SlideShare a Scribd company logo
1 of 17
Selection of Roof Casting Formwork
Systems for the Bird
Island Project: Case Study
Presentors:
Muhammad Umar nazir (cn-015)
Imran naeem (cn-012)
Selection of Roof Casting Formwork Systems for the
Bird
Island Project: Case Study
• Authors:
Tariq Abdelhamid, Ph.D
Mohamed El-Gafy, Ph.D, P.E
Panagiotis Mitropoulos, Ph.D
• JOURNAL:
PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND
CONSTRUCTION © ASCE / NOVEMBER 2009
Contents
• Abstract
• Scope
• Summary
• Objective
• Methodology
• Literature Review
• Data Analysis
• Conclusions
ABSTRACT
• Formwork is a major contributor to profitability—or the lack of it—on most large
and complex concrete jobs.
• Formwork has major consequences for the project schedule, as well as all related
trades, such as ironworkers and cement finishers.
• Consequently, selecting a formwork system and planning its field operations must
consider the effects of the system on the overall project.
• This may result in significant difficulties in meeting the project requirements.
• The paper illustrates the complexities involved in the selection and deployment of a
formwork
SCOPE
• This paper reports on an in-depth study of the formwork system selection
problem on the Bird Island Flats Tunnel project.
• The project is a part of the Central Artery/Tunnel project in Boston,
Massachusetts.
SUMMARY
• The challenge on this $290 million project was the budget and schedule requirements for the
tunnel roofs.
• The width and thickness of the roofs were on average 18.29 m 60 ft and 2.44 m 8 ft,
respectively.
• The conventional shoring methods were not able to keep the project on time for critical
interim milestones as well as on budget.
• The alternative forming systems available did not provide a solution because of the time
and effort required for setup and takedown operations.
• The management team solicited proposals from formwork manufacturers, and chose the
system from CONESCO Industries.
OBJECTIVE
• This study has two objectives:
• First to identify the issues involved in the selection and
sequencing of a custom-made formwork system
• Second to formulate a detailed analysis method to
improve decision-making.
METHODOLOGY
• The paper consists of two parts.
• The first part describes the project and presents the issues involved in the selection
of the formwork system. It identifies the complexities of the decisions that faced
the construction team, and describes how the selection was made and how the final
decision came about.
• The second part presents analytical methods and techniques to support the
decision-making process. A detailed analysis and comparison of formwork systems
is performed that accounts for all the key formwork parameters. Such analysis is
necessary in order to select the best system for the project.
LITERATURE REVIEW
• Conventional System
The conventional system available consisted of a number of aluminum joists
that are supported by standard I beams. The concrete is poured against 2.3 cm
3/4 in. plywood that is placed on the aluminum joist. The concrete, plywood,
aluminum joists, and standard I beams are supported on steel shoring legs. The
system is very similar to scaffolds used for work done at high elevations. The
systems available were categorized by the capacity of the shoring legs. 10, 25,
and 100 kip/leg shoring systems were available. The cross section and layout of
such a system is shown in Fig.
CONVENTIONAL FORMWORK
LITERATURE REVIEW
• CONESCO Roof Casting Machines
• The winning proposal for a formwork system called the “Roof Casting Machines”
was submitted by the CONESCO Corporation. Each Roof Casting Machine
consisted of two major components, a self-propelled traveler and the form set. The
traveler is a three-dimensional rectangular frame equipped with a gasoline engine
which makes it able to transport the custom form set to its desired location.
Hydraulic cylinders on the traveler are used for initial horizontal and vertical
adjustments of the form sets. The form set is also equipped with hydraulic cylinders
for further adjustment. A detailed illustration of the traveler and form set is shown
in Fig.
CONESCO ROOF CASTING MACHINE
Machine Types with Height and Width Changes
MACHINE
TYPE
HEIGHT
(meters)
WIDTH
(meters)
TRAVELLER
MIN MAX MIN MAX
I A 7.43 9.54 11.43 15.70 I A
I B 5.53 7.56 11.43 15.70 I B or II B
II A 7.41 7.60 12.95 22.71 II A or II B
II B 5.18 9.34 12.80 22.56 II B
III 6.28 9.05 17.53 28.50 III
CONESCO ROOF CASTING MACHINE
ANALYSIS
• M/O started the system evaluation process by comparing the available
conventional shoring systems and the CONESCO casting machines.
• This comparison was based on operating cost, acquisition cost, technical
performance of the systems, and ability to adjust formwork to tunnel
dimensions.
• The records we have state $4,772,300 in net savings, and 36 weeks saved in
schedule time, when comparing the conventional system to the CONESCO
casting machines
ANALYSIS
CONVENTIONAL CONESCO DIFFERENCE
COST ($) 1,500,000 3,500,000 -2,000,000
PRODUCTION
(m2/MH)
.42 1.62 1.2
MAN HOURS (MH)
REQUIRED
164,900 28,473 136427
TIME (WEEKS) 86 50 36 (8 months)
MH COST (50$/MH) 8,245,000 1,423,650 6,821,350
TOTAL COST ($) 9,745,000 4,923,650 4,821,350
CONCLUSIONS
• The case study has focused on time and cost related to the use of three different
formwork systems.
• A time-cost trade–off analysis was also followed when investigating alternative
sequencing schemes for the one system that was selected using computer
simulation.
• Contractors in projects involving nonconventional formwork must carefully
consider the implications of formwork systems selection and sequencing of
concrete casting operations.
• The use of simulation in this study reveals its utility to a long-term and
comprehensive approach to planning and management.

More Related Content

What's hot

IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...IRJET Journal
 
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) 5006
 
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...eSAT Journals
 
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...firdaus Muhammad Adnan
 
Design steps of structure.
Design steps of structure.Design steps of structure.
Design steps of structure.Hatindera Singh
 
Chapter02.structural design using staad pro
Chapter02.structural design using staad proChapter02.structural design using staad pro
Chapter02.structural design using staad proKenylNguyen
 
Seismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codesSeismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codeseSAT Journals
 
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...IRJET Journal
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...Pratik R. Atwal
 
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET Journal
 
M3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTERM3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTERVasilis Lyras
 
Introduction to prefabricated structures
Introduction to prefabricated structuresIntroduction to prefabricated structures
Introduction to prefabricated structuresAtharva Naik
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaGurjant Singh
 
Structural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive ManufactureStructural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive ManufactureAltair
 
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...IRJET Journal
 

What's hot (20)

IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
 
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981) OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
OBJECTIVES OF SITE INVESTIGATION BASED ON BS 5930 (1981)
 
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...Design of waste heat driven vapour adsorption cooling system for vehicle air ...
Design of waste heat driven vapour adsorption cooling system for vehicle air ...
 
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
WIND LOAD DESIGN OF STEEL STRUCTURE ON ROOF TOP UNDER QCS 2014 CASE STUDY : O...
 
Design steps of structure.
Design steps of structure.Design steps of structure.
Design steps of structure.
 
Chapter02.structural design using staad pro
Chapter02.structural design using staad proChapter02.structural design using staad pro
Chapter02.structural design using staad pro
 
Company profile
Company profileCompany profile
Company profile
 
Seismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codesSeismic design of multistoreyed rc building using various codes
Seismic design of multistoreyed rc building using various codes
 
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
IRJET- Comparative Study of Flat Slab Structure and Conventional Slab Structu...
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Dbr kashmiri gate
Dbr kashmiri gateDbr kashmiri gate
Dbr kashmiri gate
 
Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...Analysis and design of pre engineered building using is 800:2007 and Internat...
Analysis and design of pre engineered building using is 800:2007 and Internat...
 
Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro. Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro.
 
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
IRJET- Design and Analysis of Residential Multistory Building (G+5) by using ...
 
construction management
construction managementconstruction management
construction management
 
M3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTERM3C3098_LYRAS_POSTER
M3C3098_LYRAS_POSTER
 
Introduction to prefabricated structures
Introduction to prefabricated structuresIntroduction to prefabricated structures
Introduction to prefabricated structures
 
Six week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc LudhianaSix week software training ppt at Tcc Ludhiana
Six week software training ppt at Tcc Ludhiana
 
Structural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive ManufactureStructural Component Design Optimization for Additive Manufacture
Structural Component Design Optimization for Additive Manufacture
 
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
IRJET- Wave Analysis of Rubble Mound Steel-Concrete-Steel Sandwich Seawall in...
 

Similar to Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study

Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...IRJET Journal
 
Final project report
Final project reportFinal project report
Final project reportAnkit Sutaria
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System ashleyyeap
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKSameer Malvankar
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...IRJET Journal
 
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...ijtsrd
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfOmarSAlAbri
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfOmarSAlAbri
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraProSIM R & D Pvt. Ltd.
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingRoshni Ramakrishnan
 
ADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptxADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptxfdpnitkce19
 
IRJET- Temperature Effect on Concrete Bridge
IRJET-  	  Temperature Effect on Concrete BridgeIRJET-  	  Temperature Effect on Concrete Bridge
IRJET- Temperature Effect on Concrete BridgeIRJET Journal
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET Journal
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Ramin Vaghei
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017Czero
 
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...IRJET Journal
 
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...Cheryl Brown
 

Similar to Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study (20)

Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
Comparative Study of MIVAN Formwork with Tunnel form System for High Rise Bui...
 
Final project report
Final project reportFinal project report
Final project report
 
CT III IBS Formwork System
CT III IBS Formwork System CT III IBS Formwork System
CT III IBS Formwork System
 
July2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORKJuly2013 MASTERBUILDERS- FORMWORK
July2013 MASTERBUILDERS- FORMWORK
 
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...Introduction to advanced TUNNEL Formwork system: Case study of  ‘Rohan - Abhi...
Introduction to advanced TUNNEL Formwork system: Case study of ‘Rohan - Abhi...
 
Resume 5 13 16 months
Resume 5 13 16 monthsResume 5 13 16 months
Resume 5 13 16 months
 
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
Design Optimization of Reinforced Concrete Slabs Using Various Optimization T...
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
SPE-96655-MS (1).pdf
SPE-96655-MS (1).pdfSPE-96655-MS (1).pdf
SPE-96655-MS (1).pdf
 
Overview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _VhoraOverview of Technology Development _ S_ F _Vhora
Overview of Technology Development _ S_ F _Vhora
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
 
ADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptxADCS Full ppt-Lec 1-5 - Copy.pptx
ADCS Full ppt-Lec 1-5 - Copy.pptx
 
IRJET- Temperature Effect on Concrete Bridge
IRJET-  	  Temperature Effect on Concrete BridgeIRJET-  	  Temperature Effect on Concrete Bridge
IRJET- Temperature Effect on Concrete Bridge
 
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...IRJET-  	  Experimental Study of Structural Behaviour of Double Skin Hollow –...
IRJET- Experimental Study of Structural Behaviour of Double Skin Hollow –...
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
IRJET- Study & Improvement of Design and Construction Methodology of Precast ...
 
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
An Investigation Into Design And Manufacturing Of Mechanical Conveyors System...
 

Recently uploaded

办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfSumit Lathwal
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一Fi sss
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Sitegalleryaagency
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiSuhani Kapoor
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girlsssuser7cb4ff
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailDesigntroIntroducing
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)jennyeacort
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Douxkojalkojal131
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CANestorGamez6
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...narwatsonia7
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxnewslab143
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Servicejennyeacort
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 

Recently uploaded (20)

办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
Architecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdfArchitecture case study India Habitat Centre, Delhi.pdf
Architecture case study India Habitat Centre, Delhi.pdf
 
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
(办理学位证)埃迪斯科文大学毕业证成绩单原版一比一
 
How to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our SiteHow to Be Famous in your Field just visit our Site
How to Be Famous in your Field just visit our Site
 
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Harsh Vihar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Pandav nagar 🔝 9953056974 🔝 Delhi escort Service
 
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service AmravatiVIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
VIP Call Girl Amravati Aashi 8250192130 Independent Escort Service Amravati
 
Call Girls Meghani Nagar 7397865700 Independent Call Girls
Call Girls Meghani Nagar 7397865700  Independent Call GirlsCall Girls Meghani Nagar 7397865700  Independent Call Girls
Call Girls Meghani Nagar 7397865700 Independent Call Girls
 
NATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detailNATA 2024 SYLLABUS, full syllabus explained in detail
NATA 2024 SYLLABUS, full syllabus explained in detail
 
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
Call Us ✡️97111⇛47426⇛Call In girls Vasant Vihar༒(Delhi)
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai DouxDubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
Dubai Call Girls Pro Domain O525547819 Call Girls Dubai Doux
 
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
SCRIP Lua HTTP PROGRACMACION PLC  WECON CASCRIP Lua HTTP PROGRACMACION PLC  WECON CA
SCRIP Lua HTTP PROGRACMACION PLC WECON CA
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
Housewife Call Girls NRI Layout - Call 7001305949 Rs-3500 with A/C Room Cash ...
 
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptxIntroduction-to-Canva-and-Graphic-Design-Basics.pptx
Introduction-to-Canva-and-Graphic-Design-Basics.pptx
 
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts ServiceCall Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
Call Girls In Safdarjung Enclave 24/7✡️9711147426✡️ Escorts Service
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 

Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study

  • 1. Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study Presentors: Muhammad Umar nazir (cn-015) Imran naeem (cn-012)
  • 2. Selection of Roof Casting Formwork Systems for the Bird Island Project: Case Study • Authors: Tariq Abdelhamid, Ph.D Mohamed El-Gafy, Ph.D, P.E Panagiotis Mitropoulos, Ph.D • JOURNAL: PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2009
  • 3. Contents • Abstract • Scope • Summary • Objective • Methodology • Literature Review • Data Analysis • Conclusions
  • 4. ABSTRACT • Formwork is a major contributor to profitability—or the lack of it—on most large and complex concrete jobs. • Formwork has major consequences for the project schedule, as well as all related trades, such as ironworkers and cement finishers. • Consequently, selecting a formwork system and planning its field operations must consider the effects of the system on the overall project. • This may result in significant difficulties in meeting the project requirements. • The paper illustrates the complexities involved in the selection and deployment of a formwork
  • 5. SCOPE • This paper reports on an in-depth study of the formwork system selection problem on the Bird Island Flats Tunnel project. • The project is a part of the Central Artery/Tunnel project in Boston, Massachusetts.
  • 6. SUMMARY • The challenge on this $290 million project was the budget and schedule requirements for the tunnel roofs. • The width and thickness of the roofs were on average 18.29 m 60 ft and 2.44 m 8 ft, respectively. • The conventional shoring methods were not able to keep the project on time for critical interim milestones as well as on budget. • The alternative forming systems available did not provide a solution because of the time and effort required for setup and takedown operations. • The management team solicited proposals from formwork manufacturers, and chose the system from CONESCO Industries.
  • 7. OBJECTIVE • This study has two objectives: • First to identify the issues involved in the selection and sequencing of a custom-made formwork system • Second to formulate a detailed analysis method to improve decision-making.
  • 8. METHODOLOGY • The paper consists of two parts. • The first part describes the project and presents the issues involved in the selection of the formwork system. It identifies the complexities of the decisions that faced the construction team, and describes how the selection was made and how the final decision came about. • The second part presents analytical methods and techniques to support the decision-making process. A detailed analysis and comparison of formwork systems is performed that accounts for all the key formwork parameters. Such analysis is necessary in order to select the best system for the project.
  • 9. LITERATURE REVIEW • Conventional System The conventional system available consisted of a number of aluminum joists that are supported by standard I beams. The concrete is poured against 2.3 cm 3/4 in. plywood that is placed on the aluminum joist. The concrete, plywood, aluminum joists, and standard I beams are supported on steel shoring legs. The system is very similar to scaffolds used for work done at high elevations. The systems available were categorized by the capacity of the shoring legs. 10, 25, and 100 kip/leg shoring systems were available. The cross section and layout of such a system is shown in Fig.
  • 11. LITERATURE REVIEW • CONESCO Roof Casting Machines • The winning proposal for a formwork system called the “Roof Casting Machines” was submitted by the CONESCO Corporation. Each Roof Casting Machine consisted of two major components, a self-propelled traveler and the form set. The traveler is a three-dimensional rectangular frame equipped with a gasoline engine which makes it able to transport the custom form set to its desired location. Hydraulic cylinders on the traveler are used for initial horizontal and vertical adjustments of the form sets. The form set is also equipped with hydraulic cylinders for further adjustment. A detailed illustration of the traveler and form set is shown in Fig.
  • 13. Machine Types with Height and Width Changes MACHINE TYPE HEIGHT (meters) WIDTH (meters) TRAVELLER MIN MAX MIN MAX I A 7.43 9.54 11.43 15.70 I A I B 5.53 7.56 11.43 15.70 I B or II B II A 7.41 7.60 12.95 22.71 II A or II B II B 5.18 9.34 12.80 22.56 II B III 6.28 9.05 17.53 28.50 III
  • 15. ANALYSIS • M/O started the system evaluation process by comparing the available conventional shoring systems and the CONESCO casting machines. • This comparison was based on operating cost, acquisition cost, technical performance of the systems, and ability to adjust formwork to tunnel dimensions. • The records we have state $4,772,300 in net savings, and 36 weeks saved in schedule time, when comparing the conventional system to the CONESCO casting machines
  • 16. ANALYSIS CONVENTIONAL CONESCO DIFFERENCE COST ($) 1,500,000 3,500,000 -2,000,000 PRODUCTION (m2/MH) .42 1.62 1.2 MAN HOURS (MH) REQUIRED 164,900 28,473 136427 TIME (WEEKS) 86 50 36 (8 months) MH COST (50$/MH) 8,245,000 1,423,650 6,821,350 TOTAL COST ($) 9,745,000 4,923,650 4,821,350
  • 17. CONCLUSIONS • The case study has focused on time and cost related to the use of three different formwork systems. • A time-cost trade–off analysis was also followed when investigating alternative sequencing schemes for the one system that was selected using computer simulation. • Contractors in projects involving nonconventional formwork must carefully consider the implications of formwork systems selection and sequencing of concrete casting operations. • The use of simulation in this study reveals its utility to a long-term and comprehensive approach to planning and management.