SlideShare a Scribd company logo
1 of 8
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 283
Application of Advanced formwork system for High rise buildings in
Chennai, India
S.Gowtham1, V.Vidya2
1M.Arch (construction project management) student, Faculty of Architecture, Dr .M.G.R Educational and Research
Institution, Chennai, India.
2 Associate Professor, Faculty of Architecture, Dr .M.G.R Educational and Research Institution, Chennai, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Various different advanced self-climbing
construction systems have been developed and used
worldwide. In recent times due to growing population and
space constrains there is a need for tall high rise buildings.
Throughout India there are various high rise residential
developments. Some of these developments use advanced
formwork systems like self-climbing formwork. ButinChennai
it is not widely used but aluminum form work system is used.
The aim of the study is to study, analyze and understand the
application of self-climbing formwork in high rise building
projects. As a part of the study various case studies of the self-
climbing form works used in India are explored and we
attempt to conceptually implement the self-climbing
formwork in a project in Chennai and analyze the differences.
Key Words: Self-climbing formwork, advanced
formworks, jump formworks
1. INTRODUCTION
Various high rise residential projects from Mumbai is
studied and analyzed as the part of the study with respect to
time, cost and quality. Later suitable proposal is identified in
Chennai to apply the findings of the case study where SPR
High living in Chennai is identified as the site since it is the
1st tallest building in Chennai. It is constructed using MIVAN
formwork. For this site we try to apply self-climbing form
work and analyze the differences, results between two
formwork systems and understand the viability of the
advanced self-climbing form work systemsinChennai.From
the study it is identified that when the combination of
advanced formworks system used for (Walls & slabs) and
self-climbing formwork used for (Core wall) total cost is
10.794 % higher compared with aluminum formwork.
2. METHODOLOGY
 Literature study about self-climbing formwork
 Case studies
 Comparative analysis
 Identification of suitable construction system
 Proposal site identification
 Proposed Formwork Cost
 Proposed Construction scheduling
 Comparative Analysis
 Findings
 Conclusion
3. SCF – SELF CLIMBING FORMWORK
Self-climbing formwork system have been widely used in
Indian metropolitan cities like Delhi, Mumbai, Kolkata and
Chennai for High rise residential apartment. It is a special
formwork for tall concrete structures. It is an effective
solution for repetitive construction. SCF is a crane
independent formwork system which is widely used in
Skyscrapers, Bridge Pylons, Airport Control Towers, High
Rise Buildings, Elevator Shafts, and Silos. Its components
include Platforms for concrete workers, Wall formwork,
Lifting beam, Suspension platforms. This formwork also
provides working platforms for construction crews. It also
provide additional spaces for equipment and safety /
weather protection screens. It also enables very large
concrete structures to be constructedin onesinglepourthus
creating seamless structures with enhanced strength and
visual appearance, as well as reducing construction times
and material costs significantly.
4. PROCESS OF SELF CLIMBING FORMWORK
1. Setting up the self-climb form work system
2. Placing steel reinforcement
3. Pouring Concrete
4. Formwork Stripping
5. Formwork shifting to upper level
6. At end of all floors construction Removal formwork
using tower crane
5. COMPONENTS
1. Suspension platforms
2. Wall formwork material and pieces
3. Anchor system
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 284
4. Climbing brackets
6. ADVANTAGES
1. By using self-climbing form work we can get High-
quality surface finishes
2. This formwork has faster construction speed
3. It requires less labour to set up the formwork
4. It can sustain high wind since it has wind ties for
support
5. There is high safety for labour during the setting
and removal process
6. It is Easy to clean and reuse with little waste
generated compared to traditional systems
7. Customization is possible for any type of complex
wall geometries
8. This Crane independent construction only requires
crane during dismantling
7. DISADVANTAGES
1. Very high initial investments required for self-
climbing formworks system
2. Requires only skilled / highly skilled labours
3. Dimensional Accuracy can go low in certain
conditions
8. CASE STUDIES
1. High Rise SKY Towers
2. Omkar 1973
3. Lodha Park (Kiara Block)
4. Lodha Park (ALLURA)
5. World One
6. Palais Royale
7. CTRL S Data Center
8.1. HIGH RISE SKY TOWERS
Sky towers project has 4 residential high rise buildings
situated in Mumbai. This project is around 20 acres and has
built up area of around 8 million Sq.F. the height of towers
range from 257m+ to 300m+.the construction schedule
targeted was 10 days slab cycle and for residential floors its
7 days.to achieve this 7 days cycle automatic climbing
formwork system was used for core walls. Guided climbing
system for external wall was followed. Light weight panel
formwork for columns, generic panel slabformwork system,
and concrete placing booms,towercraneswithhighcapacity
and high performance concrete was used. Core structure
preceding construction method is followed using ACS
automatic climbing system. The formwork systems used in
this project are Automatic climbing platform SCP – 400 is
used in sky tower and SKE - 100 / 50 (DOKA) is used in sky
forest and sky suite
Construction sequence: Core wall and stair case wall >> flat
slab
8.2. OMKAR 1973
OMKAR 1973 towers has around 400 sky bungalows, sizes
varying from 2,500 sq. ft. to 18,200 sq. ft. area. It has height
of 267 meters and an area of around 5,000,000 sq. ft. The
project consists of 3 skyscrapers whicharenamelytowersA,
B, and C, all are 73 stories tall. All these towers has 3 floors
underground for parking. The Platform SCP is used for core
structure and column. It has space for all the site equipment,
and is enclosed on all sides, weather-shielded. The core
structure has a 7 days jump cycle and the column has 4 days
jump cycle. Dokadek 30, Protection screen Xclimb60,Large-
area formwork Top 50 are the other advanced formworks
and safety screens used in this project.
Construction sequence: Core wall and stair case wall >>
columns >> flat slab
Table -1: OMKAR 1973 Conceptual Baseline formwork cost
Chart -1: Pie chart formwork cost
Conceptual Baseline formwork cost
Sl.No Formwork location cost
1 (self-climbing) 2 ' thick
structural core wall
₹ 4,92,25,500
2 (self-climbing) 1' thick lift
core and stair case
₹ 9,02,52,000
3 (self-climbing) columns ₹ 4,10,67,000
4 roof slab ₹ 2,44,94,040
total ₹ 18,05,44,500
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 285
8.3. LODHA PARK (KIARA BLOCK)
LODHA - The Park TOWER – 5 is a residential high rise
project located in Mumbai, the client is Lodha developer
limited company started on July 2015 and was expected to
be finished in 44 months. Its tender cost is around 371, 16,
92,726 Rs. The project has a total built-up of 1,03,769 Sq. M.
Tower 5 is divided into 5 elements 1.Core wall (1); 2.Core
wall (2); 3.Lift lobby; 4.Staircase; 5.Wing slab. In the
construction of core wall is done usingPERIVarioAutomatic
climbing system formwork and the wind slab, lift lobby and
staircase is construction using kumkang kind aluminum
formwork. Construction sequence:Corewall 1>>corewall 2
>> lift lobby >> wing slab
Conceptual Baseline Core Wall-2 cost
Criteria Quantity Unit Cost
per
Sq.M
Scaffolding
cost
Panel
Formwork
675.58 m2 25,000 1,68,89,500
Climbing
formwork
639.84 m2 90,000 5,75,85,600
Aluminum 35.74 m2 8,000 2,85,920
total 7,46,71,000
Table -2: Lodha park (kiara Block) Conceptual Baseline
formwork cost
Figure -1: Lodha Park Floor cycle
8.4. LODHA PARK (ALLURA)
The Park by Lodha (ALLURA),locatedinPandurangBudhkar
Marg, Worli, and Mumbai is around a 7-acre private park in
the 17-acre master planned urban oasis. The project time
line is 2013 -2021. This building is 268m height. The entire
core structure is divided in two parts i.e. inner core and
external core. The main contractor for the projectissimplex.
Main challenge in the project was Irregular huge
architectural core, High Safety standards in windy coastal
region, higher safety measures to ensure effective outcome
from working people. Hydraulic climbing system was found
to be suitable solution in this project. This system also
ensures anti-fall protection hence better work environment
with low man-power requirement. LIWA panel formwork is
also used which a crane free manual installation forwall and
column formwork is adding with the crane free time from
ACS system.
8.5. WORLD ONE
World One is a 280.2 m(919 Ft)tall skyscraperwhichhas76
floor located in Mumbai, India. In 2022, it was
considered tallest completed buildinginIndia.Itislocated in
7.1-hectare (17.5-acre) site of the defunctShrinivasMill.The
site also has two other parts: World View and World Crest.
Developer of this project is the Lodha Group. Construction
on World One began in 2011.By December 2014,about75%
of civil construction on the project had been completed.
Estimated construction cost was around ₹26,566,282,284
Cr. Project time line: May 7th 2011 – 2020. Core Preceding
Construction Method - The building is constructed in two
stages the central core first and the surroundingbuildingsin
the next stage.
Conceptual baseline Formwork cost
Sl.No Location formwork cost per
Sq.F
1 Lift core wall
formwork
₹ 10,54,06,200
2 Column formwork
cost
₹ 6,05,34,000
3 Roof Slab formwork ₹ 1,54,58,400
total ₹ 18,13,98,600
Table 3 -: World one (kiara Block) Conceptual Baseline
formwork cost
8.6. PALAIS ROYALE
Palais Royale is a residential supertall skyscraper project in
Worli, Mumbai, India. At 320 meters (1,050 Ft), it is the
tallest building and third tallest structure in India.
Construction began in 2008 still under construction.The
project's progress has been stalled due to multiple public
interest litigation lawsuits filed by NGOs Janhit Manch and
UHRF, Delhi. These litigations were disposed of by
the Supreme Court of India in October 2019.On completion,
the building would have 120 apartments ranging in size
between 740 and 1,300 square meters. To deliver the works
on time, two MEVA automated climbing (MAC) systems in
parallel to pour the lift and staircase shafts. The MAC
provides complete protection for the workers. Alufix wall
formwork, was used both on the site to form walls up to
heights of 3m, and as part of the climbing systems. Every
day, slabs of different sizes were poured immediately below
the core, using the Meva Dec slabsystem.Theslabformwork
was set by hand with just a small team of workers, saving
time.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 286
8.7. DATA CENTER PROJECT
A Data centre project in Ambattur uses crane assisted
climbing formwork system.The site area is around 3.98
Acres. Total construction area for the project is around
8, 47,786 Sq.F.This building is constructed by composite
construction usingsteel structure,R.C.Candblockworks. The
climbing form works system is used for shear walls and lift
core walls due to rapid construction cycle. The formwork is
crane guided climbing system which used crane for shifting
to upper levels. RMD KWIK rapid climbformwork systemsis
used in this project. This system comprises of working
platform, formwork and ladder components. Tower crane is
required for initial setup of the system, lifting and
dismantling of the formwork system. SPEED - Climbing
bracket connects to wall with recoverable anchor screw -no
lost parts. Reduced crane time in moving forms. Platform
and formwork are crane handled in one single operation.
Speeds up concrete cycle, reducing program time on multi-
floor builds. Eliminates the need to lay down form for
cleaning and enables cores to be constructed in advance.
SAFETY - Self-contained working levels for economical core
forming. No tripping hazard on working platform - the
decking boards are at the same level as the top of the
climbing bracket. Corner platforms neatly abut one another.
8.7. CASE STUDY INFERENCE
For the case studies we can understandthattheselfclimbing
formworks are used in combination with other panel
formwork system and protection screens. Self climbing
formwork when used with the combination of aluminium
formwork can be economical. The self climbing formwork is
mostly used in the construction of lift cores. The
construction is done in two or more phases and the lift core
is constructed first this is called core structure preceeding
construction method. The planning of the building
significantly affects the form work cost so proper
preplanning in required. Form work cost of Walls withmore
Length, thickness and distance between each other is
economical compared to that of walls with lesser distance
between each other.
9.PROPOSAL SITE
Proposed High-living District is a residential complex
consisting of three residential skyscrapers in the
neighborhood of in Chennai, India. which is the tallest
residential building in Chennai. Tower B is selected for
application of self climbing form work. The project has 75
floors. at site they have used S type aluminum formwork
with an average of 12 days / floor construction cycle. In the
proposal we are going to use selfclimbingformwork forcore
structure, advanced panel formwork for walls and slabs,
steel safety protection screen.
Sl.No Criteria Area in Sq.M
1 Plinth area ( 1 floor) 1197.4
2 Built up area ( 1 floor) 996.4
3 Carpet area( 1 floor) 836
4 Plinth area for 75 floors 89,805
Table 4 -: Proposed tower B Area
9.1 cost assumptions
Cost assumptions
Cost per
Sq.M
Cost per Sq.F
Aluminum formwork
MIVAN - aluminum
formwork
8,750 813
Nylon safety net 350 33
Advanced formwork and protection screen
Self-climbing form work 95,000 11,148
Safety protection screen 14,500 1,347
Advanced panel formwork
For Wall
25,000 2,323
Advanced panel formwork
For slabs
15,000 1,394
Table 5 -: Cost assumptions data for aluminum and
advanced formwork system
This data is based on values collected from various industry
professionals and from case studies. These values may vary
based on location. This data is for Chennai and may subject
to change based on the manufactures and models.
9.2 R.C.C COST
Sl.
No
Description
of the item Unit Qty. Rate total
1 STEEL REINFORCEMENT
1.1 core wall Kg 8054 ₹ 90 ₹ 7,22,050
1.2
Interior
and
exterior
walls Kg 64119 ₹ 90
₹
57,48,309
1.3
roof slab
and
balconies Kg 23501 ₹ 90
₹
21,06,824
2 CONCRETE WORKS
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 287
2.1 core wall Cu.M 54
₹
10,222 ₹ 5,51,972
2.2
Interior
and
exterior
walls Cu.M 430
₹
10,222
₹
43,94,300
2.3
roof slab
and
balconies Cu.M 176
₹
10,222
₹
18,00,041
3 CENTERING AND SHUTTERING
3.1 core wall Sq.M 777 ₹ 670 ₹ 5,20,240
3.2
Interior
and
exterior
walls Sq.M 3587 ₹ 670
₹
24,01,897
3.3
roof slab
and
balconies Sq.M 1179 ₹ 670 ₹ 7,89,115
A TOTAL COST
₹
1,90,34,748
Table 6 -: Steel, Concrete and Shuttering cost.
9.3 ALUMINUM FORM WORK - SITE
At site the S-Type aluminum form work is done and for site
safety nylon safety nets are used
Sl.No Description of
the item Unit Qty. Rate total
1 ALUMINIUM FORM WORK
1.1 core wall Sq.M 777
₹
457 ₹ 3,54,972
1.2
Interior and
exterior walls Sq.M 3587
₹
457 ₹ 16,38,872
1.3
roof slab and
balconies Sq.M 1179
₹
457 ₹ 5,38,432
2 ALUMINIUM SHEET
2.1 core wall Sq.M 777
₹
8,500 ₹ 66,04,500
2.2
Interior and
exterior walls Sq.M 3587
₹
8,500
₹
3,04,92,308
2.3
roof slab and
balconies Sq.M 1179
₹
8,500
₹
1,00,17,894
3 NYLON SAFETY NET
3.1
Providing nylon
safety net Sq.M 1269
₹
350 ₹ 4,44,036
B
TOTAL FORMWORK & SAFETY NET
COST FOR ONE FLOOR
₹
5,00,91,014
4 1% LIFTING CHARGES
4.1
MATERIAL AND LIFTING
CHARGES FOR 1 - 5 FLOORS ₹ 9,51,73,742
4.2
FORMWORK LIFTING
CHARGES FOR 1 - 5 FLOORS ₹ 5,00,91,014
4.3
MATERIAL AND LIFTING
CHARGES FOR 6 - 75 FLOORS ₹ 1,91,63,48,748
4.4
FORMWORK LIFTING
CHARGES FOR 6 - 75 FLOORS ₹ 5,04,29,798
C
(R.C.C COST + ALUMINUM
FORMWORK + LIFTING)
TOTAL ₹ 2,11,20,43,303
Table 7 -: Aluminum formwork and safety net cost.
9.4. ADVANCED FORMWORK - PROPOSAL
For proposal we use combinations of Hi-end advanced
formwork systems and
1. Self climbing form work for core walls,
2. wall & slab panel formwork.
3. Steel protection screen for safety
5 ADVANCED FORMWORK FORM WORK
Sl.N
o
Descriptio
n of the
item Unit Qty. Rate total
A SELF CLIMBING FORMWORK SYSTEM
5.1 core wall Sq.M 777
₹
95,000 ₹ 7,38,15,000
B PANEL FORMWORK SYSTEM
5.2
Interior
and
exterior
walls Sq.M
358
7
₹
15,000 ₹ 5,38,09,954
5.3
roof slab
and
balconies Sq.M
117
9
₹
15,000 ₹ 1,76,78,637
6 SAFETY PROTECTION SCREEN
6.1
steel
safety
protection
screen Sq.M
126
9
₹
14,500 ₹ 1,83,95,764
B TOTAL FORMWORK ₹ 16,36,99,355
8 1% LIFTING CHARGES
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 288
8.1
MATERIAL AND LIFTING CHARGES
FOR 1 - 5 FLOORS ₹ 9,51,73,742
8.2
FORMWORK LIFTING CHARGES FOR
1 - 5 FLOORS ₹ 16,36,99,355
8.3
MATERIAL AND LIFTING CHARGES
FOR 6 - 75 FLOORS
₹
1,91,63,48,748
8.4
FORMWORK LIFTING CHARGES FOR
6 - 75 FLOORS ₹ 16,48,06,514
9
(R.C.C COST + ADVANCED
FORMWORK + LIFTING) TOTAL
₹
2,34,00,28,360
Table 7 -: Aluminum formwork and safety net cost.
9.5 BASELINE COST DIFFERENCE FOR 1 FLOOR
The increase percentage is 164 % higher than the aluminum
formwork when compared with advancedformwork system
Table 8 -: Baseline Cost difference for 1 floor (R.C.C and
Formwork)
9.6 TOTAL COST DIFFERENCE
The increase percentage is 10.7945 % higher than the
aluminium form work in case we use the combination of Hi-
end advanced formwork system and protection screen.
Sl.No FORMWORK TYPE COST
1 ALUMINIUM FORMWORK Approx...₹ 2,11 Cr
2 ADVANCED FORMWORK Approx...₹ 2,34 Cr
3 INCREASE ₹ 22,79,85,057
Figure -2: Schedule for Aluminum formwork (12 days /
floor cycle)
9.8 CONSTRUCTION SCHEDULE ADVANCED
FORMWORK (9 DAYS / FLOOR CYCLE)
Figure -3: Schedule for Advanced formwork (9 days /
floor cycle)
9.9. TIME DIFFERENCE
The duration difference is around 7 months in super
structure construction.
SUPERSTRUCTURE
SL.NO FORMWORK
TYPE
DAYS MONTHS YEAR
1 ALUMINIUM
FORMWORK
952 32 2.6
2 ADVANCED
FORMWORK
729 24 2.0
3 DURATION
DIFFERENCE
223 7 0.6
Table 10 -: Duration difference
Sl.No Description
Aluminium
form work
Advanced
formwork
Cost
Increase
1
Staircase
and lift core ₹ 87,53,726
₹
7,56,09,253
₹
6,68,55,528
2
Interior and
exterior wall
₹
4,46,75,685
₹
6,63,54,460
₹
2,16,78,775
3
Roof slab
and
balconies
₹
1,52,52,307
₹
2,23,74,618 ₹ 71,22,310
4 safety ₹ 4,44,036
₹
1,83,95,764
₹
1,79,51,728
5 total
₹
6,91,25,754
₹
18,27,34,095
₹
11,36,08,341
9.7.CONSTRUCTIONSCHEDULEALUMINUMFORMWORK
(12 DAYS / FLOOR CYCLE)
Table 9 -: Total cost difference or (R.C.C, Formwork and
lifting charges)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 289
9.10. COMPARISON TABLE
SI.NO DESCRIPTION ALUMINIUM
FORMWORK
ADVANCED
FORMWORK
1 Construction
cycle
12 days 9 days
2 Formwork
combination
Wall and slab- S
type - monolithic
Aluminum
Formwork
Protection –
nylon Safety net
Wall – RCS (Rail
Climbing
Formwork)
Slab – Advanced
form work
Protection -
protection screen
3 Dimensional
variations
Nil Nil
4 Finish quality Finishing Lines
will be visible
High Quality
finish
5 Initial
investments
High Very high
6 No. of labors High Nos
required
High Nos
required
7 Skilled Labor Skilled/unskilled Highly
Skilled/unskilled
8 Tower crane Not required Required for
installing and
dismantling
9 Safety during
execution
Moderate safety Very safe
10 Waste
production
medium Zero
11 Complexity of
tools
Available on
demand
Training & proper
monitoring
required
12 Repetitions 200-250 times 120 times
13 Scrap Value 30% 40 – 50 %
14 Repair cost
repair is
impossible after
the deformation
Can be repaired
(30-35 % of the
total cost)
Table 9 -: Comparative table (Aluminum formwork &
advanced formwork)
10. FINDINGS
The cost differences is 10.7945 % higher by using
combination of advanced form work system and protection
screens compared to MIVAN form work system. The
duration of construction is also affected significantly in the
superstructure by saving 7 months. The self-climbing
formwork is only suitable for sites and cities with limited
space constraints and for site where the safety and qualityis
the highest priority however cost is compromised. Self-
climbing formwork is also suitable for projects where the
speed, safety and quality of construction is the first priority.
11. CONCLUSION
From the study it is clear from the study that the self-
climbing formwork is expensive but by proper planning and
using the self-climbing form work with other economical
form works cost can be significantly reduced. From this
study we could get an overall understanding of the self-
climbing formwork used in various high-rise construction
projects in India. This proposal study is done for exploring
the possibility of incorporating self-climbing formwork in
Chennai. It shows how the self-climbing formwork even
though expensive can save time considerably with good
quality and safety aspects. Self-climbing formwork can be
ideal for densely populated locations there is space
constrains.
12. RECOMMENDATIONS
Proper Planning and designing is crucial for cutting cost by
using advanced formwork system the Formwork cost is
usually high for walls and spaces which has shorter length
and distance between each other. Advanced formwork
system is very efficient for Hi- End residential studio
apartments or commercial skyscraper projects with more
number of cores and for tall rapid construction projects. By
using combination of self-climbing formwork for core and
aluminum formwork for walls and slabs instead of panel
formwork system cost can be efficiently reduced. Self-
climbing formwork can help in fast paced construction
projects. Since it has shorter construction cycle.
REFERENCES
[1] Neenu S K, "How climbing formwork makes concrete
construction ?", Theconstructor.org
[2] Jonathan Kozlowski, "7 Facts On Self-Climbing Concrete
Forming Systems", December 10, 2021,
www.forconstructionpros.com
[3] Amitabh kumar, Amit singhal, "High Rise SKY Towers,
Mumbai -construction challenges", 2011,
global.ctbuh.org
[4] Ms. A. C. Gawali , Ms. N. D. Kolpe , Ms. S. M. Petekar , Prof.
S. M. Barelikar, "Comparative Study of Jump Formwork
with Conventional Formwork"
[5] AhkimMakmun,"DOKA’sGenNextformwork technology
at Omkar 1973", March 22,2014, www.doka.com
[6] Doka, "Omkar 1973 Worli",www.doka.com
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 290
[7] Vinod Jacob Chacko, Gopi Kannan. S, "HELMET - EHS
journal of L&T Construction (Volume - 6, Issue - 3)",July
- September 2016, eip.lntecc.com
[8] Dhruv Patel, "Understanding Core HighRise |Lodha The
Park, Mumbai", 2019, portfolio.cept.ac.in
[9] CTBUH, "Lodha the Park Complex", 14 December 2021,
CTBUH Skyscraper Center
[10] Peri, "Lodha - The Park, Mumbai", www.peri.in
[11] CTBUH,"World One", CTBUH Skyscraper Center
[12] Peri,"World One tower, Mumbai", www.peri.in
[13] Joshi, Manas,"Mumbai's iconic Palais Royale tower in
Worli to be re-auctioned at slashed rate", 14 April 2020,
www.indiatvnews.com
[14] Meva,"Green project Palais RoyaleinMumbai",meva.net
[15] CTBUH, "Palais Royale, Mumbai", CTBUH Skyscraper
Center
[16] projects today,"CtrlS Datacenters to set up Data Centre
in Chennai", 24 May 2022, www.projectstoday.com
[17] Rmdkwikform,"Rapidclimb", www.rmdkwikform.com
[18] Sprindia, "HIGHLIVING DISTRICT - TOWER B
APARTMENTS", sprindia.com
[19] Sprindia,"SPR 360˚ - (newsletter edition 01 - 14)", June
15 2018 - October 18 2019, issuu.com.

More Related Content

Similar to Application of Advanced formwork system for High rise buildings in Chennai, India

Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in ConstructionIRJET Journal
 
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...IRJET Journal
 
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...IRJET Journal
 
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET Journal
 
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURES
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURESANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURES
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURESIRJET Journal
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSIRJET Journal
 
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...Comparative Study of Seismic Analysis of RC Frame Structure with and without ...
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...IRJET Journal
 
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid Sructure
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid SructureSeismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid Sructure
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid SructureIRJET Journal
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionIRJET Journal
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingIRJET Journal
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsIRJET Journal
 
Effect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using EtabsEffect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using EtabsIRJET Journal
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction systemchirag aggarwal
 
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...IRJET Journal
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET Journal
 
Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered BuildingsIRJET Journal
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueSandeep Jain
 
Analysis Of Earthquake Resistant Structure By Base Isolation Method
Analysis Of Earthquake Resistant Structure By Base Isolation MethodAnalysis Of Earthquake Resistant Structure By Base Isolation Method
Analysis Of Earthquake Resistant Structure By Base Isolation MethodIRJET Journal
 

Similar to Application of Advanced formwork system for High rise buildings in Chennai, India (20)

Mivan Formwork in Construction
Mivan Formwork in ConstructionMivan Formwork in Construction
Mivan Formwork in Construction
 
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...
ANALYSIS OF EFFECT OF WIND & SEISMIC FORCE ON MULTISTORIED BUILDING WITH OUTR...
 
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...
IRJET- Analysis and Design of 9 Storied RC Building using various Retrofittin...
 
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...IRJET-  	  A Performance Study of (G+20) RCC Structure using Framed Bundled B...
IRJET- A Performance Study of (G+20) RCC Structure using Framed Bundled B...
 
DIA-Grid Structures
DIA-Grid StructuresDIA-Grid Structures
DIA-Grid Structures
 
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURES
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURESANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURES
ANALYSIS AND DESIGN OF HIGH-RISE DIAGRID STRUCTURES
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABS
 
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...Comparative Study of Seismic Analysis of RC Frame Structure with and without ...
Comparative Study of Seismic Analysis of RC Frame Structure with and without ...
 
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid Sructure
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid SructureSeismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid Sructure
Seismic Behaviour of Multistorey RC Frame with Shear wall and Octagrid Sructure
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional Construction
 
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed BuildingPlanning and Scheduling of Shuttering System for Multi-Storeyed Building
Planning and Scheduling of Shuttering System for Multi-Storeyed Building
 
Time, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast BuildingsTime, Cost , Productivity and Quality Analysis of Precast Buildings
Time, Cost , Productivity and Quality Analysis of Precast Buildings
 
Effect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using EtabsEffect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
Effect of Oblique Column and Viscous Damper on Podium Structure Using Etabs
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
 
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...
IRJET- Cost, Schedule and Sustainability Comparison between a Traditional and...
 
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
IRJET- Comparative Analysis of Aluminium Formwork Building and Conventional F...
 
Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered Buildings
 
Irjet v4 i7530
Irjet v4 i7530Irjet v4 i7530
Irjet v4 i7530
 
MIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction TechniqueMIVAN_An Aluminum Formwork Construction Technique
MIVAN_An Aluminum Formwork Construction Technique
 
Analysis Of Earthquake Resistant Structure By Base Isolation Method
Analysis Of Earthquake Resistant Structure By Base Isolation MethodAnalysis Of Earthquake Resistant Structure By Base Isolation Method
Analysis Of Earthquake Resistant Structure By Base Isolation Method
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Application of Advanced formwork system for High rise buildings in Chennai, India

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 283 Application of Advanced formwork system for High rise buildings in Chennai, India S.Gowtham1, V.Vidya2 1M.Arch (construction project management) student, Faculty of Architecture, Dr .M.G.R Educational and Research Institution, Chennai, India. 2 Associate Professor, Faculty of Architecture, Dr .M.G.R Educational and Research Institution, Chennai, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Various different advanced self-climbing construction systems have been developed and used worldwide. In recent times due to growing population and space constrains there is a need for tall high rise buildings. Throughout India there are various high rise residential developments. Some of these developments use advanced formwork systems like self-climbing formwork. ButinChennai it is not widely used but aluminum form work system is used. The aim of the study is to study, analyze and understand the application of self-climbing formwork in high rise building projects. As a part of the study various case studies of the self- climbing form works used in India are explored and we attempt to conceptually implement the self-climbing formwork in a project in Chennai and analyze the differences. Key Words: Self-climbing formwork, advanced formworks, jump formworks 1. INTRODUCTION Various high rise residential projects from Mumbai is studied and analyzed as the part of the study with respect to time, cost and quality. Later suitable proposal is identified in Chennai to apply the findings of the case study where SPR High living in Chennai is identified as the site since it is the 1st tallest building in Chennai. It is constructed using MIVAN formwork. For this site we try to apply self-climbing form work and analyze the differences, results between two formwork systems and understand the viability of the advanced self-climbing form work systemsinChennai.From the study it is identified that when the combination of advanced formworks system used for (Walls & slabs) and self-climbing formwork used for (Core wall) total cost is 10.794 % higher compared with aluminum formwork. 2. METHODOLOGY  Literature study about self-climbing formwork  Case studies  Comparative analysis  Identification of suitable construction system  Proposal site identification  Proposed Formwork Cost  Proposed Construction scheduling  Comparative Analysis  Findings  Conclusion 3. SCF – SELF CLIMBING FORMWORK Self-climbing formwork system have been widely used in Indian metropolitan cities like Delhi, Mumbai, Kolkata and Chennai for High rise residential apartment. It is a special formwork for tall concrete structures. It is an effective solution for repetitive construction. SCF is a crane independent formwork system which is widely used in Skyscrapers, Bridge Pylons, Airport Control Towers, High Rise Buildings, Elevator Shafts, and Silos. Its components include Platforms for concrete workers, Wall formwork, Lifting beam, Suspension platforms. This formwork also provides working platforms for construction crews. It also provide additional spaces for equipment and safety / weather protection screens. It also enables very large concrete structures to be constructedin onesinglepourthus creating seamless structures with enhanced strength and visual appearance, as well as reducing construction times and material costs significantly. 4. PROCESS OF SELF CLIMBING FORMWORK 1. Setting up the self-climb form work system 2. Placing steel reinforcement 3. Pouring Concrete 4. Formwork Stripping 5. Formwork shifting to upper level 6. At end of all floors construction Removal formwork using tower crane 5. COMPONENTS 1. Suspension platforms 2. Wall formwork material and pieces 3. Anchor system
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 284 4. Climbing brackets 6. ADVANTAGES 1. By using self-climbing form work we can get High- quality surface finishes 2. This formwork has faster construction speed 3. It requires less labour to set up the formwork 4. It can sustain high wind since it has wind ties for support 5. There is high safety for labour during the setting and removal process 6. It is Easy to clean and reuse with little waste generated compared to traditional systems 7. Customization is possible for any type of complex wall geometries 8. This Crane independent construction only requires crane during dismantling 7. DISADVANTAGES 1. Very high initial investments required for self- climbing formworks system 2. Requires only skilled / highly skilled labours 3. Dimensional Accuracy can go low in certain conditions 8. CASE STUDIES 1. High Rise SKY Towers 2. Omkar 1973 3. Lodha Park (Kiara Block) 4. Lodha Park (ALLURA) 5. World One 6. Palais Royale 7. CTRL S Data Center 8.1. HIGH RISE SKY TOWERS Sky towers project has 4 residential high rise buildings situated in Mumbai. This project is around 20 acres and has built up area of around 8 million Sq.F. the height of towers range from 257m+ to 300m+.the construction schedule targeted was 10 days slab cycle and for residential floors its 7 days.to achieve this 7 days cycle automatic climbing formwork system was used for core walls. Guided climbing system for external wall was followed. Light weight panel formwork for columns, generic panel slabformwork system, and concrete placing booms,towercraneswithhighcapacity and high performance concrete was used. Core structure preceding construction method is followed using ACS automatic climbing system. The formwork systems used in this project are Automatic climbing platform SCP – 400 is used in sky tower and SKE - 100 / 50 (DOKA) is used in sky forest and sky suite Construction sequence: Core wall and stair case wall >> flat slab 8.2. OMKAR 1973 OMKAR 1973 towers has around 400 sky bungalows, sizes varying from 2,500 sq. ft. to 18,200 sq. ft. area. It has height of 267 meters and an area of around 5,000,000 sq. ft. The project consists of 3 skyscrapers whicharenamelytowersA, B, and C, all are 73 stories tall. All these towers has 3 floors underground for parking. The Platform SCP is used for core structure and column. It has space for all the site equipment, and is enclosed on all sides, weather-shielded. The core structure has a 7 days jump cycle and the column has 4 days jump cycle. Dokadek 30, Protection screen Xclimb60,Large- area formwork Top 50 are the other advanced formworks and safety screens used in this project. Construction sequence: Core wall and stair case wall >> columns >> flat slab Table -1: OMKAR 1973 Conceptual Baseline formwork cost Chart -1: Pie chart formwork cost Conceptual Baseline formwork cost Sl.No Formwork location cost 1 (self-climbing) 2 ' thick structural core wall ₹ 4,92,25,500 2 (self-climbing) 1' thick lift core and stair case ₹ 9,02,52,000 3 (self-climbing) columns ₹ 4,10,67,000 4 roof slab ₹ 2,44,94,040 total ₹ 18,05,44,500
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 285 8.3. LODHA PARK (KIARA BLOCK) LODHA - The Park TOWER – 5 is a residential high rise project located in Mumbai, the client is Lodha developer limited company started on July 2015 and was expected to be finished in 44 months. Its tender cost is around 371, 16, 92,726 Rs. The project has a total built-up of 1,03,769 Sq. M. Tower 5 is divided into 5 elements 1.Core wall (1); 2.Core wall (2); 3.Lift lobby; 4.Staircase; 5.Wing slab. In the construction of core wall is done usingPERIVarioAutomatic climbing system formwork and the wind slab, lift lobby and staircase is construction using kumkang kind aluminum formwork. Construction sequence:Corewall 1>>corewall 2 >> lift lobby >> wing slab Conceptual Baseline Core Wall-2 cost Criteria Quantity Unit Cost per Sq.M Scaffolding cost Panel Formwork 675.58 m2 25,000 1,68,89,500 Climbing formwork 639.84 m2 90,000 5,75,85,600 Aluminum 35.74 m2 8,000 2,85,920 total 7,46,71,000 Table -2: Lodha park (kiara Block) Conceptual Baseline formwork cost Figure -1: Lodha Park Floor cycle 8.4. LODHA PARK (ALLURA) The Park by Lodha (ALLURA),locatedinPandurangBudhkar Marg, Worli, and Mumbai is around a 7-acre private park in the 17-acre master planned urban oasis. The project time line is 2013 -2021. This building is 268m height. The entire core structure is divided in two parts i.e. inner core and external core. The main contractor for the projectissimplex. Main challenge in the project was Irregular huge architectural core, High Safety standards in windy coastal region, higher safety measures to ensure effective outcome from working people. Hydraulic climbing system was found to be suitable solution in this project. This system also ensures anti-fall protection hence better work environment with low man-power requirement. LIWA panel formwork is also used which a crane free manual installation forwall and column formwork is adding with the crane free time from ACS system. 8.5. WORLD ONE World One is a 280.2 m(919 Ft)tall skyscraperwhichhas76 floor located in Mumbai, India. In 2022, it was considered tallest completed buildinginIndia.Itislocated in 7.1-hectare (17.5-acre) site of the defunctShrinivasMill.The site also has two other parts: World View and World Crest. Developer of this project is the Lodha Group. Construction on World One began in 2011.By December 2014,about75% of civil construction on the project had been completed. Estimated construction cost was around ₹26,566,282,284 Cr. Project time line: May 7th 2011 – 2020. Core Preceding Construction Method - The building is constructed in two stages the central core first and the surroundingbuildingsin the next stage. Conceptual baseline Formwork cost Sl.No Location formwork cost per Sq.F 1 Lift core wall formwork ₹ 10,54,06,200 2 Column formwork cost ₹ 6,05,34,000 3 Roof Slab formwork ₹ 1,54,58,400 total ₹ 18,13,98,600 Table 3 -: World one (kiara Block) Conceptual Baseline formwork cost 8.6. PALAIS ROYALE Palais Royale is a residential supertall skyscraper project in Worli, Mumbai, India. At 320 meters (1,050 Ft), it is the tallest building and third tallest structure in India. Construction began in 2008 still under construction.The project's progress has been stalled due to multiple public interest litigation lawsuits filed by NGOs Janhit Manch and UHRF, Delhi. These litigations were disposed of by the Supreme Court of India in October 2019.On completion, the building would have 120 apartments ranging in size between 740 and 1,300 square meters. To deliver the works on time, two MEVA automated climbing (MAC) systems in parallel to pour the lift and staircase shafts. The MAC provides complete protection for the workers. Alufix wall formwork, was used both on the site to form walls up to heights of 3m, and as part of the climbing systems. Every day, slabs of different sizes were poured immediately below the core, using the Meva Dec slabsystem.Theslabformwork was set by hand with just a small team of workers, saving time.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 286 8.7. DATA CENTER PROJECT A Data centre project in Ambattur uses crane assisted climbing formwork system.The site area is around 3.98 Acres. Total construction area for the project is around 8, 47,786 Sq.F.This building is constructed by composite construction usingsteel structure,R.C.Candblockworks. The climbing form works system is used for shear walls and lift core walls due to rapid construction cycle. The formwork is crane guided climbing system which used crane for shifting to upper levels. RMD KWIK rapid climbformwork systemsis used in this project. This system comprises of working platform, formwork and ladder components. Tower crane is required for initial setup of the system, lifting and dismantling of the formwork system. SPEED - Climbing bracket connects to wall with recoverable anchor screw -no lost parts. Reduced crane time in moving forms. Platform and formwork are crane handled in one single operation. Speeds up concrete cycle, reducing program time on multi- floor builds. Eliminates the need to lay down form for cleaning and enables cores to be constructed in advance. SAFETY - Self-contained working levels for economical core forming. No tripping hazard on working platform - the decking boards are at the same level as the top of the climbing bracket. Corner platforms neatly abut one another. 8.7. CASE STUDY INFERENCE For the case studies we can understandthattheselfclimbing formworks are used in combination with other panel formwork system and protection screens. Self climbing formwork when used with the combination of aluminium formwork can be economical. The self climbing formwork is mostly used in the construction of lift cores. The construction is done in two or more phases and the lift core is constructed first this is called core structure preceeding construction method. The planning of the building significantly affects the form work cost so proper preplanning in required. Form work cost of Walls withmore Length, thickness and distance between each other is economical compared to that of walls with lesser distance between each other. 9.PROPOSAL SITE Proposed High-living District is a residential complex consisting of three residential skyscrapers in the neighborhood of in Chennai, India. which is the tallest residential building in Chennai. Tower B is selected for application of self climbing form work. The project has 75 floors. at site they have used S type aluminum formwork with an average of 12 days / floor construction cycle. In the proposal we are going to use selfclimbingformwork forcore structure, advanced panel formwork for walls and slabs, steel safety protection screen. Sl.No Criteria Area in Sq.M 1 Plinth area ( 1 floor) 1197.4 2 Built up area ( 1 floor) 996.4 3 Carpet area( 1 floor) 836 4 Plinth area for 75 floors 89,805 Table 4 -: Proposed tower B Area 9.1 cost assumptions Cost assumptions Cost per Sq.M Cost per Sq.F Aluminum formwork MIVAN - aluminum formwork 8,750 813 Nylon safety net 350 33 Advanced formwork and protection screen Self-climbing form work 95,000 11,148 Safety protection screen 14,500 1,347 Advanced panel formwork For Wall 25,000 2,323 Advanced panel formwork For slabs 15,000 1,394 Table 5 -: Cost assumptions data for aluminum and advanced formwork system This data is based on values collected from various industry professionals and from case studies. These values may vary based on location. This data is for Chennai and may subject to change based on the manufactures and models. 9.2 R.C.C COST Sl. No Description of the item Unit Qty. Rate total 1 STEEL REINFORCEMENT 1.1 core wall Kg 8054 ₹ 90 ₹ 7,22,050 1.2 Interior and exterior walls Kg 64119 ₹ 90 ₹ 57,48,309 1.3 roof slab and balconies Kg 23501 ₹ 90 ₹ 21,06,824 2 CONCRETE WORKS
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 287 2.1 core wall Cu.M 54 ₹ 10,222 ₹ 5,51,972 2.2 Interior and exterior walls Cu.M 430 ₹ 10,222 ₹ 43,94,300 2.3 roof slab and balconies Cu.M 176 ₹ 10,222 ₹ 18,00,041 3 CENTERING AND SHUTTERING 3.1 core wall Sq.M 777 ₹ 670 ₹ 5,20,240 3.2 Interior and exterior walls Sq.M 3587 ₹ 670 ₹ 24,01,897 3.3 roof slab and balconies Sq.M 1179 ₹ 670 ₹ 7,89,115 A TOTAL COST ₹ 1,90,34,748 Table 6 -: Steel, Concrete and Shuttering cost. 9.3 ALUMINUM FORM WORK - SITE At site the S-Type aluminum form work is done and for site safety nylon safety nets are used Sl.No Description of the item Unit Qty. Rate total 1 ALUMINIUM FORM WORK 1.1 core wall Sq.M 777 ₹ 457 ₹ 3,54,972 1.2 Interior and exterior walls Sq.M 3587 ₹ 457 ₹ 16,38,872 1.3 roof slab and balconies Sq.M 1179 ₹ 457 ₹ 5,38,432 2 ALUMINIUM SHEET 2.1 core wall Sq.M 777 ₹ 8,500 ₹ 66,04,500 2.2 Interior and exterior walls Sq.M 3587 ₹ 8,500 ₹ 3,04,92,308 2.3 roof slab and balconies Sq.M 1179 ₹ 8,500 ₹ 1,00,17,894 3 NYLON SAFETY NET 3.1 Providing nylon safety net Sq.M 1269 ₹ 350 ₹ 4,44,036 B TOTAL FORMWORK & SAFETY NET COST FOR ONE FLOOR ₹ 5,00,91,014 4 1% LIFTING CHARGES 4.1 MATERIAL AND LIFTING CHARGES FOR 1 - 5 FLOORS ₹ 9,51,73,742 4.2 FORMWORK LIFTING CHARGES FOR 1 - 5 FLOORS ₹ 5,00,91,014 4.3 MATERIAL AND LIFTING CHARGES FOR 6 - 75 FLOORS ₹ 1,91,63,48,748 4.4 FORMWORK LIFTING CHARGES FOR 6 - 75 FLOORS ₹ 5,04,29,798 C (R.C.C COST + ALUMINUM FORMWORK + LIFTING) TOTAL ₹ 2,11,20,43,303 Table 7 -: Aluminum formwork and safety net cost. 9.4. ADVANCED FORMWORK - PROPOSAL For proposal we use combinations of Hi-end advanced formwork systems and 1. Self climbing form work for core walls, 2. wall & slab panel formwork. 3. Steel protection screen for safety 5 ADVANCED FORMWORK FORM WORK Sl.N o Descriptio n of the item Unit Qty. Rate total A SELF CLIMBING FORMWORK SYSTEM 5.1 core wall Sq.M 777 ₹ 95,000 ₹ 7,38,15,000 B PANEL FORMWORK SYSTEM 5.2 Interior and exterior walls Sq.M 358 7 ₹ 15,000 ₹ 5,38,09,954 5.3 roof slab and balconies Sq.M 117 9 ₹ 15,000 ₹ 1,76,78,637 6 SAFETY PROTECTION SCREEN 6.1 steel safety protection screen Sq.M 126 9 ₹ 14,500 ₹ 1,83,95,764 B TOTAL FORMWORK ₹ 16,36,99,355 8 1% LIFTING CHARGES
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 288 8.1 MATERIAL AND LIFTING CHARGES FOR 1 - 5 FLOORS ₹ 9,51,73,742 8.2 FORMWORK LIFTING CHARGES FOR 1 - 5 FLOORS ₹ 16,36,99,355 8.3 MATERIAL AND LIFTING CHARGES FOR 6 - 75 FLOORS ₹ 1,91,63,48,748 8.4 FORMWORK LIFTING CHARGES FOR 6 - 75 FLOORS ₹ 16,48,06,514 9 (R.C.C COST + ADVANCED FORMWORK + LIFTING) TOTAL ₹ 2,34,00,28,360 Table 7 -: Aluminum formwork and safety net cost. 9.5 BASELINE COST DIFFERENCE FOR 1 FLOOR The increase percentage is 164 % higher than the aluminum formwork when compared with advancedformwork system Table 8 -: Baseline Cost difference for 1 floor (R.C.C and Formwork) 9.6 TOTAL COST DIFFERENCE The increase percentage is 10.7945 % higher than the aluminium form work in case we use the combination of Hi- end advanced formwork system and protection screen. Sl.No FORMWORK TYPE COST 1 ALUMINIUM FORMWORK Approx...₹ 2,11 Cr 2 ADVANCED FORMWORK Approx...₹ 2,34 Cr 3 INCREASE ₹ 22,79,85,057 Figure -2: Schedule for Aluminum formwork (12 days / floor cycle) 9.8 CONSTRUCTION SCHEDULE ADVANCED FORMWORK (9 DAYS / FLOOR CYCLE) Figure -3: Schedule for Advanced formwork (9 days / floor cycle) 9.9. TIME DIFFERENCE The duration difference is around 7 months in super structure construction. SUPERSTRUCTURE SL.NO FORMWORK TYPE DAYS MONTHS YEAR 1 ALUMINIUM FORMWORK 952 32 2.6 2 ADVANCED FORMWORK 729 24 2.0 3 DURATION DIFFERENCE 223 7 0.6 Table 10 -: Duration difference Sl.No Description Aluminium form work Advanced formwork Cost Increase 1 Staircase and lift core ₹ 87,53,726 ₹ 7,56,09,253 ₹ 6,68,55,528 2 Interior and exterior wall ₹ 4,46,75,685 ₹ 6,63,54,460 ₹ 2,16,78,775 3 Roof slab and balconies ₹ 1,52,52,307 ₹ 2,23,74,618 ₹ 71,22,310 4 safety ₹ 4,44,036 ₹ 1,83,95,764 ₹ 1,79,51,728 5 total ₹ 6,91,25,754 ₹ 18,27,34,095 ₹ 11,36,08,341 9.7.CONSTRUCTIONSCHEDULEALUMINUMFORMWORK (12 DAYS / FLOOR CYCLE) Table 9 -: Total cost difference or (R.C.C, Formwork and lifting charges)
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 289 9.10. COMPARISON TABLE SI.NO DESCRIPTION ALUMINIUM FORMWORK ADVANCED FORMWORK 1 Construction cycle 12 days 9 days 2 Formwork combination Wall and slab- S type - monolithic Aluminum Formwork Protection – nylon Safety net Wall – RCS (Rail Climbing Formwork) Slab – Advanced form work Protection - protection screen 3 Dimensional variations Nil Nil 4 Finish quality Finishing Lines will be visible High Quality finish 5 Initial investments High Very high 6 No. of labors High Nos required High Nos required 7 Skilled Labor Skilled/unskilled Highly Skilled/unskilled 8 Tower crane Not required Required for installing and dismantling 9 Safety during execution Moderate safety Very safe 10 Waste production medium Zero 11 Complexity of tools Available on demand Training & proper monitoring required 12 Repetitions 200-250 times 120 times 13 Scrap Value 30% 40 – 50 % 14 Repair cost repair is impossible after the deformation Can be repaired (30-35 % of the total cost) Table 9 -: Comparative table (Aluminum formwork & advanced formwork) 10. FINDINGS The cost differences is 10.7945 % higher by using combination of advanced form work system and protection screens compared to MIVAN form work system. The duration of construction is also affected significantly in the superstructure by saving 7 months. The self-climbing formwork is only suitable for sites and cities with limited space constraints and for site where the safety and qualityis the highest priority however cost is compromised. Self- climbing formwork is also suitable for projects where the speed, safety and quality of construction is the first priority. 11. CONCLUSION From the study it is clear from the study that the self- climbing formwork is expensive but by proper planning and using the self-climbing form work with other economical form works cost can be significantly reduced. From this study we could get an overall understanding of the self- climbing formwork used in various high-rise construction projects in India. This proposal study is done for exploring the possibility of incorporating self-climbing formwork in Chennai. It shows how the self-climbing formwork even though expensive can save time considerably with good quality and safety aspects. Self-climbing formwork can be ideal for densely populated locations there is space constrains. 12. RECOMMENDATIONS Proper Planning and designing is crucial for cutting cost by using advanced formwork system the Formwork cost is usually high for walls and spaces which has shorter length and distance between each other. Advanced formwork system is very efficient for Hi- End residential studio apartments or commercial skyscraper projects with more number of cores and for tall rapid construction projects. By using combination of self-climbing formwork for core and aluminum formwork for walls and slabs instead of panel formwork system cost can be efficiently reduced. Self- climbing formwork can help in fast paced construction projects. Since it has shorter construction cycle. REFERENCES [1] Neenu S K, "How climbing formwork makes concrete construction ?", Theconstructor.org [2] Jonathan Kozlowski, "7 Facts On Self-Climbing Concrete Forming Systems", December 10, 2021, www.forconstructionpros.com [3] Amitabh kumar, Amit singhal, "High Rise SKY Towers, Mumbai -construction challenges", 2011, global.ctbuh.org [4] Ms. A. C. Gawali , Ms. N. D. Kolpe , Ms. S. M. Petekar , Prof. S. M. Barelikar, "Comparative Study of Jump Formwork with Conventional Formwork" [5] AhkimMakmun,"DOKA’sGenNextformwork technology at Omkar 1973", March 22,2014, www.doka.com [6] Doka, "Omkar 1973 Worli",www.doka.com
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 290 [7] Vinod Jacob Chacko, Gopi Kannan. S, "HELMET - EHS journal of L&T Construction (Volume - 6, Issue - 3)",July - September 2016, eip.lntecc.com [8] Dhruv Patel, "Understanding Core HighRise |Lodha The Park, Mumbai", 2019, portfolio.cept.ac.in [9] CTBUH, "Lodha the Park Complex", 14 December 2021, CTBUH Skyscraper Center [10] Peri, "Lodha - The Park, Mumbai", www.peri.in [11] CTBUH,"World One", CTBUH Skyscraper Center [12] Peri,"World One tower, Mumbai", www.peri.in [13] Joshi, Manas,"Mumbai's iconic Palais Royale tower in Worli to be re-auctioned at slashed rate", 14 April 2020, www.indiatvnews.com [14] Meva,"Green project Palais RoyaleinMumbai",meva.net [15] CTBUH, "Palais Royale, Mumbai", CTBUH Skyscraper Center [16] projects today,"CtrlS Datacenters to set up Data Centre in Chennai", 24 May 2022, www.projectstoday.com [17] Rmdkwikform,"Rapidclimb", www.rmdkwikform.com [18] Sprindia, "HIGHLIVING DISTRICT - TOWER B APARTMENTS", sprindia.com [19] Sprindia,"SPR 360˚ - (newsletter edition 01 - 14)", June 15 2018 - October 18 2019, issuu.com.