1. David H Moloney
Nov 2016
Motorway Construction, Project Execution Plan
Details of how a Motorway is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to
ensure that the site is environmentally friendly.
Brief Description
The purpose of this presentation is to give an
understanding of the Methods, Plant and
Sequence to construct a Motorway.
This presentation can be used to engage
Stakeholders and to get the Site Teams
commitment to the programme. Also can be
used for Induction Training and as a way to
capture and share knowledge.
Project Execution Plan (PEP) details how a
project will be executed, monitored and
controlled.
High in Educational Value and easily understood.
Recommended for Continuing Professional
Development (CPD)
4. Mass Haul Diagram
Earthworks
The mass haul diagram shows the fill and excavation volumes plotted against chainage along a road. It is
used to provide an indication of the haul distances and to ensure that haul distances are minimised.
5. Outputs - Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
7. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
11. Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Health,Safety&Environment
18. Insitu Concrete Barrier
ⓒ David H Moloney
Paving
Slipform central median barrier, the
moving formwork allow for the
simultaneous extrusion and finishing
of the concrete. Powerful vibrators
compact the semi-dry concrete.
19. Steel Traffic Safety Barrier
ⓒ David H Moloney
Paving
The barriers are designed to keep vehicles
within their roadway and prevent vehicles from
colliding with dangerous obstacles such as
bridges, buildings, walls or large storm drains.
20. Pavement Marking
Paving
Road surface markings are used on paved roadways to
provide guidance and information to drivers and
pedestrians. They can be used to delineate traffic lanes.
21. Road Signs
ⓒ David H Moloney
Paving
Road signs are signs erected at the side of or
above roads to give instructions or provide
information to road users.
25. Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
27. Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
41. Temporary Electricity Supply & Tower Lights
Generators
GeneralItems
Used so construction work can continue effectively and safely in
periods of insufficient natural light.
42. Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
43. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
47. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
48. Asphalt Batching Plant
The plant is used for the
manufacture of asphalt.
Aggregates, sand and a filler (such
as stone dust), in the correct
proportions, are heated, and
coated by mixing with a binder,
bitumen based. The temperature of
the finished asphalt mix must be
sufficient to be workable after
transport to the final destination.
53. Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
65. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
72. Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
73. Histogram Charts for Resources & Outputs
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
75. Time Chainage Diagram
Brief Description
The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Legend