Project Execution Plan for High Rise Building
Details how the construction will be executed, monitored and controlled.
You...
Table of Contents
Floor Construction
Observation Deck on Floor 124
Floor Construction Cycle Time
Floor Construction Cycle timeGeneralItems
Formwork Quantities
Column formwork = ½ set (50%)
Core wall formwork = 1 set (10...
Floor Construction Overview
ⓒ David H Moloney
GeneralItems
Floor Construction Formwork Types
Shuttering to ColumnsGeneralItems
Brief Description
Column formwork can be moved with
only one crane lift complete with pu...
Shuttering – Columns
ⓒ David H Moloney
GeneralItems
Shuttering to Core ( Lifts & Stairs)GeneralItems
Brief Description
Automatic climbing formwork system
lifts itself upwards...
ⓒ David H Moloney
GeneralItems
Shuttering to Core ( Lifts & Stairs)
Shuttering Self Climbing for Core
Concrete
Cycle Time 4 Days
Shuttering to Floor Slabs – Table formsGeneralItems
Brief Description
Table forms are preassembled formwork
and false unit...
Shuttering to Floor Slabs – Table formsGeneralItems
Leapfrog
table forms
Shuttering – Floor Slabs
ⓒ David H Moloney
GeneralItems
Shuttering – StairsGeneralItems
Shuttering – Stairs
ⓒ David H Moloney
GeneralItems
Dubai High Rise Buildings
ⓒ David H Moloney
Main Equipment
Climbing Tower Cranes
Brief Description
A climbing tower crane lifts itself up using a climbing
attachment with hydraulic ...
Climbing Tower Cranes
Miscellaneous
Climbing Tower Cranes – Tie-in Assembly
Miscellaneous
Concrete Pump – Self ClimbingGeneralItems
Brief Description
The concrete is pumped by a diesel powered, static
concrete pu...
Concrete Pump
Miscellaneous
Protection Screen - Self climbingGeneralItems
Brief Description
Protection screens enclose the top floors of a high
rise e...
Ensuring VerticalityGeneralItems
Brief Description
Leave 3 holes in the floor, forming a
right angle. Use a laser plumb bo...
Platforms, Chutes & LiftsGeneralItems
ⓒ David H Moloney
GeneralItems
Platforms, Chutes & Lifts
General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
GeneralItems
Brief Description
Contractors Site facilities compri...
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwa...
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwa...
Dewatering
ⓒ David H Moloney
GeneralItems
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
GeneralItems
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Safety & Environmental
Emergency Phone Numbers & Response
Health,Safety&Environment
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE statistics and ...
Safety Precautions
Health,Safety&Environment
Signs Examples
Health,Safety&Environment
Hazardous Substances Symbols
Health,Safety&Environment
COSHH stands for the
Control of Substances
Hazardous to Health
Show...
Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to l...
Water Pollution PreventionHealth,Safety&Environment
Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
unde...
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Trench - Safety Measures
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Earthworks
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weig...
Excavation for Trench with Stepped FacesEarthworks
Excavation for Trench with Battered FacesEarthworks
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demon...
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
Concrete batching plant comprises -
concrete m...
Concrete Batching Plant
ⓒ David H Moloney
Concrete
Concrete Batching Plant 3Nr.
ⓒ David H Moloney
Concrete
Concrete Batching Plant - Liebherr Betomix Animation
Concrete
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
.
The mixing is computer controlled
and has a ...
Concrete Batching Plant – Computer Controlled
ⓒ David H Moloney
Concrete
Concrete Mix Proportions per Cu M
Brief Description
.
Details of Mix for C40
1. Concrete Grade C40
2. Cement Type = OPC
3....
Reinforcement Cutting & Bending Yard
ⓒ David H Moloney
Concrete
Brief Description
Reinforcement in 12 m lengths.
Delivery ...
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bu...
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced ...
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Vibrating Concrete
ⓒ David H Moloney
Concrete
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer...
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Piling Construction - Vertical PilesPiling
Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any ...
Pile Load Test
ⓒ David H Moloney
Piling
Progress Monitoring & Administration
Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progr...
Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Pro...
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities ...
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relat...
Staff Directory
Brief Description
List of staff and their
contact details
Quality Assurance
Quality Assurance Dashboard
Dashboard is a single page, graphical representation of current
statistics and historical tren...
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
Upcoming SlideShare
Loading in …5
×

Project Execution Plan for High Rise Building

16,301 views

Published on

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Published in: Engineering
  • Hi dear Mr. moloney, I am a civil engineer and I am a supervisor at 32 storey builing project, whuold you please help me how we can protect our edgs in every storey?
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Want to earn $4000/m? Of course you do. Learn how when you join today! ◆◆◆ http://ishbv.com/ezpayjobs/pdf
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • Slim Down in Just 1 Minute? What if I told you, you've been lied to for nearly all of your life? CLICK HERE TO SEE THE TRUTH ●●● https://tinyurl.com/1minweight4u
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • DOWNLOAD FULL BOOKS, INTO AVAILABLE FORMAT ......................................................................................................................... ......................................................................................................................... 1.DOWNLOAD FULL. PDF EBOOK here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... 1.DOWNLOAD FULL. EPUB Ebook here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... 1.DOWNLOAD FULL. doc Ebook here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... 1.DOWNLOAD FULL. PDF EBOOK here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... 1.DOWNLOAD FULL. EPUB Ebook here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... 1.DOWNLOAD FULL. doc Ebook here { https://tinyurl.com/y3nhqquc } ......................................................................................................................... ......................................................................................................................... ......................................................................................................................... .............. Browse by Genre Available eBooks ......................................................................................................................... Art, Biography, Business, Chick Lit, Children's, Christian, Classics, Comics, Contemporary, Cookbooks, Crime, Ebooks, Fantasy, Fiction, Graphic Novels, Historical Fiction, History, Horror, Humor And Comedy, Manga, Memoir, Music, Mystery, Non Fiction, Paranormal, Philosophy, Poetry, Psychology, Religion, Romance, Science, Science Fiction, Self Help, Suspense, Spirituality, Sports, Thriller, Travel, Young Adult,
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • The #1 Woodworking Resource With Over 16,000 Plans, Download 50 FREE Plans...  http://ishbv.com/tedsplans/pdf
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here

Project Execution Plan for High Rise Building

  1. 1. Project Execution Plan for High Rise Building Details how the construction will be executed, monitored and controlled. YouTube Link https://youtu.be/_gikBOisPH8 DavidHMoloney 17thJuly2016 Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a high-rise building. This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Can be use to demonstrate entitlement for delays and additional payment. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Presentation is innovative and has many beneficial uses.
  2. 2. Table of Contents
  3. 3. Floor Construction Observation Deck on Floor 124
  4. 4. Floor Construction Cycle Time
  5. 5. Floor Construction Cycle timeGeneralItems Formwork Quantities Column formwork = ½ set (50%) Core wall formwork = 1 set (100%) Slab formwork = 2 sets (200%) Table forms Formwork types Columns - Crane handled units Core Walls - self climbing floor to floor Slabs Formwork & Falsework – Table forms Crane handled Cycle Time 7 working days cycle per floor Programme Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Columns Rebar, Shutter & Pour 50% Rebar, Shutter & Pour 50% Strip shutters Walls Pour walls Climb up Fix Rebar Fix shutters Floor Strike & Move Forms Slab Formwork Rebar MEP Slab Formwork Rebar MEP Slab Formwork Rebar MEP Slab Formwork Rebar MEP Pour slab 100%
  6. 6. Floor Construction Overview ⓒ David H Moloney GeneralItems
  7. 7. Floor Construction Formwork Types
  8. 8. Shuttering to ColumnsGeneralItems Brief Description Column formwork can be moved with only one crane lift complete with push- pull props and concreting platform with guard rails and ladder – alternatively moved by hand using transportation wheels. QUATTRO system by Peri
  9. 9. Shuttering – Columns ⓒ David H Moloney GeneralItems
  10. 10. Shuttering to Core ( Lifts & Stairs)GeneralItems Brief Description Automatic climbing formwork system lifts itself upwards on rails bolted to the walls using hydraulic jacks Doka Xclimb 60
  11. 11. ⓒ David H Moloney GeneralItems Shuttering to Core ( Lifts & Stairs)
  12. 12. Shuttering Self Climbing for Core Concrete Cycle Time 4 Days
  13. 13. Shuttering to Floor Slabs – Table formsGeneralItems Brief Description Table forms are preassembled formwork and false units and are moved horizontally on wheels or a trolley and vertically from floor to floor by crane or by a lift fixed to the outside of the building
  14. 14. Shuttering to Floor Slabs – Table formsGeneralItems Leapfrog table forms
  15. 15. Shuttering – Floor Slabs ⓒ David H Moloney GeneralItems
  16. 16. Shuttering – StairsGeneralItems
  17. 17. Shuttering – Stairs ⓒ David H Moloney GeneralItems
  18. 18. Dubai High Rise Buildings ⓒ David H Moloney
  19. 19. Main Equipment
  20. 20. Climbing Tower Cranes Brief Description A climbing tower crane lifts itself up using a climbing attachment with hydraulic jacks that surrounds the mast. The climbing attachment lifts itself up off the erected mast and inserts a new mast section. GeneralItems
  21. 21. Climbing Tower Cranes Miscellaneous
  22. 22. Climbing Tower Cranes – Tie-in Assembly Miscellaneous
  23. 23. Concrete Pump – Self ClimbingGeneralItems Brief Description The concrete is pumped by a diesel powered, static concrete pump, through a fixed 125 mm pipeline, to the folding placing boom. The boom is mounted on a steel column of up to 20 metres high. The column is supported by a cross base or a system of floor frames set into the concrete floors. With floor frames , the whole column / boom assembly can climb with the building as the work progresses. For placing concrete pumping is faster than using a crane and skip and is less likely to be adversely affected by high winds.
  24. 24. Concrete Pump Miscellaneous
  25. 25. Protection Screen - Self climbingGeneralItems Brief Description Protection screens enclose the top floors of a high rise enabling construction work to be carry out in great safety, and protected from the weather. The screen will contain any debris and tools that would otherwise fall to the surface. The Protection screen can be moved upwards hydraulically or using a tower crane.
  26. 26. Ensuring VerticalityGeneralItems Brief Description Leave 3 holes in the floor, forming a right angle. Use a laser plumb bob and a transparent sheet on the floors above. "Jump" the laser every 5 or 6 floors.
  27. 27. Platforms, Chutes & LiftsGeneralItems
  28. 28. ⓒ David H Moloney GeneralItems Platforms, Chutes & Lifts
  29. 29. General Items
  30. 30. Contractor’s Temporary Site Facilities ⓒ David H Moloney GeneralItems Brief Description Contractors Site facilities comprise: Offices, Canteens, Toilets, Drying Rooms, Stores, Plant Yard, generators and Workshops.
  31. 31. Dewatering ⓒ David H Moloney GeneralItems Brief Description Construction dewatering is the removal or drainage of groundwater and or surface / rain water usually by pumping to keep the works dry.
  32. 32. Dewatering ⓒ David H Moloney GeneralItems Brief Description Construction dewatering is the removal or drainage of groundwater and or surface / rain water usually by pumping to keep the works dry.
  33. 33. Dewatering ⓒ David H Moloney GeneralItems
  34. 34. Site Hoarding examples ⓒ David H Moloney GeneralItems
  35. 35. Temporary Electricity Supply & Tower Lights ⓒ David H Moloney GeneralItems
  36. 36. Welfare Facilities ⓒ David H Moloney GeneralItems Toilets – Washing Canteen, Drying Room, Toilet & Generator
  37. 37. Safety & Environmental
  38. 38. Emergency Phone Numbers & Response Health,Safety&Environment
  39. 39. HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current HSE statistics and historical trends Health,Safety&Environment
  40. 40. Safety Precautions Health,Safety&Environment
  41. 41. Signs Examples Health,Safety&Environment
  42. 42. Hazardous Substances Symbols Health,Safety&Environment COSHH stands for the Control of Substances Hazardous to Health Shown are the new hazard symbols
  43. 43. Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
  44. 44. Segregation of WasteHealth,Safety&Environment Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe. Colour Code for Skips & Bins
  45. 45. Water Pollution PreventionHealth,Safety&Environment
  46. 46. Existing Underground Utilities ⓒ David H Moloney Brief Description Before digging establish the location and route of underground utilities. Locator to find Utilities Spray Paint to mark pavement Health,Safety&Environment
  47. 47. Existing Underground Utilities & Overhead Cables - Safety Measures ⓒ David H Moloney Health,Safety&Environment
  48. 48. Trench - Safety Measures Health,Safety&Environment
  49. 49. Trench - Safety Measures ⓒ David H Moloney Health,Safety&Environment
  50. 50. Earthworks
  51. 51. Excavate & Load, Cart, Tip & Return Brief Description Cycle Time for 7km haulage distance using an Excavator 45 tonne weight and Dumper with a 40 tonne capacity, the cycle time is 34 minutes Earthworks 7 minutes 14 minutes 3 minutes 14 minutes 7 km 7 km
  52. 52. Excavation for Trench with Stepped FacesEarthworks
  53. 53. Excavation for Trench with Battered FacesEarthworks
  54. 54. Concrete
  55. 55. Concrete Full Scale Trial Castings of Pier ⓒ David H Moloney Brief Description The full-scale trial casting(s) shall demonstrate/document that all requirements to the concrete and the execution of the work are fulfilled simultaneously using the actual methods and performed by personnel as for the future production. Concrete BIM 3D Model Shutter Fibreglass
  56. 56. Concrete Batching Plant David H Moloney ⓒ David H Moloney Brief Description Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. Concrete
  57. 57. Concrete Batching Plant ⓒ David H Moloney Concrete
  58. 58. Concrete Batching Plant 3Nr. ⓒ David H Moloney Concrete
  59. 59. Concrete Batching Plant - Liebherr Betomix Animation Concrete
  60. 60. Concrete Batching Plant David H Moloney ⓒ David H Moloney Brief Description . The mixing is computer controlled and has a dynamic screen display, showing the process. The material storage capacity is, to match two days concrete production. Concrete
  61. 61. Concrete Batching Plant – Computer Controlled ⓒ David H Moloney Concrete
  62. 62. Concrete Mix Proportions per Cu M Brief Description . Details of Mix for C40 1. Concrete Grade C40 2. Cement Type = OPC 3. Slump =125mm 4. Max size aggregate = 20mm 5. Max water / Cementitious ration =0.42 Concrete Materials Qty Units Cement 310 Kgs Fly ash 100 Kgs Micro-silica 12 Kgs Washed Sand 670 Kgs Fine Sand 106 Kgs 10mm Crushed aggregate 400 Kgs 20mm Crushed aggregates 725 Kgs Water 145 Ltr. Additive Rheobuild 7.5 Ltr. Early age strength concrete is required for quick floor cycle time
  63. 63. Reinforcement Cutting & Bending Yard ⓒ David H Moloney Concrete Brief Description Reinforcement in 12 m lengths. Delivery in 3 ton Bundles
  64. 64. Reinforcement Cutting & Bending ⓒ David H Moloney Concrete
  65. 65. Reinforcement Cutting & Bending ⓒ David H Moloney Concrete
  66. 66. Reinforcement Cutting & Bending Yard David H Moloney ⓒ David H Moloney Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site Concrete
  67. 67. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete Brief Description The sequence to construct a reinforced concrete wall is as follows: Tie the reinforcement. Erect stop-ends and the wall shutters. Pour and vibrate the concrete mix. Remove the shutters after the concrete has hardened. . Cycle Time Pour per Day
  68. 68. Reinforced Wall Construction Sequence ⓒ David H Moloney Concrete
  69. 69. Vibrating Concrete ⓒ David H Moloney Concrete
  70. 70. Piling
  71. 71. Piling Construction - Plant & Methods Brief Description Piling Plant, Equipment and Material; Crawler Crane, Piling Hammer, Temporary Casing, Piling Rig, Concrete Pump, Concrete Mixer Trucks, Tremie Pipe and Reinforcement Cage Piling
  72. 72. Piling Construction - Plant, Methods & SequencePiling
  73. 73. Piling Construction - Plant & MethodsPiling
  74. 74. Piling Construction - Vertical PilesPiling
  75. 75. Pile Load Test ⓒ David H Moloney Piling Brief Description A jack is used to load the pile in steps and gauges measure any settlement.
  76. 76. Pile Load Test ⓒ David H Moloney Piling
  77. 77. Progress Monitoring & Administration
  78. 78. Progress Monthly, Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of current progress and historical trends
  79. 79. Histogram Charts for Resources & Outputs Manpower per Discipline Concrete per Location Man-hours for each month of the Project Quantity for each month of the Project ⓒ David H Moloney Brief Description Histograms shows resources etc. for each month of a project.
  80. 80. Plant & Equipment List & Worker’s Job Titles ⓒ David H Moloney
  81. 81. Daily Work Record Brief Description Daily Work Records showing the allocation of resources, materials and work activities carried out daily.
  82. 82. Organogram Brief Description Shown are the line and lateral relationships between the various team members and their relative position in the site organisation.
  83. 83. Staff Directory Brief Description List of staff and their contact details
  84. 84. Quality Assurance