SlideShare a Scribd company logo
1 of 2
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane
Issued: Rev. Date:
Revision: 0
Page 1 of 2 HSEQ -Rev-01(Jan-2023)
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Lifting operations using Tower crane within site boundary
Relevant Applicable MAS:
 01412 – Lifting Operations;
 00941 – Lifting equipment
Additional Training required:
Riggers / Slingers
NOC’s Required for task:
As applicable
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1
Access of Tower crane
sections to work areas
 Plant and workers in
same working area
as delivery truck;
 Collision with plant or vehicles and
live traffic;
 Workers struck by plant, very high
risk of fatality;
 Uncontrolled crane reversing;
3 4
12
High
i. Worker pedestrian routes to be designed and implemented with clear
signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the
project;
iii. Flagmen to be used to control crane movements;
iv. The Logistics plan shall clearly illustrate crane access and egress points;
Workers not
complying with
flagmen
Regular topic in TBT’s Low
2 Tower crane
foundations
 Excavations;
 Use of plant –
excavators etc.;
 Use of concrete;
 Temporary Works;
 See Risk Assessment 010 –
Excavations;
 See Risk Assessment 014 – use of
Mobile Concrete pump;
 Failure due to incorrect design;
4 5
20
High
i. Crane foundations to be designed by approved persons, to clear design
criteria;
ii. Foundations given adequate curing time before crane erection;
iii. Temporary Works Coordinator to control excavations and concrete pours;
Low
3 Siting, setting up and
testing of Tower crane
 Works at Height;
 Working in proximity
to existing structures
and services;
 Fall from height;
 Falling materials from height;
 Use of untrained erectors;
 Erection in adverse weather;
 Collision with overhead services;
 Blocking access routes;
 Load striking moving and/or
stationary structures;
 Use of untested crane;
 Use of unqualified operator;
3 4
12
High
i. Ensure crane is erected to standards by trained competent erection
personnel;
ii. No crane erection in adverse weather or high wind speed;
iii. Concise erection Method Statement compiled and available in work area
for review;
iv. Area below works cleared and barriers implemented;
v. Solid barriers should be situated, where practicable, to protect erected
crane from traffic routes;
vi. Consideration given to overhead services and existing structures when
siting tower crane;
vii. All Tower cranes to be Third Party Certificated by a DM approved
inspector prior to use, documentation available on arrival to site;
viii.Load tests undertaken prior to use and available for review;
ix. Operators to have in-date Third Party certificate by approved body,
available for review;
x. Crane load indicator to be installed and functioning correctly;
Failure of crash
detector
Crane quarantined until
repaired and tested
Low
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane
Issued: Rev. Date:
Revision: 0
Page 2 of 2 HSEQ -Rev-01(Jan-2023)
xi. Crash detectors installed and functioning correctly;
4
Lifting of equipment
and material
(Tower crane Operator)
 Operator competency
and health;
 Lift planning;
 Incident due to use of defective
lifting gear / equipment;
 Crane collapse due to lifting loads
beyond SWL;
 No crane documentation in place;
 Tower crane operator collapse whilst
in cab;
4 5
20
HIGH
i. HLG Minimum Acceptable Standard HLG/OHS/MAS/00941 to be adhered
to at all times;
ii. Lift Plan to be completed prior to any lift taking place by crane supervisor
and engineer;
iii. Ensure all lifting tackle and equipment have valid test certificate before
use (6 monthly 3rd
party inspections);
iv. Method statements and risk assessments to be submitted and adhered to
for technical and/or non-routine lifts;
v. Crane load indicator to be functioning correctly, and not to be overridden
under any circumstances;
vi. Operator to adhere to crane safe working load limits, weight of load and
COG established before lifting;
vii. Tower crane operator subject to regular health checks;
Machine
breakdown
Hydraulic fluid spill
Operator deemed
unfit to operate
crane
Machine isolated and
quarantined until repaired.
Spoil removed and treated as
hazardous waste
Removed from operation
Low
5
Tower Crane
supervision
 Lifting operations
around workers;
 Workers in crane
operating radius;
 Persons underneath load struck by
materials;
 Load swinging / spinning
uncontrolled;
 Falling materials;
 Damage to lifting slings from sharp
edges;
 Over-sailing of material over live
traffic routes;
 High winds – adverse weather;
4 5
20
High
i. Lift controlled by designated trained rigger/banks man using approved
hand signals only;
ii. No personnel situated or walking under elevated loads, avoid over-
sailing of personnel if practicable;
iii. No over-sailing of loads over live traffic routes without road closure;
iv. No lifts undertaken when wind speed exceeds 40kph;
v. No blind lifts without visual and communication aids, radios etc.;
vi. Tag lines shall be used to guide materials while lifting, 2 lines minimum
10m in length;
vii. Slings protected from sharp edges with rubber etc.;
viii. Riggers to undertake visual inspection of all lifting equipment daily;
ix. Tower crane allowed to ‘weather vane’ in high winds;
Incident – falling
materials
Work stopped, area cleared
and full investigation
undertaken
Low
6
Jumping and
dismantling of Tower
Crane
 Works at Height;
 Fall from height;
 Falling materials from height;
 Use of untrained personnel;
 Dismantling in adverse weather;
4 5
20
High
i. Ensure crane is jumped or dismantled to standards by trained competent
erection personnel;
ii. No dismantling or jumping in adverse weather or high winds;
iii. Concise Dismantling Method Statement compiled and available in work
area for review;
iv. Area below works cleared and barriers implemented during jumping or
dismantling;
Storage of
dismantled
material
Designated area established
clear of access routes Low

More Related Content

What's hot

20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templatesDwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templatesDwarika Bhushan Sharma
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templatesDwarika Bhushan Sharma
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessmentSimba Zhao
 
Lifting plan
Lifting planLifting plan
Lifting plantnsv22
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templatesDwarika Bhushan Sharma
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templatesDwarika Bhushan Sharma
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputGaurav Singh Rajput
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptssuser0ebdc3
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 

What's hot (20)

20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
3 emergency management risk assessment templates
3 emergency management risk assessment templates3 emergency management risk assessment templates
3 emergency management risk assessment templates
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates23 casting of concrete slabs risk assessment templates
23 casting of concrete slabs risk assessment templates
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templates
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh RajputJob Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
Hira
HiraHira
Hira
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 

Similar to 9 Lifting Operations with Tower crane Risk Assessment Templates.docx

24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docxDwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docxDwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docxDwarika Bhushan Sharma
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templatesDwarika Bhushan Sharma
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docxDwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docxDwarika Bhushan Sharma
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templatesDwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docxDwarika Bhushan Sharma
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docxDwarika Bhushan Sharma
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...Dwarika Bhushan Sharma
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 

Similar to 9 Lifting Operations with Tower crane Risk Assessment Templates.docx (20)

24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx24 Casting of Bridge Decks Risk Assessment Templates.docx
24 Casting of Bridge Decks Risk Assessment Templates.docx
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates24 casting of bridge decks risk assessment templates
24 casting of bridge decks risk assessment templates
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
 
32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates32 use of aluminium mobile scaffolding risk assessment templates
32 use of aluminium mobile scaffolding risk assessment templates
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx
 
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
32 Use of Aluminium mobile Scaffolding Risk Assessment Templates.docx
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdfDwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdfDwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdfDwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdfDwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docxDwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxDwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxDwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxDwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxDwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxDwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxDwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxDwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docxDwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docDwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docDwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxDwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

9 Lifting Operations with Tower crane Risk Assessment Templates.docx

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane Issued: Rev. Date: Revision: 0 Page 1 of 2 HSEQ -Rev-01(Jan-2023) Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Lifting operations using Tower crane within site boundary Relevant Applicable MAS:  01412 – Lifting Operations;  00941 – Lifting equipment Additional Training required: Riggers / Slingers NOC’s Required for task: As applicable RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the work place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards? Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1 No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 1 Access of Tower crane sections to work areas  Plant and workers in same working area as delivery truck;  Collision with plant or vehicles and live traffic;  Workers struck by plant, very high risk of fatality;  Uncontrolled crane reversing; 3 4 12 High i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation; ii. Instruction to workers at induction on use of access routes around the project; iii. Flagmen to be used to control crane movements; iv. The Logistics plan shall clearly illustrate crane access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low 2 Tower crane foundations  Excavations;  Use of plant – excavators etc.;  Use of concrete;  Temporary Works;  See Risk Assessment 010 – Excavations;  See Risk Assessment 014 – use of Mobile Concrete pump;  Failure due to incorrect design; 4 5 20 High i. Crane foundations to be designed by approved persons, to clear design criteria; ii. Foundations given adequate curing time before crane erection; iii. Temporary Works Coordinator to control excavations and concrete pours; Low 3 Siting, setting up and testing of Tower crane  Works at Height;  Working in proximity to existing structures and services;  Fall from height;  Falling materials from height;  Use of untrained erectors;  Erection in adverse weather;  Collision with overhead services;  Blocking access routes;  Load striking moving and/or stationary structures;  Use of untested crane;  Use of unqualified operator; 3 4 12 High i. Ensure crane is erected to standards by trained competent erection personnel; ii. No crane erection in adverse weather or high wind speed; iii. Concise erection Method Statement compiled and available in work area for review; iv. Area below works cleared and barriers implemented; v. Solid barriers should be situated, where practicable, to protect erected crane from traffic routes; vi. Consideration given to overhead services and existing structures when siting tower crane; vii. All Tower cranes to be Third Party Certificated by a DM approved inspector prior to use, documentation available on arrival to site; viii.Load tests undertaken prior to use and available for review; ix. Operators to have in-date Third Party certificate by approved body, available for review; x. Crane load indicator to be installed and functioning correctly; Failure of crash detector Crane quarantined until repaired and tested Low
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with Tower crane Issued: Rev. Date: Revision: 0 Page 2 of 2 HSEQ -Rev-01(Jan-2023) xi. Crash detectors installed and functioning correctly; 4 Lifting of equipment and material (Tower crane Operator)  Operator competency and health;  Lift planning;  Incident due to use of defective lifting gear / equipment;  Crane collapse due to lifting loads beyond SWL;  No crane documentation in place;  Tower crane operator collapse whilst in cab; 4 5 20 HIGH i. HLG Minimum Acceptable Standard HLG/OHS/MAS/00941 to be adhered to at all times; ii. Lift Plan to be completed prior to any lift taking place by crane supervisor and engineer; iii. Ensure all lifting tackle and equipment have valid test certificate before use (6 monthly 3rd party inspections); iv. Method statements and risk assessments to be submitted and adhered to for technical and/or non-routine lifts; v. Crane load indicator to be functioning correctly, and not to be overridden under any circumstances; vi. Operator to adhere to crane safe working load limits, weight of load and COG established before lifting; vii. Tower crane operator subject to regular health checks; Machine breakdown Hydraulic fluid spill Operator deemed unfit to operate crane Machine isolated and quarantined until repaired. Spoil removed and treated as hazardous waste Removed from operation Low 5 Tower Crane supervision  Lifting operations around workers;  Workers in crane operating radius;  Persons underneath load struck by materials;  Load swinging / spinning uncontrolled;  Falling materials;  Damage to lifting slings from sharp edges;  Over-sailing of material over live traffic routes;  High winds – adverse weather; 4 5 20 High i. Lift controlled by designated trained rigger/banks man using approved hand signals only; ii. No personnel situated or walking under elevated loads, avoid over- sailing of personnel if practicable; iii. No over-sailing of loads over live traffic routes without road closure; iv. No lifts undertaken when wind speed exceeds 40kph; v. No blind lifts without visual and communication aids, radios etc.; vi. Tag lines shall be used to guide materials while lifting, 2 lines minimum 10m in length; vii. Slings protected from sharp edges with rubber etc.; viii. Riggers to undertake visual inspection of all lifting equipment daily; ix. Tower crane allowed to ‘weather vane’ in high winds; Incident – falling materials Work stopped, area cleared and full investigation undertaken Low 6 Jumping and dismantling of Tower Crane  Works at Height;  Fall from height;  Falling materials from height;  Use of untrained personnel;  Dismantling in adverse weather; 4 5 20 High i. Ensure crane is jumped or dismantled to standards by trained competent erection personnel; ii. No dismantling or jumping in adverse weather or high winds; iii. Concise Dismantling Method Statement compiled and available in work area for review; iv. Area below works cleared and barriers implemented during jumping or dismantling; Storage of dismantled material Designated area established clear of access routes Low