SlideShare a Scribd company logo
1 of 92
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 1 of 92
Contents
01 General Site Activities 29 Nightwork 57 Powder-Actuated Tools (Hilti Gun)
02 Abrasive Wheels 30 Night Emergency Procedures 58 HDPE Pipe - Butt Fusion Machine
03 Aircraft Overhead see 41 for Working Airside 31 Noise – high levels 59 Directional Drilling
04 Buried Services 32 Overhead cables 60 Paint Spray Guns
05 Cement, Wet Concrete, Grout & Mixer 33 Paving Bituminous & Milling 61 Managing Sub-contractors
06 Concreting 34 Pipe Jacking 62 Operating Plaster Mixer Spray machine
07 Compressors & Air Tools 35 Pinch Points & Hand Injuries 63 Hydrochloric Acid Handling & Use
08 Confined Spaces 36 Plant, Equipment & Plant Operators 64 Cladding to Roofs
09 Cranes - Lifting Operations 37 Plant Repairs & Maintenance 65 Fixing Windows, Doors & Glazing
10 Deliveries – Unloading & Storage 38 Plant Collision 66 Roof Waterproofing Membrane
11 Driving – Dangerous & Unsafe 39 Reinforcement 67 Roof Sheeting - Roll Forming on site
12 Electrical Tools 40 Road Works 68 Demolition of Buildings
13 Electrical Works 41 Road Saw 69 Working on Median beside Live Traffic
14 Employees New Starts 42 Scaffolding 70 Cable & Coiled Duct Laying from Drums
15 Emergency Procedures 43 Steel Structures Erection 71 Demolition of Underground Tanks & Pipelines
16 Excavations, Backfilling, Filling & Earthworks 44 Welding & Cutting Metal 72 Butt Fusion Welding of PE Pipes
17 Excavators 45 Working at Height 73 Cold Milling Machine Operation
18 Falsework & Formwork 46 Working On, Above or Near Water 74 Shot Blasting
19 Fencing 47 Working Airside 75 Not Wearing PPP
20 Fuelling & Oiling 48 Operating Vibrating Hand Tools 76 Working Indoors
21 Hazardous Substances 49 Poor Housekeeping 77 Working Outdoors
22 Heat 50 Working in Sewer Manhole 78 HAVS (Hand-arm vibration )
23 Hydrostatic Testing - Pipelines 51 Felling Trees by Cutting 79 Rock Drilling & Blasting in Quarry
24 Joints Sealing with hot Bitumen 52 Post Tensioning 80 Pipeline Inspection by CCTV
25 Lorries Hiab 53 Hydraulic Pump & Jack
26 Lorries Tippers & Trailers 54 Traffic Management
27 Manual Handling 55 Auger Boring with Casing
28 MEWP Mobile Elevating Work Platforms 56 Concrete Saws & Core Drills etc
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 2 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
O1 Site Activities General
01  Construction
activities
 Injuries
 Property Damage
6 6 36  Site HSE Project Procedures
 Work Permit Systems
 Method Statement for Risk Activities
 Risk Assessments
 On Site Safety Training
 HSE Supervision
 Issue of PPE
 COSHH Assessments
 On site Medical Clinic
 Site Emergency Response Plan
 Site Health, Safety & Environmental Plan
 First Aid Kits available
 First Aiders
 Site Inductions for Employees
 Welfare Facilities
 Waste bins
 Managers must take responsibility and
accountability for HSE Management
 Training and implement above.
6 2 12 Adequately
Controlled
Risk
02 Abrasive Wheels
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 3 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
02  Disc
Disintegration
 Electricity
 Entrapment /
Entanglement
 Spoil Ejection
 Fire
 Noise
 Dust
 Lacerations [may be
severe, even fatal.
 Contact burns /
electric shocks
 Penetrating injuries
 Property damage
 Tinnitus / Threshold
shift / Noise induced
Hearing loss
 Respiratory problems
 Eye Injury
6 6 36  Use of approved suppliers
 Use of appropriate speed rated discs
 Use of task specific discs
 Use of correctly adjusted guards
 Use of suitable PPE ( body / hands / face /
eyes /ears )
 Trained and competent persons only to use
abrasive wheels / change discs
 All electrical equipment to be 110V with
industrial sockets
 Routine inspection / testing
 All electrical equipment colour coded
 Damaged equipment tagged and taken out of
service
 All cutters and grinders regularly maintained
 No loose clothing worn
 Adequate training & supervision
 Use of Hot work permit system
 Fire points available
 Trained fire extinguisher operatives
 Removal of combustible materials
 Sound screens / isolation of high noise
activities
 Abrasive wheel signs.
 Eye protection – high impact glasses at all
times.
 Eye wash station on site
6 2 12 Adequately
Controlled
Risk
03 Aircraft Overhead
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 4 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
03a  Collision with
aircraft in flight
 Severe physical
damage
 Fatalities
 Public outcry
10 6 60  Fan corridor height restrictions briefed to all
site teams
 Works in the fan corridor will be controlled by
Restricted Area Access Work Permits
 Heightmarkers ( such as goal posts ) shall be
constructed as applicable to advise of heightlimits
 All plantequipmentshall be selected on basis of
maximum operating heights so as to notinterfere
with airportoperations
 Authorisation from 3rd
party.
 Supervision atall times.
 MS/ RA briefed to all affected workers
10 2 20 Adequately
Controlled
Risk
03b  Lighting
Distraction to
Pilots on Finals to
landing
 Severe physical
damage
 Fatalities
10 4 40  Tower lights to be setup so the light beam shines
across the runway (North to South) so as not to be
a distraction to pilots on finals to landing.
 The heightof tower lights to be limited to 13m.
 Lighttowers established on raised bridge decks to
be approved by OAMC
 Lights to have welded restrictors to ensure the light
beam is downwards facing.
 Lighting control will be via liaison with the OAMC
 MS/ RA briefed to all affected workers
 A lighting plan will be prepared and submitted prior
to any nightwork, showing location and direction
and illuminated area oflightbeams.
10 2 20 Adequately
Controlled
Risk
04 Buried Services
04  Underground
services ;- gas,
electricity or water
 Personal Injury –
electrocution /
drowning /
8 6 48  Area to be visually checked for markers or
physical signs of services, i.e. manholes.
 Up to date drawings detailing existing services
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 5 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
asphyxiation
 Property Damage
 Fire
 Disruption of utility
services
shall be obtained and checked thoroughly.
 Service providers shall be contacted to assess
if there are services in the area and also to let
them know work is going to be carried out.
 Obtain permit from Utility Company if required.
 Use of trial holes and hand excavation around
known services
 Hand tools that are non conductive shall be
used when excavating around existing
services.
 Prior to excavation the affected area shall be
surveyed with a CAT and competent person.
 Records of all CAT surveyed areas to be kept
on file and briefed to excavation team
 Surveyed area clearly demarked on site
 NOC from municipality to be obtained before
excavation
 Emergency contact numbers displayed on site
 Where required use Permit to Dig.
 Obtain NOC where applicable
 Protect existing services by either, marking the
ground surface, providing protection slabs,
tiles or timbers or exposing & encasing in
concrete.
05 Cement, Wet Concrete, Grout & Mixer
a.  Handling Cement  Contact dermatitis /
skin irritation
 Cement dust
6 6 36  Wear suitable protective eye wear
 Compliance with COSHH assessment
 Have eye station on hand
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 6 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
inhalation
 Eye Injury
 Wash hands after each exposure
 Use of gloves
 Use of full length uniforms
 First Aiders available
b  Handling wet
concrete & grout
 Contact dermatitis /
skin irritation
 Eye Injury
6 6 36  Wear suitable protective eye wear
 Compliance with COSHH assessment
 Have eye station on hand
 Wash hands after each exposure
 Use of gloves
 Use of full length uniforms
 First Aiders available
6 2 12 Adequately
Controlled
Risk
c  Using Mixers  Personal Injuries to
include cuts and
crush injuries
 Electrocution
 Contact dermatitis /
skin irritation
 Electric shocks /
contact burns
 Tinnitus / Noise
induced hearing loss
 Cement dust
inhalation
6 6 36  All necessary guards are to be in place on the
mixer.
 All equipment is to be inspected by a
competent person prior to use.
 Only trained operatives to use mixer
 Planned preventative maintenance programs
 No persons are to put tools or limbs in to mixer
while drum is rotating.
 Mixer is to be set up on firm level ground and
should never be over loaded.
 All mixers should be 110 volt to prevent
electrocution.
 All temporary plant to be suitably earthed
 Use of suitable PPE ( body / face / eyes/
hands /ears )
 Adequate training & supervision
 Tool box talks ref manual handling
 Noise levels assessed and sound screens
provided as required
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 7 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Availability of first aid / eye wash station
 Compliance with COSHH assessment
 Use protective mask.
06 Concreting
06a  Hazardous
chemicals
 Burns,
 Contact Dermatitis
 Eye irritations
6 4 24  Selection and use of Appropriate PPE ( body /
hands /face /eyes / ears)
 Wear eye protection
 Eye wash station nearby.
 First Aid nearby
 Trained first aider
 Completion of COSHH Assessment
 Use friendly chemicals
 Washing facilities will be provided with hot
water, showers, soap & paper towels
 First Aid & First Aid Equipment provided
6 2 12 Adequately
Controlled
Risk
06b  Vibration.  Vibration-induced
white finger
6 4 24  Limit exposure time / regular breaks
 Job rotation
 Selection and use of appropriate PPE
 Operatives will be briefed on dangers
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 8 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
06c  Falls on working
levels or from
height
 Personal Injury
 Deaths
 Serious injury
6 4 24  Provide leading edge protection and safe
access.
 Good housekeeping disciplines
 Adequate training & supervision
 Training and supervision
6 2 12 Adequately
Controlled
Risk
06d  Prolonged
exposure to noisy
plant
 Tinnitus, threshold
shift , Noise induced
hearing loss
4 4 16  Ear Protection if you have to shout to be
heard.
 Monitor noise levels and enforce PPE use
above 85dB
 Place warning signage for noise
 If you have to shout to be heard wear ear
protection
4 2 8 Trivial Risk
06e  Failure of support
system or
platform
 Personal Injury
 Property damage
6 4 24  Structural sign off for all falsework and
formwork before any concrete placement
6 2 12 Adequately
Controlled
Risk
06f  Concrete Pumps  Property damage
 Personal Injury
6 6 36  All equipment is to be inspected by a
competent person prior to use.
 Whip checks fitted on pressure hoses
 Operator has Valid license / certification
 Exclusion zone created around working
concrete pump
 Noise levels assessed and PPE provided as
required
 No manual clearance of pump hopper while
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 9 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
pump is in operation
 Adequate training & Supervision
 Pump is to be set up on firm level ground with
outriggers fully deployed using load pads.
 Wash-out facility will be provided and for night
work will be illuminated.
 Clean out in an area set aside for this
particular activity.
 Exclude people not involved in the clean out
procedure from the work zone.
 Do not “Shoot” the clean out plug from the
end of the concrete line.
06g Wastage  Environmental
damage
6 4 24  Use Wash-out facility provided around the site
and in the concrete batching yard
6 2 12 Adequately
Controlled
Risk
07 Compressors & Air Tools
07  Airlines Whipping
 Noise
 Injury 6 2 12  Use whip wire on airlines
 Visual inspection of air hoses prior to starting
work, any damaged hoses to be replaced
 No horseplay with airlines or misuse
 Ear & Dust protection
 Exhaust fumes not to cause hazard
6 2 12 Adequately
Controlled
Risk
 Jackhammer  Vibration white finger
 Eye injuries
 Hearing loss
 HAND ARM
VIBRATIONS (HAV)
6 4 24  Anti-vibration tools used if possible
 Eye protection to grade one impact when
using metal cutting or stone cutting tools
 Heavy leather gloves when using tools
causing hand-arm vibration
 Suitable protective gloves when handling parts
contaminated with hydraulic fluid
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 10 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Hearing protection
 Respiratory protection against dust where
assessed as necessary
 Safety boots with Airlines
 Air hoses should be laid out properly without
kinks and not in the way of machinery
movement
 Rotate workers when using tools that produce
HAV and record time on tools per shift.
08 Confined Space Note difference between Permit and Non-Permit confined spaces
Refer to HSE Project Procedure for Confined Spaces Entry Doc # PP710-CSE-1008
08a  Increased or
decreased
oxygen levels
 Asphyxiation 6 6 36  Use of confined space permit system
 Atmospheric testing.
 Suitable means of communication
 No lone working permitted
 Emergency plan in place ( rescue from
Confined Space etc )
 Adequate ventilation / lighting
 Suitable access points ( preferably 2 points
where poss. )
 Hourly records of Gas levels
 Signage /exclusion zone to prevent
unauthorized access
 Training & Supervision
 Good housekeeping
6 2 12 Adequately
Managed
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 11 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
08b  Hazardous gases  Poisonings 4 6 24  Atmospheric testing.
 Use of confined space permit system
 Adequate ventilation / lighting
 Hourly records of Gas levels
4 2 12 Adequately
Managed
08c  Fire Burns 4 6 24  Fire points available
 No Smoking
 Exclude inflammable materials & liquids
 Intrinsically safe lighting, emergency lighting
and torches.
4 2 8 Negligible
Risk
Non Permit Confined Space
08d  Fumes Injury 6 4 24  Good access & egress routes
 Smoking Prohibited
 No Working Alone
 No petrol or diesel engines
 No combustible material stored
 Natural Ventilation
6 2 12 Adequately
Controlled
Risk
Permit Confined Space 
08e  Hazardous Gases Injury 6 4 24  Note - Depending on circumstances select
from following
 Good access & egress routes
 Smoking Prohibited
 No Working Alone
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 12 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 No petrol or diesel engines
 No combustible material stored
 Natural Ventilation
 Permit to Work System
 Personnel Training in Confined Spaces
 Lights Instrinically Safe
 Gas Dectors
 Entry Log System
 Force Ventilation
 Rescue Harness ( connected to Lifeline
leading to outside)
 Rescue Equipment Self Rescuers carried
09 Cranes – Lifting Operations
General  Comply with Project Procedure for Lifting
Operations PP 738-LOP-1008
 Wind Speed Limit on Site is 9m/sec or
32.5Km/hr
 Notes
Slinger = Rigger
Signaller = Banksman
09a  Crane overturning  Personal injury
 Property damage
6 4 24  Crane set up on firm and level ground
 Outriggers to be fully extended
 Load pads under all outriggers
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 13 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Crane set up controlled by competent lifting
supervisor
 Crane has PMV inspection prior to
mobilisation
 Crane has valid 3rd party inspection
certification.
 Licensed crane operator
 Selection of correct crane for task ( SWL etc ).
 Weights of loads known before lifting
 Exclusion zones created around lifting
operations
 Daily checks by operator recorded
 No work in strong winds
 Certified slings, shackles and other lifting
appliances to be used & be in period colour
code.
 Do not exceed SWL
 Check area under outriggers for drains etc
09b  Crane failure  Personal Injury
 Property damage
6 4 24  Crane set up on firm and level ground
 Outriggers fully deployed
 Load pads under all outriggers
 Crane set up controlled by competent lifting
supervisor
 Crane has PMV inspection prior to
mobilisation + daily pre use inspection
 Crane has valid 3rd party inspection
certification.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 14 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Licensed crane operator
 Selection of correct crane for task (SWL etc ).
 Weights of loads known before lifting
 Exclusion zones created around lifting
operations
 Daily checks by operator prior to starting
 Do not exceed SWL
09c  Failure of lifting
equipment
 Personal Injury
 Property damage
6 4 24  All lifting equipment shall be 3rd party
inspected and certified as fit for purpose,
 All areas of lifting operations shall be
adequately lit
 Crane operators to have valid licenses
 All lift accessories shall be inspected, certified
and comply with CCC /TAV JV colour coding
scheme for the period
 Specific lift paths will be created to avoid any
overhead lifting
 All cranes or lifting operations shall be
controlled by competent signal man
 All rigging activities shall be conducted by
trained and competent rigger.
 Exclusion zones with fixed barriers will be
established around lifting operations / zone
 All operations supervised
 Equipment to comply with colour code for
period
 Select correct lifting accessories for planned
load.
 All lifting accessories to be checked daily by
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 15 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
crane driver and riggers before use.
09d  Rigging  Personal Injury
 Property damage
6 4 24  All lifting tackle shall be 3rd party inspected,
certified and CCCTAVJV colour coded
 Rigging operations shall only be performed by
trained & competent riggers.
 All lifts will be controlled and supervised by a
rigging supervisor.
 Lifting plans will be used for all abnormal loads
 Exclusion zones created around lifting
operations
 Personnel will be advised of risks through tool
box talks prior to commencement of work.
 All riggers shall wear appropriate PPE
 Riggers shall be identifiable via helmet colour
 Tag lines used for all lifts
 Helmets colour coded
 All lifting accessories to be checked daily by
crane driver and riggers before use.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 16 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
09e  Equipment &
Material Handling
 Personal Injury
 Property damage
6 4 24  All equipment will be stored, handled in a safe
and proper manner & managed by trained
staff.
 Offloading and storage will be properly
controlled / supervised at all times by trained
staff at all times.
 Tag lines will be used to control equipment
during loading and offloading.
 Personnel will be properly trained in safe
methods of Equipment handling including the
danger of pinch points – fenced off.
 Erection areas will be identified and
unauthorized entry will be controlled by use
of barriers, warning signs and close
supervision.
 Appropriate personnel protective equipment
will be worn at all times.
 Personnel will be reminded of risks through
tool box talks.
 Period colour coded equipment.
 Beware of trapping while moving loads
6 2 12 Adequately
Controlled
Risk
09f  Adverse weather  Property damage
 Personal injury
 Crane failure
6 6 36  Install anemometers on cranes / site
 Safe operating limits for wind speed set for all
lifting operations
 Liaison with OAMC meteorology dept.
 Protocols for all adverse weather situations
such as sand storms established
 Training and competent supervision
 Crane supervisor with authority to suspend all
lift operations project wide
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 17 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Crane driver and riggers authorised to stop
lifts if deemed unsafe or high winds
09g  Multiple Cranes &
suspended loads
Collision
 Personal injury
 Property damage
6 6 36
Crane & suspended loads, Anti Collision
Measures
 Banksman to guide and coordinate the
movements of cranes working in close
proximity.
 Vehicles not to be parked in swing area of
cranes
 No person to stand sit or walk near working
cranes
 No unauthorised access
 Exclusion zones created around working plant
6 2 12 Adequately
Controlled
Risk
09h Working in crane
suspended man
baskets
 Personal injury
6 6 36
 Basket will be certified by 3rd Party
 Personnel will wear harnesses
 Adequate signage and exclusion zones
around temporary structures.
6 2 12 Adequately
Controlled
Risk
10 Deliveries Unloading & Storage
10  Moving Delivery
Vehicles
Entering/Leaving
site
 Traffic accidents
 Property damage
 Personal injury
6 6 36  Good visibility of oncoming vehicles.
 Traffic calming measures such as speed
bumps
 Pedestrian routing. High visibility clothing.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 18 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Reversing alarms.
 All vehicle reversing controlled by trained
banksman.
 Banksmen not to get between moving
vehicles and fixed objects
 Adequate signage
 Adequate lighting at site entrances
 Site driving rules posted
 Security marshalling traffic
 All CCCTAVJV / Subcontractors drivers HSE
inducted
 All drivers to hold valid Omani license
 Authorised vehicles only on site
 Security identify drop zones & advise delivery
drivers on site traffic rules.
 Unloading  Injury
 Material damage
6 6 36  Comply with Lifting Operations project
Procedure PP 738
6 2 12 Adequately
Controlled
Risk
 Storage  Injury
 Material damage
6 6 36  Stack materials in designated areas
 Cordon off area
 Keep storage area tidy
6 2 12 Adequately
Controlled
Risk
11 Driving – Dangerous or Unsafe
11  Dangerous or
unsafe driving
 Road traffic accident
 Personal Injury
 Property damage
8 6 48  Designated and signposted access routes
required.
 All drivers must have an appropriate license
8 2 16 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 19 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
for the particular piece of plant they are using.
 All personnel involved in the work shall be
inducted, instructed on the site driving rules
and have their license checked and recorded.
 Regular tool box talks and Night Activity
Briefings (NAB) shall be given to reiterate
driving standards.
 Supervisors and H&S shall monitor driving
and take appropriate action if necessary.
 All reversing vehicles to be controlled by a
trained banksman
 All mobile plant to have audible reversing
alarm
 Blind spots to be mitigated by appropriate
mirrors. .
 All necessary lights should be in place on
vehicles including orange flashing beckons
and should be used at all times as well as
being regularly inspected.
 Vehicle Lights, windows and mirrors shall be
cleaned regularly to ensure a clear view.
12 Electrical Tools
12  Electricity
 Moving parts
 Noise
 Vibration
 Dusts
 Personal Injuries:
Cuts and lacerations.
 Potential amputations
 Penetrating Injuries.
 Respiratory problems
 Upper limb work
disorders
 Vibration white finger.
 Electrocution.
4 6 24  110Volt tools only permitted on project
 Use of approved industrial sockets
 Inspected and CCCTAVJV colour coded
 HSE Induction for all workers.
 Toolbox talks.
 Selection and use of suitable PPE.
 Adequate training and supervision.
 Tool maintenance and record keeping.
 Damaged tools tagged, isolated and removed
from service
4 2 8 Trivial Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 20 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 All tools fitted with appropriately adjusted
guards.
 Pre use daily inspections
 PAT test to all Electric equipment.
 Job rotation as required & recorded.
 Equipment to comply with the site colour code
for period
13 Electrical Work
13  Using Electrical
Equipment.
 Electrical
installation works
 Electrocution.
 Fire.
 Property damage
4 4 16  All Electrical Distribution boards shall be fitted
with suitable circuit breakers
 All hand tools on site shall be 110V
 Use of approved industrial sockets
 Only authorized and trained personnel to carry
out work with electrical equipment.
 Only trained and authorised personnel to
complete electrical installations ( DB’s etc )
 Portable equipment to be checked by
authorized electrician or independent
assessor.
 All electrical equipment shall be colour coded
 Suitable fire extinguishers stored at strategic
locations.
 Training in use of extinguishers
 Any damaged equipment to be removed from
use, isolated and tagged to prevent accidental
re-use
 No ‘hot wiring / splicing of cables ‘ on site
 Lock out tag out system ( for DB boxes etc )
 Suitable earthing for all temporary plant
 Suitable training and supervision
4 2 8 Trivial Risk
14 Employees New Starts
14  Inexperience of  Increased risk of 4 4 16  Induction training. 4 2 8 Trivial Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 21 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
New Employees unsafe activities
 Potential poor quality
works
 Personal Injury
 Property damage
 Training in site rules and procedures.
 HSE training programs
 Close supervision / use buddy system
 Pre planning of tasks assigned based on
experience required
 Issued with PPE
 Issued with Identification Card
15 Emergency Procedures
15  Emergency
situations / poor
emergency
procedures.
 Disruption to project
 Personal injuries
 Property damage
 Worsening of an
incident if dealt with
incorrectly
6 6 36  Project specific emergency plan created
 Emergency procedure included in induction
and reiterated in briefings and Tool box talks.
 Emergency contact details posted on site
notice boards and office bulletin boards
 Emergency contact detail cards distributed to
all supervisory staff
 Emergency facilities on standby ( ambulance /
fire engine / clinic )
 Trained First Aiders available throughout the
site
 Trained fire wardens available throughout the
site
 Fire points / first aid boxes available
throughout the site
 Incident control room established at MC 1
offices
 Duty Incident Controller Rota established
 Scheduled emergency drills
 Liaison with civilian emergency services.
 All personnel to have Emergency #
 Security at gates.
 Emergency drills.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 22 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
16 Excavations, Backfilling, Filling & Earthworks
 General  Comply with Project Procedure PP712-EXE-
1008
 Any excavation left open for 7days or more to
have a weekly inspection carried out and
recorded within 24 hours.
 Provide safe access & egress
16a  Trench Collapse  Entrapment
 Death
 Injury
6 6 36  Slope or step faces
 Daily excavation inspections
 Permit to Dig in place.
 Keep spoil and plant 2 metres away from edge
of excavation
 Keep excavations dry, water at safe level.
6 2 12 Adequately
Controlled
Risk
16b  Persons falling
into excavations
 Personal Injury
 Property damage
6 6 36  All excavations will have suitable fixed barriers
at least 1.5m from leading edges
 Provision of adequate signage
 Creation of safe pedestrian access routes
away from excavations
 Safe access and egress shall be provided for
all excavations and access bridges over the
trenches should be provided if required.
 Excavation daily inspection checklist to be
completed by competent person
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 23 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Training & Supervision
 Regular TB Talks ref: excavation safety
16c  Material or plant
falling into
excavations
including trench
collapse
 Personal Injury
 Property damage
6 6 36  All excavations will have suitable fixed barriers
at least 1.5m from leading edges
 All excavated spoil to be placed at least 2m
from leading edges
 Provision of adequate signage
 Creation of vehicle access routes away from
excavations
 Safe access and egress shall be provided for
all excavations and access bridges over the
trenches should be provided.
 No lone working in excavations
 Excavation daily inspection checklist to be
completed by competent person
 Training & Supervision
 Regular TB Talks ref: excavation safety
 Stop blocks shall be used where plant is
working near the trench. The stop blocks must
of sufficient height and strength to stop the
vehicle and of sufficient distance from the
trench so as to stop collapse.
 All excavations of greater depth than 1.2 shall
have a suitable means of ground support such
as. battering, benching, trench sheets, trench
boxes, sheet piling, etc.
 In solid and non fractured rock the above
requirement may be relaxed
 Adequate angle of repose shall be in place for
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 24 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
all excavations where above ground support
measures are not possible
 Lighting as required
16d  Weakening of
adjacent
structures by
excavation
 Collapse of structure
 Property damage
 Personal Injury
6 4 24  Suitable prior planning of shoring
requirements before works commence.
 Structural engineer to advise on any additional
shoring / support required.
 Daily check inspections
6 2 12 Adequately
Controlled
Risk
16e  Buried Services
gas, electricity
water
 Personal Injury –
electrocution /
drowning /
asphyxiation
 Property Damage
 Fire
 Disruption of utility
services
8 6 48  Area to be visually checked for markers or
physical signs of services, i.e. manholes.
 Up to date Drawings detailing existing services
shall be obtained and checked thoroughly.
 Liaison with concerned authority
 Use of trial holes and hand excavation around
known services
 Hand tools that are non conductive shall be
used when excavating around existing
services.
 Prior to excavation the affected area shall be
surveyed with a CAT by a competent person.
 Records of all CAT surveyed areas to be kept
on file and briefed to excavation team
 Surveyed area clearly demarked on site
 NOC from municipality to be obtained before
excavation
6 2 12 Adequately
Controlled
Risk
16f  Overhead Power
Lines
 Personal Injury –
electrocution / burns
 Property Damage
6 6 36  Selection of appropriate plant in respect of
max operating heights
6 2 12 Adequately
Controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 25 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Fire
 Disruption of utility
services
 Erect barriers with warning signs parallel
 Erect goal posts with cross bars for passing
under
 All plant movement under overhead power
lines controlled by trained banksman
 All plant and temporary scaffolds to be suitably
earthed to safeguard against arcing
 All drivers and plant operators to receive Tool
box talks
 Security to stop all vehicles and warn drivers
of any overhead power line hazards
 Exclusion zones created to prevent
encroachment of plant & vehicles near
overhead lines
 Competent supervision
 Reroute service where possible
 Follow CCCTAVJV procedure
 Operate Permit to Work
 Safe System of Work in place
 Working under or around Power Lines
Procedure in place.
 Re route power lines where possible.
 Overhead power line procedure in place.
 Notify service company
 Obtain NOC
16g  Access & Egress  Falling, Injuries 6 6 36  Ensure that all access ladders are in good
condition and are inspected
6 2 12 Adequately
Controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 26 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Ensure that all access Ladders are tied on top
 Ensure that the ladders are standing on stable
ground
 Areas at top and bottom to be free from
materials and debris.
 Ladders to be industrial type not home made
 Ensure that the ladders are supported on
bottom in case tying the top is not possible
 Ensure that no rebar or other objects are
protruding into the ladders
 Operators shall remove lumps of material from
footwear prior using ladders
16h  Working in vicinity
of moving plant
 Injury
 Property Damage
6 4 24  All plant to be operated by suitably licensed
and competent operators.
 All reversing vehicles to be controlled by a
trained banksman
 All mobile plant to have audible reversing
alarm
 Blind spots to be mitigated by appropriate
mirrors.
 Site driving rules enforced.
 All necessary lights should be in place on
vehicles including orange flashing beckons
and should be used at all times as well as
being regularly inspected.
 Vehicle Lights, windows and mirrors shall be
cleaned regularly to ensure a clear view.
 Exclusion zones created around working plant
 Emergency procedures in place
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 27 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
17 Excavators
17a  Working
excavator
 Excavator failure
 Personal Injury [may
be severe, even fatal]
 Property damage.
 Traffic accidents
6 6 36  All excavator operators to hold valid license /
certification
 All operators familiarised with the SAFE
WORKING PROCEDURE FOR
EXCAVATORS.
 Prior to mobilising all excavators to be
inspected by PMV
 Operator to carry out visual inspection of
machine prior to start up.
 All excavators shall deploy outriggers if fitted
 Visibility blind spots to be minimised by
mirrors.
 Flashing beacon fitted.
 Windows, lights, Mirrors to be cleaned
regularly.
 The cab floor to be kept clean and free from
any obstacles which may affect the safe
operation of the Machine.
 Ground workers to wear Hi Visibility Vests,
safety boots and helmets at all times.
 Exclusion zone to be created around working
excavators
 All excavators to be included in Planned
Preventative Maintenance schedule
 All excavators to have Fire extinguisher in cab
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 28 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Spill kits available on site
 Banksman to supervise & direct driver.
 No persons to be in any trench or excavation
during machine excavation work.
 With quick hitches – locking bars or self
locking pins to be fully inserted and visually
checked by driver.
.
17b  Lifting operations  Property damage
 Personal injury
 Machine overturn
6 6 36  Fully deployed outriggers
 Posted SWL on machine
 Selection of appropriate plant for task ( SWL
etc )
 Competent rigging
 Suitable lifting attachments / eyes on machine
– certified
 Exclusion zone
 In date equipment colour code.
 Only lift using the lifting eye and not the teeth
of the bucket.
6 2 12 Adequately
Controlled
Risk
17c  Rockbreakers  Hearing
 Injury
6 6 36  Wear ear muffs
 Wear Goggles
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 29 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
18 Falsework / Formwork
18  Structural
collapse
 Personal Injury
 Property damage
6 4 24  Falsework designed by structural engineer
 Separate MS / RA for each bridge
 MS/ RA briefed to all affected workers
 Structural engineer inspection, approval & sign
off prior to any loading of falsework
 Formwork inspected / signed off prior to any
concrete placement
 Provide proper access and egress routes
 Erect and strip falsework & formwork as per
design drawings
6 2 12 Adequately
Controlled
Risk
19 Fencing
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 30 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
19a  Sharp wire to be
fitted to fence by
hand
 Cuts to hands, face
and body.
6 6 36  All personnel using and fitting the barbed wire
should be trained, experienced and competent
in the use of the material
 Coveralls, appropriate gloves and face shield
to be worn by personnel fitting and handling
barbed wire material.
 None essential personnel to be kept away
from area barbed wire is being used by
barriers with signs erected to high light the
issue.
6 2 12 Adequately
Controlled
Risk
19b  Falls from ladders
 Falling
materials
 Broken bones
 Cuts and bruises
6 6 36  Ladders will be inspected and tagged by a
competent person.
 Ladders shall be footed at all times.
 Coils of wire shall be left at ground level and a
section of uncoiled wire shall be passed up to
person securing the wire to the post.
 Ladders shall be locked securely or removed
from site when not in use.
 Ensure three points of contact when climbing
ladders.
6 2 12 Adequately
Controlled
Risk
20 Fuelling & Oiling Plant
20  Hazardous
chemicals
 Spillage
 Flammable
chemicals
 Damage to
Environment
 Fire
 Personal Injury /
Illness
 Property damage
 Explosion
6 4 24  Selection and use of appropriate PPE
 Use fuel nozzles that automaticallyshut-offthe flow
of fuel when tank is full.
 Keep a spill kit near fuel and oil storage areas and
refuelling areas.
 Turn off machines during refuelling
 Drip trays in place for all static plant to catch any
nuisance leaks and drips thatmay occur.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 31 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Routine servicing only permitted in PMV
 Environmental protective measures such as plastic
sheeting in place for any mobile plantfuelling /
servicing
 Store oil away from watercourses or surface water
drains.
 No mixed storage
 Use funnels when fuelling from containers
 Fire extinguishers at fuel stations and on any
mobile refuelling /service vehicles,AFFF foam
 Trained fire marshals / fire extinguisher operatives
available
 Complete COSHH assessmentfor all fuels and oils
 Complywith COSHH assessment
 MSDS with stores /PMV / HSE / Env team / clinic
 Training & Supervision
 Eye wash stations
 First Aid
 Emergencyphone numbers at hand.
 Safe disposal ofany contaminated ground
 Fuel tanks to be double skinned or bunded
21 Hazardous Substances
21  Hazardous
substances
 Flammable
chemicals
 Spillages
.
 Damage to
Environment
 Fire
 Personal Injury /
Illness
 Property damage
6 6 36  MSDS reviewed for all substances and
COSHH assessments produced for any with
adverse health affects
 Spill kits and eye wash kits to be available
with personnel trained in their use
 Adequate fire precautions available
 Trained fire marshals / fire extinguisher operatives
available
 Selection and use of appropriate PPE, as per
COSHH assessment
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 32 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 MSDS’s available at work locations, to include
HSE / Env. / Clinic / PMV / Stores
 Suitable bunded storage facilities or drip trays
available for all hazardous chemicals
 All workers fully briefed as to requirements of
COSHH assessments
 Use, storage & disposal in line with COSHH
assessment
 No mixed storage of hazardous chemicals
 First aid & Eye wash nearby
 All container to have labels identifying
substance
 Store personnel will know the hazards
associated with items they dispense
 No decanting of hazardous and flammable
substances into plastic bottles or containers
 Store person will be responsible to issue the
necessary PPE with any hazardous
substances.
22 Heat
What Is Heat Stress?
It's a signal that says the body is having difficulty maintaining its narrow temperature range. The heart pumps faster, blood is diverted from internal organs to
the skin, breathing rate increases, sweating increases, all in an attempt to transfer more heat to the outside air and cool the skin by evaporation of sweat. If
the body can't keep up then the person suffers effects ranging from heat cramps to heat exhaustion, and finally to heat stroke.
22a  Thermal  Heat Stress 4 4 16  Provision of drinking water for all work 4 2 8 Trivial risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 33 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
Radiation  Heat Stroke
 Fatigue
 Dehydration
 Collapse
locations
 Provision of electrolyte replacement additives
for drinking water supplies
 Provide shaded rest areas for all work
locations ( with fans / AC’s where poss. )
 HSE training department - Heat stress
awareness campaign
 Poster campaigns
 Regular Tool box talks ref: heat stress
 Toilets to have urine colour charts posted to
aid self assessment of dehydration levels
 Monitoring of operatives by supervisors for
signs of heat stress and sweat rash.
 Adherence to Summer working hours
regulations
 Planning of critical tasks in cooler conditions
 Provision of fans / AC’s in work areas as
appropriate
 Job rotation
 Provision of canopy’s for exposed work areas
 Provision of suitable PPE
 Availability and awareness of First Aiders
22b  UV Radiation  Sunburn
 Skin ageing
 Premature cancer
 Eye strain
 Arc eye ( welders)
6 4 24
 Selection and use of appropriate PPE
( welding masks etc )
 Training & Supervision
 Full length overalls
6 2 12 Adequately
Controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 34 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
23 Hydrostatic Testing of Pressure Mains
23 Pipe Testing  High pressure water
that may cause pipe
bursting and cause
injuries to persons
4 6 24  Arrange exclusion zones around the areas of
testing
 Insure only authorized persons are in the
exclusion zone
 PPE
 Only qualified and competent persons
conducting the tests
 Pressure testing permit system in place.
 Erect warning signage.
4 2 8 Trivial Risk
24 Joint Sealing with Hot Bitumen
24 Hot Material &
Equipment
Burns to skin & eyes 6 6 36  Use Bitumen Boiler – trained operatives only
 Use Bitumen Bucket –trained operatives only
 Wear heat resistant Gauntlets
 Wear heat resistant Boots
 Wear protective eye wear
 Job rotation to prevent heat related disorders
 Exclusion zone around the hot bitumen work
 Availability of first aiders and cool water to
flush affected area in the event of burn injury
 Comply with COSHH assessment
requirements
 Tool box talks
 Cotton coveralls to be used with hot bitumen
not nylon.
6 2 12 Adequately
Controlled
Risk
25 Lorry Hiab
25a  Hiab Lorry
overturning
 Personal injury
 Property damage
6 4 24  Lorry set up on firm and level ground
 Outriggers fully deployed
 Load pads under all outriggers
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 35 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Hiab has valid 3rd party inspection certification.
 PMV inspection prior to mobilisation
 Licensed operator
 Selection of correct crane for task ( SWL etc ).
 Weights of loads known before lifting
 Exclusion zones created around lifting
operations
 Training
 Check for drains etc before placing out-
riggers.
25b  Failure of lifting
equipment
 Personal Injury
 Property damage
6 4 24  All lifting equipment shall be 3rd party
inspected and certified as fit for purpose,
 All areas of lifting operations shall be
adequately lit
 Operators to have valid licenses
 All lift accessories shall be 3rd party inspected,
certified and comply with CCC /TAV JV colour
coding scheme for the period
6 2 12 Adequately
Controlled
Risk
25c  Equipment &
Material Handling
 Personal Injury
 Property damage
6 4 24  All equipment will be stored, handled in a safe
and proper manner.
 Offloading and storage will be properly
controlled / supervised at all times.
 Tag lines will be used to control equipment
during loading and offloading.
 Personnel will be properly trained in safe
methods of Equipment handling including the
danger of pinch points
 Erection areas will be identified and
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 36 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
unauthorized entry will be controlled by use
of barriers, warning signs and close
supervision.
 Appropriate personnel protective equipment
will be worn at all times.
 Personnel will be reminded of risks through
tool box talks.
 Period colour coded equipment.
26 Lorries Tippers & Trailers
26a Working at height
whilst Sheeting and
unsheeting of
lorries
Falls, injuries 8 6 48  Lorries with powered sheeting/ unsheeting
are preferred
 Lorries shall park in a safe place and on
even flat ground before sheeting/unsheeting
 Proper access ladders shall be provided for
manual sheeting
 Sheeting & unsheeting will be done by 2
persons, one on each side of the lorry
 Banksman shall be available during the
sheeting/ unsheeting
8 2 12 Adequately
controlled
26b Mobile phones Reduced attention
whilst driving leading to
accidents
8 6 48  No Mobile Phone shall be used whilst
driving
 Site induction to cover use of mobile phones
 Ban from site for persistent offenders
8 2 12 Adequately
controlled
26c Speeding Accidents 8 6 48  Speed limits on site.
 Adequate signage.
 Speed humps
 Speed monitoring
 Ban from site for persistent offenders
 Site induction to be delivered to all
personnel entering site.
8 2 12 Adequately
controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 37 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
26d Overhead Electrical
Cables
Elocution 8 6 48  Don’t tip under overhead cables
 Look up for overhead cables before tipping
8 2 12 Adequately
controlled
27 Manual Handling
27  Heavy loads
 Uneven loads
 Poor techniques
 Back strains
 Personal Injury
 Property damage
6 6 36  All staff HSE inducted
 Regular Tool Box Talks ref: manual handling.
 Mechanical aids to be used where possible.
 Appropriate selection of materials by
procurement Dept i.e. 25kg bags of cement.
 Blocks to be stacked on level ground close to
the work site by mechanical means.
 Job rotation for lifting tasks
 Regular breaks
 Consider 2 person lift
 No stacking above shoulder level.
 Carry out manual handling assessments for
large loads or repetitive work
 Suitable clear flat area to be used for loading /
unloading with restricted access.
6 4 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 38 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
28 MEWP ( Mobile Elevating Work Platform)
28a  General hazards  Injury 6 6 36  Do not exceed lifting capacity of MEWP
 Only carry materials thatfit inside the basket
 Trained and competentoperators
6 2 12 Adequately
Controlled
Risk
28b  Persons Falling
from height
 Personal Injury 6 6 36  All operators to have valid 3rd party
certification
 All operators to wear full body harnesses with
double lanyards
 Equipment to have secure working platform /
man basket with appropriate guard rails & toe
boards where applicable.
 All works shall be conducted from inside
platform / basket.
 List of authorised operators posted on
machines

6 2 12 Adequately
Controlled
Risk
28c  Falling objects.  Personal Injury
 Property damage
6 6 36  Exclusion zones created around working
MEWP’s.
 Only essential tools to be taken in MEWP
basket,
 Tools should be tethered where possible or
should be stored in appropriate holders
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 39 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
28d  Mechanical
Failure
 Personal Injury
 Property damage
6 4 24  All equipment to have valid 3rd party inspection
certificate
 All equipment to have PMV inspection before
mobilisation
 Pre use daily inspection
 Planned preventative maintenance schedules
 Selection of appropriate MEWP as per task
requirements
 Drivers to carry out daily / weekly inspection of
MEWP,
6 2 12 Adequately
Controlled
Risk
28e  Overturning
MEWP
 Personal Injury
 Property damage
6 6 36  If fitted, out riggers fully deployed with use of
load pads
 SWL posted on machine
 On unpaved areas ensure ground is
compacted and stable. The correct type of
MEWP to be used for the area.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 40 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
29 Night-work
29a  Insufficient
Lighting
 Traffic collisions
 Property damage
 Personal Injury
8 6 48  Appropriate lighting as per Procedure for
Night Works: PP727-NWP-1008.
 Lighting plans and night works permits to be
provided by CCC /TAV JV HS&E department.
 Nominated person responsible per shift to
ensure that all lighting is compliant with OAMC
requirements
 Tower lights to be setup so the light beam shines
across the runway (North to South) so as not to be
a distraction to pilots on finals to landing.
 The max heightof ground based tower lightmasts
to be limited to 13m.
 Lighting established on raised bridge decks to be
approved by OAMC
 Lights to have welded restrictors to ensure the light
beam is downwards facing.
 Lighting control will be via liaison with the OAMC
 Light Towers erected on firm / level ground
 A PMV mechanic will be available for
maintenance work.
 Safety cover
 Emergency contact #’s posted.
 Inspection by supervisor
 Vehicular access route to be adequately
signposted and illuminated.
8 2 16 Adequately
Controlled
Risk
29b  Lighting Nuisance
to public roads
 Risk of traffic
collisions
 Complaints from
public
8 6 48
All lighting beams shall be suitable shaded to
prevent unwanted distraction to public roads
Lightbeams shall be directed down wards to flood
requisite task only
8 2 16 Adequately
Controlled
Risk
30 Night Emergency Procedures
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 41 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
30  Emergency
situations
 Property damage
 Personal injuries
 Disruption to project
6 4 24  Project specific emergency plan created
 Emergency procedure included in induction
and reiterated in briefings and Tool box talks.
 Emergency contact details posted on site
notice boards and office bulletin boards
 Emergency contact detail cards distributed to
all supervisory staff
 Emergency facilities on standby ( ambulance /
fire engine / clinic )
 Trained First Aiders available throughout the
site
 Trained fire wardens available throughout the
site
 Fire points / first aid boxes available
throughout the site
 Incident control room established at MC 1
offices
 Duty Incident Controller Rota established
 Scheduled emergency drills
 Liaison with civilian emergency services
6 2 12 Adequately
Controlled
Risk
31 Noise High levels
31  High Noise levels  Threshold shift
 Noise induced
hearing loss
 Tinnitus
 Miscommunications
4 6 24  Monitoring of noise levels and signs placed in
high noise areas.
 Provision of sound screens where appropriate
to mitigate high noise levels generated by
plant / machinery
 Creation of high noise area exclusion zones
 Availability of suitable Hearing protection as
required
 Mandatory PPE use for noise levels above 85
4 2 8 Trivial Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 42 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
dB.
32 Overhead Cables Electrical
32 a  Electricity
 Contact with
cables
 Burns
 Electrocution
 Fatality
 Property damage
 Disruption to utility
services
8 6 48  Create fixed barrier exclusion zones & traffic
marshalling zones with appropriate signage
 Erect goal posts with cross bars for passing
under ( constructed of non conductive
materials )
 When working underneath banksman to
control plant movements
 Overhead power lines identified at earliest
possible time
 Power Company contracted to establish
voltage, height and safety clearance
 Where possible, overhead lines de-energised
or relocated prior to any works
 Hazards identified by warning signs / notices,
goal posts where necessary
 Inform all site personnel of danger and ensure
a safe system of work is adopted
 Provide adequate / competent supervision
 All temporary structures in vicinity to be
suitably earthed against possibility of arcing
caused by overhead cables
 Operate Permit to Work.
8 2 16 Adequately
controlled
risk
32 b Poor Lighting  Inability to discern
power lines
6 4 24  All works in proximity to overhead lines will be
suspended unless approved task lighting and
adequate supervision is provided
6 2 12 Adequately
Controlled
Risk
32 c Adverse weather  Increased risk of
atmospheric
6 4 24  Works suspended as dictated by HSE
department eg: during electrical storms etc
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 43 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
conductivity and
arcing
 Exclusion zones widened in humid conditions
33 Paving Bituminous with Machine & Milling
33a  Struck or rolled
over by Lorries.
 Trapping.
 Crushing
 Broken limbs.
 Fatality
8 6 48  Banksman to control reversing lorries
 Drivers to hold valid licence
 Correct PPE i.e. safety boots, gloves, hard
hats.
 Traffic calming measures shall be
implemented as appropriate
 A flagman will be in attendance when required
to guide vehicles safely into and out of the site
 All drivers must have an appropriate license
for the particular piece of plant they are using
 Exclusion zones created around work area
 Roads closed and diverted as appropriate
 Posting of suitable warning signage
8 2 16 Adequately
Controlled
Risk
33b  Hazardous
chemicals
 Contact Burns
 Skin irritation
6 6 36  MSDS and COSHH assessments to be
produced, followed and submitted to the
Engineer for all hazardous materials to be
used
 Correct PPE to be worn when using
hazardous substances, as per COSHH
assessment
6 2 12 Adequately
Controlled
Risk
33c  Milling Machines  Injury 6 6 36  Trained and Experience driver
 Banksman to control reversing.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 44 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
34 Pipe-Jacking
34a Excavation Slips, trips & falls
Serious Injury
6 6 36  Follow good housekeeping at site
 Remove rocks and debris from the area
 Follow method of statements
6 2 12 Adequately
Controlled
Risk
34b Noise Occupational illness 6 6 36  Proper Maintenance of Vehicle and
Equipment
 Use ear protection
6 2 12 Adequately
Controlled
Risk
34c Damage to Utilities Property Damage 6 6 36  carry out survey of the area before work
 Install "goal Post" to prevent machines hitting
overhead lines.
 Certified / Qualified operators to Operate the
equipment
 Manual excavation were mechanical
excavation is not practical,
6 2 12 Adequately
Controlled
Risk
34d Persons being
struck by plant or
other vehicles
Serious Injury / Death 6 6 36  A dedicated Flag man at all times
 lag man must wear reflective vest
 Operators must not use mobile phones while
operating machines
 People on foot must be kept clear of the area.
6 2 12 Adequately
Controlled
Risk
34e Persons Falling in
to pits
Serious Injury 6 6 36  Barricade & put signage in trenched area
 Prevent access to unauthorised people
 Install "STOP" blocks if necessary
 Ensure ladder and life line for rescue
operation
 Ensure standby vehicle & trained person at
site always for emergency.
6 2 12 Adequately
Controlled
Risk
34f Vehicle Equipment
/Materials falling
into pits (Pipe, sand
Etc.)
Property Damage 6 6 36  Do not park vehicle near trench
 Do not store excavated materials close to the
trench
 Ensure pipes are chocked & kept 1.5mtrs from
trench
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 45 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
34g Collapse of Pit
walls or sides
Injury 6 6 36  Ensure trench walls are well supported, use
shoring if necessary
 Slope sides when excavating in sand / loose
soil
 The excavation must be inspected daily,
before work start, by a competent person.
6 2 12 Adequately
Controlled
Risk
34h Hazardous fume
accumulation in pits
Serious Injury/death 6 6 36  Do not use petrol / Diesel Engines in
trenches- exhaust gases can accumulate.
6 2 12 Adequately
Controlled
Risk
35 Pinch Points
35 Pinch Points  Hand Injuries
 Body Injuries
6 6 36  Keep workplace clean & tidy
 Wear gloves
 Never tamper with machine guards
 Care when handling equipment & materials
 Know how to turn off machinery in an
emergency
 Don’t wear loose cloths or jewellery when
working near machines
6 2 12 Adequately
Controlled
Risk
36 Plant , Equipment & Plant Operators
36  Plant & Plant
Operators
 Injury
 Property Damage
6 4 24  All plant to be operated by suitably licensed
and competent operators.
 All reversing vehicles to be controlled by a
trained banksman
 All mobile plant to have audible reversing
alarm
 Blind spots to be mitigated by appropriate
mirrors.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 46 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Site driving rules enforced.
 All necessary lights should be in place on
vehicles including orange flashing beckons
and should be used at all times as well as
being regularly inspected.
 Vehicle Lights, windows and mirrors shall be
cleaned regularly to ensure a clear view.
 Exclusion zones created around working plant
 PPE, specific to night works i.e. clear lens
glasses.
 Operators to be trained, competent and hold
current Omani Licences.
 Stationary plant to have drip trays.
 Emergency procedures in place
37 Plant Repairs, Maintenance, Assembling & Dismantling
37 Electrocution  Injury 6 4 24  Provide access
 Task lighting
 Trained & competent fitters
 Electrical cables to be insulated
 Use correct tools
 Exclusion zones created around work area
 Stationary plant to have drip trays.
6 2 12 Adequately
Controlled
Risk
38 Plant Collision
38 Collision with other  Injury 6 4 24  Banksman to guide and coordinate the 6 2 12 Adequately
Controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 47 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
plant  Damage movements of plant items working in close
proximity and reversing plant
 Vehicles not to be parked in swing area of
cranes or excavators etc.
Risk
Collision with
persons
 Injury 6 4 24  No person to stand sit or walk near working
cranes excavators etc
 No person shall sleep or take rest under plant
 No unauthorised access
 Reversing Alarms fitted.
 Exclusion zones created around working plant
6 2 12 Adequately
Controlled
Risk
39 Reinforcement
39  Protruding steel  injury 6 4 24  Starter bars covered by timbers or caps
 Binding wire bent away
6 2 12 Adequately
Controlled
Risk
 Cutting  injury 6 4 24  Wear grinder glasses
 Abrasive wheel training
6 2 12 Adequately
Controlled
Risk
40 Road Works
40a  Working on or
near roads
 Personal Injury /
Fatality
6 4 24  Suitable NOC’s shall be obtained for all road
works prior to works commencing
 The working area should be barricaded and
signs erected so that vehicle drivers are
informed
 Drivers shall follow site driving rules at all
times.
 Suitable lighting shall be provided for all areas
of operation
 Traffic calming measures shall be
implemented as appropriate
6 2 12 Adequately
controlled
risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 48 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
40b  Collision with
plant or traffic
 Vehicles gaining
access to the site
from poorly
designed Traffic
Management
 Falls into
excavations or
from plant
 Serious/fatal injuries
from falls or collisions
 Hand, foot and eye
injuries from contact
with hazardous
materials or flying
particles
8 6 48  Correct signing/coning/barriers in place for all
roadwork’s and path works. Signs made
stable by sandbags
 Safe access for vehicles, plant and persons.
Correct placing of signage shall ensure that
public vehicles do not enter the work area.
 A flagman will be in attendance when required
to guide vehicles safely into and out of the site
 Safe crossing of traffic lanes
 Fixed barriers erected around any excavations
which are 2 metres or more in depth
 Open excavations fenced and illuminated at
night with adequate signage
 Adequate space and sufficient time allocated
to the job
 Noise minimised where possible
 High-visibility clothing worn
8 2 16 Adequately
Controlled
Risk
40c Realignment of Sultan Qaboos Street
Step 1 - Realignment Built off line
 Collision with Site  Injury 8 6 48  A flagman will be in attendance when required 8 2 16 Adequately
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 49 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
Traffic to guide vehicles safely into and out of the site Controlled
Risk
Step 2a - Temporary Link Roads & widening SQS
 Vehicles gaining
access to the site
 Injury
 Property damage
8 6 48  Signage
 Barriers
8 2 16 Adequately
Controlled
Risk
Step 2b - Diverting Live Traffic
 Road accidents  Injury 8 6 48  Signage
 Police escort for first cars
 Method Statement to give methodology and
sequence.
8 2 16 Adequately
Controlled
Risk
Step 3a - Tie-ins construction
 Collision with Site
Traffic
 Injury 8 6 48  A flagman will be in attendance when required
to guide vehicles safely into and out of the site
8 2 16 Adequately
Controlled
Risk
Step 3b - Diverting Live Traffic
 Road accidents  Injury 8 6 48  Signage
 Police escort for first cars
8 2 16 Adequately
Controlled
Risk
 
   Method Statement to give methodology and
Step 4 - Removal of Redundant section of SQS
 sequence.
 Vehicles gaining
access to the site
 Injury
 Property damage
8 6 48  Signage
 Barriers
8 2 16 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 50 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
Step 5 Work in Median
 Traffic Accidents  Injury 8 6 48  Close outside lane
 Night work
 Proper access off SQS
8 2 16 Adequately
Controlled
Risk
40 D Working site side of Temporary Road Barriers
 Struck by road
vehicle crashing
thru barriers
 Injury
 Property damage
8 4 24  Where possible restrict persons on the ground
( not drivers in machines) working, standing or
walking within a 10m danger zone inside the
barriers
 Warning signage
 Workers to be warned of the risks
8 2 16 Adequately
Controlled
Risk
41 Road Saw
41  Using Saw
machine
 Cuts, injuries, eye
injuries, Dust
6 4 24  Training to personnel
 Permit system for operators
 Inspect the equipment regularly
 Test the machine prior setting for cutting
 Change the blade regularly
 Wear Eye protection
 Wear Dust mask.
 Set up exclusion zone with barriers and
signage
6 2 12 Adequately
Controlled
Risk
42 Scaffolding
42  Structural  Personal Injury 8 6 48  Temporary works structural design. 8 2 16 Adequately
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 51 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
collapse
 Works at height
 Fall of materials
 Fall of persons
 Property  Competent supervision
 Only essential personnel and equipment to be
allowed on to raised working platforms.
 Regular briefings, tool box talks and night
works activity briefs to be given related to
working at height.
 All temporary working platforms ( scaffold
systems ) shall be erected by trained and
competent personnel
 All scaffold systems shall be regularly
inspected by competent persons every 7
days.
 All scaffold systems shall display a valid
(signed and dated) scaff tag to identify if safe
to use
 Use fall arrest harnesses on scaffolding and
falsework systems
 Use double rail fixed barriers and toe boards
on leading edges.
 Use of suitable load rated steel life lines in
absence of fixed guard rails
 Adequate signage and exclusion zones
around temporary structures
 Structural design sign off before loading
controlled
risk
43 Steel Structures Erection
43  Works at height
 Adverse weather
conditions
 Lifting operations
 Property damage
 Personal Injury
6 6 36  The work carried out in accordance with a
design plan
 Erection carried out by competent workers
 Pre work briefings ref: MS and RA
 Training & Supervision
 Use of appropriate PPE
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 52 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 See Works at height section
 See Lifting operations section
 Trained riggers in attendance.
44 Welding & Cutting
44 a  Fire and
explosion
 Thermal
Radiation
 Ultra-violet
radiation
 Gases and fumes
 Electricity
 Burns
 Electric shock,
electrocution
 Arc Eye
 Heat Disorders
 Respiratory problems
 Systemic poisoning
from fumes
 Fire initiation and
spread
6 6 36  Hot work Permits
 Tool Inspections
 Welding screens
 All hot works conducted by suitably trained
and competent persons
 Proper identification and storage of acetylene
and oxygen tanks
 All cutting / welding rigs to be fitted with flash
back arrestors
 Provision of suitable PPE
 Remove all combustible materials from areas
of hot works
 Fire watch for 30 mins post hot work activity
 Provision of suitable task lighting
 Provision of suitable ventilation ( dilution /
forced )
 Atmospheric testing as required ( confined
space etc )
 All cylinders when being transported shall
have the protective guards or caps in place
over the valve assemblies. They should be
transported in an upright position to and from
the site in the special racks provided for this
purpose.
 Eliminate damp conditions.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 53 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
44 b  Grinding
Operation
 Disc
Disintegration
 Lacerations [may be
severe, even fatal.
 Penetrating injuries
 Eye Injury
6 6 36  Use of approved suppliers
 Use of appropriate speed rated discs
 Use of task specific discs
 Use of correctly adjusted guards
 Use of suitable PPE ( body / hands / face /
eyes /ears )
 Trained and competent persons only to use
abrasive wheels / change discs
 All electrical equipment to be 110V with
industrial sockets
 Routine inspection / testing
 All electrical equipment colour coded
 Damaged equipment tagged and taken out of
service
 All cutters and grinders regularly maintained
 No loose clothing worn
 Adequate training & supervision
 activities
 Abrasive wheel signs.
 Eye protection – high impact glasses at all
times.
 Eye wash station on site
6 2 12 Adequately
Controlled
Risk
45 Working at Height On Scaffolding & Other Platforms
45  Persons Falling  Personnel injuries 8 6 48  Temporary works structural design.
 Competent supervision
 Regular briefings, tool box talks and night
works activity briefs to be given related to
working at height.
8 2 16 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 54 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 All temporary working platforms ( scaffold
systems ) shall be erected by trained and
competent personnel
 All scaffold systems shall be regularly
inspected by competent persons every 7 days
 All scaffold systems shall display a valid
(signed and dated) scaff tag to identify if safe
to use
 Use fall arrest harnesses on scaffolding and
falsework systems
 Use double rail fixed barriers and toe boards
on leading edges.
 Use of suitable load rated steel life lines in
absence of fixed guard rails
 Adequate signage and exclusion zones
around temporary structures
Structural design sign-off before loading.
 Operate Permit to Work
 Loading platforms provided for materials &
equipment
 Materials to be securely & safely stacked.
 Provide safe access and egress for personnel.
 Falling Objects  Personnel injuries 8 6 48  Only essential personnel, materials and
equipment to be allowed on to raised working
platforms.
 Use and toe boards on leading edges.
 Materials to be securely & safely stacked.
 Erect signs re danger of falling objects
 All tools being used in areas with open edges
must be secured using lanyards, attached to
the operative, or the fixed lines.
8 2 16 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 55 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Exclusion zones to be set up underneath
working area, with use of demarcation barriers
and signage.
 Inadequate
access & egress
 Personnel injuries 8 6 48  Proper and safe ladder or stairs access to
heights will be provided
8 2 16 Adequately
Controlled
Risk
46 Working On, Above or Near Water
46 Water  Drowning
 Physical effects of
swallowing
contaminated water
4 6 24  Warning signs
 No lone working
 Edge protection where practical
 Safety lines and harnesses if edge protection
is not present
 Lifebuoys and rescue lines
 Access routes free of hazards
4 2 8 Trivial Risk
47 Working Airside
47a General  Injuries
 Property Damage
6 6 36  Site HSE Project Procedures
 Work Permit Systems
 Method Statement for Risk Activities
 Risk Assessments
6 2 12 Adequately
controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 56 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 On Site Safety Training
 HSE Supervision
 Issue of PPE
 Tool box Talks Works to be made
knowledgeable on site specific Safety risks.
 COSHH Assessments
 On site Medical Clinic
 Site Emergency Response Plan
 Site Health, Safety & Environmental Plan
 First Aid Kits available
 First Aiders
 Site Inductions for Employees
 Welfare Facilities
 Waste bins
 Managers must take responsibility and
accountability for HSE Management
 Training and implement above.
 Welfare Facilities
 Emergency Contact list
 Emergency Contact List
47b Security Risk
Bombings,
Shootings.
Hijacking
 Multiple Fatalities 4 6 24  Security Passes
 Check vehicles entering Airside
4 2 8 Trivial Risk
47c Breaking
Navigational Aids
 Closure of Airport
Runway
4 6 24  Fence off 4 2 8 Trivial Risk
47d Breaking
underground power
supply to landing
 Closure of airport
runway
 Elocutions
6 6 24  Scan check for underground services
 Supervision
 Area to be visually checked for markers or
physical signs of services, i.e. manholes.
6 2 12 Adequately
Controlled
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 57 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
lights and IT cables  Up to date drawings detailing existing services
shall be obtained and checked thoroughly.
 OAMC shall be contacted to assess if there
are services in the area and also to let them
know work is going to be carried out.
 Obtain Dig permit from OAMC.
 Use of trial holes and hand excavation around
known services
 Hand tools that are non conductive shall be
used when excavating around existing
services.
 Prior to excavation the affected area shall be
surveyed with a CAT and competent person.
 Records of all CAT surveyed areas to be kept
on file and briefed to excavation team
 Surveyed area clearly demarked on site
 Emergency contact numbers displayed on site
47e Collision with
Aircraft in flight
 Multiple Fatalities 4 6 24  Communication with ATC
 Observe height limits
4 2 8 Trivial Risk
47f FODs (Foreign
Object Debris)
 Aircraft damage
 Aircraft engines may
get damaged
4 6 24  All FODs to be cleared after the job is done
 Good housekeeping
4 2 8 Trivial Risk
47g Noise Fight jets  Injury to hearing 4 6 24  Issue Ear protection 4 2 8 Trivial Risk
47h DUST
Source of
emissions from
dust/particulates
during leveling,
scraping, and earth
moving operations
 Reduced visibility
 Due to increased
emissions, impacts
on human health
within the site and
neighboring areas
4 6 24  Regular water spraying of unpaved and
sweeping of paved roads to minimize dust
and remove mud
 Sheeting vehicles carrying dusty materials
to prevent materials being blown from the
vehicle whilst travelling
 Reducing the quantity of dusty materials
4 2 8 Trivial Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 58 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
via traffic
movements to and
from site.
stored on site or covering stored material to
minimize the amount of dust being blown
47i Mud Control
Vehicles exiting the
work site may carry
mud onto adjacent
roads
 Road
Contamination
 Slips
4 6 24  Vehicles going from the work site onto
paved roads must be free of excessive
mud.
4 2 8 Trivial Risk
47j Moving Plant
 Injuries
 Collisions
 Property Damage
6 6 36  Banksman to guide and coordinate the
movements of plant items working in close
proximity and reversing plant
 Vehicles not to be parked in swing area of
cranes or excavators etc.
 No person to stand sit or walk near working
cranes excavators etc
 No person shall sleep or take rest under plant
 No unauthorised access
 Reversing Alarms fitted.
 Exclusion zones created around working plant
6 2 12 Adequately
Controlled
47k Birdstrike  Aircraft damage
 Aircraft engines
may get damaged
6 6 36  Don’t feed birds
 Remove all waste food immediately
 Report any birds to Airport Authority
6 2 12 Adequately
Controlled
48 Operating Vibrating Hand Tools
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 59 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
48a
48b
Vibration  Vibration White Finger
 Hand-Arm Vibration
Syndrome (HAVS)
6 6 36  Limit exposure time i.e. actual trigger time
 Regular breaks
 Job rotation
 Ensure tools are used correctly and
maintained.
 Wear gloves
 Oil the tool daily before use.
6 2 12 Adequately
Controlled
Risk
Dust  Eye injury
 Dust Inhalation
6 6 36  Wear dust mask.
 Wear goggles
6 2 12 Adequately
Controlled
Risk
49 Poor Housekeeping
49 Housekeeping  Skin puncture.
 Dust inhalation.
 Material handling
injuries.
6 6 36  Toolbox talks.
 Signs and posters.
 PPE issue and training. Police use of.
 Supervised daily by site supervisors
6 2 12 Adequately
Controlled
Risk
50 Working in Live Sewer Manhole (Haya Manhole # 17)
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 60 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
50  Illnesses e.g.
diarrhea,
Hepatitis,
Weill’s disease
 Health problems 6 6 36  Provide suitable personal protective
equipment, that include waterproof/abrasion-
resistant gloves, footwear, eye and respiratory
protection.
 Disposable overalls
 Power wash inside of manhole with
disinfectant
 Provide washing facilities with disinfectant
6 2 12 Adequately
Controlled
Risk
 Water &
Sewage
 Drowning 6 6 36  Over-pump manhole from manhole upstream
to manhole downstream which will have
inflatable stoppers fitted to outlet and inlet
pipes.
6 2 12 Adequately
Controlled
Risk
Note - Permit Confined Space because of Hazardous Gases danger
Refer to Site HSE Project Procedure PP710 for Confined Spaces
 Hazardous
Gases
 Fumes
 Health problems
6 6 36  Note - Depending on circumstances select
from following
 Vent manhole including upstream &
downstream manhole for 24 hours
 Provide good ladder access.
 Smoking Prohibited.
 No Working Alone,
 Standby Person on surface fulltime in verbal
and visual contact with worker. Will execute
non-entry rescue and raise emergency alarm.
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 61 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 No petrol or diesel engines in manhole
 No combustible material stored in manhole
 Permit to Work System
 Personnel Training in Confined Spaces
 Gas Monitoring for toxic gases & permissible
oxygen levels. Before & during manhole
occupancy.
 Force Ventilation
 Rescue Harness (connected to Lifeline
leading to outside)
 Tripod erected or crane / excavator on
standby to lift out worker
 Rescue Equipment - Self Rescuers carried

51 Felling Trees
51  Struck by falling
tree / branch
 Injury
 Property Damage 6 6 36
 Establish and maintain exclusion zone
minimum the greater than the length of tree to
be felled
 Don’t fell a tree in windy conditions
 Trees to be felled towards a clear open area
 Maintain awareness of potential butt recoil /
deflection.
 Ensure felling operations do not damage
features
 Remove potential trip hazards
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 62 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 Use 3 cut technique ( undercut, top cut, final
cut)
 Chainsaw  Injury
 Cuts and abrasions
 Noise
 Eye injury
6 6 36
 Operator to be trained and competent
 Chainsaw shall be maintained
 Ensure guards are in place and the saw is in
good working order.
 Wear ear muffs
 Restrict work to 30 minutes between breaks
 Wear safety glasses
 Two hand operation
 Suspend work during severe weather
6 2 12 Adequately
Controlled
Risk
52 Post tensioning
 52 a Fixing Anchorages 
 Falling materials
 Equipment
failure
 Crane failure
 Working at
Height
 Physical Injuries
 Equipment & Material
damage
6 4 24  Refer to Mobile Cranes – Lifting Operations in
this document
 Only essential personal and equipment
allowed on to working area / platform
 Refer to Working at Height in this document
 Use proper tools while fixing cast in trumpet
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 63 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 52 b Placing Ducts 
 Working with
sharp edges
 Works at height
 Working with
flame torch
 Cuts
 Physical Injuries
 Equipment & Material
damage
 Burns
6 4 24  Wear gloves
 Use of Trained personnel
 Competent supervision
 Control of access to work location
 Hot work Permits
 Flask back arrestors
 Fire precautions ( extinguishers etc )
 Remove all combustible materials from areas
of hot works
 Fire watch for 30 mins post hot work activity
 All hot works conducted by suitably trained
and competent persons
6 2 12 Adequately
Controlled
Risk
 52 c Threading Strand 
 Being struck by
strand.
 Entanglement
 Injury from sparks
when cutting
strand
 Working at height
 Physical Injury 6 4 24  Use the correct tools
 Position strand coil in dispenser prior to
cutting straps
 Exclusion zone set up around area
 Using Trained operatives
 No loose clothing to be worn by operatives of
threading machine
 Wearing suitable gloves
 Face shield to be worn
 Competent supervision
 Hot works controls
 Refer to Working at Height in this document
 Know how to turn off machinery in an
emergency using emergency switch
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 64 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 52 d Stressing Strand
 Burst hydraulic
hose
 Overstressing of
strand
 Strand Breaking
 Confined space
works
 Concrete failure
 Hardware failure
 Working at height
 Fatalities/ physical
injuries.
 Equipment and
material damage
10 4 40  All stressing equipment and accessories to be
certified and inspected prior to use.
 Forces applied shall be properly calculated
and applied as the specification.
 Workers shall be made aware that the forces
they are handling during stressing are
enormous and carelessness may lead to loss
of life.
 Regularly examine hydraulic hoses, hydraulic
equipment shall be fitted with suitable quick
connecting couplers.
 Check concrete strength by cube tests.
 Place safety solid timber plywood barrier
behind stressing jack
 Erect signs – Danger no Entry
 During stressing persons will not stand or
cross behind or close to the jack and not in
line with the anchorage at the non jacking
end, or behind any tendons anchor already
stressed.
 Trained and authorized operatives only
 Competent supervision
 Strand to have certificates.
 Refer to Working at Height in this document
 Refer to Confined Spaces in this document
 Know how to turn off machinery in an
emergency using emergency switch
10 2 20 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 65 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
 52 e Grouting & Sealing
Grouting Chemicals  Eye irritations
 Contact dermatitis
 Mild burns
6 6 36  Wear suitable protective eye wear
 Compliance with COSHH assessment
 Have eye station on hand
 Wash hands after each exposure
 Use of gloves
 Use of full length uniforms
 First Aiders available
6 2 12 Adequately
Controlled
Risk
Use of cement
mixers
 Broken arms
 Strains
 Cuts
 Electrocution
6 6 36  All necessary guards are to be in place on the
mixer.
 All equipment is to be inspected by a
competent person to ensure the equipment is
mechanically and electrically safe.
 No persons are to put tools or limbs in to mixer
while drum is rotating.
 Mixer is to be set up on firm level ground and
should never be over loaded
 110V plant only on project.
 Suitable earthing of static plant
 Planned preventative maintenance
 PMV inspection prior to mobilisation
6 2 12 Adequately
Controlled
Risk
Use of grout pump
Bursting of hose
pipes
 Personal injuries 6 6 36  Use whip arrestor on feed lines
 Inspect all the equipment and accessories
prior to use
 Ensure hoses are maintained
 Trained / authorised operators
 Know how to turn off machinery in an
6 2 12 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 66 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
emergency.

 52 f De-tensioning & Re-tensioning 
 Burst hydraulic
hose
 Overstressing of
strand
 Strand Breaking
 Confined space
works
 Concrete failure
 Hardware failure
 Working at height
 Fatalities/ physical
injuries.
 Equipment and
material damage
10 4 40  All stressing equipment and accessories to be
certified and inspected prior to use.
 Forces applied shall be properly calculated
and applied as per specification
 Workers shall be made aware that the forces
they are handling during stressing are
enormous and carelessness may lead to loss
of life.
 Regularly examine hydraulic hoses, hydraulic
equipment shall be fitted with suitable quick
connecting couplers.
 Check concrete strength by cube tests.
 Place safety solid timber plywood barrier
behind stressing jack
 Erect signs – Danger no Entry
 During stressing persons will not stand or
cross behind or close to the jack and not in
line with the anchorage at the non jacking
end, or behind any tendons anchor already
stressed.
 Trained and authorized operatives only
 Competent supervision
 Strand to have certificates
 Refer to Working at Height in this document
 Refer to Confined Spaces in this document
 Know how to turn off machinery in an
emergency using emergency switch.
10 2 20 Adequately
Controlled
Risk
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 67 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
53 Hydraulic Pump & Jacks
 Plant & Plant
Operators
 Injury
 Property Damage
6 4 24  All plant to be operated by competent
operators.
 Exclusion zones created around working plant
 Stationary plant to have drip trays.
 Know how to turn off machinery in an
emergency.
6 2 12 Adequately
Controlled
Risk
54 Traffic Management
 Moving Delivery
Vehicles
Entering/Leaving
site
 Traffic accidents
 Property damage
 Personal injury
6 6 36  Good visibility of oncoming vehicles.
 Traffic calming measures such as speed
bumps
 Pedestrian routing. High visibility clothing.
 Reversing alarms.
 All vehicle reversing controlled by trained
banksman.
 Adequate signage
 Adequate lighting at site entrances
 Site driving rules posted
 Security marshalling traffic
 All CCCTAVJV / Subcontractors drivers HSE
inducted
 All drivers to hold valid Omani license
 Authorised vehicles only on site
 Security identify drop zones & advise delivery
drivers on site traffic rules.
6 2 12 Adequately
Controlled
Risk
55 Auger Boring with Casing
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 68 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
a Excavation Slips, trips & falls
Serious Injury 4 6 24
 Follow good housekeeping at site
 Remove rocks and debris from the area
 Follow method of statements
4 4 16
Adequately
Controlled
Risk
b Noise Occupational illness
4 6 24
 Proper Maintenance of Vehicle and
Equipment
 Use ear protection
4 6 24
Adequately
Controlled
Risk
c Damage to Utilities Property Damage
4 6 24
 Carry out survey of the area before work
 Certified / Qualified operators to Operate the
equipment 4 4 16
Adequately
Controlled
Risk
d Persons being
struck by plant or
other vehicles
Serious Injury / Death
4 4 16
 A dedicated Flag man at all times
 Flag man must wear reflective vest
 Operators must not use mobile phones while
operating machines
 People on foot must be kept clear of the area.
 Trained operators
 Demarcation fence for restricted area
 Authorised personnel only
4 4 16
Adequately
Controlled
Risk
e Persons Falling in
to pits
Serious Injury
4 6 24`
 Barricade & put signage in trenched area
 Prevent access to unauthorised people
 Install "STOP" blocks if necessary
 Ensure access and egress
4 4 16
Adequately
Controlled
Risk


 Ensure standby vehicle & trained person at
shaft side
Health & Safety Construction RISK ASSESSMENTS 96 pages
Page 69 of 92
Activ
ity
HAZARD EFFECT
RISK ANALYSIS /
NO CONTROLS
CONTROL MEASURES
RISK ANALYSIS /
WITH CONTROLS
Residual
Risk
remarks
severity likelihood risk severity likelihood risk
f Vehicle Equipment
/Materials falling
into pits (Pipe, sand
Etc.)
Property Damage
4 4 16
 Do not park vehicle near trench
 Do not store excavated materials close to the
trench
 Ensure pipes are chocked & kept 1.5mtrs from
trench
 Trained banksmen
4 4 16
Adequately
Controlled
Risk
g Collapse of Pit
walls or sides
Injury
4 6 24
 Ensure trench walls are well supported, use
shoring if necessary
 Slope sides when excavating in sand / loose
soil
 The excavation must be inspected daily,
before work start, by a competent person.
4 4 16
Adequately
Controlled
Risk
h Hazardous fume
accumulation in pits
Serious Injury/death
4 4 16
 Do not use petrol / Diesel Engines in shafts -
exhaust gases can accumulate.
 Ensure good ventilation
 Good house keeping
4 4 16
Adequately
Controlled
Risk
i Confined Spaces /
Ventilation
Serious Injury/death 4 6 24  Confined spaces procedure in place
 Permit to entre
 Use of Gas Monitor
 Use of proper ventilation inside sleeve pipe
(fans etc).
 All personnel involved to be aware on
confined space working including rescue,
4 4 16 Adequately
Controlled
Risk

Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages
Risk Assessments 96 pages

More Related Content

What's hot

Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis soumenmakar
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templatesDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
17 traffic operations working on live roads risk assessment templates
17 traffic operations   working on live roads risk assessment templates17 traffic operations   working on live roads risk assessment templates
17 traffic operations working on live roads risk assessment templatesDwarika Bhushan Sharma
 
working at height
working at heightworking at height
working at heightJYOTHISHKT
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptKamran Zafar
 
Emergency response osha 2012
Emergency response osha 2012Emergency response osha 2012
Emergency response osha 2012Charles Brawley
 
Confined Space.ppt
Confined Space.pptConfined Space.ppt
Confined Space.pptNizar541646
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templatesDwarika Bhushan Sharma
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations Amol Pawar
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at heightsankarnagar
 
Site induction uks 2007 2011
Site induction uks 2007   2011Site induction uks 2007   2011
Site induction uks 2007 2011Clive Burgess
 
Working Safely around Plant and Equipment
Working Safely around Plant and EquipmentWorking Safely around Plant and Equipment
Working Safely around Plant and EquipmentDjCurrie
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety InductionJames McCann
 

What's hot (20)

Job safety analysis
Job safety analysis Job safety analysis
Job safety analysis
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
17 traffic operations working on live roads risk assessment templates
17 traffic operations   working on live roads risk assessment templates17 traffic operations   working on live roads risk assessment templates
17 traffic operations working on live roads risk assessment templates
 
working at height
working at heightworking at height
working at height
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
Work At Height
Work At HeightWork At Height
Work At Height
 
PPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie EPPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie E
 
BANKSMAN TRAINING.ppt
BANKSMAN TRAINING.pptBANKSMAN TRAINING.ppt
BANKSMAN TRAINING.ppt
 
Emergency response osha 2012
Emergency response osha 2012Emergency response osha 2012
Emergency response osha 2012
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
Confined Space.ppt
Confined Space.pptConfined Space.ppt
Confined Space.ppt
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at height
 
Site induction uks 2007 2011
Site induction uks 2007   2011Site induction uks 2007   2011
Site induction uks 2007 2011
 
Working Safely around Plant and Equipment
Working Safely around Plant and EquipmentWorking Safely around Plant and Equipment
Working Safely around Plant and Equipment
 
Amn safety induction j 175 - staff rev 4 - s 14
Amn safety induction  j 175 - staff rev 4 - s 14Amn safety induction  j 175 - staff rev 4 - s 14
Amn safety induction j 175 - staff rev 4 - s 14
 
A Part 1 Safety Induction
A  Part 1 Safety InductionA  Part 1 Safety Induction
A Part 1 Safety Induction
 

Similar to Risk Assessments 96 pages

JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdfJHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdfJESUSBASILIOANTONIO
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJESUSBASILIOANTONIO
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside ConstructionDavid H Moloney
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfJESUSBASILIOANTONIO
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Hazard identification and risk analysis in mining industry
Hazard identification and risk analysis in mining industryHazard identification and risk analysis in mining industry
Hazard identification and risk analysis in mining industrygopal karmakar
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and ControlsAbbas Tahir
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...Dwarika Bhushan Sharma
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...Dwarika Bhushan Sharma
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxAamirAbbas75
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Compling with terminal process safety
Compling with terminal process safetyCompling with terminal process safety
Compling with terminal process safetyPreeju Anirudhan
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment filechopriroti
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docxDwarika Bhushan Sharma
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...MohammedAliQazi
 

Similar to Risk Assessments 96 pages (20)

JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdfJHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
JHA06_Installation of Transversal beams in Flare Pipe Rack_Rev00.pdf
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdfJSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
JSA01_De-Ethanizer_Foundation_Execution_Rev00.pdf
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
LPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdfLPG Chloride treaters foundation execution_Rev.00.pdf
LPG Chloride treaters foundation execution_Rev.00.pdf
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Hazard identification and risk analysis in mining industry
Hazard identification and risk analysis in mining industryHazard identification and risk analysis in mining industry
Hazard identification and risk analysis in mining industry
 
Demolition Hazards and Controls
Demolition Hazards and ControlsDemolition Hazards and Controls
Demolition Hazards and Controls
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
 
31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptx
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
Compling with terminal process safety
Compling with terminal process safetyCompling with terminal process safety
Compling with terminal process safety
 
Fire Suppression System Risk assessment file
Fire Suppression System Risk assessment fileFire Suppression System Risk assessment file
Fire Suppression System Risk assessment file
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
Appendix 23.3 HS-RA-33 Demobilization of Site Offices Welfare Facilities Stor...
 

More from David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824David H Moloney
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionDavid H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTERDavid H Moloney
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution PlanDavid H Moloney
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionDavid H Moloney
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 kmDavid H Moloney
 

More from David H Moloney (20)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Risk Assessments 96 pages

  • 1. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 1 of 92 Contents 01 General Site Activities 29 Nightwork 57 Powder-Actuated Tools (Hilti Gun) 02 Abrasive Wheels 30 Night Emergency Procedures 58 HDPE Pipe - Butt Fusion Machine 03 Aircraft Overhead see 41 for Working Airside 31 Noise – high levels 59 Directional Drilling 04 Buried Services 32 Overhead cables 60 Paint Spray Guns 05 Cement, Wet Concrete, Grout & Mixer 33 Paving Bituminous & Milling 61 Managing Sub-contractors 06 Concreting 34 Pipe Jacking 62 Operating Plaster Mixer Spray machine 07 Compressors & Air Tools 35 Pinch Points & Hand Injuries 63 Hydrochloric Acid Handling & Use 08 Confined Spaces 36 Plant, Equipment & Plant Operators 64 Cladding to Roofs 09 Cranes - Lifting Operations 37 Plant Repairs & Maintenance 65 Fixing Windows, Doors & Glazing 10 Deliveries – Unloading & Storage 38 Plant Collision 66 Roof Waterproofing Membrane 11 Driving – Dangerous & Unsafe 39 Reinforcement 67 Roof Sheeting - Roll Forming on site 12 Electrical Tools 40 Road Works 68 Demolition of Buildings 13 Electrical Works 41 Road Saw 69 Working on Median beside Live Traffic 14 Employees New Starts 42 Scaffolding 70 Cable & Coiled Duct Laying from Drums 15 Emergency Procedures 43 Steel Structures Erection 71 Demolition of Underground Tanks & Pipelines 16 Excavations, Backfilling, Filling & Earthworks 44 Welding & Cutting Metal 72 Butt Fusion Welding of PE Pipes 17 Excavators 45 Working at Height 73 Cold Milling Machine Operation 18 Falsework & Formwork 46 Working On, Above or Near Water 74 Shot Blasting 19 Fencing 47 Working Airside 75 Not Wearing PPP 20 Fuelling & Oiling 48 Operating Vibrating Hand Tools 76 Working Indoors 21 Hazardous Substances 49 Poor Housekeeping 77 Working Outdoors 22 Heat 50 Working in Sewer Manhole 78 HAVS (Hand-arm vibration ) 23 Hydrostatic Testing - Pipelines 51 Felling Trees by Cutting 79 Rock Drilling & Blasting in Quarry 24 Joints Sealing with hot Bitumen 52 Post Tensioning 80 Pipeline Inspection by CCTV 25 Lorries Hiab 53 Hydraulic Pump & Jack 26 Lorries Tippers & Trailers 54 Traffic Management 27 Manual Handling 55 Auger Boring with Casing 28 MEWP Mobile Elevating Work Platforms 56 Concrete Saws & Core Drills etc
  • 2. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 2 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk O1 Site Activities General 01  Construction activities  Injuries  Property Damage 6 6 36  Site HSE Project Procedures  Work Permit Systems  Method Statement for Risk Activities  Risk Assessments  On Site Safety Training  HSE Supervision  Issue of PPE  COSHH Assessments  On site Medical Clinic  Site Emergency Response Plan  Site Health, Safety & Environmental Plan  First Aid Kits available  First Aiders  Site Inductions for Employees  Welfare Facilities  Waste bins  Managers must take responsibility and accountability for HSE Management  Training and implement above. 6 2 12 Adequately Controlled Risk 02 Abrasive Wheels
  • 3. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 3 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 02  Disc Disintegration  Electricity  Entrapment / Entanglement  Spoil Ejection  Fire  Noise  Dust  Lacerations [may be severe, even fatal.  Contact burns / electric shocks  Penetrating injuries  Property damage  Tinnitus / Threshold shift / Noise induced Hearing loss  Respiratory problems  Eye Injury 6 6 36  Use of approved suppliers  Use of appropriate speed rated discs  Use of task specific discs  Use of correctly adjusted guards  Use of suitable PPE ( body / hands / face / eyes /ears )  Trained and competent persons only to use abrasive wheels / change discs  All electrical equipment to be 110V with industrial sockets  Routine inspection / testing  All electrical equipment colour coded  Damaged equipment tagged and taken out of service  All cutters and grinders regularly maintained  No loose clothing worn  Adequate training & supervision  Use of Hot work permit system  Fire points available  Trained fire extinguisher operatives  Removal of combustible materials  Sound screens / isolation of high noise activities  Abrasive wheel signs.  Eye protection – high impact glasses at all times.  Eye wash station on site 6 2 12 Adequately Controlled Risk 03 Aircraft Overhead
  • 4. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 4 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 03a  Collision with aircraft in flight  Severe physical damage  Fatalities  Public outcry 10 6 60  Fan corridor height restrictions briefed to all site teams  Works in the fan corridor will be controlled by Restricted Area Access Work Permits  Heightmarkers ( such as goal posts ) shall be constructed as applicable to advise of heightlimits  All plantequipmentshall be selected on basis of maximum operating heights so as to notinterfere with airportoperations  Authorisation from 3rd party.  Supervision atall times.  MS/ RA briefed to all affected workers 10 2 20 Adequately Controlled Risk 03b  Lighting Distraction to Pilots on Finals to landing  Severe physical damage  Fatalities 10 4 40  Tower lights to be setup so the light beam shines across the runway (North to South) so as not to be a distraction to pilots on finals to landing.  The heightof tower lights to be limited to 13m.  Lighttowers established on raised bridge decks to be approved by OAMC  Lights to have welded restrictors to ensure the light beam is downwards facing.  Lighting control will be via liaison with the OAMC  MS/ RA briefed to all affected workers  A lighting plan will be prepared and submitted prior to any nightwork, showing location and direction and illuminated area oflightbeams. 10 2 20 Adequately Controlled Risk 04 Buried Services 04  Underground services ;- gas, electricity or water  Personal Injury – electrocution / drowning / 8 6 48  Area to be visually checked for markers or physical signs of services, i.e. manholes.  Up to date drawings detailing existing services 6 2 12 Adequately Controlled Risk
  • 5. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 5 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk asphyxiation  Property Damage  Fire  Disruption of utility services shall be obtained and checked thoroughly.  Service providers shall be contacted to assess if there are services in the area and also to let them know work is going to be carried out.  Obtain permit from Utility Company if required.  Use of trial holes and hand excavation around known services  Hand tools that are non conductive shall be used when excavating around existing services.  Prior to excavation the affected area shall be surveyed with a CAT and competent person.  Records of all CAT surveyed areas to be kept on file and briefed to excavation team  Surveyed area clearly demarked on site  NOC from municipality to be obtained before excavation  Emergency contact numbers displayed on site  Where required use Permit to Dig.  Obtain NOC where applicable  Protect existing services by either, marking the ground surface, providing protection slabs, tiles or timbers or exposing & encasing in concrete. 05 Cement, Wet Concrete, Grout & Mixer a.  Handling Cement  Contact dermatitis / skin irritation  Cement dust 6 6 36  Wear suitable protective eye wear  Compliance with COSHH assessment  Have eye station on hand 6 2 12 Adequately Controlled Risk
  • 6. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 6 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk inhalation  Eye Injury  Wash hands after each exposure  Use of gloves  Use of full length uniforms  First Aiders available b  Handling wet concrete & grout  Contact dermatitis / skin irritation  Eye Injury 6 6 36  Wear suitable protective eye wear  Compliance with COSHH assessment  Have eye station on hand  Wash hands after each exposure  Use of gloves  Use of full length uniforms  First Aiders available 6 2 12 Adequately Controlled Risk c  Using Mixers  Personal Injuries to include cuts and crush injuries  Electrocution  Contact dermatitis / skin irritation  Electric shocks / contact burns  Tinnitus / Noise induced hearing loss  Cement dust inhalation 6 6 36  All necessary guards are to be in place on the mixer.  All equipment is to be inspected by a competent person prior to use.  Only trained operatives to use mixer  Planned preventative maintenance programs  No persons are to put tools or limbs in to mixer while drum is rotating.  Mixer is to be set up on firm level ground and should never be over loaded.  All mixers should be 110 volt to prevent electrocution.  All temporary plant to be suitably earthed  Use of suitable PPE ( body / face / eyes/ hands /ears )  Adequate training & supervision  Tool box talks ref manual handling  Noise levels assessed and sound screens provided as required 6 2 12 Adequately Controlled Risk
  • 7. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 7 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Availability of first aid / eye wash station  Compliance with COSHH assessment  Use protective mask. 06 Concreting 06a  Hazardous chemicals  Burns,  Contact Dermatitis  Eye irritations 6 4 24  Selection and use of Appropriate PPE ( body / hands /face /eyes / ears)  Wear eye protection  Eye wash station nearby.  First Aid nearby  Trained first aider  Completion of COSHH Assessment  Use friendly chemicals  Washing facilities will be provided with hot water, showers, soap & paper towels  First Aid & First Aid Equipment provided 6 2 12 Adequately Controlled Risk 06b  Vibration.  Vibration-induced white finger 6 4 24  Limit exposure time / regular breaks  Job rotation  Selection and use of appropriate PPE  Operatives will be briefed on dangers 6 2 12 Adequately Controlled Risk
  • 8. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 8 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 06c  Falls on working levels or from height  Personal Injury  Deaths  Serious injury 6 4 24  Provide leading edge protection and safe access.  Good housekeeping disciplines  Adequate training & supervision  Training and supervision 6 2 12 Adequately Controlled Risk 06d  Prolonged exposure to noisy plant  Tinnitus, threshold shift , Noise induced hearing loss 4 4 16  Ear Protection if you have to shout to be heard.  Monitor noise levels and enforce PPE use above 85dB  Place warning signage for noise  If you have to shout to be heard wear ear protection 4 2 8 Trivial Risk 06e  Failure of support system or platform  Personal Injury  Property damage 6 4 24  Structural sign off for all falsework and formwork before any concrete placement 6 2 12 Adequately Controlled Risk 06f  Concrete Pumps  Property damage  Personal Injury 6 6 36  All equipment is to be inspected by a competent person prior to use.  Whip checks fitted on pressure hoses  Operator has Valid license / certification  Exclusion zone created around working concrete pump  Noise levels assessed and PPE provided as required  No manual clearance of pump hopper while 6 2 12 Adequately Controlled Risk
  • 9. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 9 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk pump is in operation  Adequate training & Supervision  Pump is to be set up on firm level ground with outriggers fully deployed using load pads.  Wash-out facility will be provided and for night work will be illuminated.  Clean out in an area set aside for this particular activity.  Exclude people not involved in the clean out procedure from the work zone.  Do not “Shoot” the clean out plug from the end of the concrete line. 06g Wastage  Environmental damage 6 4 24  Use Wash-out facility provided around the site and in the concrete batching yard 6 2 12 Adequately Controlled Risk 07 Compressors & Air Tools 07  Airlines Whipping  Noise  Injury 6 2 12  Use whip wire on airlines  Visual inspection of air hoses prior to starting work, any damaged hoses to be replaced  No horseplay with airlines or misuse  Ear & Dust protection  Exhaust fumes not to cause hazard 6 2 12 Adequately Controlled Risk  Jackhammer  Vibration white finger  Eye injuries  Hearing loss  HAND ARM VIBRATIONS (HAV) 6 4 24  Anti-vibration tools used if possible  Eye protection to grade one impact when using metal cutting or stone cutting tools  Heavy leather gloves when using tools causing hand-arm vibration  Suitable protective gloves when handling parts contaminated with hydraulic fluid 6 2 12 Adequately Controlled Risk
  • 10. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 10 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Hearing protection  Respiratory protection against dust where assessed as necessary  Safety boots with Airlines  Air hoses should be laid out properly without kinks and not in the way of machinery movement  Rotate workers when using tools that produce HAV and record time on tools per shift. 08 Confined Space Note difference between Permit and Non-Permit confined spaces Refer to HSE Project Procedure for Confined Spaces Entry Doc # PP710-CSE-1008 08a  Increased or decreased oxygen levels  Asphyxiation 6 6 36  Use of confined space permit system  Atmospheric testing.  Suitable means of communication  No lone working permitted  Emergency plan in place ( rescue from Confined Space etc )  Adequate ventilation / lighting  Suitable access points ( preferably 2 points where poss. )  Hourly records of Gas levels  Signage /exclusion zone to prevent unauthorized access  Training & Supervision  Good housekeeping 6 2 12 Adequately Managed
  • 11. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 11 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 08b  Hazardous gases  Poisonings 4 6 24  Atmospheric testing.  Use of confined space permit system  Adequate ventilation / lighting  Hourly records of Gas levels 4 2 12 Adequately Managed 08c  Fire Burns 4 6 24  Fire points available  No Smoking  Exclude inflammable materials & liquids  Intrinsically safe lighting, emergency lighting and torches. 4 2 8 Negligible Risk Non Permit Confined Space 08d  Fumes Injury 6 4 24  Good access & egress routes  Smoking Prohibited  No Working Alone  No petrol or diesel engines  No combustible material stored  Natural Ventilation 6 2 12 Adequately Controlled Risk Permit Confined Space  08e  Hazardous Gases Injury 6 4 24  Note - Depending on circumstances select from following  Good access & egress routes  Smoking Prohibited  No Working Alone 6 2 12 Adequately Controlled Risk
  • 12. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 12 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  No petrol or diesel engines  No combustible material stored  Natural Ventilation  Permit to Work System  Personnel Training in Confined Spaces  Lights Instrinically Safe  Gas Dectors  Entry Log System  Force Ventilation  Rescue Harness ( connected to Lifeline leading to outside)  Rescue Equipment Self Rescuers carried 09 Cranes – Lifting Operations General  Comply with Project Procedure for Lifting Operations PP 738-LOP-1008  Wind Speed Limit on Site is 9m/sec or 32.5Km/hr  Notes Slinger = Rigger Signaller = Banksman 09a  Crane overturning  Personal injury  Property damage 6 4 24  Crane set up on firm and level ground  Outriggers to be fully extended  Load pads under all outriggers 6 2 12 Adequately Controlled Risk
  • 13. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 13 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Crane set up controlled by competent lifting supervisor  Crane has PMV inspection prior to mobilisation  Crane has valid 3rd party inspection certification.  Licensed crane operator  Selection of correct crane for task ( SWL etc ).  Weights of loads known before lifting  Exclusion zones created around lifting operations  Daily checks by operator recorded  No work in strong winds  Certified slings, shackles and other lifting appliances to be used & be in period colour code.  Do not exceed SWL  Check area under outriggers for drains etc 09b  Crane failure  Personal Injury  Property damage 6 4 24  Crane set up on firm and level ground  Outriggers fully deployed  Load pads under all outriggers  Crane set up controlled by competent lifting supervisor  Crane has PMV inspection prior to mobilisation + daily pre use inspection  Crane has valid 3rd party inspection certification. 6 2 12 Adequately Controlled Risk
  • 14. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 14 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Licensed crane operator  Selection of correct crane for task (SWL etc ).  Weights of loads known before lifting  Exclusion zones created around lifting operations  Daily checks by operator prior to starting  Do not exceed SWL 09c  Failure of lifting equipment  Personal Injury  Property damage 6 4 24  All lifting equipment shall be 3rd party inspected and certified as fit for purpose,  All areas of lifting operations shall be adequately lit  Crane operators to have valid licenses  All lift accessories shall be inspected, certified and comply with CCC /TAV JV colour coding scheme for the period  Specific lift paths will be created to avoid any overhead lifting  All cranes or lifting operations shall be controlled by competent signal man  All rigging activities shall be conducted by trained and competent rigger.  Exclusion zones with fixed barriers will be established around lifting operations / zone  All operations supervised  Equipment to comply with colour code for period  Select correct lifting accessories for planned load.  All lifting accessories to be checked daily by 6 2 12 Adequately Controlled Risk
  • 15. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 15 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk crane driver and riggers before use. 09d  Rigging  Personal Injury  Property damage 6 4 24  All lifting tackle shall be 3rd party inspected, certified and CCCTAVJV colour coded  Rigging operations shall only be performed by trained & competent riggers.  All lifts will be controlled and supervised by a rigging supervisor.  Lifting plans will be used for all abnormal loads  Exclusion zones created around lifting operations  Personnel will be advised of risks through tool box talks prior to commencement of work.  All riggers shall wear appropriate PPE  Riggers shall be identifiable via helmet colour  Tag lines used for all lifts  Helmets colour coded  All lifting accessories to be checked daily by crane driver and riggers before use. 6 2 12 Adequately Controlled Risk
  • 16. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 16 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 09e  Equipment & Material Handling  Personal Injury  Property damage 6 4 24  All equipment will be stored, handled in a safe and proper manner & managed by trained staff.  Offloading and storage will be properly controlled / supervised at all times by trained staff at all times.  Tag lines will be used to control equipment during loading and offloading.  Personnel will be properly trained in safe methods of Equipment handling including the danger of pinch points – fenced off.  Erection areas will be identified and unauthorized entry will be controlled by use of barriers, warning signs and close supervision.  Appropriate personnel protective equipment will be worn at all times.  Personnel will be reminded of risks through tool box talks.  Period colour coded equipment.  Beware of trapping while moving loads 6 2 12 Adequately Controlled Risk 09f  Adverse weather  Property damage  Personal injury  Crane failure 6 6 36  Install anemometers on cranes / site  Safe operating limits for wind speed set for all lifting operations  Liaison with OAMC meteorology dept.  Protocols for all adverse weather situations such as sand storms established  Training and competent supervision  Crane supervisor with authority to suspend all lift operations project wide 6 2 12 Adequately Controlled Risk
  • 17. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 17 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Crane driver and riggers authorised to stop lifts if deemed unsafe or high winds 09g  Multiple Cranes & suspended loads Collision  Personal injury  Property damage 6 6 36 Crane & suspended loads, Anti Collision Measures  Banksman to guide and coordinate the movements of cranes working in close proximity.  Vehicles not to be parked in swing area of cranes  No person to stand sit or walk near working cranes  No unauthorised access  Exclusion zones created around working plant 6 2 12 Adequately Controlled Risk 09h Working in crane suspended man baskets  Personal injury 6 6 36  Basket will be certified by 3rd Party  Personnel will wear harnesses  Adequate signage and exclusion zones around temporary structures. 6 2 12 Adequately Controlled Risk 10 Deliveries Unloading & Storage 10  Moving Delivery Vehicles Entering/Leaving site  Traffic accidents  Property damage  Personal injury 6 6 36  Good visibility of oncoming vehicles.  Traffic calming measures such as speed bumps  Pedestrian routing. High visibility clothing. 6 2 12 Adequately Controlled Risk
  • 18. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 18 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Reversing alarms.  All vehicle reversing controlled by trained banksman.  Banksmen not to get between moving vehicles and fixed objects  Adequate signage  Adequate lighting at site entrances  Site driving rules posted  Security marshalling traffic  All CCCTAVJV / Subcontractors drivers HSE inducted  All drivers to hold valid Omani license  Authorised vehicles only on site  Security identify drop zones & advise delivery drivers on site traffic rules.  Unloading  Injury  Material damage 6 6 36  Comply with Lifting Operations project Procedure PP 738 6 2 12 Adequately Controlled Risk  Storage  Injury  Material damage 6 6 36  Stack materials in designated areas  Cordon off area  Keep storage area tidy 6 2 12 Adequately Controlled Risk 11 Driving – Dangerous or Unsafe 11  Dangerous or unsafe driving  Road traffic accident  Personal Injury  Property damage 8 6 48  Designated and signposted access routes required.  All drivers must have an appropriate license 8 2 16 Adequately Controlled Risk
  • 19. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 19 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk for the particular piece of plant they are using.  All personnel involved in the work shall be inducted, instructed on the site driving rules and have their license checked and recorded.  Regular tool box talks and Night Activity Briefings (NAB) shall be given to reiterate driving standards.  Supervisors and H&S shall monitor driving and take appropriate action if necessary.  All reversing vehicles to be controlled by a trained banksman  All mobile plant to have audible reversing alarm  Blind spots to be mitigated by appropriate mirrors. .  All necessary lights should be in place on vehicles including orange flashing beckons and should be used at all times as well as being regularly inspected.  Vehicle Lights, windows and mirrors shall be cleaned regularly to ensure a clear view. 12 Electrical Tools 12  Electricity  Moving parts  Noise  Vibration  Dusts  Personal Injuries: Cuts and lacerations.  Potential amputations  Penetrating Injuries.  Respiratory problems  Upper limb work disorders  Vibration white finger.  Electrocution. 4 6 24  110Volt tools only permitted on project  Use of approved industrial sockets  Inspected and CCCTAVJV colour coded  HSE Induction for all workers.  Toolbox talks.  Selection and use of suitable PPE.  Adequate training and supervision.  Tool maintenance and record keeping.  Damaged tools tagged, isolated and removed from service 4 2 8 Trivial Risk
  • 20. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 20 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  All tools fitted with appropriately adjusted guards.  Pre use daily inspections  PAT test to all Electric equipment.  Job rotation as required & recorded.  Equipment to comply with the site colour code for period 13 Electrical Work 13  Using Electrical Equipment.  Electrical installation works  Electrocution.  Fire.  Property damage 4 4 16  All Electrical Distribution boards shall be fitted with suitable circuit breakers  All hand tools on site shall be 110V  Use of approved industrial sockets  Only authorized and trained personnel to carry out work with electrical equipment.  Only trained and authorised personnel to complete electrical installations ( DB’s etc )  Portable equipment to be checked by authorized electrician or independent assessor.  All electrical equipment shall be colour coded  Suitable fire extinguishers stored at strategic locations.  Training in use of extinguishers  Any damaged equipment to be removed from use, isolated and tagged to prevent accidental re-use  No ‘hot wiring / splicing of cables ‘ on site  Lock out tag out system ( for DB boxes etc )  Suitable earthing for all temporary plant  Suitable training and supervision 4 2 8 Trivial Risk 14 Employees New Starts 14  Inexperience of  Increased risk of 4 4 16  Induction training. 4 2 8 Trivial Risk
  • 21. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 21 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk New Employees unsafe activities  Potential poor quality works  Personal Injury  Property damage  Training in site rules and procedures.  HSE training programs  Close supervision / use buddy system  Pre planning of tasks assigned based on experience required  Issued with PPE  Issued with Identification Card 15 Emergency Procedures 15  Emergency situations / poor emergency procedures.  Disruption to project  Personal injuries  Property damage  Worsening of an incident if dealt with incorrectly 6 6 36  Project specific emergency plan created  Emergency procedure included in induction and reiterated in briefings and Tool box talks.  Emergency contact details posted on site notice boards and office bulletin boards  Emergency contact detail cards distributed to all supervisory staff  Emergency facilities on standby ( ambulance / fire engine / clinic )  Trained First Aiders available throughout the site  Trained fire wardens available throughout the site  Fire points / first aid boxes available throughout the site  Incident control room established at MC 1 offices  Duty Incident Controller Rota established  Scheduled emergency drills  Liaison with civilian emergency services.  All personnel to have Emergency #  Security at gates.  Emergency drills. 6 2 12 Adequately Controlled Risk
  • 22. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 22 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 16 Excavations, Backfilling, Filling & Earthworks  General  Comply with Project Procedure PP712-EXE- 1008  Any excavation left open for 7days or more to have a weekly inspection carried out and recorded within 24 hours.  Provide safe access & egress 16a  Trench Collapse  Entrapment  Death  Injury 6 6 36  Slope or step faces  Daily excavation inspections  Permit to Dig in place.  Keep spoil and plant 2 metres away from edge of excavation  Keep excavations dry, water at safe level. 6 2 12 Adequately Controlled Risk 16b  Persons falling into excavations  Personal Injury  Property damage 6 6 36  All excavations will have suitable fixed barriers at least 1.5m from leading edges  Provision of adequate signage  Creation of safe pedestrian access routes away from excavations  Safe access and egress shall be provided for all excavations and access bridges over the trenches should be provided if required.  Excavation daily inspection checklist to be completed by competent person 6 2 12 Adequately Controlled Risk
  • 23. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 23 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Training & Supervision  Regular TB Talks ref: excavation safety 16c  Material or plant falling into excavations including trench collapse  Personal Injury  Property damage 6 6 36  All excavations will have suitable fixed barriers at least 1.5m from leading edges  All excavated spoil to be placed at least 2m from leading edges  Provision of adequate signage  Creation of vehicle access routes away from excavations  Safe access and egress shall be provided for all excavations and access bridges over the trenches should be provided.  No lone working in excavations  Excavation daily inspection checklist to be completed by competent person  Training & Supervision  Regular TB Talks ref: excavation safety  Stop blocks shall be used where plant is working near the trench. The stop blocks must of sufficient height and strength to stop the vehicle and of sufficient distance from the trench so as to stop collapse.  All excavations of greater depth than 1.2 shall have a suitable means of ground support such as. battering, benching, trench sheets, trench boxes, sheet piling, etc.  In solid and non fractured rock the above requirement may be relaxed  Adequate angle of repose shall be in place for 6 2 12 Adequately Controlled Risk
  • 24. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 24 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk all excavations where above ground support measures are not possible  Lighting as required 16d  Weakening of adjacent structures by excavation  Collapse of structure  Property damage  Personal Injury 6 4 24  Suitable prior planning of shoring requirements before works commence.  Structural engineer to advise on any additional shoring / support required.  Daily check inspections 6 2 12 Adequately Controlled Risk 16e  Buried Services gas, electricity water  Personal Injury – electrocution / drowning / asphyxiation  Property Damage  Fire  Disruption of utility services 8 6 48  Area to be visually checked for markers or physical signs of services, i.e. manholes.  Up to date Drawings detailing existing services shall be obtained and checked thoroughly.  Liaison with concerned authority  Use of trial holes and hand excavation around known services  Hand tools that are non conductive shall be used when excavating around existing services.  Prior to excavation the affected area shall be surveyed with a CAT by a competent person.  Records of all CAT surveyed areas to be kept on file and briefed to excavation team  Surveyed area clearly demarked on site  NOC from municipality to be obtained before excavation 6 2 12 Adequately Controlled Risk 16f  Overhead Power Lines  Personal Injury – electrocution / burns  Property Damage 6 6 36  Selection of appropriate plant in respect of max operating heights 6 2 12 Adequately Controlled
  • 25. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 25 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Fire  Disruption of utility services  Erect barriers with warning signs parallel  Erect goal posts with cross bars for passing under  All plant movement under overhead power lines controlled by trained banksman  All plant and temporary scaffolds to be suitably earthed to safeguard against arcing  All drivers and plant operators to receive Tool box talks  Security to stop all vehicles and warn drivers of any overhead power line hazards  Exclusion zones created to prevent encroachment of plant & vehicles near overhead lines  Competent supervision  Reroute service where possible  Follow CCCTAVJV procedure  Operate Permit to Work  Safe System of Work in place  Working under or around Power Lines Procedure in place.  Re route power lines where possible.  Overhead power line procedure in place.  Notify service company  Obtain NOC 16g  Access & Egress  Falling, Injuries 6 6 36  Ensure that all access ladders are in good condition and are inspected 6 2 12 Adequately Controlled
  • 26. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 26 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Ensure that all access Ladders are tied on top  Ensure that the ladders are standing on stable ground  Areas at top and bottom to be free from materials and debris.  Ladders to be industrial type not home made  Ensure that the ladders are supported on bottom in case tying the top is not possible  Ensure that no rebar or other objects are protruding into the ladders  Operators shall remove lumps of material from footwear prior using ladders 16h  Working in vicinity of moving plant  Injury  Property Damage 6 4 24  All plant to be operated by suitably licensed and competent operators.  All reversing vehicles to be controlled by a trained banksman  All mobile plant to have audible reversing alarm  Blind spots to be mitigated by appropriate mirrors.  Site driving rules enforced.  All necessary lights should be in place on vehicles including orange flashing beckons and should be used at all times as well as being regularly inspected.  Vehicle Lights, windows and mirrors shall be cleaned regularly to ensure a clear view.  Exclusion zones created around working plant  Emergency procedures in place 6 2 12 Adequately Controlled Risk
  • 27. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 27 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 17 Excavators 17a  Working excavator  Excavator failure  Personal Injury [may be severe, even fatal]  Property damage.  Traffic accidents 6 6 36  All excavator operators to hold valid license / certification  All operators familiarised with the SAFE WORKING PROCEDURE FOR EXCAVATORS.  Prior to mobilising all excavators to be inspected by PMV  Operator to carry out visual inspection of machine prior to start up.  All excavators shall deploy outriggers if fitted  Visibility blind spots to be minimised by mirrors.  Flashing beacon fitted.  Windows, lights, Mirrors to be cleaned regularly.  The cab floor to be kept clean and free from any obstacles which may affect the safe operation of the Machine.  Ground workers to wear Hi Visibility Vests, safety boots and helmets at all times.  Exclusion zone to be created around working excavators  All excavators to be included in Planned Preventative Maintenance schedule  All excavators to have Fire extinguisher in cab 6 2 12 Adequately Controlled Risk
  • 28. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 28 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Spill kits available on site  Banksman to supervise & direct driver.  No persons to be in any trench or excavation during machine excavation work.  With quick hitches – locking bars or self locking pins to be fully inserted and visually checked by driver. . 17b  Lifting operations  Property damage  Personal injury  Machine overturn 6 6 36  Fully deployed outriggers  Posted SWL on machine  Selection of appropriate plant for task ( SWL etc )  Competent rigging  Suitable lifting attachments / eyes on machine – certified  Exclusion zone  In date equipment colour code.  Only lift using the lifting eye and not the teeth of the bucket. 6 2 12 Adequately Controlled Risk 17c  Rockbreakers  Hearing  Injury 6 6 36  Wear ear muffs  Wear Goggles 6 2 12 Adequately Controlled Risk
  • 29. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 29 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 18 Falsework / Formwork 18  Structural collapse  Personal Injury  Property damage 6 4 24  Falsework designed by structural engineer  Separate MS / RA for each bridge  MS/ RA briefed to all affected workers  Structural engineer inspection, approval & sign off prior to any loading of falsework  Formwork inspected / signed off prior to any concrete placement  Provide proper access and egress routes  Erect and strip falsework & formwork as per design drawings 6 2 12 Adequately Controlled Risk 19 Fencing
  • 30. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 30 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 19a  Sharp wire to be fitted to fence by hand  Cuts to hands, face and body. 6 6 36  All personnel using and fitting the barbed wire should be trained, experienced and competent in the use of the material  Coveralls, appropriate gloves and face shield to be worn by personnel fitting and handling barbed wire material.  None essential personnel to be kept away from area barbed wire is being used by barriers with signs erected to high light the issue. 6 2 12 Adequately Controlled Risk 19b  Falls from ladders  Falling materials  Broken bones  Cuts and bruises 6 6 36  Ladders will be inspected and tagged by a competent person.  Ladders shall be footed at all times.  Coils of wire shall be left at ground level and a section of uncoiled wire shall be passed up to person securing the wire to the post.  Ladders shall be locked securely or removed from site when not in use.  Ensure three points of contact when climbing ladders. 6 2 12 Adequately Controlled Risk 20 Fuelling & Oiling Plant 20  Hazardous chemicals  Spillage  Flammable chemicals  Damage to Environment  Fire  Personal Injury / Illness  Property damage  Explosion 6 4 24  Selection and use of appropriate PPE  Use fuel nozzles that automaticallyshut-offthe flow of fuel when tank is full.  Keep a spill kit near fuel and oil storage areas and refuelling areas.  Turn off machines during refuelling  Drip trays in place for all static plant to catch any nuisance leaks and drips thatmay occur. 6 2 12 Adequately Controlled Risk
  • 31. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 31 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Routine servicing only permitted in PMV  Environmental protective measures such as plastic sheeting in place for any mobile plantfuelling / servicing  Store oil away from watercourses or surface water drains.  No mixed storage  Use funnels when fuelling from containers  Fire extinguishers at fuel stations and on any mobile refuelling /service vehicles,AFFF foam  Trained fire marshals / fire extinguisher operatives available  Complete COSHH assessmentfor all fuels and oils  Complywith COSHH assessment  MSDS with stores /PMV / HSE / Env team / clinic  Training & Supervision  Eye wash stations  First Aid  Emergencyphone numbers at hand.  Safe disposal ofany contaminated ground  Fuel tanks to be double skinned or bunded 21 Hazardous Substances 21  Hazardous substances  Flammable chemicals  Spillages .  Damage to Environment  Fire  Personal Injury / Illness  Property damage 6 6 36  MSDS reviewed for all substances and COSHH assessments produced for any with adverse health affects  Spill kits and eye wash kits to be available with personnel trained in their use  Adequate fire precautions available  Trained fire marshals / fire extinguisher operatives available  Selection and use of appropriate PPE, as per COSHH assessment 6 2 12 Adequately Controlled Risk
  • 32. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 32 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  MSDS’s available at work locations, to include HSE / Env. / Clinic / PMV / Stores  Suitable bunded storage facilities or drip trays available for all hazardous chemicals  All workers fully briefed as to requirements of COSHH assessments  Use, storage & disposal in line with COSHH assessment  No mixed storage of hazardous chemicals  First aid & Eye wash nearby  All container to have labels identifying substance  Store personnel will know the hazards associated with items they dispense  No decanting of hazardous and flammable substances into plastic bottles or containers  Store person will be responsible to issue the necessary PPE with any hazardous substances. 22 Heat What Is Heat Stress? It's a signal that says the body is having difficulty maintaining its narrow temperature range. The heart pumps faster, blood is diverted from internal organs to the skin, breathing rate increases, sweating increases, all in an attempt to transfer more heat to the outside air and cool the skin by evaporation of sweat. If the body can't keep up then the person suffers effects ranging from heat cramps to heat exhaustion, and finally to heat stroke. 22a  Thermal  Heat Stress 4 4 16  Provision of drinking water for all work 4 2 8 Trivial risk
  • 33. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 33 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk Radiation  Heat Stroke  Fatigue  Dehydration  Collapse locations  Provision of electrolyte replacement additives for drinking water supplies  Provide shaded rest areas for all work locations ( with fans / AC’s where poss. )  HSE training department - Heat stress awareness campaign  Poster campaigns  Regular Tool box talks ref: heat stress  Toilets to have urine colour charts posted to aid self assessment of dehydration levels  Monitoring of operatives by supervisors for signs of heat stress and sweat rash.  Adherence to Summer working hours regulations  Planning of critical tasks in cooler conditions  Provision of fans / AC’s in work areas as appropriate  Job rotation  Provision of canopy’s for exposed work areas  Provision of suitable PPE  Availability and awareness of First Aiders 22b  UV Radiation  Sunburn  Skin ageing  Premature cancer  Eye strain  Arc eye ( welders) 6 4 24  Selection and use of appropriate PPE ( welding masks etc )  Training & Supervision  Full length overalls 6 2 12 Adequately Controlled
  • 34. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 34 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 23 Hydrostatic Testing of Pressure Mains 23 Pipe Testing  High pressure water that may cause pipe bursting and cause injuries to persons 4 6 24  Arrange exclusion zones around the areas of testing  Insure only authorized persons are in the exclusion zone  PPE  Only qualified and competent persons conducting the tests  Pressure testing permit system in place.  Erect warning signage. 4 2 8 Trivial Risk 24 Joint Sealing with Hot Bitumen 24 Hot Material & Equipment Burns to skin & eyes 6 6 36  Use Bitumen Boiler – trained operatives only  Use Bitumen Bucket –trained operatives only  Wear heat resistant Gauntlets  Wear heat resistant Boots  Wear protective eye wear  Job rotation to prevent heat related disorders  Exclusion zone around the hot bitumen work  Availability of first aiders and cool water to flush affected area in the event of burn injury  Comply with COSHH assessment requirements  Tool box talks  Cotton coveralls to be used with hot bitumen not nylon. 6 2 12 Adequately Controlled Risk 25 Lorry Hiab 25a  Hiab Lorry overturning  Personal injury  Property damage 6 4 24  Lorry set up on firm and level ground  Outriggers fully deployed  Load pads under all outriggers 6 2 12 Adequately Controlled Risk
  • 35. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 35 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Hiab has valid 3rd party inspection certification.  PMV inspection prior to mobilisation  Licensed operator  Selection of correct crane for task ( SWL etc ).  Weights of loads known before lifting  Exclusion zones created around lifting operations  Training  Check for drains etc before placing out- riggers. 25b  Failure of lifting equipment  Personal Injury  Property damage 6 4 24  All lifting equipment shall be 3rd party inspected and certified as fit for purpose,  All areas of lifting operations shall be adequately lit  Operators to have valid licenses  All lift accessories shall be 3rd party inspected, certified and comply with CCC /TAV JV colour coding scheme for the period 6 2 12 Adequately Controlled Risk 25c  Equipment & Material Handling  Personal Injury  Property damage 6 4 24  All equipment will be stored, handled in a safe and proper manner.  Offloading and storage will be properly controlled / supervised at all times.  Tag lines will be used to control equipment during loading and offloading.  Personnel will be properly trained in safe methods of Equipment handling including the danger of pinch points  Erection areas will be identified and 6 2 12 Adequately Controlled Risk
  • 36. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 36 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk unauthorized entry will be controlled by use of barriers, warning signs and close supervision.  Appropriate personnel protective equipment will be worn at all times.  Personnel will be reminded of risks through tool box talks.  Period colour coded equipment. 26 Lorries Tippers & Trailers 26a Working at height whilst Sheeting and unsheeting of lorries Falls, injuries 8 6 48  Lorries with powered sheeting/ unsheeting are preferred  Lorries shall park in a safe place and on even flat ground before sheeting/unsheeting  Proper access ladders shall be provided for manual sheeting  Sheeting & unsheeting will be done by 2 persons, one on each side of the lorry  Banksman shall be available during the sheeting/ unsheeting 8 2 12 Adequately controlled 26b Mobile phones Reduced attention whilst driving leading to accidents 8 6 48  No Mobile Phone shall be used whilst driving  Site induction to cover use of mobile phones  Ban from site for persistent offenders 8 2 12 Adequately controlled 26c Speeding Accidents 8 6 48  Speed limits on site.  Adequate signage.  Speed humps  Speed monitoring  Ban from site for persistent offenders  Site induction to be delivered to all personnel entering site. 8 2 12 Adequately controlled
  • 37. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 37 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 26d Overhead Electrical Cables Elocution 8 6 48  Don’t tip under overhead cables  Look up for overhead cables before tipping 8 2 12 Adequately controlled 27 Manual Handling 27  Heavy loads  Uneven loads  Poor techniques  Back strains  Personal Injury  Property damage 6 6 36  All staff HSE inducted  Regular Tool Box Talks ref: manual handling.  Mechanical aids to be used where possible.  Appropriate selection of materials by procurement Dept i.e. 25kg bags of cement.  Blocks to be stacked on level ground close to the work site by mechanical means.  Job rotation for lifting tasks  Regular breaks  Consider 2 person lift  No stacking above shoulder level.  Carry out manual handling assessments for large loads or repetitive work  Suitable clear flat area to be used for loading / unloading with restricted access. 6 4 12 Adequately Controlled Risk
  • 38. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 38 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 28 MEWP ( Mobile Elevating Work Platform) 28a  General hazards  Injury 6 6 36  Do not exceed lifting capacity of MEWP  Only carry materials thatfit inside the basket  Trained and competentoperators 6 2 12 Adequately Controlled Risk 28b  Persons Falling from height  Personal Injury 6 6 36  All operators to have valid 3rd party certification  All operators to wear full body harnesses with double lanyards  Equipment to have secure working platform / man basket with appropriate guard rails & toe boards where applicable.  All works shall be conducted from inside platform / basket.  List of authorised operators posted on machines  6 2 12 Adequately Controlled Risk 28c  Falling objects.  Personal Injury  Property damage 6 6 36  Exclusion zones created around working MEWP’s.  Only essential tools to be taken in MEWP basket,  Tools should be tethered where possible or should be stored in appropriate holders 6 2 12 Adequately Controlled Risk
  • 39. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 39 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 28d  Mechanical Failure  Personal Injury  Property damage 6 4 24  All equipment to have valid 3rd party inspection certificate  All equipment to have PMV inspection before mobilisation  Pre use daily inspection  Planned preventative maintenance schedules  Selection of appropriate MEWP as per task requirements  Drivers to carry out daily / weekly inspection of MEWP, 6 2 12 Adequately Controlled Risk 28e  Overturning MEWP  Personal Injury  Property damage 6 6 36  If fitted, out riggers fully deployed with use of load pads  SWL posted on machine  On unpaved areas ensure ground is compacted and stable. The correct type of MEWP to be used for the area. 6 2 12 Adequately Controlled Risk
  • 40. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 40 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 29 Night-work 29a  Insufficient Lighting  Traffic collisions  Property damage  Personal Injury 8 6 48  Appropriate lighting as per Procedure for Night Works: PP727-NWP-1008.  Lighting plans and night works permits to be provided by CCC /TAV JV HS&E department.  Nominated person responsible per shift to ensure that all lighting is compliant with OAMC requirements  Tower lights to be setup so the light beam shines across the runway (North to South) so as not to be a distraction to pilots on finals to landing.  The max heightof ground based tower lightmasts to be limited to 13m.  Lighting established on raised bridge decks to be approved by OAMC  Lights to have welded restrictors to ensure the light beam is downwards facing.  Lighting control will be via liaison with the OAMC  Light Towers erected on firm / level ground  A PMV mechanic will be available for maintenance work.  Safety cover  Emergency contact #’s posted.  Inspection by supervisor  Vehicular access route to be adequately signposted and illuminated. 8 2 16 Adequately Controlled Risk 29b  Lighting Nuisance to public roads  Risk of traffic collisions  Complaints from public 8 6 48 All lighting beams shall be suitable shaded to prevent unwanted distraction to public roads Lightbeams shall be directed down wards to flood requisite task only 8 2 16 Adequately Controlled Risk 30 Night Emergency Procedures
  • 41. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 41 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 30  Emergency situations  Property damage  Personal injuries  Disruption to project 6 4 24  Project specific emergency plan created  Emergency procedure included in induction and reiterated in briefings and Tool box talks.  Emergency contact details posted on site notice boards and office bulletin boards  Emergency contact detail cards distributed to all supervisory staff  Emergency facilities on standby ( ambulance / fire engine / clinic )  Trained First Aiders available throughout the site  Trained fire wardens available throughout the site  Fire points / first aid boxes available throughout the site  Incident control room established at MC 1 offices  Duty Incident Controller Rota established  Scheduled emergency drills  Liaison with civilian emergency services 6 2 12 Adequately Controlled Risk 31 Noise High levels 31  High Noise levels  Threshold shift  Noise induced hearing loss  Tinnitus  Miscommunications 4 6 24  Monitoring of noise levels and signs placed in high noise areas.  Provision of sound screens where appropriate to mitigate high noise levels generated by plant / machinery  Creation of high noise area exclusion zones  Availability of suitable Hearing protection as required  Mandatory PPE use for noise levels above 85 4 2 8 Trivial Risk
  • 42. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 42 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk dB. 32 Overhead Cables Electrical 32 a  Electricity  Contact with cables  Burns  Electrocution  Fatality  Property damage  Disruption to utility services 8 6 48  Create fixed barrier exclusion zones & traffic marshalling zones with appropriate signage  Erect goal posts with cross bars for passing under ( constructed of non conductive materials )  When working underneath banksman to control plant movements  Overhead power lines identified at earliest possible time  Power Company contracted to establish voltage, height and safety clearance  Where possible, overhead lines de-energised or relocated prior to any works  Hazards identified by warning signs / notices, goal posts where necessary  Inform all site personnel of danger and ensure a safe system of work is adopted  Provide adequate / competent supervision  All temporary structures in vicinity to be suitably earthed against possibility of arcing caused by overhead cables  Operate Permit to Work. 8 2 16 Adequately controlled risk 32 b Poor Lighting  Inability to discern power lines 6 4 24  All works in proximity to overhead lines will be suspended unless approved task lighting and adequate supervision is provided 6 2 12 Adequately Controlled Risk 32 c Adverse weather  Increased risk of atmospheric 6 4 24  Works suspended as dictated by HSE department eg: during electrical storms etc 6 2 12 Adequately Controlled Risk
  • 43. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 43 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk conductivity and arcing  Exclusion zones widened in humid conditions 33 Paving Bituminous with Machine & Milling 33a  Struck or rolled over by Lorries.  Trapping.  Crushing  Broken limbs.  Fatality 8 6 48  Banksman to control reversing lorries  Drivers to hold valid licence  Correct PPE i.e. safety boots, gloves, hard hats.  Traffic calming measures shall be implemented as appropriate  A flagman will be in attendance when required to guide vehicles safely into and out of the site  All drivers must have an appropriate license for the particular piece of plant they are using  Exclusion zones created around work area  Roads closed and diverted as appropriate  Posting of suitable warning signage 8 2 16 Adequately Controlled Risk 33b  Hazardous chemicals  Contact Burns  Skin irritation 6 6 36  MSDS and COSHH assessments to be produced, followed and submitted to the Engineer for all hazardous materials to be used  Correct PPE to be worn when using hazardous substances, as per COSHH assessment 6 2 12 Adequately Controlled Risk 33c  Milling Machines  Injury 6 6 36  Trained and Experience driver  Banksman to control reversing. 6 2 12 Adequately Controlled Risk
  • 44. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 44 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 34 Pipe-Jacking 34a Excavation Slips, trips & falls Serious Injury 6 6 36  Follow good housekeeping at site  Remove rocks and debris from the area  Follow method of statements 6 2 12 Adequately Controlled Risk 34b Noise Occupational illness 6 6 36  Proper Maintenance of Vehicle and Equipment  Use ear protection 6 2 12 Adequately Controlled Risk 34c Damage to Utilities Property Damage 6 6 36  carry out survey of the area before work  Install "goal Post" to prevent machines hitting overhead lines.  Certified / Qualified operators to Operate the equipment  Manual excavation were mechanical excavation is not practical, 6 2 12 Adequately Controlled Risk 34d Persons being struck by plant or other vehicles Serious Injury / Death 6 6 36  A dedicated Flag man at all times  lag man must wear reflective vest  Operators must not use mobile phones while operating machines  People on foot must be kept clear of the area. 6 2 12 Adequately Controlled Risk 34e Persons Falling in to pits Serious Injury 6 6 36  Barricade & put signage in trenched area  Prevent access to unauthorised people  Install "STOP" blocks if necessary  Ensure ladder and life line for rescue operation  Ensure standby vehicle & trained person at site always for emergency. 6 2 12 Adequately Controlled Risk 34f Vehicle Equipment /Materials falling into pits (Pipe, sand Etc.) Property Damage 6 6 36  Do not park vehicle near trench  Do not store excavated materials close to the trench  Ensure pipes are chocked & kept 1.5mtrs from trench 6 2 12 Adequately Controlled Risk
  • 45. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 45 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 34g Collapse of Pit walls or sides Injury 6 6 36  Ensure trench walls are well supported, use shoring if necessary  Slope sides when excavating in sand / loose soil  The excavation must be inspected daily, before work start, by a competent person. 6 2 12 Adequately Controlled Risk 34h Hazardous fume accumulation in pits Serious Injury/death 6 6 36  Do not use petrol / Diesel Engines in trenches- exhaust gases can accumulate. 6 2 12 Adequately Controlled Risk 35 Pinch Points 35 Pinch Points  Hand Injuries  Body Injuries 6 6 36  Keep workplace clean & tidy  Wear gloves  Never tamper with machine guards  Care when handling equipment & materials  Know how to turn off machinery in an emergency  Don’t wear loose cloths or jewellery when working near machines 6 2 12 Adequately Controlled Risk 36 Plant , Equipment & Plant Operators 36  Plant & Plant Operators  Injury  Property Damage 6 4 24  All plant to be operated by suitably licensed and competent operators.  All reversing vehicles to be controlled by a trained banksman  All mobile plant to have audible reversing alarm  Blind spots to be mitigated by appropriate mirrors. 6 2 12 Adequately Controlled Risk
  • 46. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 46 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Site driving rules enforced.  All necessary lights should be in place on vehicles including orange flashing beckons and should be used at all times as well as being regularly inspected.  Vehicle Lights, windows and mirrors shall be cleaned regularly to ensure a clear view.  Exclusion zones created around working plant  PPE, specific to night works i.e. clear lens glasses.  Operators to be trained, competent and hold current Omani Licences.  Stationary plant to have drip trays.  Emergency procedures in place 37 Plant Repairs, Maintenance, Assembling & Dismantling 37 Electrocution  Injury 6 4 24  Provide access  Task lighting  Trained & competent fitters  Electrical cables to be insulated  Use correct tools  Exclusion zones created around work area  Stationary plant to have drip trays. 6 2 12 Adequately Controlled Risk 38 Plant Collision 38 Collision with other  Injury 6 4 24  Banksman to guide and coordinate the 6 2 12 Adequately Controlled
  • 47. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 47 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk plant  Damage movements of plant items working in close proximity and reversing plant  Vehicles not to be parked in swing area of cranes or excavators etc. Risk Collision with persons  Injury 6 4 24  No person to stand sit or walk near working cranes excavators etc  No person shall sleep or take rest under plant  No unauthorised access  Reversing Alarms fitted.  Exclusion zones created around working plant 6 2 12 Adequately Controlled Risk 39 Reinforcement 39  Protruding steel  injury 6 4 24  Starter bars covered by timbers or caps  Binding wire bent away 6 2 12 Adequately Controlled Risk  Cutting  injury 6 4 24  Wear grinder glasses  Abrasive wheel training 6 2 12 Adequately Controlled Risk 40 Road Works 40a  Working on or near roads  Personal Injury / Fatality 6 4 24  Suitable NOC’s shall be obtained for all road works prior to works commencing  The working area should be barricaded and signs erected so that vehicle drivers are informed  Drivers shall follow site driving rules at all times.  Suitable lighting shall be provided for all areas of operation  Traffic calming measures shall be implemented as appropriate 6 2 12 Adequately controlled risk
  • 48. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 48 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 40b  Collision with plant or traffic  Vehicles gaining access to the site from poorly designed Traffic Management  Falls into excavations or from plant  Serious/fatal injuries from falls or collisions  Hand, foot and eye injuries from contact with hazardous materials or flying particles 8 6 48  Correct signing/coning/barriers in place for all roadwork’s and path works. Signs made stable by sandbags  Safe access for vehicles, plant and persons. Correct placing of signage shall ensure that public vehicles do not enter the work area.  A flagman will be in attendance when required to guide vehicles safely into and out of the site  Safe crossing of traffic lanes  Fixed barriers erected around any excavations which are 2 metres or more in depth  Open excavations fenced and illuminated at night with adequate signage  Adequate space and sufficient time allocated to the job  Noise minimised where possible  High-visibility clothing worn 8 2 16 Adequately Controlled Risk 40c Realignment of Sultan Qaboos Street Step 1 - Realignment Built off line  Collision with Site  Injury 8 6 48  A flagman will be in attendance when required 8 2 16 Adequately
  • 49. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 49 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk Traffic to guide vehicles safely into and out of the site Controlled Risk Step 2a - Temporary Link Roads & widening SQS  Vehicles gaining access to the site  Injury  Property damage 8 6 48  Signage  Barriers 8 2 16 Adequately Controlled Risk Step 2b - Diverting Live Traffic  Road accidents  Injury 8 6 48  Signage  Police escort for first cars  Method Statement to give methodology and sequence. 8 2 16 Adequately Controlled Risk Step 3a - Tie-ins construction  Collision with Site Traffic  Injury 8 6 48  A flagman will be in attendance when required to guide vehicles safely into and out of the site 8 2 16 Adequately Controlled Risk Step 3b - Diverting Live Traffic  Road accidents  Injury 8 6 48  Signage  Police escort for first cars 8 2 16 Adequately Controlled Risk      Method Statement to give methodology and Step 4 - Removal of Redundant section of SQS  sequence.  Vehicles gaining access to the site  Injury  Property damage 8 6 48  Signage  Barriers 8 2 16 Adequately Controlled Risk
  • 50. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 50 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk Step 5 Work in Median  Traffic Accidents  Injury 8 6 48  Close outside lane  Night work  Proper access off SQS 8 2 16 Adequately Controlled Risk 40 D Working site side of Temporary Road Barriers  Struck by road vehicle crashing thru barriers  Injury  Property damage 8 4 24  Where possible restrict persons on the ground ( not drivers in machines) working, standing or walking within a 10m danger zone inside the barriers  Warning signage  Workers to be warned of the risks 8 2 16 Adequately Controlled Risk 41 Road Saw 41  Using Saw machine  Cuts, injuries, eye injuries, Dust 6 4 24  Training to personnel  Permit system for operators  Inspect the equipment regularly  Test the machine prior setting for cutting  Change the blade regularly  Wear Eye protection  Wear Dust mask.  Set up exclusion zone with barriers and signage 6 2 12 Adequately Controlled Risk 42 Scaffolding 42  Structural  Personal Injury 8 6 48  Temporary works structural design. 8 2 16 Adequately
  • 51. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 51 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk collapse  Works at height  Fall of materials  Fall of persons  Property  Competent supervision  Only essential personnel and equipment to be allowed on to raised working platforms.  Regular briefings, tool box talks and night works activity briefs to be given related to working at height.  All temporary working platforms ( scaffold systems ) shall be erected by trained and competent personnel  All scaffold systems shall be regularly inspected by competent persons every 7 days.  All scaffold systems shall display a valid (signed and dated) scaff tag to identify if safe to use  Use fall arrest harnesses on scaffolding and falsework systems  Use double rail fixed barriers and toe boards on leading edges.  Use of suitable load rated steel life lines in absence of fixed guard rails  Adequate signage and exclusion zones around temporary structures  Structural design sign off before loading controlled risk 43 Steel Structures Erection 43  Works at height  Adverse weather conditions  Lifting operations  Property damage  Personal Injury 6 6 36  The work carried out in accordance with a design plan  Erection carried out by competent workers  Pre work briefings ref: MS and RA  Training & Supervision  Use of appropriate PPE 6 2 12 Adequately Controlled Risk
  • 52. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 52 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  See Works at height section  See Lifting operations section  Trained riggers in attendance. 44 Welding & Cutting 44 a  Fire and explosion  Thermal Radiation  Ultra-violet radiation  Gases and fumes  Electricity  Burns  Electric shock, electrocution  Arc Eye  Heat Disorders  Respiratory problems  Systemic poisoning from fumes  Fire initiation and spread 6 6 36  Hot work Permits  Tool Inspections  Welding screens  All hot works conducted by suitably trained and competent persons  Proper identification and storage of acetylene and oxygen tanks  All cutting / welding rigs to be fitted with flash back arrestors  Provision of suitable PPE  Remove all combustible materials from areas of hot works  Fire watch for 30 mins post hot work activity  Provision of suitable task lighting  Provision of suitable ventilation ( dilution / forced )  Atmospheric testing as required ( confined space etc )  All cylinders when being transported shall have the protective guards or caps in place over the valve assemblies. They should be transported in an upright position to and from the site in the special racks provided for this purpose.  Eliminate damp conditions. 6 2 12 Adequately Controlled Risk
  • 53. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 53 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 44 b  Grinding Operation  Disc Disintegration  Lacerations [may be severe, even fatal.  Penetrating injuries  Eye Injury 6 6 36  Use of approved suppliers  Use of appropriate speed rated discs  Use of task specific discs  Use of correctly adjusted guards  Use of suitable PPE ( body / hands / face / eyes /ears )  Trained and competent persons only to use abrasive wheels / change discs  All electrical equipment to be 110V with industrial sockets  Routine inspection / testing  All electrical equipment colour coded  Damaged equipment tagged and taken out of service  All cutters and grinders regularly maintained  No loose clothing worn  Adequate training & supervision  activities  Abrasive wheel signs.  Eye protection – high impact glasses at all times.  Eye wash station on site 6 2 12 Adequately Controlled Risk 45 Working at Height On Scaffolding & Other Platforms 45  Persons Falling  Personnel injuries 8 6 48  Temporary works structural design.  Competent supervision  Regular briefings, tool box talks and night works activity briefs to be given related to working at height. 8 2 16 Adequately Controlled Risk
  • 54. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 54 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  All temporary working platforms ( scaffold systems ) shall be erected by trained and competent personnel  All scaffold systems shall be regularly inspected by competent persons every 7 days  All scaffold systems shall display a valid (signed and dated) scaff tag to identify if safe to use  Use fall arrest harnesses on scaffolding and falsework systems  Use double rail fixed barriers and toe boards on leading edges.  Use of suitable load rated steel life lines in absence of fixed guard rails  Adequate signage and exclusion zones around temporary structures Structural design sign-off before loading.  Operate Permit to Work  Loading platforms provided for materials & equipment  Materials to be securely & safely stacked.  Provide safe access and egress for personnel.  Falling Objects  Personnel injuries 8 6 48  Only essential personnel, materials and equipment to be allowed on to raised working platforms.  Use and toe boards on leading edges.  Materials to be securely & safely stacked.  Erect signs re danger of falling objects  All tools being used in areas with open edges must be secured using lanyards, attached to the operative, or the fixed lines. 8 2 16 Adequately Controlled Risk
  • 55. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 55 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Exclusion zones to be set up underneath working area, with use of demarcation barriers and signage.  Inadequate access & egress  Personnel injuries 8 6 48  Proper and safe ladder or stairs access to heights will be provided 8 2 16 Adequately Controlled Risk 46 Working On, Above or Near Water 46 Water  Drowning  Physical effects of swallowing contaminated water 4 6 24  Warning signs  No lone working  Edge protection where practical  Safety lines and harnesses if edge protection is not present  Lifebuoys and rescue lines  Access routes free of hazards 4 2 8 Trivial Risk 47 Working Airside 47a General  Injuries  Property Damage 6 6 36  Site HSE Project Procedures  Work Permit Systems  Method Statement for Risk Activities  Risk Assessments 6 2 12 Adequately controlled
  • 56. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 56 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  On Site Safety Training  HSE Supervision  Issue of PPE  Tool box Talks Works to be made knowledgeable on site specific Safety risks.  COSHH Assessments  On site Medical Clinic  Site Emergency Response Plan  Site Health, Safety & Environmental Plan  First Aid Kits available  First Aiders  Site Inductions for Employees  Welfare Facilities  Waste bins  Managers must take responsibility and accountability for HSE Management  Training and implement above.  Welfare Facilities  Emergency Contact list  Emergency Contact List 47b Security Risk Bombings, Shootings. Hijacking  Multiple Fatalities 4 6 24  Security Passes  Check vehicles entering Airside 4 2 8 Trivial Risk 47c Breaking Navigational Aids  Closure of Airport Runway 4 6 24  Fence off 4 2 8 Trivial Risk 47d Breaking underground power supply to landing  Closure of airport runway  Elocutions 6 6 24  Scan check for underground services  Supervision  Area to be visually checked for markers or physical signs of services, i.e. manholes. 6 2 12 Adequately Controlled
  • 57. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 57 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk lights and IT cables  Up to date drawings detailing existing services shall be obtained and checked thoroughly.  OAMC shall be contacted to assess if there are services in the area and also to let them know work is going to be carried out.  Obtain Dig permit from OAMC.  Use of trial holes and hand excavation around known services  Hand tools that are non conductive shall be used when excavating around existing services.  Prior to excavation the affected area shall be surveyed with a CAT and competent person.  Records of all CAT surveyed areas to be kept on file and briefed to excavation team  Surveyed area clearly demarked on site  Emergency contact numbers displayed on site 47e Collision with Aircraft in flight  Multiple Fatalities 4 6 24  Communication with ATC  Observe height limits 4 2 8 Trivial Risk 47f FODs (Foreign Object Debris)  Aircraft damage  Aircraft engines may get damaged 4 6 24  All FODs to be cleared after the job is done  Good housekeeping 4 2 8 Trivial Risk 47g Noise Fight jets  Injury to hearing 4 6 24  Issue Ear protection 4 2 8 Trivial Risk 47h DUST Source of emissions from dust/particulates during leveling, scraping, and earth moving operations  Reduced visibility  Due to increased emissions, impacts on human health within the site and neighboring areas 4 6 24  Regular water spraying of unpaved and sweeping of paved roads to minimize dust and remove mud  Sheeting vehicles carrying dusty materials to prevent materials being blown from the vehicle whilst travelling  Reducing the quantity of dusty materials 4 2 8 Trivial Risk
  • 58. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 58 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk via traffic movements to and from site. stored on site or covering stored material to minimize the amount of dust being blown 47i Mud Control Vehicles exiting the work site may carry mud onto adjacent roads  Road Contamination  Slips 4 6 24  Vehicles going from the work site onto paved roads must be free of excessive mud. 4 2 8 Trivial Risk 47j Moving Plant  Injuries  Collisions  Property Damage 6 6 36  Banksman to guide and coordinate the movements of plant items working in close proximity and reversing plant  Vehicles not to be parked in swing area of cranes or excavators etc.  No person to stand sit or walk near working cranes excavators etc  No person shall sleep or take rest under plant  No unauthorised access  Reversing Alarms fitted.  Exclusion zones created around working plant 6 2 12 Adequately Controlled 47k Birdstrike  Aircraft damage  Aircraft engines may get damaged 6 6 36  Don’t feed birds  Remove all waste food immediately  Report any birds to Airport Authority 6 2 12 Adequately Controlled 48 Operating Vibrating Hand Tools
  • 59. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 59 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 48a 48b Vibration  Vibration White Finger  Hand-Arm Vibration Syndrome (HAVS) 6 6 36  Limit exposure time i.e. actual trigger time  Regular breaks  Job rotation  Ensure tools are used correctly and maintained.  Wear gloves  Oil the tool daily before use. 6 2 12 Adequately Controlled Risk Dust  Eye injury  Dust Inhalation 6 6 36  Wear dust mask.  Wear goggles 6 2 12 Adequately Controlled Risk 49 Poor Housekeeping 49 Housekeeping  Skin puncture.  Dust inhalation.  Material handling injuries. 6 6 36  Toolbox talks.  Signs and posters.  PPE issue and training. Police use of.  Supervised daily by site supervisors 6 2 12 Adequately Controlled Risk 50 Working in Live Sewer Manhole (Haya Manhole # 17)
  • 60. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 60 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 50  Illnesses e.g. diarrhea, Hepatitis, Weill’s disease  Health problems 6 6 36  Provide suitable personal protective equipment, that include waterproof/abrasion- resistant gloves, footwear, eye and respiratory protection.  Disposable overalls  Power wash inside of manhole with disinfectant  Provide washing facilities with disinfectant 6 2 12 Adequately Controlled Risk  Water & Sewage  Drowning 6 6 36  Over-pump manhole from manhole upstream to manhole downstream which will have inflatable stoppers fitted to outlet and inlet pipes. 6 2 12 Adequately Controlled Risk Note - Permit Confined Space because of Hazardous Gases danger Refer to Site HSE Project Procedure PP710 for Confined Spaces  Hazardous Gases  Fumes  Health problems 6 6 36  Note - Depending on circumstances select from following  Vent manhole including upstream & downstream manhole for 24 hours  Provide good ladder access.  Smoking Prohibited.  No Working Alone,  Standby Person on surface fulltime in verbal and visual contact with worker. Will execute non-entry rescue and raise emergency alarm. 6 2 12 Adequately Controlled Risk
  • 61. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 61 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  No petrol or diesel engines in manhole  No combustible material stored in manhole  Permit to Work System  Personnel Training in Confined Spaces  Gas Monitoring for toxic gases & permissible oxygen levels. Before & during manhole occupancy.  Force Ventilation  Rescue Harness (connected to Lifeline leading to outside)  Tripod erected or crane / excavator on standby to lift out worker  Rescue Equipment - Self Rescuers carried  51 Felling Trees 51  Struck by falling tree / branch  Injury  Property Damage 6 6 36  Establish and maintain exclusion zone minimum the greater than the length of tree to be felled  Don’t fell a tree in windy conditions  Trees to be felled towards a clear open area  Maintain awareness of potential butt recoil / deflection.  Ensure felling operations do not damage features  Remove potential trip hazards 6 2 12 Adequately Controlled Risk
  • 62. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 62 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  Use 3 cut technique ( undercut, top cut, final cut)  Chainsaw  Injury  Cuts and abrasions  Noise  Eye injury 6 6 36  Operator to be trained and competent  Chainsaw shall be maintained  Ensure guards are in place and the saw is in good working order.  Wear ear muffs  Restrict work to 30 minutes between breaks  Wear safety glasses  Two hand operation  Suspend work during severe weather 6 2 12 Adequately Controlled Risk 52 Post tensioning  52 a Fixing Anchorages   Falling materials  Equipment failure  Crane failure  Working at Height  Physical Injuries  Equipment & Material damage 6 4 24  Refer to Mobile Cranes – Lifting Operations in this document  Only essential personal and equipment allowed on to working area / platform  Refer to Working at Height in this document  Use proper tools while fixing cast in trumpet 6 2 12 Adequately Controlled Risk
  • 63. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 63 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  52 b Placing Ducts   Working with sharp edges  Works at height  Working with flame torch  Cuts  Physical Injuries  Equipment & Material damage  Burns 6 4 24  Wear gloves  Use of Trained personnel  Competent supervision  Control of access to work location  Hot work Permits  Flask back arrestors  Fire precautions ( extinguishers etc )  Remove all combustible materials from areas of hot works  Fire watch for 30 mins post hot work activity  All hot works conducted by suitably trained and competent persons 6 2 12 Adequately Controlled Risk  52 c Threading Strand   Being struck by strand.  Entanglement  Injury from sparks when cutting strand  Working at height  Physical Injury 6 4 24  Use the correct tools  Position strand coil in dispenser prior to cutting straps  Exclusion zone set up around area  Using Trained operatives  No loose clothing to be worn by operatives of threading machine  Wearing suitable gloves  Face shield to be worn  Competent supervision  Hot works controls  Refer to Working at Height in this document  Know how to turn off machinery in an emergency using emergency switch 6 2 12 Adequately Controlled Risk
  • 64. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 64 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  52 d Stressing Strand  Burst hydraulic hose  Overstressing of strand  Strand Breaking  Confined space works  Concrete failure  Hardware failure  Working at height  Fatalities/ physical injuries.  Equipment and material damage 10 4 40  All stressing equipment and accessories to be certified and inspected prior to use.  Forces applied shall be properly calculated and applied as the specification.  Workers shall be made aware that the forces they are handling during stressing are enormous and carelessness may lead to loss of life.  Regularly examine hydraulic hoses, hydraulic equipment shall be fitted with suitable quick connecting couplers.  Check concrete strength by cube tests.  Place safety solid timber plywood barrier behind stressing jack  Erect signs – Danger no Entry  During stressing persons will not stand or cross behind or close to the jack and not in line with the anchorage at the non jacking end, or behind any tendons anchor already stressed.  Trained and authorized operatives only  Competent supervision  Strand to have certificates.  Refer to Working at Height in this document  Refer to Confined Spaces in this document  Know how to turn off machinery in an emergency using emergency switch 10 2 20 Adequately Controlled Risk
  • 65. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 65 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk  52 e Grouting & Sealing Grouting Chemicals  Eye irritations  Contact dermatitis  Mild burns 6 6 36  Wear suitable protective eye wear  Compliance with COSHH assessment  Have eye station on hand  Wash hands after each exposure  Use of gloves  Use of full length uniforms  First Aiders available 6 2 12 Adequately Controlled Risk Use of cement mixers  Broken arms  Strains  Cuts  Electrocution 6 6 36  All necessary guards are to be in place on the mixer.  All equipment is to be inspected by a competent person to ensure the equipment is mechanically and electrically safe.  No persons are to put tools or limbs in to mixer while drum is rotating.  Mixer is to be set up on firm level ground and should never be over loaded  110V plant only on project.  Suitable earthing of static plant  Planned preventative maintenance  PMV inspection prior to mobilisation 6 2 12 Adequately Controlled Risk Use of grout pump Bursting of hose pipes  Personal injuries 6 6 36  Use whip arrestor on feed lines  Inspect all the equipment and accessories prior to use  Ensure hoses are maintained  Trained / authorised operators  Know how to turn off machinery in an 6 2 12 Adequately Controlled Risk
  • 66. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 66 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk emergency.   52 f De-tensioning & Re-tensioning   Burst hydraulic hose  Overstressing of strand  Strand Breaking  Confined space works  Concrete failure  Hardware failure  Working at height  Fatalities/ physical injuries.  Equipment and material damage 10 4 40  All stressing equipment and accessories to be certified and inspected prior to use.  Forces applied shall be properly calculated and applied as per specification  Workers shall be made aware that the forces they are handling during stressing are enormous and carelessness may lead to loss of life.  Regularly examine hydraulic hoses, hydraulic equipment shall be fitted with suitable quick connecting couplers.  Check concrete strength by cube tests.  Place safety solid timber plywood barrier behind stressing jack  Erect signs – Danger no Entry  During stressing persons will not stand or cross behind or close to the jack and not in line with the anchorage at the non jacking end, or behind any tendons anchor already stressed.  Trained and authorized operatives only  Competent supervision  Strand to have certificates  Refer to Working at Height in this document  Refer to Confined Spaces in this document  Know how to turn off machinery in an emergency using emergency switch. 10 2 20 Adequately Controlled Risk
  • 67. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 67 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk 53 Hydraulic Pump & Jacks  Plant & Plant Operators  Injury  Property Damage 6 4 24  All plant to be operated by competent operators.  Exclusion zones created around working plant  Stationary plant to have drip trays.  Know how to turn off machinery in an emergency. 6 2 12 Adequately Controlled Risk 54 Traffic Management  Moving Delivery Vehicles Entering/Leaving site  Traffic accidents  Property damage  Personal injury 6 6 36  Good visibility of oncoming vehicles.  Traffic calming measures such as speed bumps  Pedestrian routing. High visibility clothing.  Reversing alarms.  All vehicle reversing controlled by trained banksman.  Adequate signage  Adequate lighting at site entrances  Site driving rules posted  Security marshalling traffic  All CCCTAVJV / Subcontractors drivers HSE inducted  All drivers to hold valid Omani license  Authorised vehicles only on site  Security identify drop zones & advise delivery drivers on site traffic rules. 6 2 12 Adequately Controlled Risk 55 Auger Boring with Casing
  • 68. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 68 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk a Excavation Slips, trips & falls Serious Injury 4 6 24  Follow good housekeeping at site  Remove rocks and debris from the area  Follow method of statements 4 4 16 Adequately Controlled Risk b Noise Occupational illness 4 6 24  Proper Maintenance of Vehicle and Equipment  Use ear protection 4 6 24 Adequately Controlled Risk c Damage to Utilities Property Damage 4 6 24  Carry out survey of the area before work  Certified / Qualified operators to Operate the equipment 4 4 16 Adequately Controlled Risk d Persons being struck by plant or other vehicles Serious Injury / Death 4 4 16  A dedicated Flag man at all times  Flag man must wear reflective vest  Operators must not use mobile phones while operating machines  People on foot must be kept clear of the area.  Trained operators  Demarcation fence for restricted area  Authorised personnel only 4 4 16 Adequately Controlled Risk e Persons Falling in to pits Serious Injury 4 6 24`  Barricade & put signage in trenched area  Prevent access to unauthorised people  Install "STOP" blocks if necessary  Ensure access and egress 4 4 16 Adequately Controlled Risk    Ensure standby vehicle & trained person at shaft side
  • 69. Health & Safety Construction RISK ASSESSMENTS 96 pages Page 69 of 92 Activ ity HAZARD EFFECT RISK ANALYSIS / NO CONTROLS CONTROL MEASURES RISK ANALYSIS / WITH CONTROLS Residual Risk remarks severity likelihood risk severity likelihood risk f Vehicle Equipment /Materials falling into pits (Pipe, sand Etc.) Property Damage 4 4 16  Do not park vehicle near trench  Do not store excavated materials close to the trench  Ensure pipes are chocked & kept 1.5mtrs from trench  Trained banksmen 4 4 16 Adequately Controlled Risk g Collapse of Pit walls or sides Injury 4 6 24  Ensure trench walls are well supported, use shoring if necessary  Slope sides when excavating in sand / loose soil  The excavation must be inspected daily, before work start, by a competent person. 4 4 16 Adequately Controlled Risk h Hazardous fume accumulation in pits Serious Injury/death 4 4 16  Do not use petrol / Diesel Engines in shafts - exhaust gases can accumulate.  Ensure good ventilation  Good house keeping 4 4 16 Adequately Controlled Risk i Confined Spaces / Ventilation Serious Injury/death 4 6 24  Confined spaces procedure in place  Permit to entre  Use of Gas Monitor  Use of proper ventilation inside sleeve pipe (fans etc).  All personnel involved to be aware on confined space working including rescue, 4 4 16 Adequately Controlled Risk 