Contract – Types of contracts – Formation of contract – Contract conditions – Contract for labour, material, design, construction – Drafting of contract documents based on IBRD / MORTH Standard bidding documents – Construction contracts – Contract problems – Arbitration and legal requirements.
Heart Disease Prediction using machine learning.pptx
Contracts - Estimation, Costing and Valuation Engineering
1. SNS COLLEGE OF ENGINEERING & TECHNOLOGY
An Autonomous Institutions
Accredited by NBA – AICTE and Accredited by NAAC – UGC with ‘A’ & ‘A+’Grade
Approved by AICTE, New Delhi & Affiliated to Anna University, Chennai
DEPARTMENT OF CIVIL ENGINEERING
COURSE NAME:
CE8701 - ESTIMATION, COSTING AND VALUATION ENGINEERING
IV YEAR / VII SEMESTER
Unit IV: CONTRACT
Topic : CONTRACT
3. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
A contract is a legally binding document between that defines and
governs the rights and duties of the parties to an agreement.
A contract is legally enforceable because it meets the requirements
and approval of the law.
3/42
4. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
For a CONTRACT to be valid, there must be an offer from the owner in
the form of tender notice to get some specified work to be executed
and there must be an acceptance from the contractor to execute the
work, both the offer and the acceptance must be definite and legal.
Contract Documents
When the tender of a contractor is accepted, an agreement between
the contractor and the owner takes place and the documents defining
the rights and obligations of he owner and the contractor are attached
to the agreement bond and this is called a contract document.
Each page of the contract document bears the signature of the
contractor and the accepting authority and any correction in it is
initialled.
4/42
5. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
The contract document must contain
1. Title page – name of work, name of owner, name of contractor,
contract agreement no., contents, etc.
2. Index page – contents of the agreement with reference pages
3. Tender notice – brief description of work, estimated cost of work,
date and time of receiving tender, amount of EMD and security
deposit, time of completion, etc.
4. Tender form – the bill of quantities, contractor’s rate, total cost of
work, time of completion, amount of security deposit, etc.
5. Schedule of issue of materials – list of materials to be issued by
the owner/department to the contractor with the rates and place of
issue.
5/42
6. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
The contract document must contain
6. Drawings - Complete set of drawings including plan, elevation,
sections, detailed drawings, etc. all fully dimensioned.
7. Specifications
(a) General Specifications - Which specify the class and type of
work, quality of materials, etc.
(b)Detailed specifications - Detailed description of each item of
work including material and method to be used along with the
quality of workmanship required.
6/42
7. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Conditions of contract
1. Rates of each item of work inclusive of materials, labour, transport,
plant/equipment and other arrangements required for completion of
work
2. Amount and form of earnest money and security deposit
3. Mode of payment to contractor including running payment, final
payment and refund of security money, etc.
4. Time of completion of work
5. Extension of time for completion of work Engagement of sub contractor
and other agencies at contractor’s cost and risk.
6. Penalty for poor quality and unsatisfactory work progress.
7. Termination of contract.
8. Arbitration for settlement of disputes.
7/42
8. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Conditions of contract
9. Special conditions – depending upon the nature of work taxes and
royalties included in the rates, labour camp, labour amenities,
compensation to labour in case of accidents, etc.
10. Deed of pledge.
8/42
9. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Classification of Contracts
1. Lump-sum contract
2. Cost plus a fixed percentage contract
3. Cost plus a fixed fee contract
4. Percentage rate contract
5. Item rate contract
6. Turn-key contract
7. Cost plus sliding scale of fees
8. Negotiated contracts
9/42
10. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
1. Lump-sum contract
In this system, the contractor undertakes the execution of a specific work
for a definite lump-sum amount within a specified time period.
On completion of the work, it is checked as per drawings and specifications
and if approved the amount is paid to the contractor.
The quantities of various items is not measured.
For decorative works this system is adopted.
10/42
11. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Advantages of lump-sum contract
Low risk on the owner, Higher risk to the contractor
Cost known at the beginning
Contractor selection is easy.
Disadvantages
In this it is essential that the work be accurately and completely shown
on the drawings in the specifications and the full information about the
site condition should be available other wise it will leads to disputes.
Contractor is free to use the lowest cost of material equipment & and
methods.
Difficulty arises in making any intermediate payment.
11/42
12. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
2. Cost plus a fixed percentage contract
The contractor is reimbursed for all his costs with a fixed % age of costs to
cover his services.
Project/site overheads may be covered by the % or computed as one of the
costs.
Fee = percentage of the total project cost
(Cost =$500.000,Fee = 2%)
12/42
13. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
2. Cost plus a fixed percentage contract
Advantages
Construction can start before design is completed.
If the contractor is efficient in the utilization of resources then the cost to
the client should represent a fair price for the work undertaken.
Disadvantages
The project total cost is completely unknown before the project start.
No incentive for the contractor to be efficient in his use of labors,
materials or equipments.
Minimum efficiency maximizes the profit.
13/42
14. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
3. Cost plus a fixed fee contract
In this system a fixed fee is given as contractor’s profit irrespective of the
total cost of work.
This is to control the tendency of the contractor to increase the cost of the
project unnecessarily.
Smaller the completion time more is the profit and hence the contractors
hurry to complete the work and the quality of workmanship is not
maintained.
This system is not generally used.
14/42
15. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
4. Percentage rate contract
In this system the contractors are required to quote single percentage
either higher or lower at which he wants to execute the job.
Here scrutiny of the tenders become easier and as cement and steel is
usually supplied by the department chances of manipulation is less.
Most of the state is adopted this type of contract.
Advantages
profitable for the contractor.
Disadvantages
No incentive to finish job quickly
Owner does not know total price
Larger the cost of the job, the higher the fee the owner pays.
15/42
16. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
5.Item rate of contract
Here the contractor gets the payment depending on the rate at which he has
quoted every item of the work.
It was rather difficult to scrutinize the tenders submitted by various bidders
and the system was hence modified and now the department quotes the
items of work along with their quantities and the bidders are required to quote
the percentages at which he can execute the various items.
16/42
17. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Advantages
Early start is possible.
Saves the heavy cost of preparing many bills of quantities by the
contractors.
Fair basis for competition.
In comparing with lump-sum contract, changes in contract documents
can be made easily by the owner.
Lower risk for contractor.
Disadvantages
Final cost not known from the beginning (BOQ only is estimated)
Staff needed to measure the finished quantities and report on the units.
17/42
18. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
6. Turn-key contract
In this system all the works related to a project including designing,
planning, execution etc. are to be done by the contractor.
Once the project is completed it is handed over to the owner.
The owner has to complete the transaction works and
occupy the structure by simply turning the key.
18/42
19. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
7. Cost plus sliding scale of fees
In this type of contract the contractor is paid by the owner the actual
cost of construction plus an amount of fee inversely variable according
to the increase or decrease of the estimated cost agreed first by both
parties.
Thus the higher the actual cost, lower will be the value of fee and vice
versa.
Advantages
In this case the contractor shall not try to increase the actual cost.
The actual cost is lower and lower so both the owner and the contractor
will be benefited.
19/42
20. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
Disadvantages
Estimated cost should be accurate.Other wise the contractor get profit if the
actual cost is much higher than the estimated cost.
8.Negotiated contract
When the work is awarded on contract by mutual negotiation between the
parties with out call of tenders, it is said to be negotiated contract.
A negotiated contract will eliminate the costs associated with the bidding
process.
This could make it possible to avoid unforeseen problems and building
issues during construction.
Reference - https://callsierra.com/how-businesses-benefit-from-
negotiated-contracts/
20/42
21. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Arbitration (மத்தியஸ்தம்)
Arbitration is a process in which a dispute is submitted to an impartial
outsider who makes a decision which is usually binding on both the
parties.
21/42
22. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
Arbitration (மத்தியஸ்தம்)
The arbitrator enforces his own point of view on the contending parties and
the opinions of the participants are not given any predominance.
Arbitration is a judicial process.
The award of the arbitrator is binding and rests on equity and justice, i.e.,
there is no scope for compromise
22/42
25. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Non Arbitral Disputes
Matters of criminal nature.
Disputes relating to matrimonial relations.
Testamentary matters relating to the validity of a will.
Relating to trusts for public purposes of charitable or religious nature.
Insolvency matters.
Matters relating to the guardianship of a minor or lunatic.
Any execution proceedings .
25/42
26. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Duties Arbitral
To administer oath to the parties and witness appearing
To act judicially and impartially.
To put necessary interrogatories (விசாரணையாளர்கள் ) to any party to the
dispute.
To determine by and to whom the costs of reference and the award shall
be paid.
To award interest.
To fix amount, mode and time of payment.
26/42
28. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Arbitration Advantages
Choice of decision maker with expertise
Speed
Lower-cost
Flexible
Confidentiality
Less formal than court
Preservation of business relationships
28/42
29. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
Arbitration disadvantages
Limited recourse
Uneven playing field
Lack of transparency
Cost: parties pay for arbitrator and agency
Limited rights of appeal, fewer means to challenge award
Lack of formal discovery
29/42
30. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Types of Arbitral
1. Voluntary arbitration
2. Compulsory arbitration
Voluntary arbitration
Implies that the two contending parties, unable to compose their
differences by themselves agree to submit the conflict/dispute to an
impartial authority, whose decision they are ready to accept.
Essentials of voluntary arbitration
The voluntary submission of dispute to an arbitrator.
The subsequent attendance of witnesses and investigations.
The enforcement of an award may not be necessary and binding.
Voluntary arbitration may be specially needed for disputes arising
under agreements/contracts.
30/42
31. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Compulsory arbitration
It is one where the parties are required to accept arbitration without
any willingness on their part.
When one of the parties to an industrial dispute feels aggrieved by an
act of the other, it may apply to the appropriate government to refer
the dispute to an adjudication machinery
31/42
32. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Essentials of Compulsory Arbitration
The country is passing through grave economic crisis.
Industries of strategic importance are involved.
Parties are ill balanced.
Compulsory arbitration leaves no scope for strikes and lockouts; it deprives
both the parties of their very important and fundamental rights.
Other Types of Arbitration
1. Ad-hoc Arbitration
2. Institutional Arbitration
3. Statutory Arbitration
4. Domestic or International Arbitration
5. Foreign Arbitration
32/42
33. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
(1) Ad-hoc Arbitration
When a dispute or difference arises between the parties in course of
commercial transactions.
This arbitration is agreed to get justice for the balance of the un-settled
part of the dispute only.
(2) Institutional Arbitration
There is prior agreement between the parties that in case of future
differences or disputes arising between the parties during their
commercial transactions, such differences or disputes will be settled by
arbitration as per clause provide in the agreement.
33/42
34. 12/4/2020
Contract
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
(3) Statutory Arbitration
It is mandatory arbitration which is imposed on the parties by operation
of law.
In such a case the parties have no option as such but to abide by the law of
land.
(4) Domestic or International Arbitration
Arbitration which occurs in India and have all the parties within India is
termed as Domestic Arbitration.
An Arbitration in which any party belongs to other than India and the
dispute is to be settled in India is termed as International Arbitration.
34/42
35. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
(5) Foreign Arbitration
When arbitration proceedings are conducted in a place outside India
and the Award is required to be enforced in India, it is termed as
Foreign Arbitration.
Arbitration in India
Indian council of arbitration (1965).
Abide Arbitration and Conciliation Act, 1996.
Comprehensive legal framework.
95% arbitration is of type ad-hoc.
India No. 2 in arbitration cases reaching Singapore centre.
Mumbai to have India's first International Arbitration Centre soon.
35/42
36. 12/4/2020 SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Contract
Requirements for the Arbitration agreement
It must arise out of mutual consent.
The parties must have legal capacity.
The agreement must be made in writing.
It must arise out of a defined legal
relationship.
The subject matter must be arbitral.
Section. 8 of arbitration conciliation act 1996
Power to refer parties to arbitration where there is an arbitration
agreement
36/42
37. 12/4/2020
Contract
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Section. 9 of arbitration Conciliation act 1996
Interim Measures by Court
Termination of arbitration agreement
Termination of arbitration agreement by mutual consent
Other grounds for termination of the arbitration agreement
37/42
38. 12/4/2020
IBRD
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
International Bank of Reconstruction and Development (IBRD) is
a development bank administered by the World Bank.
The IBRD offers financial products and policy advice to countries
aiming to reduce poverty and promote sustainable development.
The International Bank of Reconstruction and Development is a
cooperative owned by 189 member countries.
38/42
40. 12/4/2020
MORTH
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Ministry of Road Transport and Highways
https://en.wikipedia.org/wiki/Ministry_of_Road_Transport_and_Highwa
ys
40/42
41. 12/4/2020
MORTH
.
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Ministry of Road Transport and Highways
It is a ministry of the Government of India, that is the apex body for
formulation and administration of the rules, regulations and laws relating
to road transport, transport research and in also to increase the mobility
and efficiency of the road transport system in India.
Through its officers of Central Engineering Services (Roads) cadre it is
responsible for the development of National Highways of the country.
Road transport is a critical infrastructure for economic development of the
country.
It influences the pace, structure and pattern of development.
MORTH - Ministry of Road Transport & Highway.pdf
41/42
42. 12/4/2020
MORTH
SNSCE/ Civil Engg /VII sem / Shanmugasundaram N/ Ap/Civil
Ministry of Road Transport and Highways
In India, roads are used to transport over 60 percent of the total goods and
85 percent of the passenger traffic.
Hence, development of this sector is of paramount importance for India
and accounts for a significant part in the budget.
As many of the regional transport offices are not regularly functioning due
to covid-19 situation, the Govt has given some relaxation to the people
whose driving license has expired during this period.
Now the old driving license can be used till September 2020.
So the people can drive their vehicles up to September 2020 without
renewing the old license
42/42