management of
Sub-Contractor
0.87 1.81 0.54
Clarity of contractual
agreement between Sub-
contractor and General
contractor
0.89 1.81 0.54
Table-5: Result for Two Variance Test
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1732
F value corresponding to 5% and 95% were taken fromthe
relevant chart. The F value for the given factor was
calculated by the formula:-
Variance of Sub-Contractor Responses / Variance Main
Contactor Responses
From the above table, as the f value lies between the
permissible interval of 95% confidence limit, it can be
inferred that Main-Contractors and Sub-Contractors have
a similar notion for every factor identified.
5. DISCUSSIONS
1. Sub-Contractor Bid Price
2. Regular performance monitoring of Sub-
Contractor
A subcontractor’s ability to execute the work within the
stipulated time and desired level of quality depends
upon the price at which the firm acquires the job.
Sometimes with an expectationof
the
quality of work, ruining the reputation of all the
stakeholders involved. In line with the above facts,
Sub-contractor bid price had an RII value of 0.7106 and
was ranked as the most important factor
affecting the performance of the sub-contractor.
In large-scale construction projects, performance
monitoring of sub-contractors working at a
construction site is a challenging task and often a
source of conflict between both parties. (Amin
Mahmoudi, 2022) With an RII of 0.6988, regular
performance monitoring emerged as the second most
important factor in this study. In order to effectively
deal with this issue, various researchers and industry
professionals have stressed using
drones for capturing real-time information from the
project site. Further to ensure that desired level of
progress, regular meetings between stakeholders
involved are a viable solution.
3. Sub-contractor selection process
A rigorous sub-contractor selection process can
prove to be successful in mitigating the risk
associated with execution of the work. As per the
the
financial and technical capabilities of a sub-
contractor, general contractors generally conducted a
rigorous review of submitted documents and
performance in similar works. However, in the case of
routine works in a project
4. Distribution of risk between Sub-
Contractor and General contractor: -
exchange of services.
profits from
following contracts, sub-contractor might underbid for a
given contract and fail to execute it. In order to avoid
such peculiar situations, general contractors must set a
threshold price and not award the project
below the same. Further, the general contractors
should restrain from resorting to unethical practices like
bid shopping during finalization of the contract.
Although in the initial stage, it might improve the
profit margins in the project, in long runitwill hurt
like mix transportation,
aggregate production etc, general contractors were more
reliant on local contractors due to which pre-qualification
criteria were often sacrificed. In such cases bid price was
the main criterion for awarding the subcontract.
The distribution of risk and obligations between the
general contractor and sub-contractor generally
depends upon the contracting strategy adopted in the
project. Scoring 0.6511 on RII scale, this factor was
ranked as the fourth most important in the study.
Previous studies revealed that contract clauses were
designed to take advantage of the sub-contractor by
shifting the risk into their scope. A review of various
sub-contract documents validated the above fact. In
most of thecontract agreements, the local and financial
risks were in the scope of the sub-contractor, without a
proper mechanism for mitigation. Further, the
various clauses like the scope of work, payment
schedule, etc., were ambiguous and lacked clarity.
Although during the execution phase of the project, all the
stakeholders jointly resolved issues encountered, such
arrangements were spontaneous and unplanned,
resembling to
5. Cash Flow Management: -
As the cost of capital increases in the market, cashflow
management is one of the major issues being faced by the
stakeholders involved in construction projects. The clients
have now shifted from monthly billing mode of payment to
milestone- based payment in a project. Though this has
motivated the general contractors to execute the works on
a fast-track basis, on the other side it has created a
significant cash lag. The general contractor generally
adopts pay when paid and pay if paid strategies for
billing of sub-contractor. This
creates a peculiar situation for sub-contractors with
30-40% of their equity stuck up in a project. In the
projects selected for study, numerous cases were
observed where the sub-contractor didn’t receive
payment as per the agreed schedule. The interviews with
various sub-contractors revealed that the
payment cycle for an executed work spans between 45- 60
days. In some cases, the performance bonds of sub-
contractors were also not released after the
completion of the works.
responses received, the Sub-Contractor selection
process had an RII score of 0.7106. Further
, discussions with industry professionals revealed that
general contractors had a stringent pre-
qualification criterion for selecting subcontractors,
especially for specialized works. In order to assess
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
6. Ambiguous contractual agreement
between Sub-contractor and General
contractor
7. STRATEGIES TO BE INCORPORATED IN
TRADITIONAL SUB-CONTRACTOR
MANAGEMENT FRAMEWORK:-
In order to identify strategies for factors identified in the
study, interviews with industry leaders and consultants
were conducted. These led to the identification of
following strategies for improving sub- contractors’
performance in the life cycle of a project.
1. Region-wise vendor redeployment, vendor
consolidation: -
The strategy of region-wise vendor redeployment and
vendor consolidation has been successfully adopted by
general contractors in the procurement of raw materials.
Vendor consolidation refers to aprocess in which all the
vendors offering aparticular material/ equipment in the
given region are shortlisted. Vendor Redeployment
refers to deploying the same vendor for the supply of a
particular material/service at multiple sites. The general
contractors should shortlist some good- performing sub-
contractors based upon a set of pre-qualification criteria.
Once the Sub-contractor has satisfied the Pre-
qualification criteria, when a requirement for service is
identified, the general contractor shall directly approach
these sub- contractors for the services instead of
searching the market again. The review of case studies
revealed a high rate of vendor redeployment in case of
purchase items but in the case of sub- contracting, the
rate of vendor redeployment was very low. Discussion
with the experts from the general contractor side
revealedthatredeployinga
A review of various sub-contract documents revealed
that contractual agreements between general
contractors and sub-contractors generally lack clarity in
terms of the scope of work and obligations of both the
parties. With an RII value of 0.6541, this factor
emerged as the fourth most important factor affecting
the performance of sub- contractors. Experts involved in
the study stressed the fact that ambiguity of contractual
clauses often leads to disputes among the stakeholders,
ultimately delaying the progress of the project. To address
this issue, various experts agreed that standard contract
documents must be established by the general
contractors with the contract document containing two
parts, one including the general conditions and part
two including the special site-specific conditions of the
work. Further, with the complexity of projects on a rise,
various researchers in past have suggested that clauses
related to amendment of orders and management of
claims in a project must be formulated in consultation
with legal experts in a project.
particular sub-contractor for similar work at another
project is attributed to his, willingness andcapacity to
execute the work.
2. Negotiation of Payment terms: -
During the finalization of contract, both the parties must
understand the short-term and long terms implication of
delayed payments on the project. To minimize the
payment risk, the sub-contractors and general contractors
must ensure that the paymentterms agreed in the contract
are adhered to strictly. In order to lure the general
contractors for timely release of payments, dynamic
discounts on net payable must be included in the payment
terms. The prices of the contracts must be negotiated
based on concepts such as Day sales outstanding. If the day
sales outstanding ishigher than initially agreed by both the
parties, the total value of the contract must also increase
proportionately and vice versa must also be applicable.Also,
in order to improve the cash position in contracts various
options like mobilization payment, and lower retained
percentages can be beneficial in improving project finances
andmaximizing the finalcashbalance.
3. Inclusion of performance-based incentives in
the contracts: -
Most of the experts agreed that to motivate the sub-
contractors, performance-based incentiveclauses must be
introduced in the contract documents. These incentives
can be in form of monetary incentives like Cost plus
incentive fees, share-in-savings- incentive, and non-
monetary such as an automatic extension of contracts in
caseof services. The strategy of monetary incentives was
utilized in one project selected as a case studyand yielded
successful results. The sub-contractorcompleted the given
scope of work one week ahead of the scheduled date of
completion. To utilize sucharrangements effectively more
research needs to be carried out in terms of understanding
the type of incentive to be used and the extent to which
these incentives must be passed on along the supply chain.
8. CONCLUSION
The main objective of the study was to understand the
traditional sub-contractor management strategy which is
currently being adoptedforexecutionof projects andvarious
challenges encountered. It can be concluded that there is a
wide spread of sub-contracting in construction industry.
But the sub-contractor management strategies being
utilized by various stakeholders are not being able to
deliver the expected result. The sub-contractor selection
process in notregulated through any statutory body. Lack
of standardization in contractual terms and conditions has
led to exploitation of sub-contractors in various cases. The
pace at which sub-contractors execute the works has not
been able to match the requirements ofclients and general
contractors. Cash flow managementhas also emerged as one
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1733
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072
the critical issue in traditional sub-contractor
management setup. To overcome all these issues various
strategies which must be integrated with traditional
sub-contractor management framework were identified
anddiscussedin detail with experts.Theutilizationofthese
strategies can prove to be effective in improving the
overall relationship between the stakeholders and
enhancingthe performance of subcontractors.
REFERENCES
1. Arditi, 2005. Issues in sub-contracting practice.
Journal of construction engineering and
management
2. Choudhry1, R. M., Jimmie W. Hinze, M., Arshad3, M.
& Gabriel4, a. H. F., 2012. Sub- contracting
parctices in construction industry of pakistan.
Journal of Construction Engineering and
Management.
3. Abisugab,2016. “Effect of path-goal leadership
styles on the commitment of employees on
construction projects”. International Journal of
Construction Management.
4. El-Kholy, A. M., 2019. A new technique for
subcontractor selection by adopting choosing by
advantages. International Journal of Construction
Management
5. Hailu, H. A., 2017. Determinants of Subcontracting
Performance in road Construction projects..
International Journal ofScientific Engineering and
Research (IJSER).
6. Ashraf M. Elazouni and Fikry G. Metwally. (2000).
Decision Support System for Subcontracting
Construction Works. Journal of Construction
Engineering and Management
, 191-200.
7. Li, Weifang. (2018). The Study on Sub- contract
Management in EPC Engineering.
10. Liu, Jun Ying, Yang, Pengfei, Xia, Bo, Skitmore,Martin .
(2017). Effect of perceived justice on subcontractor
willingness to cooperate: The mediating role of
relationship value. ASCE.
11. Loosemore Martina, Lim Benson. (2021). Relationship
quality in construction projects: A subcontractor
perspective of principle contractor relationship.
International Journalof Project Management.
12. Temitope Seun Omotayo, Oskar Danvers- Watson,
Adekunle Sabitu Oyegoke . (2022). Subcontractor
trust issues on payment and valuation practices in UK
private projects. Journal of Financial Management of
Propertyand Construction.
13. Marshamll, 2000. Partnering in construction: a critical
review of issues, problems and dilemmas,”.
Construction Management andEconomics.
14. Assbeihat, J. M., 2019. Reasons behind Sub- contractor
faiulre in construction projects.. International Journal
of Civil Engineering and Technology (IJCIET).
15. Creed S. J. Eom, P., Seok H. Yun, P. & and Joon H.Paek, P.,
2008. Subcontractor Evaluation and Management
Framework for Strategic Partnering. Journal of
ConstructionEngineeringand Management
16. Dimitrios Robert I Stamatiou, K. A. K. S. T. P. S.
G. &. I. T., 2019. A process reference model forclaims
management in construction supply chains: the
contractors’ perspective. International Journal of
ConstructionManagement.
17. Jammal.M, 2018. Reasons behind sub- contractor
default in construction projects..International journal
of civil engineering and management.
18. Jianga, 2014. Negotiating Construction Contracts
through Practical Cash Flow Planning and Analysis
Model. International Journal of Construction
Management.
19. Will hughes, Incentives in constrution contracts.. CIB
world congress 2007.
8. LIM, P. X. Z. a. B. T., 2014. An Emperical StudyIn
Subcontracotr Selection and Long -TermAlliance
Relationship Between Main - Contractor And
Subcontractor. International Journal of
Construction Management.
9. H. Randolph Thomas, Flynn, Christopher J.
(2011). Fundamentals of Sub Contractor
management. ASCE.
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1734

More Related Content

Similar to Critical Success Factors and Strategies for Sub-contractor Management in Infrastructure Projects

IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...IRJET Journal
 
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...IRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...IJSRED
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...IRJET Journal
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET Journal
 
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...
IRJET- Influence of Stakeholder Management on the Success Construction Pr...IRJET Journal
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction ProjectsIRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...IRJET Journal
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET Journal
 
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”IRJET Journal
 
IRJET- Influence of Stakeholders on Project Time Overrun
IRJET- Influence of Stakeholders on Project Time OverrunIRJET- Influence of Stakeholders on Project Time Overrun
IRJET- Influence of Stakeholders on Project Time OverrunIRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 

Similar to Critical Success Factors and Strategies for Sub-contractor Management in Infrastructure Projects (20)

IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
Analysis of Cost Variation between Estimated Cost and Actual Cost of Resident...
 
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...IRJET-  	  Identification of Critical Factors Affecting Infrastructure Projec...
IRJET- Identification of Critical Factors Affecting Infrastructure Projec...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
Construction Site Monitoring and Predictive Analysis Using Artificial Neural ...
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
A COMPARATIVE STUDY ON PPP AND BOT MODEL OF WORKING CAPITAL MANAGEMENT IN MET...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction Projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction Projects
 
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”
“RISK MANAGEMENT IN CONSTRUCTION INDUSTRY”
 
IRJET- Influence of Stakeholders on Project Time Overrun
IRJET- Influence of Stakeholders on Project Time OverrunIRJET- Influence of Stakeholders on Project Time Overrun
IRJET- Influence of Stakeholders on Project Time Overrun
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 

Critical Success Factors and Strategies for Sub-contractor Management in Infrastructure Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 Critical Success Factors and Strategiesfor Sub-contractorManagementin Infrastructure Projects Akhilesh Gandhi Assistant Professor, Jaypee University of Information Technology ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - With complexities involved in construction projects continuously on a rise, the role of subcontractors has become crucial for the successful execution of these projects. This paper tries to examine the current subcontractor management system adopted by general contractors. A case study approach was adopted for the same and 3 projects basedupon contract value are selected. In the second phase, through literature review and expert opinions, critical factors affecting the performance of subcontractors were identified and ranked based on their relative importance. Lastly, interviews with experts working as industry leaders were conducted to understand the various strategies which can be adopted to improve the performance of subcontractors in a project. Key Words: Vendor Management, Supply Chain Management, Construction Management, Sub- contractor Management. 1. INTRODUCTION Each construction project possesses a unique characteristic in terms of engineering and construction.To deal with the arising complexities of projects, general contractors must either develop in-house expertise for each construction activity or sub-let the work to a sub- contractor. The option of sub- contracting generally emerges to be more profitable and sustainable in the market. While the general contractor is responsible for the overall success or failure, sub-contractors are deployed to perform specific tasks under the supervision of the general contractor without any obligation to the client. In countries like Hong Kong, United Kingdom researchers have arrived at a consensus that sub- contracting of activities in a project helps the general contractors toreduce the cost and resources required [1]. However,sub-contracting, in certain cases has also proved to be fatal in the success of a project. According to [2] , poor subcontractor performance is a major reason for delaysand poor quality of work in construction projects. In Malaysia and UAE, poor subcontracting is found to be among the top five reasons contributing to project delays [3]. With global spending in the construction sector projected to reach $17.5 Trillion by 2030, it becomes important for the general contractors to maximize the performance of sub-contractors in a project. In order to achieve the same general contractors, need to focus on factors or uncertainties that might impact the performance of a sub-contractor. Along this line, the objective of this study is to:- a. To understand the sub-contractor management system adopted by general contractors in construction projects. b. Identify the critical factors affecting performance ofsub- contractors in construction projects. c. To statically analyse the identified factors and rankthe factors based upon their impact on sub- contractor performance. d. To identify the strategies which can be adopted inthe industry to counter the challenges encountered in management of sub-contractors. 2. RESEARCH METHODOLOGY A mixed research methodology was adopted to conduct the study. The study was conducted in four phases. Firstly, a literature review was conducted to identify the factor’s affecting performance of sub-contractors in construction projects. Inthe second phase, a qualitativeresearch technique was adopted to understand the applicability of identified factors. In this direction, five infrastructure projects were shortlisted. The criteria for selection of projects are mentioned below:- 1. The Project has major amount of work being carried out by sub-contractor Value of the project is greater than 500 Cr. In the third phase of the study, interviews were conducted with the relevant professionals from the projects. The objective of these interviews was to understand the sub-contractor management system adopted by the stakeholders and applicability of the identified factors in context of Indian construction industry. (Patton, 2002) suggested that sample size in qualitative research should be determined by the concept of saturation and can be limited to between five to fifty interviews depending upon the interview content. In the present study to avoid biased results from the interviews representatives from the side of General contractor, Sub-contractor and Client were interviewed. Saturation was observed in the Tenth interview, further one more interview was carried out.4 General contractors, 4 Subcontractors, and 3 clients were interviewed. The © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1728
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1729 selection was made based on position in the organization and experience of the individual in project management. The interviews werecarried out personally and the duration of each interview varied from 45 minutes to 1 hour. Further to quantitatively assess the identified factors, a questionnaire approach was adopted. The questionnaire designedforthisstudyhad2sections.1st section included questions related to demographic information of the respondent. The 2nd section of the questionnaire included questions related to identifiedfactors affecting performance of subcontractors in a project. The experts were asked to rate the impact of a factor on the performance of sub-contractor on a scaleof 1-5. The scale was defined as follows: Table-1: Definition of rating scale adopted in the study In total 150 questionnaires were floated, and 88 responses were received from industry professionals. Demographic information about respondents is summarized below: - Figure-1: Demographic information about respondents The data collected was analyzed in MS Excel and Python. The RII (Relative Importance index) method was used to rank the factors affecting the subcontractor’s performance. The relationship for computing RII is depicted below:- ∑W/(A*N) ∑W = The weighting given to each factor by the respondent. A= The highest weight N= Sample Number Rating Meaning 1: Very Low The given factor has a negligible impact on performance of the sub- contractor in the project. 2: Low The given factor has a slightly significant impact on performanceof the sub-contractor in the project. 3: Moderate The given factor has a significant impact on performance of the sub- contractor in the project. 4: High The given factor has a remarkable impact on performance of the sub- contractor in the project. 5: Very High Thegiven factorhasaconsequential impact on performance of the sub- contractor in the project.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1730 To check the internal consistency of the data, the Cronbach Alpha test was conducted. Alpha = 0.85 was obtained. The relation between Coefficient of Cronbach alpha and Reliability level of data is summarized below: Table-2: Relation between Cronbach Alpha and Reliability Levelofthe data Coefficient of Cronbach Alpha Reliability Level More than .90 Excellent 0.80- 0.89 Good 0.70- 0.79 Acceptable 0.60- 0.69 Questionable 0.50- 0.59 Poor Less than 0.49 Unacceptable Further, to understand the variation betweenresponses received from Sub-Contractors and Main- Contractors, two variance test was conducted. The hypothesis assumed for Two variance tests arementioned below: - Null Hypothesis: General contractor and Sub- Contractor had same notion for a given factor. Alternate Hypothesis: General contractor and Sub- Contractor had a different notion for a given factor. For all the factors shortlisted in the study, the f value obtained in two variance tests was within permissible limits to accept the null hypothesis with a 95% confidence interval. In the last phase of the study, structured interviews were conducted with professionals from leading construction firms to identify the strategies that can be adopted to nullify these challenges. 2. LITERATURE REVIEW to achieve the same include open communication, top management commitment, and proportionate risk distribution. Further,[9] identified conflicts between When a general contractor is awarded a project, the first step is to decide the packages in the project which must be outsourced. So as to support general contractors in their selection of packages, [6] devised a decision support system to identify the works that must be subcontracted based upon the given constraints (Maximum units of work that can be assigned to a sub- contractor). Attempting to understand the existing subcontractor management processes adopted by general contractors to manage subcontractors working is a project, [7] conducted a study, ultimately identifying strategies for mitigating the issues encountered in sub- contractors. Addressing the issue of non-compliancetocontractual clauses by Subcontractors in the United Kingdom [12] conducted thematic interviews withsub- Based on the literature review conducted, the factors identified in the study are listed below:- that competitive advantage in the market is a major factor that promotes establishment of long terms relations between the general contractor and subcontractor. The key strategies that can be adopted individual personalities as a major challenge for efficient sub-contractor management in construction industry. Extending the research on this line [10] developed a model based upon social exchange theory,examining the relation between justice perception of a subcontractor in previous works with a particular general contractor and their willingness to corporate in present job. [11] identified that lack of integrity respectand fairness, and unwillingness to negotiate the risk and price as the major factors for prevalence of poor relationship between general contractors and general contractors. The findings of these interviews led to the conclusion that subcontractors generally have limited knowledge about the contractual clauses they are entering into. Thus, in addition to understanding the pricing of contract, the top management of subcontractors must also focus upon the contractual clauses. contractor management. The study concluded that relevant pre-qualification criteria, warning systems for sub-contractor performance can be viable solutions for Factor Source Sub-Contractor Selection process (Li, Weifang, 2018); (Ashraf M. Elazouni and Fikry G.Metwally, 2000) Sub-Contractor Bid Price (Li, Weifang, 2018) Distribution of Risk Between General contractor and Sub- Contractor (Loosemore Martina, Lim Benson, 2021); (Assbeihat J.M, 2019) Cash Flow Management of Sub- Contractor (Loosemore Martina, Lim Benson, 2021); (Jianga, 2014) Impact of Regular Performance Monitoring of Sub-Contractor (Temitope Seun Omotayo et.al ,2022), (Arditi, 2005) The ambiguous contractual agreement between Sub- contractor and General contractor (Temitope Seun Omotayo et. al ,2022) ; (LIM, Patrick X.W. ZOU , Benson T.H., 2014) Table-3: Factors Identified from Literature Review the same. [8] conducted research to understand the perception of general contractors towards development of long-termrelations with Sub-contractors. The research concluded
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1731 3. Case Study A detailed review of sub-contract documents and interviews with multiple stakeholders involved in the projects selected for case studies were conducted to understand how sub-contractors are managed in a project. The same has been summarized below in a phase-wise manner. issued. to track the progress of the work. Pre-Award Phase : Detailed discussions are carried out within various stakeholders of the general contractor to understand the major benefits and consequences of subletting a particular package and not doing the works inhouse. In coordination with the project team a detailed scope matrix, resource requirement and a pre- qualification criterion for the works is prepared. Further market research is carried out to identify the major sub-contractors carrying the similar works. most importantly the final price received, work is awarded to the suitable sub-contractor and LOI is Award phase: The identified sub-contractors are asked to share their company profile, turnover information, and relevant information for pre- qualification criteria evaluation. Detailed drawings, BOQ, designs and site related details are shared with sub-contractors. Multiple rounds of negotiations and technical evaluation offers received from sub- contractors in carried out. Based upon the score in prequalification criteria, methodology of the work and Execution phase: In this phase, kick off meeting is conducted between the site team of general contractor and sub-contractor to ascertain the work plan and mobilization schedule for the work. Bills for the works certified by the general contractor are booked and submitted to the clients for further certification and invoicing. Regular review meetings between the top management of both the stakeholders are carried out Closure phase: In this phase, final certification of the sub-contractor’s work is done, the sub-contractor is issued completion certificate, maintenance of the finished services as per the contract document is carried out by the sub-contractor. All the retentions and other withheld amounts are released as per the agreed schedule. was calculated to understand the relative importanceof the factors. 4. RESULTS 5.1 Relative Importance Index Test:- As per the responses received to the questionnaire, RII Factor Rank RII Mean Sub-contractor bid price. 1 0.7106 3.55 Impact of regular performance monitoring of Sub- contractor. 2 0.6988 3.49 Sub-contractor selection process. 2 0.6988 3.49 Distribution of risk between General contractor and Sub- contractor. 3 0.6541 3.27 Cash Flow management of Sub-contractor. 4 0.6424 3.21 The ambiguous contractual agreement between Sub- contractor and General contractor. 5 0.6400 3.20 Table-4: Result for RII value 5.2Two Variance Test In addition to RII value, to understand the variance between notions of subcontractor’s and general contractor about a particular factor, two variance testwas conducted. The results of the same are tabulated below:- Factor Calculated F Value F(5%) F(95%) Sub-Contractor Bid Price 0.84 1.81 0.54 Impact of Regular Performance Monitoring of Sub-Contractor 1.39 1.81 0.54 Sub-Contractor Selection process 1.09 1.81 0.54 Distribution of Risk Between General contractor and Sub- Contractor 0.93 1.81 0.54 Cash Flow Management of Sub-Contractor 0.87 1.81 0.54 Clarity of contractual agreement between Sub- contractor and General contractor 0.89 1.81 0.54 Table-5: Result for Two Variance Test
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1732 F value corresponding to 5% and 95% were taken fromthe relevant chart. The F value for the given factor was calculated by the formula:- Variance of Sub-Contractor Responses / Variance Main Contactor Responses From the above table, as the f value lies between the permissible interval of 95% confidence limit, it can be inferred that Main-Contractors and Sub-Contractors have a similar notion for every factor identified. 5. DISCUSSIONS 1. Sub-Contractor Bid Price 2. Regular performance monitoring of Sub- Contractor A subcontractor’s ability to execute the work within the stipulated time and desired level of quality depends upon the price at which the firm acquires the job. Sometimes with an expectationof the quality of work, ruining the reputation of all the stakeholders involved. In line with the above facts, Sub-contractor bid price had an RII value of 0.7106 and was ranked as the most important factor affecting the performance of the sub-contractor. In large-scale construction projects, performance monitoring of sub-contractors working at a construction site is a challenging task and often a source of conflict between both parties. (Amin Mahmoudi, 2022) With an RII of 0.6988, regular performance monitoring emerged as the second most important factor in this study. In order to effectively deal with this issue, various researchers and industry professionals have stressed using drones for capturing real-time information from the project site. Further to ensure that desired level of progress, regular meetings between stakeholders involved are a viable solution. 3. Sub-contractor selection process A rigorous sub-contractor selection process can prove to be successful in mitigating the risk associated with execution of the work. As per the the financial and technical capabilities of a sub- contractor, general contractors generally conducted a rigorous review of submitted documents and performance in similar works. However, in the case of routine works in a project 4. Distribution of risk between Sub- Contractor and General contractor: - exchange of services. profits from following contracts, sub-contractor might underbid for a given contract and fail to execute it. In order to avoid such peculiar situations, general contractors must set a threshold price and not award the project below the same. Further, the general contractors should restrain from resorting to unethical practices like bid shopping during finalization of the contract. Although in the initial stage, it might improve the profit margins in the project, in long runitwill hurt like mix transportation, aggregate production etc, general contractors were more reliant on local contractors due to which pre-qualification criteria were often sacrificed. In such cases bid price was the main criterion for awarding the subcontract. The distribution of risk and obligations between the general contractor and sub-contractor generally depends upon the contracting strategy adopted in the project. Scoring 0.6511 on RII scale, this factor was ranked as the fourth most important in the study. Previous studies revealed that contract clauses were designed to take advantage of the sub-contractor by shifting the risk into their scope. A review of various sub-contract documents validated the above fact. In most of thecontract agreements, the local and financial risks were in the scope of the sub-contractor, without a proper mechanism for mitigation. Further, the various clauses like the scope of work, payment schedule, etc., were ambiguous and lacked clarity. Although during the execution phase of the project, all the stakeholders jointly resolved issues encountered, such arrangements were spontaneous and unplanned, resembling to 5. Cash Flow Management: - As the cost of capital increases in the market, cashflow management is one of the major issues being faced by the stakeholders involved in construction projects. The clients have now shifted from monthly billing mode of payment to milestone- based payment in a project. Though this has motivated the general contractors to execute the works on a fast-track basis, on the other side it has created a significant cash lag. The general contractor generally adopts pay when paid and pay if paid strategies for billing of sub-contractor. This creates a peculiar situation for sub-contractors with 30-40% of their equity stuck up in a project. In the projects selected for study, numerous cases were observed where the sub-contractor didn’t receive payment as per the agreed schedule. The interviews with various sub-contractors revealed that the payment cycle for an executed work spans between 45- 60 days. In some cases, the performance bonds of sub- contractors were also not released after the completion of the works. responses received, the Sub-Contractor selection process had an RII score of 0.7106. Further , discussions with industry professionals revealed that general contractors had a stringent pre- qualification criterion for selecting subcontractors, especially for specialized works. In order to assess
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 6. Ambiguous contractual agreement between Sub-contractor and General contractor 7. STRATEGIES TO BE INCORPORATED IN TRADITIONAL SUB-CONTRACTOR MANAGEMENT FRAMEWORK:- In order to identify strategies for factors identified in the study, interviews with industry leaders and consultants were conducted. These led to the identification of following strategies for improving sub- contractors’ performance in the life cycle of a project. 1. Region-wise vendor redeployment, vendor consolidation: - The strategy of region-wise vendor redeployment and vendor consolidation has been successfully adopted by general contractors in the procurement of raw materials. Vendor consolidation refers to aprocess in which all the vendors offering aparticular material/ equipment in the given region are shortlisted. Vendor Redeployment refers to deploying the same vendor for the supply of a particular material/service at multiple sites. The general contractors should shortlist some good- performing sub- contractors based upon a set of pre-qualification criteria. Once the Sub-contractor has satisfied the Pre- qualification criteria, when a requirement for service is identified, the general contractor shall directly approach these sub- contractors for the services instead of searching the market again. The review of case studies revealed a high rate of vendor redeployment in case of purchase items but in the case of sub- contracting, the rate of vendor redeployment was very low. Discussion with the experts from the general contractor side revealedthatredeployinga A review of various sub-contract documents revealed that contractual agreements between general contractors and sub-contractors generally lack clarity in terms of the scope of work and obligations of both the parties. With an RII value of 0.6541, this factor emerged as the fourth most important factor affecting the performance of sub- contractors. Experts involved in the study stressed the fact that ambiguity of contractual clauses often leads to disputes among the stakeholders, ultimately delaying the progress of the project. To address this issue, various experts agreed that standard contract documents must be established by the general contractors with the contract document containing two parts, one including the general conditions and part two including the special site-specific conditions of the work. Further, with the complexity of projects on a rise, various researchers in past have suggested that clauses related to amendment of orders and management of claims in a project must be formulated in consultation with legal experts in a project. particular sub-contractor for similar work at another project is attributed to his, willingness andcapacity to execute the work. 2. Negotiation of Payment terms: - During the finalization of contract, both the parties must understand the short-term and long terms implication of delayed payments on the project. To minimize the payment risk, the sub-contractors and general contractors must ensure that the paymentterms agreed in the contract are adhered to strictly. In order to lure the general contractors for timely release of payments, dynamic discounts on net payable must be included in the payment terms. The prices of the contracts must be negotiated based on concepts such as Day sales outstanding. If the day sales outstanding ishigher than initially agreed by both the parties, the total value of the contract must also increase proportionately and vice versa must also be applicable.Also, in order to improve the cash position in contracts various options like mobilization payment, and lower retained percentages can be beneficial in improving project finances andmaximizing the finalcashbalance. 3. Inclusion of performance-based incentives in the contracts: - Most of the experts agreed that to motivate the sub- contractors, performance-based incentiveclauses must be introduced in the contract documents. These incentives can be in form of monetary incentives like Cost plus incentive fees, share-in-savings- incentive, and non- monetary such as an automatic extension of contracts in caseof services. The strategy of monetary incentives was utilized in one project selected as a case studyand yielded successful results. The sub-contractorcompleted the given scope of work one week ahead of the scheduled date of completion. To utilize sucharrangements effectively more research needs to be carried out in terms of understanding the type of incentive to be used and the extent to which these incentives must be passed on along the supply chain. 8. CONCLUSION The main objective of the study was to understand the traditional sub-contractor management strategy which is currently being adoptedforexecutionof projects andvarious challenges encountered. It can be concluded that there is a wide spread of sub-contracting in construction industry. But the sub-contractor management strategies being utilized by various stakeholders are not being able to deliver the expected result. The sub-contractor selection process in notregulated through any statutory body. Lack of standardization in contractual terms and conditions has led to exploitation of sub-contractors in various cases. The pace at which sub-contractors execute the works has not been able to match the requirements ofclients and general contractors. Cash flow managementhas also emerged as one © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1733
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 07 | July 2022 www.irjet.net p-ISSN: 2395-0072 the critical issue in traditional sub-contractor management setup. To overcome all these issues various strategies which must be integrated with traditional sub-contractor management framework were identified anddiscussedin detail with experts.Theutilizationofthese strategies can prove to be effective in improving the overall relationship between the stakeholders and enhancingthe performance of subcontractors. REFERENCES 1. Arditi, 2005. Issues in sub-contracting practice. Journal of construction engineering and management 2. Choudhry1, R. M., Jimmie W. Hinze, M., Arshad3, M. & Gabriel4, a. H. F., 2012. Sub- contracting parctices in construction industry of pakistan. Journal of Construction Engineering and Management. 3. Abisugab,2016. “Effect of path-goal leadership styles on the commitment of employees on construction projects”. International Journal of Construction Management. 4. El-Kholy, A. M., 2019. A new technique for subcontractor selection by adopting choosing by advantages. International Journal of Construction Management 5. Hailu, H. A., 2017. Determinants of Subcontracting Performance in road Construction projects.. International Journal ofScientific Engineering and Research (IJSER). 6. Ashraf M. Elazouni and Fikry G. Metwally. (2000). Decision Support System for Subcontracting Construction Works. Journal of Construction Engineering and Management , 191-200. 7. Li, Weifang. (2018). The Study on Sub- contract Management in EPC Engineering. 10. Liu, Jun Ying, Yang, Pengfei, Xia, Bo, Skitmore,Martin . (2017). Effect of perceived justice on subcontractor willingness to cooperate: The mediating role of relationship value. ASCE. 11. Loosemore Martina, Lim Benson. (2021). Relationship quality in construction projects: A subcontractor perspective of principle contractor relationship. International Journalof Project Management. 12. Temitope Seun Omotayo, Oskar Danvers- Watson, Adekunle Sabitu Oyegoke . (2022). Subcontractor trust issues on payment and valuation practices in UK private projects. Journal of Financial Management of Propertyand Construction. 13. Marshamll, 2000. Partnering in construction: a critical review of issues, problems and dilemmas,”. Construction Management andEconomics. 14. Assbeihat, J. M., 2019. Reasons behind Sub- contractor faiulre in construction projects.. International Journal of Civil Engineering and Technology (IJCIET). 15. Creed S. J. Eom, P., Seok H. Yun, P. & and Joon H.Paek, P., 2008. Subcontractor Evaluation and Management Framework for Strategic Partnering. Journal of ConstructionEngineeringand Management 16. Dimitrios Robert I Stamatiou, K. A. K. S. T. P. S. G. &. I. T., 2019. A process reference model forclaims management in construction supply chains: the contractors’ perspective. International Journal of ConstructionManagement. 17. Jammal.M, 2018. Reasons behind sub- contractor default in construction projects..International journal of civil engineering and management. 18. Jianga, 2014. Negotiating Construction Contracts through Practical Cash Flow Planning and Analysis Model. International Journal of Construction Management. 19. Will hughes, Incentives in constrution contracts.. CIB world congress 2007. 8. LIM, P. X. Z. a. B. T., 2014. An Emperical StudyIn Subcontracotr Selection and Long -TermAlliance Relationship Between Main - Contractor And Subcontractor. International Journal of Construction Management. 9. H. Randolph Thomas, Flynn, Christopher J. (2011). Fundamentals of Sub Contractor management. ASCE. © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 1734