SlideShare a Scribd company logo
1 of 16
GUJARAT TECHNOLOGICAL UNIVERSITY
Chandkheda , Ahmedabad
Affiliated
S. N. PATEL INSTITUTE OF TECHNOLOGY & RESEARCH
CENTER, UMRAKH
SUBJECT: Professional Practice & Valuation
TOPIC: Types of estimation
Guided By
Bhavin Kashiyani
 PREPERED BY:
SR NO NAME ENROLLMENT NO
1 Modi Nagma R. 130490106065
2 Patel Aayushi Y. 130490106072
3 Patel Kishan J. 130490106079
4 Savaj Sunny G. 130490106103
5 Patel Aashish D. 140493106016
 TYPES OF ESTIMATION:
 Different types of estimates are as follows:
1. Approximate estimate or preliminary Estimate
2. Detailed Estimate
3. Quantity Estimate
4. Revised Estimate
5. Supplementary Estimate
6. Supplementary and Revised Estimate
7. Annual repair or Maintenance Estimate
 APPROXIMATE ESTIMATE:
 Regarded as the most reliable and
accurate method of estimating,
provided that there is sufficient
information to work on.
Depending on the experience of the surveyor,
measurement can be carried out fairly quickly using
composite rates to save time.
 The rules of measurement are simple, although it must
be said; they are not standardized and tend to vary
slightly from one surveyor to another.
 Preliminary study of the project
 Administrative approval
 To investigate feasibility
 To get loan from bank
 For insurance purpose
 For deciding taxes
 To decide rent of a building
 PURPOSE OF APPROXIMATE ESTIMATE:
 DETAILED ESTIMATE:
• This estimate is an accurate and is based on
the plan and sanctions of the building.
• This include the detailed particulars for the
quantities, rate and cost of all the items
involved for satisfactory completion of a
project
• Quantities of all items of work are calculated
from their respective dimension on the
drawing on a measurement sheet .multiplying
these quantities by their respective rate in
separate sheet, the cost of all items of work
are worked out individually and then
summarized
 A detail estimate is accompanied by
 Report
 Specification
 Detailed drawing showing plane Design data and calculation
 Basis of rates adopted in the estimate
 QUANTITY ESTIMATE:
• This is complete estimate or list
of quantities for all items of work
required to complete the concerned
project.
• The quantity of each individual items of work is worked
out form respective dimensions on the drawing of the
structure to find the cost of an item in quantity is
multiplied by the rate per unit from that item.
• The purpose of the bill quantity i.e. to provide a
complete list of quantities necessary for the competition
of any engineering project and when price given to the
estimated cost of the project
 REVISED ESTIMATE:
• IT Is also a detailed estimate and is prepared a fresh
when the original sanctioned detailed estimate exceeds
by 10% or more ,either due to rates being found
insufficient or due to some other reasons
• It is always possible that in spite of
all precaution in the planning stages
it becomes clearly during execution
the actual cost of a project will exceed
the original estimate, now generally
a certain cushion of the cost is available,
if the exceedance is higher
 SUPPLYMENTARY ESTIMATE:
• This is a fresh detailed estimate of the additional
work in additional work in addition to the original
one and is prepared when additional work is
required to supplement the original work
• There is always a like hood that while executing a
certain project it may be considered worthwhile to
carry out additional work ,which was not foreseen
in initial stages and therefore not actual for the
preliminary estimate
• Execution of such work required drawing up and
approval of supplementary estimate and the exercise is
essential similar to that of drawing up the estimate for
the main work it is naturally expected that the cost of
additional work will be much smaller than the main
work
• But in case where the saving is due to a material
deviation of structural nature from the design originally
approved supplement estimate is prepared for a revised
technical sanction
• The method of preparation of supplementary estimate
is the same as that of detail estimate and it should be
accompanied by full report of the circumstances which
render it necessity.
 SUPPLEMENTARY AND REVISED ESTIMATE:
 When a work is partially abandoned and the estimated
cost of the remaining work is less than 95% of the
original work,or when there are material deviations and
changes in design which may cause substantial saving in
the estimate , then the amount of the original estimate
is revised by the competent authority.
A supplementary and revised estimate
is the prepared and fresh technical
sanction of the competent authority
is obtained
 ANNUAL REPAIR OR MAINTENANCE
ESTIMATE:
 Annual Repair estimate is called detailed estimate and is
prepared to maintain the structure or work in proper
order and safe condition.
 For building this includes,
1.White washing
2.Colour washing
3.Painting of doors and windows
4.Minor repairs,etc
 For road works A.R. estimate includes,
1.patch repairing
2.renewals
3.repair bridges
4.repairof culverts etc.
For building,the quantities are based on the previous
measurements recorded in the standard M.B. for petty work,
such as replacement of glass panes,repairs of floors,patch repair
to cement plaster to walls etc.whose repairs can not be
estimated in the beginning only lump sum provision is made for
different items in the estimate.
 Professional Practice & Valuation (Atul Publication)
 REFRENCES:
Ppv ppt

More Related Content

What's hot

What's hot (20)

Design period
Design periodDesign period
Design period
 
Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)Highway Drainage (Highway Engineering)
Highway Drainage (Highway Engineering)
 
Geometric design
Geometric designGeometric design
Geometric design
 
Population forecasting methods
Population forecasting methodsPopulation forecasting methods
Population forecasting methods
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
Valuation
ValuationValuation
Valuation
 
Flood routing
Flood routingFlood routing
Flood routing
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Cross Drainage Works
Cross Drainage WorksCross Drainage Works
Cross Drainage Works
 
Lined canal ppt
Lined canal ppt Lined canal ppt
Lined canal ppt
 
Embankment
EmbankmentEmbankment
Embankment
 
Highway Drainage System
Highway Drainage SystemHighway Drainage System
Highway Drainage System
 
Geometric design
Geometric designGeometric design
Geometric design
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Unit 2
Unit 2Unit 2
Unit 2
 

Viewers also liked

Retaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structureRetaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structureKavin Raval
 
introduction of intze tank
introduction of intze tankintroduction of intze tank
introduction of intze tankjenish patel
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building constructionKHUSHBU SHAH
 
Foot bridge presentation
Foot bridge presentationFoot bridge presentation
Foot bridge presentationTausif Kauswala
 
Counterfort Retaining Wall
Counterfort Retaining WallCounterfort Retaining Wall
Counterfort Retaining WallKaizer Dave
 
Design of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankDesign of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankShoaib Wani
 
Flat slab design
Flat slab designFlat slab design
Flat slab designMoussa Rili
 
Earthquake resistant building construction
Earthquake resistant building constructionEarthquake resistant building construction
Earthquake resistant building constructiondaspriyabrata3
 

Viewers also liked (12)

Retaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structureRetaining wall - design of reinforced concrete structure
Retaining wall - design of reinforced concrete structure
 
introduction of intze tank
introduction of intze tankintroduction of intze tank
introduction of intze tank
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building construction
 
Foot bridge presentation
Foot bridge presentationFoot bridge presentation
Foot bridge presentation
 
Counterfort Retaining Wall
Counterfort Retaining WallCounterfort Retaining Wall
Counterfort Retaining Wall
 
Watertank
WatertankWatertank
Watertank
 
Flat bottom Overhead Water tank
Flat bottom Overhead Water tankFlat bottom Overhead Water tank
Flat bottom Overhead Water tank
 
Design of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankDesign of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tank
 
Flat slab design
Flat slab designFlat slab design
Flat slab design
 
Earthquake resistant building construction
Earthquake resistant building constructionEarthquake resistant building construction
Earthquake resistant building construction
 
Flat slab ppt
Flat slab pptFlat slab ppt
Flat slab ppt
 
PPT - Powerful Presentation Techniques
PPT - Powerful Presentation TechniquesPPT - Powerful Presentation Techniques
PPT - Powerful Presentation Techniques
 

Similar to Ppv ppt

EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdfBSuresh26
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimationSomashekar S.M
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing Vijay325
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templatesHoa PN Thaycacac
 

Similar to Ppv ppt (20)

EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Project Cost Management for IEM talk on 13 January 2018.
Project Cost Management  for IEM talk on 13 January 2018.Project Cost Management  for IEM talk on 13 January 2018.
Project Cost Management for IEM talk on 13 January 2018.
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
2015 Toronto Section Presentation
2015 Toronto Section Presentation2015 Toronto Section Presentation
2015 Toronto Section Presentation
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Estimation guidelines and templates
Estimation guidelines and templatesEstimation guidelines and templates
Estimation guidelines and templates
 

More from Nagma Modi

Sub soil exploration
Sub soil exploration Sub soil exploration
Sub soil exploration Nagma Modi
 
Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineeringNagma Modi
 
Influence line for structure analysis in civil engineering
Influence line for structure analysis in civil engineeringInfluence line for structure analysis in civil engineering
Influence line for structure analysis in civil engineeringNagma Modi
 
algebric solutions by newton raphson method and secant method
algebric solutions by newton raphson method and secant methodalgebric solutions by newton raphson method and secant method
algebric solutions by newton raphson method and secant methodNagma Modi
 
Energy principle in structure analysis in civil engineering
Energy principle in structure analysis in civil engineeringEnergy principle in structure analysis in civil engineering
Energy principle in structure analysis in civil engineeringNagma Modi
 
design philosophy in structure design in civil engineering
design philosophy in structure design in civil engineeringdesign philosophy in structure design in civil engineering
design philosophy in structure design in civil engineeringNagma Modi
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building constructionNagma Modi
 
Slope deflection method for structure analysis in civil engineering
Slope deflection method for structure analysis in civil engineeringSlope deflection method for structure analysis in civil engineering
Slope deflection method for structure analysis in civil engineeringNagma Modi
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tankNagma Modi
 
Pile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsPile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsNagma Modi
 

More from Nagma Modi (10)

Sub soil exploration
Sub soil exploration Sub soil exploration
Sub soil exploration
 
Irrigation engineering
Irrigation engineeringIrrigation engineering
Irrigation engineering
 
Influence line for structure analysis in civil engineering
Influence line for structure analysis in civil engineeringInfluence line for structure analysis in civil engineering
Influence line for structure analysis in civil engineering
 
algebric solutions by newton raphson method and secant method
algebric solutions by newton raphson method and secant methodalgebric solutions by newton raphson method and secant method
algebric solutions by newton raphson method and secant method
 
Energy principle in structure analysis in civil engineering
Energy principle in structure analysis in civil engineeringEnergy principle in structure analysis in civil engineering
Energy principle in structure analysis in civil engineering
 
design philosophy in structure design in civil engineering
design philosophy in structure design in civil engineeringdesign philosophy in structure design in civil engineering
design philosophy in structure design in civil engineering
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building construction
 
Slope deflection method for structure analysis in civil engineering
Slope deflection method for structure analysis in civil engineeringSlope deflection method for structure analysis in civil engineering
Slope deflection method for structure analysis in civil engineering
 
Stucture Design of various Watre tank
 Stucture Design of various Watre tank Stucture Design of various Watre tank
Stucture Design of various Watre tank
 
Pile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsPile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipments
 

Recently uploaded

welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 

Recently uploaded (20)

welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Ppv ppt

  • 1. GUJARAT TECHNOLOGICAL UNIVERSITY Chandkheda , Ahmedabad Affiliated S. N. PATEL INSTITUTE OF TECHNOLOGY & RESEARCH CENTER, UMRAKH SUBJECT: Professional Practice & Valuation TOPIC: Types of estimation Guided By Bhavin Kashiyani
  • 2.  PREPERED BY: SR NO NAME ENROLLMENT NO 1 Modi Nagma R. 130490106065 2 Patel Aayushi Y. 130490106072 3 Patel Kishan J. 130490106079 4 Savaj Sunny G. 130490106103 5 Patel Aashish D. 140493106016
  • 3.  TYPES OF ESTIMATION:  Different types of estimates are as follows: 1. Approximate estimate or preliminary Estimate 2. Detailed Estimate 3. Quantity Estimate 4. Revised Estimate 5. Supplementary Estimate 6. Supplementary and Revised Estimate 7. Annual repair or Maintenance Estimate
  • 4.  APPROXIMATE ESTIMATE:  Regarded as the most reliable and accurate method of estimating, provided that there is sufficient information to work on. Depending on the experience of the surveyor, measurement can be carried out fairly quickly using composite rates to save time.  The rules of measurement are simple, although it must be said; they are not standardized and tend to vary slightly from one surveyor to another.
  • 5.  Preliminary study of the project  Administrative approval  To investigate feasibility  To get loan from bank  For insurance purpose  For deciding taxes  To decide rent of a building  PURPOSE OF APPROXIMATE ESTIMATE:
  • 6.  DETAILED ESTIMATE: • This estimate is an accurate and is based on the plan and sanctions of the building. • This include the detailed particulars for the quantities, rate and cost of all the items involved for satisfactory completion of a project • Quantities of all items of work are calculated from their respective dimension on the drawing on a measurement sheet .multiplying these quantities by their respective rate in separate sheet, the cost of all items of work are worked out individually and then summarized
  • 7.  A detail estimate is accompanied by  Report  Specification  Detailed drawing showing plane Design data and calculation  Basis of rates adopted in the estimate
  • 8.  QUANTITY ESTIMATE: • This is complete estimate or list of quantities for all items of work required to complete the concerned project. • The quantity of each individual items of work is worked out form respective dimensions on the drawing of the structure to find the cost of an item in quantity is multiplied by the rate per unit from that item. • The purpose of the bill quantity i.e. to provide a complete list of quantities necessary for the competition of any engineering project and when price given to the estimated cost of the project
  • 9.  REVISED ESTIMATE: • IT Is also a detailed estimate and is prepared a fresh when the original sanctioned detailed estimate exceeds by 10% or more ,either due to rates being found insufficient or due to some other reasons • It is always possible that in spite of all precaution in the planning stages it becomes clearly during execution the actual cost of a project will exceed the original estimate, now generally a certain cushion of the cost is available, if the exceedance is higher
  • 10.  SUPPLYMENTARY ESTIMATE: • This is a fresh detailed estimate of the additional work in additional work in addition to the original one and is prepared when additional work is required to supplement the original work • There is always a like hood that while executing a certain project it may be considered worthwhile to carry out additional work ,which was not foreseen in initial stages and therefore not actual for the preliminary estimate
  • 11. • Execution of such work required drawing up and approval of supplementary estimate and the exercise is essential similar to that of drawing up the estimate for the main work it is naturally expected that the cost of additional work will be much smaller than the main work • But in case where the saving is due to a material deviation of structural nature from the design originally approved supplement estimate is prepared for a revised technical sanction • The method of preparation of supplementary estimate is the same as that of detail estimate and it should be accompanied by full report of the circumstances which render it necessity.
  • 12.  SUPPLEMENTARY AND REVISED ESTIMATE:  When a work is partially abandoned and the estimated cost of the remaining work is less than 95% of the original work,or when there are material deviations and changes in design which may cause substantial saving in the estimate , then the amount of the original estimate is revised by the competent authority. A supplementary and revised estimate is the prepared and fresh technical sanction of the competent authority is obtained
  • 13.  ANNUAL REPAIR OR MAINTENANCE ESTIMATE:  Annual Repair estimate is called detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.  For building this includes, 1.White washing 2.Colour washing 3.Painting of doors and windows 4.Minor repairs,etc
  • 14.  For road works A.R. estimate includes, 1.patch repairing 2.renewals 3.repair bridges 4.repairof culverts etc. For building,the quantities are based on the previous measurements recorded in the standard M.B. for petty work, such as replacement of glass panes,repairs of floors,patch repair to cement plaster to walls etc.whose repairs can not be estimated in the beginning only lump sum provision is made for different items in the estimate.
  • 15.  Professional Practice & Valuation (Atul Publication)  REFRENCES: